| issue date = 03/14/2018
| issue date = 03/14/2018
| title = Notification of Changes to Comprehensive Recovery Plan and Area Action Plan Action Completion Dates
| title = Notification of Changes to Comprehensive Recovery Plan and Area Action Plan Action Completion Dates
| author name = Sullivan B R
| author name = Sullivan B
| author affiliation = Entergy Nuclear Operations, Inc
| author affiliation = Entergy Nuclear Operations, Inc
| addressee name = Lew D C
| addressee name = Lew D
| addressee affiliation = NRC/NRR, NRC/RGN-I
| addressee affiliation = NRC/NRR, NRC/RGN-I
| docket = 05000293
| docket = 05000293
Line 16: Line 16:


=Text=
=Text=
{{#Wiki_filter:~Entergy March 14, 2018 Mr. David C. Lew Acting Regional Administrator, Region I U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713 Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360 Brian R. Sullivan Site Vice President
{{#Wiki_filter:~                                                                   Entergy Nuclear Operations, Inc.
Pilgrim Nuclear Power Station
  ~Entergy                                                          600 Rocky Hill Road Plymouth, MA 02360 Brian R. Sullivan Site Vice President March 14, 2018 Mr. David C. Lew Acting Regional Administrator, Region I U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713


==SUBJECT:==
==SUBJECT:==
Notification of Changes to Comprehensive Recovery Plan and Area Action Plan Action Completion Dates Pilgrim Nuclear Power Station Docket No. 50-293 Renewed License No. DPR-35  
Notification of Changes to Comprehensive Recovery Plan and Area Action Plan Action Completion Dates Pilgrim Nuclear Power Station Docket No. 50-293 Renewed License No. DPR-35


==REFERENCES:==
==REFERENCES:==
: 1. Entergy letter to NRC, "Pilgrim Nuclear Power Station Recovery Plan," dated July 28, 2017 (Letter Number 2.17.056) (ML 17212A571)
: 1. Entergy letter to NRC, "Pilgrim Nuclear Power Station Recovery Plan," dated July 28, 2017 (Letter Number 2.17.056) (ML17212A571)
: 2. NRC letter to Entergy, "Confirmatory Action Letter -Pilgrim Nuclear Power Station," dated August 2, 2017 (ML 17214A088)
: 2. NRC letter to Entergy, "Confirmatory Action Letter - Pilgrim Nuclear Power Station," dated August 2, 2017 (ML17214A088)
LETTER NUMBER: 2.18.012  
LETTER NUMBER: 2.18.012


==Dear Mr. Lew:==
==Dear Mr. Lew:==
On July 28, 2017, Entergy Nuclear Operations, Inc. (Entergy) transmitted the Pilgrim Nuclear Power Station (PNPS) Comprehensive Recovery Plan (CRP) (Reference
 
: 1) to the U.S. Nuclear Regulatory Commission (NRC). The CRP contains the actions that Entergy is taking to address the decline in performance at PNPS, including actions to address the issues that led to PNPS being placed in the Multiple/Repetitive Degraded Cornerstone Column (Column IV) of the NRC Action Matrix. In response, the NRC transmitted the PNPS Confirmatory Action Letter (CAL), dated August 2, 2017, confirming the commitments made by Entergy (Reference 2). Subsequent to the issuance of the CAL, refinement of the schedule for Area Action Plan (AAP) inspections has been discussed with the NRC Staff. The purpose of these discussions was to ensure alignment between the PNPS schedule for completion of Enclosure 2 action items supporting closure of AAPs, and the availability of NRC inspection resources.
On July 28, 2017, Entergy Nuclear Operations, Inc. (Entergy) transmitted the Pilgrim Nuclear Power Station (PNPS) Comprehensive Recovery Plan (CRP) (Reference 1) to the U.S. Nuclear Regulatory Commission (NRC). The CRP contains the actions that Entergy is taking to address the decline in performance at PNPS, including actions to address the issues that led to PNPS being placed in the Multiple/Repetitive Degraded Cornerstone Column (Column IV) of the NRC Action Matrix.
Based on coordination with the NRC Staff, the schedule of inspections was revised. Accordingly, correspondence is required pursuant to Section 182 of the Atomic Energy Act, 42 U.S.C. 2232 to notify the NRC in advance, if for any reason, an action listed in the CAL cannot be completed within the specified schedule.
In response, the NRC transmitted the PNPS Confirmatory Action Letter (CAL), dated August 2, 2017, confirming the commitments made by Entergy (Reference 2). Subsequent to the issuance of the CAL, refinement of the schedule for Area Action Plan (AAP) inspections has been discussed with the NRC Staff. The purpose of these discussions was to ensure alignment between the PNPS schedule for completion of Enclosure 2 action items supporting closure of AAPs, and the availability of NRC inspection resources. Based on coordination with the NRC Staff, the schedule of inspections was revised. Accordingly, correspondence is required pursuant to Section 182 of the Atomic Energy Act, 42 U.S.C. 2232 to notify the NRC in advance, if for any reason, an action listed in the CAL cannot be completed within the specified schedule. Since some of the dates will be shifted, NRC notification is required in advance of the changes.
Since some of the dates will be shifted, NRC notification is required in advance of the changes.
 
