{{#Wiki_filter:CATEGORY j.REGULATORY
{{#Wiki_filter:CATEGORY j.REGULATORY INFORMATION-DISTRIBUTION SYSTEM (RIDS)*ACCESSION'NBR:9610250150 DOC.DATE: 96/10/18 NOTARIZED:
INFORMATION-
NO FACIL:50-335 St.Lucie Plant, Unit 1, Florida Power a Light Co.50-389 St.Lucie Plant, Unit 2, Florida Power 6 Light Co.AUTH.NAME AUTHOR AFFILIATION PLUNKETT,T.F.
DISTRIBUTION
Florida Power a Light Co.RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)
SYSTEM (RIDS)*ACCESSION'NBR:9610250150
 
DOC.DATE: 96/10/18 NOTARIZED:
==SUBJECT:==
NO FACIL:50-335
Responds to violations noted in insp repts 50-335/96-16 a 50-389/96-16.Corrective actions:revised security procedure 0006125,"Reporting of Safeguards Events," 6 will develop security event response guidance.DISTRIBUTION CODE: IE01D COPIES RECEIVED:LTR ENCL SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES: DOCKET g 05000335 05000389 RECIPIENT ID CODE/NAME PD2-3 PD INTERNAL: ACRS C FIL CENTER NRR DRC HHFB NRR/DRPM/PERB OE DIR RGN2 FILE 01 EXTERNAL: LITCO BRYCE,J H NRC PDR COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME WIENS,L.AEOD/SPD/RAB DEDRO NRR/DISP/PIPB NRR/DRPM/PECB NUDOCS-ABSTRACT OGC/HDS3 NOAC COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 D E N T'OTE TO ALL"RIDS" RECIPIENTS:
St.Lucie Plant, Unit 1, Florida Power a Light Co.50-389 St.Lucie Plant, Unit 2, Florida Power 6 Light Co.AUTH.NAME AUTHOR AFFILIATION
PLEASE HELP US TO REDUCE WASTE.TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 19 ENCL 19 Florida Power 5 Light Company, P.O.Box 14000, Juno Beach, FL 33408.0420 OCT18$996 L-96-255 10 CFR 2.201 U.S.Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.20555 Re: St.Lucie Units 1 and 2 Docket No.50-335 and 50-389 Reply to a Notice of Violation NRC S ecial Ins ection Re ort 96-16 Florida Power and Light Company has reviewed the subject Notice of Violation and, pursuant to 10 CFR 2.201, the responses to the violations are attached.Very truly yours, T.F.Plunkett President Nuclear Division TFP/JAS/EJW Attachment cc: Stewart D.Ebneter, Regional Administrator, USNRC Region II Senior Resident Inspector, USNRC, St.Lucie Plant~.,'r j/l~9trr f 0250i 50 5000335 0 96i018 pDR ADOCK 0 6 an FPL Group company  
PLUNKETT,T.F.
 
Florida Power a Light Co.RECIP.NAME
~~L-96-255 Attachment Re I to a Notice of Violation VIOLATION A: 10 CFR 73.71, Reporting of Safeguards Events, Appendix G, (a)(3)"Reportable Safeguards Events," requires the licensee to report to the NRC within one hour following discovery, followed by a written report within 30 days, events which cause interruption of normal operations through tampering with controls including the security system.The licensee's Security Procedure, SP-0006125, Reporting of Safeguards Events, Revision 9, dated April 20, 1995, Paragraph 8.2 (I)defines one of those specific events as being a"confirmed tampering of suspicious origin with safety or security equipment." Contrary to the above on July 29, 1996, the licensee failed to report the confirmed tampering with security equipment (locks)within one hour to the NRC.This is a Severity Level IV violation (Supplement ID)RESPONSE: 1.FPL concurs with the violation.
RECIPIENT AFFILIATION
2.REASON FOR VIOLATION The reason for the violation was personnel error in that the event was not correctly identified as involving tampering.
