|
|
(4 intermediate revisions by the same user not shown) |
Line 3: |
Line 3: |
| | issue date = 06/17/2015 | | | issue date = 06/17/2015 |
| | title = NRC Fire Protection Inspection at Ginna Station | | | title = NRC Fire Protection Inspection at Ginna Station |
| | author name = Richmond J E | | | author name = Richmond J |
| | author affiliation = NRC/RGN-I/DRS/EB3 | | | author affiliation = NRC/RGN-I/DRS/EB3 |
| | addressee name = Bradshaw C, Harding T | | | addressee name = Bradshaw C, Harding T |
Line 13: |
Line 13: |
| | page count = 1 | | | page count = 1 |
| }} | | }} |
| | |
| | =Text= |
| | {{#Wiki_filter:From: Richmond, John Sent: Wednesday, June 17, 2015 2:04 PM To: Harding Jr, Thomas:(GenCo-Nuc) (thomas.hardingjr@exeloncorp.com); |
| | Bradshaw, Christopher E:(GenCo-Nuc) |
| | (christopher.bradshaw@exeloncorp.com) |
| | Cc: Rogge, John; Robinson, Jay |
| | |
| | ==Subject:== |
| | NRC Fire Protection Inspection at Ginna Attachments: Ginna Document Request for Appendix R Licensing Basis.docx Gentlemen, The Ginna License Amendment Request (LAR) to transition Ginna's fire protection program licensing basis from 10 CFR 50 Appendix R to the National Fire Protection Association (NFPA) 805 is in progress, and may or may not be completed by the scheduled date for Ginna's Triennial Fire Protection Inspection. The notification for the Triennial Fire Protection Inspection, along with a Request for Information (i.e., the document request list) was sent to you on May 26, 2015 (ML15147A004). That document request list, dated May 26, 2015, was based on the expectation that Ginnas fire protection program licensing basis would transition to NFPA 805 prior to the start of the NRC inspection. |
| | A revised document request list is attached to this email. The revised list reflects the differences between those documents needed for an Appendix R licensing basis verses an NFPA 805 licensing basis, by deleting documents specific to NFPA 805 (shown in strike-out) and adding additional documents specific to Appendix R (yellow highlighting). Please note that the majority of the document request list has remained unchanged. |
| | In addition, for an Appendix R licensing basis facility, the NRC team will use Inspection Procedure 71111.05T (not 71111.05XT). |
| | The schedule for the inspection remains unchanged, as follows: |
| | * Information Gathering Visit: September 1 - 3, 2015 |
| | * On-Site Inspections: September 14 - 18, 2015 and September 28 - October 2, 2015 If you have any questions regarding this information request, please contact me as soon as possible. |
| | A copy of this email and its attachment will be available electronically for public inspection in the NRC Public Document Room or from the Publically Available Records (PARS) component of the NRC's document system (ADAMS). |
| | John Richmond NRC Senior Reactor Inspector (610) 337-5220}} |
Latest revision as of 11:00, 31 October 2019
Similar Documents at Ginna |
---|
Category:E-Mail
MONTHYEARML24250A1062024-09-0606 September 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24073A3602024-03-13013 March 2024 Request for Additional Information (RAI) Alternative Request PR-03 Sixth Interval Inservice Testing Program ML24045A2892024-02-14014 February 2024 R. E. Ginna Nuclear Power Plant Acceptance Review: IST Relief Request for B Auxiliary Feedwater Pump ML23311A1682023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (L-2023-LLR-0053 and L-2023-LLR-005 ML23311A1692023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Exam Categories B-B, B-D, and C-A SG Pressure Retaining Welds and Full Penetration Welded Nozzles (L-2023-LLR-0055 and L-2023-LLR-00 ML23312A1302023-11-0707 November 2023 Final Rci/Rai - Constellation R. E. Ginna Nuclear Power Plant - Exemption from Security Rule (EPID L-2023-LLE-0029) (Email) ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22325A0052022-11-18018 November 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-273-A, Revision 2 ML22339A0032022-09-28028 September 2022 R. E. Ginna Nuclear Power Plant - Ginna: Acceptance Review: to Revise Technical Specifications (TS) TS 5.6.5, Core Operating Limits Report ML22269A4522022-09-22022 September 2022 R. E. Ginna Nuclear Power Plant - Acceptance Review: to Revise Technical Specifications (TS) TS 5.6.5, Core Operating Limits Report (COLR) ML22255A0132022-09-0909 September 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, Calvert Cliffs, Ginna - License Amendment Request to Adopt TSTF-577 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22138A1672022-05-16016 May 2022 R. E. Ginna Nuclear Power Plant - Acceptance Review TS to Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes (EPID-L-2022-LLA-0057) ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22116A0242022-04-25025 April 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, and Ginna Request to Adopt TSTF-246 ML22088A1562022-03-0202 March 2022 NRR E-mail Capture - Byron, Braidwood, Calvert Cliffs, and