Entergy Nuclear Operations, Inc. Pilgrim Nuclear Power Station Letter No. 2.18.012 Page 2 of 2 In addition, during preparation activities for the upcoming CAL inspections, Entergy identified a number of AAP actions in Enclosure 1 of Reference 2 (the CRP) that need to be clarified or modified to ensure common *understanding of the required actions. The changes are provided in Attachment 1 of this letter. Notification of the modified PNPS schedule is provided in Attachment
Entergy Nuclear Operations, Inc.                                       Letter No. 2.18.012 Pilgrim Nuclear Power Station                                                  Page 2 of 2 In addition, during preparation activities for the upcoming CAL inspections, Entergy identified a number of AAP actions in Enclosure 1 of Reference 2 (the CRP) that need to be clarified or modified to ensure common *understanding of the required actions. The changes are provided in Attachment 1 of this letter. Notification of the modified PNPS schedule is provided in Attachment 2.
: 2. If you have any questions or require additional information, please contact Mr. Peter J. Miner at (508) 830-7127.
If you have any questions or require additional information, please contact Mr. Peter J. Miner at (508) 830-7127.
Sincerely, Brian R. Sullivan Site Vice President BRS/pm  
Sincerely, Brian R. Sullivan Site Vice President BRS/pm


==Attachment:==
==Attachment:==
: 1. Notification of Changes to Actions in Comprehensive Recovery Plan 2. Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule cc: U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001  
: 1. Notification of Changes to Actions in Comprehensive Recovery Plan
*** Mr. John Lamb, Senior Project Manager Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 0-8C2A Washington, DC 20555-0001 NRG Senior Resident Inspector Pilgrim Nuclear Power Station Attachment 1 Letter Number 2.18.012 Notification of Changes to Actions in Comprehensive Recovery Plan Attachment 1 Notification of Changes to Actions in Comprehensive Recovery Plan 1. ODFA-5.6 should state, "The actions specified in ODFA-5.1 and 5.2 also address deficiencies identified during the 95003 inspection." 2. The following Operations Standards and Site Leadership actions are listed under the Risk Recognition and Decision-Making Action Plan (RRDM) and are more appropriately addressed under the Operations Standards and Site Leadership Action Plan (OPS). To address this the following revisions are requested:
: 2. Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule cc:
: a. Add new section OPS-5: Additional Actions (Enclosure 1 and 2) b. RRDM-4.1 to become OPS-5.1 (Enclosure
U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001
: 1) c. RRDM-4.2 to become OPS-5.2 (Enclosure
***         Mr. John Lamb, Senior Project Manager Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 0-8C2A Washington, DC 20555-0001 NRG Senior Resident Inspector Pilgrim Nuclear Power Station
: 1) d. RRDM-4.3 to become OPS-5.3 (Enclosure 1 and 2) e. RRDM-4.5 to become OPS-5.4 (Enclosure
 
: 1) f. RRDM-4.6 to become OPS-5.5 (Enclosure
Attachment 1 Letter Number 2.18.012 Notification of Changes to Actions in Comprehensive Recovery Plan
: 1) 3. OPS-5.2 (formerly RRDM-4.2) should be reworded to read "Schedule 3 operations manager mentor visits to Pilgrim following RF0-21." 4. OPS-5.3 (formerly RRDM-4.3) should be reworded to read "Issue additional actions based on the results and insights from the mentor visits conducted per OPS-5.1 and OPS-5.2." 5. Revise RRDM-4.8 to read: "RRDM-4.8 addresses the NRC 95003 observation that based on interviews and a review of current open corrective action program items generated by the subject matter experts, the NRC team noted resistance to the improvement recommendations of the subject matter experts by some station managers.
 