Document Control Branch (Document Control Desk)SUBJECT: Responds to violations
A contributing factor to the error was inadequate procedural guidance.The security event reporting procedure in use on July 26, 1996, did not provide a clear definition of tampering nor clear guidance for making reportability determinations for tampering events.On July 26, 1996, glue was discovered in the lock core of an entry door to the Unit 2 Control Element Drive Mechanism Control System (CEDMCS)room.Further inspection revealed that several padlock/door lock sets (a total of eleven locks)on both units had been similarly vandalized.
noted in insp repts 50-335/96-16
The affected locks were determined not to adversely impact plant operations or the Physical Security Plan.Based on this determination, it was incorrectly interpreted that this event did not constitute"tampering" as described in St.Lucie Plant Security Procedure No.0006125,"Reporting of Safeguards Events." The procedure required  
a 50-389/96-16.Corrective
 
actions:revised
~~~~L-96-255 Attachment Re 1 to a Notice of Violation"confirmed tampering of suspicious origin with safety or security equipment" to be reported as a Safeguards Event.Failure to identify this incident as"tampering with security/safety equipment" resulted in utility personnel not reporting the incident to the Nuclear Regulatory Commission (NRC)within one hour, as required.3.CORRECTIVE STEPS TAKEN AND THE RESULTS ACHIEVED The event was reported to the NRC in Licensee Event Report 96-S01 on September 11, 1996, in FPL's 30 day report on the discovery of additional tampering of key-locked switches on August 14, 1996.CORRECTIVE STEPS TO AVOID FURTHER VIOLATIONS A.Security Procedure No.0006125,"Reporting of Safeguards Events" was revised to clarify the definition of"tampering" and the reportability determinations for similar events.B.Security event response guidance will be developed to provide for actions in response to an event that resulted from, or is suspected to have resulted from, deliberate or malicious acts directed against plant safety or security equipment.
security procedure 0006125,"Reporting
This action will be completed by October 31, 1996.5.Full compliance was achieved on September 11, 1996 with the completion of Item 3 above.VIOLATION B: Technical Specification 6.8.1.a requires that written procedures be established, implemented, and maintained covering the activities recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978.Appendix A, paragraph l.c includes administrative procedures for equipment control.Administrative Procedure No.2-0010123,"Administrative Control of Valves, Locks and Switches," Revision 73 implements this requirement with respect to administratively controlled keys.Step 8.2.1 of this procedure states in part that cubicles containing critical controls in remote locations shall be locked and the keys maintained under Administrative Control.Contrary to the above, on August 19, 1996, keys used for the control of Power Operated Relief Valves V1474 and V1475 located in the 2A and 2B electrical penetration rooms respectively, were located in the unlocked cubicles which house L-96-255 Attachment Re I to a Notice of Violation these switches.This is a Severity Level IV violation (Supplement I)RESPONSE: 1.FPL concurs with the violation, as clarified below.2.REASON FOR VIOLATION Re uirements Step 8.1.2.of Administrative Procedure (AP)No.2-0010123,"Administrative Control of Valves, Locks and Switches," states, in part, that: A valve, switch or fuse is placed under Administrative Control by: A.Physically locking the valve or switch Step 8.2.1.of AP No.2-0010123 states, in part, that: Cubicles and racks containing critical instrumentation and controls shall be locked and the keys maintained under administrative control.~Back round The power operated relief valve (PORV)electrical isolation switches are used to electrically isolate PORV operation from the control room in the event of a fire requiring reactor shutdown and evacuation of the control room.The electrical isolation switches are located in the electrical penetration room and are key locked switches housed in protective boxes.Since the electrical isolation switches themselves are key locked, the protective boxes in which the key locked electrical isolation switches are housed are not required to be locked in accordance with AP No.2-0010123.
of Safeguards
The keys used for the electrical isolation of the PORVs require administrative control in accordance with AP No.2-0010123.
Events," 6 will develop security event response guidance.DISTRIBUTION
Maintaining the keys for the PORV electrical isolation key locked switches in the unsecured switch boxes violated the administrative control requirements of AP No.2-0010123.  
