RS-17-117, Radiological Emergency Plan Addendum Revision: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:/ za 1 4300 Winfield Road Warrenville, IL 60555 ., Exelon.Generation 630 657 2000 Office RS-17-117 August17,2017 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 1 O CFR 50.54(q)(5) 10 CFR 50.4 10 CFR 72.44(f) Quad Cities Nuclear Power Station, Units 1 and 2  
{{#Wiki_filter:/
za
    ., 1 4300 Winfield Road Warrenville, IL 60555
~        Exelon.Generation                                                 630 657 2000 Office 1O CFR 50.54(q)(5) 10 CFR 50.4 10 CFR 72.44(f)
RS-17-117 August17,2017 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254, 50-265, and 72-53


==Subject:==
==Subject:==
Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254, 50-265, and 72-53 Exelon Nuclear Radiological Emergency Plan Addendum Revision In accordance with 1 O CFR 50.4(b)(5), "Emergency Plan and related submissions," Exelon Generation Company, LLC (Exelon) is submitting the Emergency Plan Addendum revision listed in the table below for the Quad Cities Nuclear Power Station (Quad Cities). Document Revision Title EP-AA-1006, Addendum 3 4 Emergency Action Levels tor Quad Cities Station The changes to the Emergency Plan Addendum were evaluated under the requirements of 1 O CFR 50.54(q) and were determined not to result in a .. reduction in the effectiveness of the Emergency Plans for Quad Cities. This notification is being submitted within 30 days of implementation of the changes as required by 1 O CFR 50.54(q)(5).
Exelon Nuclear Radiological Emergency Plan Addendum Revision In accordance with 1O CFR 50.4(b)(5), "Emergency Plan and related submissions," Exelon Generation Company, LLC (Exelon) is submitting the Emergency Plan Addendum revision listed in the table below for the Quad Cities Nuclear Power Station (Quad Cities).
The changes continue to meet th.e applicable planning standards established in 1 O CFR 50.47(b) and 1 O CFR 50, Appendix E. In addition, as required by 1 O CFR 50.54(q)(5), this submittal includes a summary analysis of the changes to the Emergency Plan Addendum (Attachment 1 ). This submittal also satisfies the reporting requirements associated with 10 CFR 72.44(f), which stipulates that within six months after any change is made to the Emergency Plan, the licensee shall submit a report containing a description of the changes to the Director, Division of Spent Fuel Management.
Document               Revision                           Title EP-AA-1006, Addendum 3             4         Emergency Action Levels tor Quad Cities Station The changes to the Emergency Plan Addendum were evaluated under the requirements of 1O CFR 50.54(q) and were determined not to result in a . reduction in the effectiveness of the Emergency Plans for Quad Cities. This notification is being submitted within 30 days of implementation of the changes as required by 1O CFR 50.54(q)(5). The changes continue to meet th.e applicable planning standards established in 1O CFR 50.47(b) and 1O CFR 50, Appendix E.
N1-1ss,-i&  
In addition, as required by 1O CFR 50.54(q)(5), this submittal includes a summary analysis of the changes to the Emergency Plan Addendum (Attachment 1).
;Jll-1JfvfSS U.S. Nuclear Regulatory Commission Emergency Plan Addendum Revision NRC Docket Nos. 50-254, 50-265, and 72-53 August 17, 2017 Page2 A copy of the revised Emergency Plan Addendum and supporting change summary analysis are included in the attachments to this letter. There are no regulatory commitments in this submittal.
This submittal also satisfies the reporting requirements associated with 10 CFR 72.44(f),
which stipulates that within six months after any change is made to the Emergency Plan, the licensee shall submit a report containing a description of the changes to the Director, Division of Spent Fuel Management.
A~45 N1-1ss,-i&
                                                                                                            ;Jll-1JfvfSS
 