For example, in reference to CR-PNP-2016-07486, subject matter experts identified that numerous outage preventive maintenance activities were extended without sufficient technical justification and without conducting a risk review in accordance with procedure 1.3.142, PNPS Risk Review and Disposition.
Attachment 1 Notification of Changes to Actions in Comprehensive Recovery Plan
: 6. Revise RRDM-4.9 to read: "RRDM-4.9 addresses the NRC 95003 observation that some station leaders (managers and first-line supervisors) from across multiple departments appeared to be lagging in their demonstration of the new decision-making principles and implementation of procedure 1.3.142, PNPS Risk Review and Disposition, and the NRC 95003 observation that the current action plans allow the station 'the flexibility to remove the SMEs and mentors following a successful effectiveness review of the related area.' Implementation of the SMEs and mentors should continue until a positive change in safety culture is sustained and verified by NRC inspection." Page 1 of 1 Attachment 2 Letter Number 2.18.012 Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule Attachment 2 Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule Human Performance Corrective Action Program SRV White Finding Nuclear Safety Culture Operational Standards and Leadership Engineering Programs and Equipment Performance Procedure Use and Adherence Operability Determinations and Functionality Assessments Corrective Action Program SRV White Finding Nuclear Safety Culture Operational Standards and Leadership Risk Recognition and Decision Making Engineering Programs Equipment Reliability Work Management 02/28/18 05/18/18 02/28/18 No Change 03/30/18 05/18/18 03/30/18 No Change 05/31/18 11/23/18 05/31/18 08/24/18 05/31/18 08/24/18 06/28/18 08/24/18 06/28/18 08/24/18 06/28/18 08/24/18 J Page 1 of 1}}
: 1. ODFA-5.6 should state, "The actions specified in ODFA-5.1 and 5.2 also address deficiencies identified during the 95003 inspection."
: 2. The following Operations Standards and Site Leadership actions are listed under the Risk Recognition and Decision-Making Action Plan (RRDM) and are more appropriately addressed under the Operations Standards and Site Leadership Action Plan (OPS). To address this the following revisions are requested:
: a. Add new section OPS-5: Additional Actions (Enclosure 1 and 2)
: b. RRDM-4.1 to become OPS-5.1 (Enclosure 1)
: c. RRDM-4.2 to become OPS-5.2 (Enclosure 1)
: d. RRDM-4.3 to become OPS-5.3 (Enclosure 1 and 2)
: e. RRDM-4.5 to become OPS-5.4 (Enclosure 1)
: f. RRDM-4.6 to become OPS-5.5 (Enclosure 1)
: 3. OPS-5.2 (formerly RRDM-4.2) should be reworded to read "Schedule 3 operations manager mentor visits to Pilgrim following RF0-21."
: 4. OPS-5.3 (formerly RRDM-4.3) should be reworded to read "Issue additional actions based on the results and insights from the mentor visits conducted per OPS-5.1 and OPS-5.2."
: 5. Revise RRDM-4.8 to read:
  "RRDM-4.8 addresses the NRC 95003 observation that based on interviews and a review of current open corrective action program items generated by the subject matter experts, the NRC team noted resistance to the improvement recommendations of the subject matter experts by some station managers. For example, in reference to CR-PNP-2016-07486, subject matter experts identified that numerous outage preventive maintenance activities were extended without sufficient technical justification and without conducting a risk review in accordance with procedure 1.3.142, PNPS Risk Review and Disposition.
: 6. Revise RRDM-4.9 to read:
  "RRDM-4.9 addresses the NRC 95003 observation that some station leaders (managers and first-line supervisors) from across multiple departments appeared to be lagging in their demonstration of the new decision-making principles and implementation of procedure 1.3.142, PNPS Risk Review and Disposition, and the NRC 95003 observation that the current action plans allow the station 'the flexibility to remove the SMEs and mentors following a successful effectiveness review of the related area.' Implementation of the SMEs and mentors should continue until a positive change in safety culture is sustained and verified by NRC inspection."
Page 1 of 1
 