CODE: IE01D COPIES RECEIVED:LTR
 
ENCL SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice
L-96-255 Attachment Re 1 to a Notice of Violation Discussion The cause of the violation was inadequate administrative controls to ensure adequate key accessibility and while, at the same time, maintaining key control.The development and review of the original procedures for control room inaccessibility focused only on the ability of the operators to carry out their shutdown functions.
of Violation Response NOTES: DOCKET g 05000335 05000389 RECIPIENT ID CODE/NAME PD2-3 PD INTERNAL: ACRS C FIL CENTER NRR DRC HHFB NRR/DRPM/PERB
The review was not sufficient in that, while the procedure assured the accessibility of keys post-control room evacuation, it did not ensure that the keys were maintained under adequate administrative control.Operating procedure ONOP 2-0030135,"Control Room Inaccessibility," stated that a backup set of the PORV electrical isolation switch keys are located in the switch boxes in the electrical penetration room (one set of keys is also maintained in the locked key box on the remote shutdown panel).Maintaining a set of keys in the switch boxes was intended to ensure that the keys were accessible to support control room evacuation.
OE DIR RGN2 FILE 01 EXTERNAL: LITCO BRYCE,J H NRC PDR COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME WIENS,L.AEOD/SPD/RAB
Procedure AP No.2-0010123, in step 8.1.2.A, lists one means of administrative control for switches to be the physical locking of the switch.Placing the keys inside the unsecured switch boxes, in accordance with ONOP 2-0030135, violated the administrative control requirements of AP No.2-0010123.
DEDRO NRR/DISP/PIPB
3.CORRECTIVE STEPS TAKEN AND THE RESULTS ACHIEVED A.The Unit 2 PORV electrical isolation switch keys were removed from the unsecured switch boxes.Control of the PORV electrical isolation switch keys was assigned to a utility nonlicensed operator, the senior nuclear plant operator (SNPO).B.The requirement for the PORV electrical isolation switch keys to be kept in the unsecured switch boxes was deleted from ONOP 2-0030135.
NRR/DRPM/PECB
This action was completed by August 29, 1996.CORRECTIVE STEPS TO AVOID FURTHER VIOLATIONS A.Physical custody of the PORV electrical isolation switch keys was assigned to the SNPO, who maintains them on the watchstanding shift key ring.This was done to ensure both the control of the keys as well as their availability to operate the switches in a timely manner, if required.This resolves the previous conflict between the operating procedure and administrative procedure.
NUDOCS-ABSTRACT
The chain of custody for the keys is maintained by the SNPO acknowledging custody of the keys, via his signature, on Check Sheet 2, Nuclear Plant  
OGC/HDS3 NOAC COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 D E N T'OTE TO ALL"RIDS" RECIPIENTS:
 
PLEASE HELP US TO REDUCE WASTE.TO HAVE YOUR NAME OR ORGANIZATION
L-96-255 Attachment Re I to a Notice of Violation 0 erator/SNPO Turnover Check Sheet of AP No.0010120, Conduct of~Oeretioos.
REMOVED FROM DISTRIBUTION
B.Procedures AP No.1-0010123 and AP No.2-0010123 (for Units 1 and 2, respectively) will be revised to add to each procedure a list of key rings and keys held by each watchstander.
LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 19 ENCL 19  
This will also ensure the periodic performance of a key inventory.
Florida Power 5 Light Company, P.O.Box 14000, Juno Beach, FL 33408.0420
The procedure revisions will be completed by October 31, 1996.C.The potential for additional previously unrecognized procedural conflicts in Unit 2 procedures AP No.2-0010123 and ONOP 2-0030135 concerning key and lock control was reviewed and no additional conflicts were identified.
OCT18$996 L-96-255 10 CFR 2.201 U.S.Nuclear Regulatory
D.The potential for previously unrecognized procedural conflicts in Unit 1 procedures AP No.1-0010123,"Administrative Control of Valves, Locks and Switches," and ONOP 1-0030135,"Control Room Inaccessibility," concerning key and lock control was reviewed and no additional conflicts were identified.