U.S. Nuclear Regulatory Commission Emergency Plan Addendum Revision NRC Docket Nos. 50-254, 50-265, and 72-53 August 17, 2017 Page2 A copy of the revised Emergency Plan Addendum and supporting change summary analysis are included in the attachments to this letter.
There are no regulatory commitments in this submittal.
If you have any questions or require additional information, please contact Richard Gropp at (610) 765-5557.
If you have any questions or require additional information, please contact Richard Gropp at (610) 765-5557.
Respectfully,  
Respectfully,
.. M. Imburgia Manager, Licensing Programs Exelon Generation Company, LLC Attachments: 1 ) 2) 1 O CFR 50.54(q)(5)
<t?~JVt~
Procedure Change Summary Analysis EP-AA-1006, Addendum 3, Revision 4, "Emergency Action Levels for Quad Cities Station" cc: w/ Attachment 1 only Regional Administrator  
.. ~~c      M. Imburgia Manager, Licensing Programs Exelon Generation Company, LLC Attachments: 1)     1O CFR 50.54(q)(5) Procedure Change Summary Analysis
-NRC Region Ill Director, NRC Division of Spent Fuel Management, ONMSS NRC Senior Resident Inspector  
: 2)  EP-AA-1006, Addendum 3, Revision 4, "Emergency Action Levels for Quad Cities Station" cc:     w/ Attachment 1 only Regional Administrator - NRC Region Ill Director, NRC Division of Spent Fuel Management, ONMSS NRC Senior Resident Inspector - Quad Cities Nuclear Power Station NRC Project Manager, NRR - Quad Cities Nuclear Power Station Illinois Emergency Management Agency - Division of Nuclear Safety}}
-Quad Cities Nuclear Power Station NRC Project Manager, NRR -Quad Cities Nuclear Power Station Illinois Emergency Management Agency -Division of Nuclear Safety}}

Revision as of 21:37, 29 October 2019

Radiological Emergency Plan Addendum Revision
ML17234A455
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 08/17/2017
From: Imburgia D
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
RS-17-117
Download: ML17234A455 (2)


Text

/

za

., 1 4300 Winfield Road Warrenville, IL 60555

~ Exelon.Generation 630 657 2000 Office 1O CFR 50.54(q)(5) 10 CFR 50.4 10 CFR 72.44(f)

RS-17-117 August17,2017 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254, 50-265, and 72-53

Subject:

Exelon Nuclear Radiological Emergency Plan Addendum Revision In accordance with 1O CFR 50.4(b)(5), "Emergency Plan and related submissions," Exelon Generation Company, LLC (Exelon) is submitting the Emergency Plan Addendum revision listed in the table below for the Quad Cities Nuclear Power Station (Quad Cities).

Document Revision Title EP-AA-1006, Addendum 3 4 Emergency Action Levels tor Quad Cities Station The changes to the Emergency Plan Addendum were evaluated under the requirements of 1O CFR 50.54(q) and were determined not to result in a . reduction in the effectiveness of the Emergency Plans for Quad Cities. This notification is being submitted within 30 days of implementation of the changes as required by 1O CFR 50.54(q)(5). The changes continue to meet th.e applicable planning standards established in 1O CFR 50.47(b) and 1O CFR 50, Appendix E.

In addition, as required by 1O CFR 50.54(q)(5), this submittal includes a summary analysis of the changes to the Emergency Plan Addendum (Attachment 1).

This submittal also satisfies the reporting requirements associated with 10 CFR 72.44(f),

which stipulates that within six months after any change is made to the Emergency Plan, the licensee shall submit a report containing a description of the changes to the Director, Division of Spent Fuel Management.

A~45 N1-1ss,-i&

Jll-1JfvfSS

U.S. Nuclear Regulatory Commission Emergency Plan Addendum Revision NRC Docket Nos. 50-254, 50-265, and 72-53 August 17, 2017 Page2 A copy of the revised Emergency Plan Addendum and supporting change summary analysis are included in the attachments to this letter.

There are no regulatory commitments in this submittal.

If you have any questions or require additional information, please contact Richard Gropp at (610) 765-5557.

Respectfully,

<t?~JVt~

.. ~~c M. Imburgia Manager, Licensing Programs Exelon Generation Company, LLC Attachments: 1) 1O CFR 50.54(q)(5) Procedure Change Summary Analysis

2) EP-AA-1006, Addendum 3, Revision 4, "Emergency Action Levels for Quad Cities Station" cc: w/ Attachment 1 only Regional Administrator - NRC Region Ill Director, NRC Division of Spent Fuel Management, ONMSS NRC Senior Resident Inspector - Quad Cities Nuclear Power Station NRC Project Manager, NRR - Quad Cities Nuclear Power Station Illinois Emergency Management Agency - Division of Nuclear Safety