Attachment 2 Letter Number 2.18.012 Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule
 
Attachment 2 Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule Procedure Use and 02/28/18                 05/18/18 Adherence Human Performance Operability Determinations and 02/28/18                 No Change Functionality Assessments Corrective Action        Corrective Action 03/30/18                 05/18/18 Program                Program SRV White Finding        SRV White Finding              03/30/18                 No Change Nuclear Safety Culture  Nuclear Safety Culture            05/31/18                 11/23/18 Operational Standards 05/31/18                 08/24/18 Operational Standards        and Leadership and Leadership Risk Recognition and 05/31/18                 08/24/18 Decision Making Engineering Programs              06/28/18                 08/24/18 Engineering Programs and Equipment        Equipment Reliability            06/28/18                 08/24/18 Performance Work Management                06/28/18                 08/24/18 J
Page 1 of 1}}

Latest revision as of 14:13, 21 October 2019

Notification of Changes to Comprehensive Recovery Plan and Area Action Plan Action Completion Dates
ML18087A041
Person / Time
Site: Pilgrim
Issue date: 03/14/2018
From: Brian Sullivan
Entergy Nuclear Operations
To: David Lew
Office of Nuclear Reactor Regulation, NRC Region 1
References
2.18.012
Download: ML18087A041 (6)


Text

~ Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station

~Entergy 600 Rocky Hill Road Plymouth, MA 02360 Brian R. Sullivan Site Vice President March 14, 2018 Mr. David C. Lew Acting Regional Administrator, Region I U.S. Nuclear Regulatory Commission 2100 Renaissance Blvd, Suite 100 King of Prussia, PA 19406-2713

SUBJECT:

Notification of Changes to Comprehensive Recovery Plan and Area Action Plan Action Completion Dates Pilgrim Nuclear Power Station Docket No. 50-293 Renewed License No. DPR-35

REFERENCES:

1. Entergy letter to NRC, "Pilgrim Nuclear Power Station Recovery Plan," dated July 28, 2017 (Letter Number 2.17.056) (ML17212A571)
2. NRC letter to Entergy, "Confirmatory Action Letter - Pilgrim Nuclear Power Station," dated August 2, 2017 (ML17214A088)

LETTER NUMBER: 2.18.012

Dear Mr. Lew:

On July 28, 2017, Entergy Nuclear Operations, Inc. (Entergy) transmitted the Pilgrim Nuclear Power Station (PNPS) Comprehensive Recovery Plan (CRP) (Reference 1) to the U.S. Nuclear Regulatory Commission (NRC). The CRP contains the actions that Entergy is taking to address the decline in performance at PNPS, including actions to address the issues that led to PNPS being placed in the Multiple/Repetitive Degraded Cornerstone Column (Column IV) of the NRC Action Matrix.

In response, the NRC transmitted the PNPS Confirmatory Action Letter (CAL), dated August 2, 2017, confirming the commitments made by Entergy (Reference 2). Subsequent to the issuance of the CAL, refinement of the schedule for Area Action Plan (AAP) inspections has been discussed with the NRC Staff. The purpose of these discussions was to ensure alignment between the PNPS schedule for completion of Enclosure 2 action items supporting closure of AAPs, and the availability of NRC inspection resources. Based on coordination with the NRC Staff, the schedule of inspections was revised. Accordingly, correspondence is required pursuant to Section 182 of the Atomic Energy Act, 42 U.S.C. 2232 to notify the NRC in advance, if for any reason, an action listed in the CAL cannot be completed within the specified schedule. Since some of the dates will be shifted, NRC notification is required in advance of the changes.