Ginna - Non-acceptance of Application to Revise Technical Specifications 5.6.5.b, the Core Operating Limits Report (COLR) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML21308A5592021-11-0404 November 2021 NRR E-mail Capture - NRC Request for Additional Information for Ginna Biennial EP Exercise Exemption Request ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21293A2342021-10-19019 October 2021 R. E. Ginna Nuclear Power Plant - Acceptance of Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.C ML21293A1332021-10-19019 October 2021 R. E. Ginna Nuclear Power Plant - Acceptance of Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.C ML21279A1122021-10-0606 October 2021 R. E. Ginna Nuclear Power Plant - Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.c ML21273A1092021-09-30030 September 2021 R. E. Ginna Nuclear Power Plant - Acceptance Review - Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (EPID L-2021-LLR-0074 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21172A2702021-06-22022 June 2021 E-Mail Acceptance of Application - Risk Informed Completion Times in Accordance with TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, ML21172A2692021-06-22022 June 2021 E Mail Acceptance of Application to Adopt 10 CFR 50.69, _Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors (Epid_ L-2021-LLA-0092) ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21123A2442021-05-0303 May 2021 NRR E-mail Capture - NRC Acceptance Review of Braidwood/Byron/Ginna - Application to Address the Issues Identified in Westinghouse Documents NSAL-09-5 and NSAL-15-1 (L-2021-LLA-0066) ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21076A5152021-03-17017 March 2021 R. E. Ginna Nuclear Power Plant - RAI Steam Generator LAR to Revise Technical Specifications for Steam Generator Tube Inspection Frequency (EPID L-2020-LLA-0207) (e-mail) ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML20357A2232020-12-17017 December 2020 Update on Ginna POV - 3504A and 4562 (Email Request for Inspection Information) ML20350B5582020-12-14014 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC -Alternative Request for Documentation of Replacement of Pressure Retaining Bolting ML20335A5692020-11-30030 November 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review: Alternative to ASME Code, Section XI ML20325A1002020-11-20020 November 2020 Acceptance Review: Force-on-Force Temporary Exemption Request ML20294A4942020-10-20020 October 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review: to Revise Technical Specifications for Steam Generator Tube Inspection Frequency ML20276A1032020-10-0202 October 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review - Exemptions from 10 CFR 2.109(b), Effect of Timely Renewal Application 2024-09-06
[Table view] |
Text
From: Richmond, John Sent: Wednesday, June 17, 2015 2:04 PM To: Harding Jr, Thomas:(GenCo-Nuc) (thomas.hardingjr@exeloncorp.com);
Bradshaw, Christopher E:(GenCo-Nuc)
(christopher.bradshaw@exeloncorp.com)
Cc: Rogge, John; Robinson, Jay
Subject:
NRC Fire Protection Inspection at Ginna Attachments: Ginna Document Request for Appendix R Licensing Basis.docx Gentlemen, The Ginna License Amendment Request (LAR) to transition Ginna's fire protection program licensing basis from 10 CFR 50 Appendix R to the National Fire Protection Association (NFPA) 805 is in progress, and may or may not be completed by the scheduled date for Ginna's Triennial Fire Protection Inspection. The notification for the Triennial Fire Protection Inspection, along with a Request for Information (i.e., the document request list) was sent to you on May 26, 2015 (ML15147A004). That document request list, dated May 26, 2015, was based on the expectation that Ginnas fire protection program licensing basis would transition to NFPA 805 prior to the start of the NRC inspection.
A revised document request list is attached to this email. The revised list reflects the differences between those documents needed for an Appendix R licensing basis verses an NFPA 805 licensing basis, by deleting documents specific to NFPA 805 (shown in strike-out) and adding additional documents specific to Appendix R (yellow highlighting). Please note that the majority of the document request list has remained unchanged.
In addition, for an Appendix R licensing basis facility, the NRC team will use Inspection Procedure 71111.05T (not 71111.05XT).
The schedule for the inspection remains unchanged, as follows:
- Information Gathering Visit: September 1 - 3, 2015
- On-Site Inspections: September 14 - 18, 2015 and September 28 - October 2, 2015 If you have any questions regarding this information request, please contact me as soon as possible.
A copy of this email and its attachment will be available electronically for public inspection in the NRC Public Document Room or from the Publically Available Records (PARS) component of the NRC's document system (ADAMS).
John Richmond NRC Senior Reactor Inspector (610) 337-5220