Entergy Nuclear Operations, Inc. Letter No. 2.18.012 Pilgrim Nuclear Power Station Page 2 of 2 In addition, during preparation activities for the upcoming CAL inspections, Entergy identified a number of AAP actions in Enclosure 1 of Reference 2 (the CRP) that need to be clarified or modified to ensure common *understanding of the required actions. The changes are provided in Attachment 1 of this letter. Notification of the modified PNPS schedule is provided in Attachment 2.

If you have any questions or require additional information, please contact Mr. Peter J. Miner at (508) 830-7127.

Sincerely, Brian R. Sullivan Site Vice President BRS/pm

Attachment:

1. Notification of Changes to Actions in Comprehensive Recovery Plan
2. Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule cc:

U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

      • Mr. John Lamb, Senior Project Manager Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Mail Stop 0-8C2A Washington, DC 20555-0001 NRG Senior Resident Inspector Pilgrim Nuclear Power Station

Attachment 1 Letter Number 2.18.012 Notification of Changes to Actions in Comprehensive Recovery Plan

Attachment 1 Notification of Changes to Actions in Comprehensive Recovery Plan

1. ODFA-5.6 should state, "The actions specified in ODFA-5.1 and 5.2 also address deficiencies identified during the 95003 inspection."
2. The following Operations Standards and Site Leadership actions are listed under the Risk Recognition and Decision-Making Action Plan (RRDM) and are more appropriately addressed under the Operations Standards and Site Leadership Action Plan (OPS). To address this the following revisions are requested:
a. Add new section OPS-5: Additional Actions (Enclosure 1 and 2)
b. RRDM-4.1 to become OPS-5.1 (Enclosure 1)
c. RRDM-4.2 to become OPS-5.2 (Enclosure 1)
d. RRDM-4.3 to become OPS-5.3 (Enclosure 1 and 2)
e. RRDM-4.5 to become OPS-5.4 (Enclosure 1)
f. RRDM-4.6 to become OPS-5.5 (Enclosure 1)
3. OPS-5.2 (formerly RRDM-4.2) should be reworded to read "Schedule 3 operations manager mentor visits to Pilgrim following RF0-21."
4. OPS-5.3 (formerly RRDM-4.3) should be reworded to read "Issue additional actions based on the results and insights from the mentor visits conducted per OPS-5.1 and OPS-5.2."
5. Revise RRDM-4.8 to read:

"RRDM-4.8 addresses the NRC 95003 observation that based on interviews and a review of current open corrective action program items generated by the subject matter experts, the NRC team noted resistance to the improvement recommendations of the subject matter experts by some station managers. For example, in reference to CR-PNP-2016-07486, subject matter experts identified that numerous outage preventive maintenance activities were extended without sufficient technical justification and without conducting a risk review in accordance with procedure 1.3.142, PNPS Risk Review and Disposition.

6. Revise RRDM-4.9 to read:

"RRDM-4.9 addresses the NRC 95003 observation that some station leaders (managers and first-line supervisors) from across multiple departments appeared to be lagging in their demonstration of the new decision-making principles and implementation of procedure 1.3.142, PNPS Risk Review and Disposition, and the NRC 95003 observation that the current action plans allow the station 'the flexibility to remove the SMEs and mentors following a successful effectiveness review of the related area.' Implementation of the SMEs and mentors should continue until a positive change in safety culture is sustained and verified by NRC inspection."

Page 1 of 1

Attachment 2 Letter Number 2.18.012 Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule

Attachment 2 Notification of Changes to Area Action Plan Action Completion Dates to Support Revised Inspection Schedule Procedure Use and 02/28/18 05/18/18 Adherence Human Performance Operability Determinations and 02/28/18 No Change Functionality Assessments Corrective Action Corrective Action 03/30/18 05/18/18 Program Program SRV White Finding SRV White Finding 03/30/18 No Change Nuclear Safety Culture Nuclear Safety Culture 05/31/18 11/23/18 Operational Standards 05/31/18 08/24/18 Operational Standards and Leadership and Leadership Risk Recognition and 05/31/18 08/24/18 Decision Making Engineering Programs 06/28/18 08/24/18 Engineering Programs and Equipment Equipment Reliability 06/28/18 08/24/18 Performance Work Management 06/28/18 08/24/18 J

Page 1 of 1