Commission
E.Programmatic improvements to the St.Lucie Plant's administrative control of keys will be made.The changes being considered include: 1)Stricter shift controls and accountability for keys checked out by the operating crew during the operating shift;2)A review of the key control log at shift turnover meetings to confirm shift to shift control of administratively controlled keys;3)Changes to the Operations and Security procedures to define actions and notifications to be taken in the event of loss of control of administratively controlled keys;and, 4)The establishment of a site-wide numbering system for controlled keys to ensure better response to missing or lost key events.The evaluation and implementation of changes determined to be required will be completed by November 29, 1996.The quality of St.Lucie Plant procedures, and revisions to those procedures, as well as the quality of procedures being developed to implement plant process  
Attn: Document Control Desk Washington, D.C.20555 Re: St.Lucie Units 1 and 2 Docket No.50-335 and 50-389 Reply to a Notice of Violation NRC S ecial Ins ection Re ort 96-16 Florida Power and Light Company has reviewed the subject Notice of Violation and, pursuant to 10 CFR 2.201, the responses to the violations
 
are attached.Very truly yours, T.F.Plunkett President Nuclear Division TFP/JAS/EJW
L-96-255 Attachment Re 1 to a Notice of Violation improvements, are the focus of management attention and action.In order to ensure that plant procedures are of consistent quality, St.Lucie Plant has formed the Procedures Development Group within the Information Services Department.
Attachment
It is intended that this group will ultimately be responsible for the development of, and revisions to, plant procedures.
cc: Stewart D.Ebneter, Regional Administrator, USNRC Region II Senior Resident Inspector, USNRC, St.Lucie Plant~.,'r j/l~9trr f 0250i 50 5000335 0 96i018 pDR ADOCK 0 6 an FPL Group company  
The focused accountability for the development, maintenance, and administration of plant procedures will help to ensure that procedural conflicts such as the one identified by this violation will be prevented from occurring for new procedures, and systematically identified and corrected, if present in existing procedures.
5.Full compliance was achieved on August 29, 1996, with the completion the actions identified in Item 3 above.}}
~~L-96-255 Attachment
Re I to a Notice of Violation VIOLATION A: 10 CFR 73.71, Reporting of Safeguards
Events, Appendix G, (a)(3)"Reportable
Safeguards
Events," requires the licensee to report to the NRC within one hour following discovery, followed by a written report within 30 days, events which cause interruption
of normal operations
through tampering with controls including the security system.The licensee's
Security Procedure, SP-0006125, Reporting of Safeguards
Events, Revision 9, dated April 20, 1995, Paragraph 8.2 (I)defines one of those specific events as being a"confirmed
tampering of suspicious
origin with safety or security equipment." Contrary to the above on July 29, 1996, the licensee failed to report the confirmed tampering with security equipment (locks)within one hour to the NRC.This is a Severity Level IV violation (Supplement
ID)RESPONSE: 1.FPL concurs with the violation.
2.REASON FOR VIOLATION The reason for the violation was personnel error in that the event was not correctly identified
as involving tampering.
A contributing
factor to the error was inadequate
procedural
guidance.The security event reporting procedure in use on July 26, 1996, did not provide a clear definition
of tampering nor clear guidance for making reportability
determinations
for tampering events.On July 26, 1996, glue was discovered
in the lock core of an entry door to the Unit 2 Control Element Drive Mechanism Control System (CEDMCS)room.Further inspection
revealed that several padlock/door
lock sets (a total of eleven locks)on both units had been similarly vandalized.
The affected locks were determined
not to adversely impact plant operations
or the Physical Security Plan.Based on this determination, it was incorrectly
interpreted
that this event did not constitute"tampering" as described in St.Lucie Plant Security Procedure No.0006125,"Reporting
of Safeguards
Events." The procedure required  
~~~~L-96-255 Attachment
Re 1 to a Notice of Violation"confirmed
tampering of suspicious
origin with safety or security equipment" to be reported as a Safeguards
Event.Failure to identify this incident as"tampering
with security/safety
equipment" resulted in utility personnel not reporting the incident to the Nuclear Regulatory
Commission (NRC)within one hour, as required.3.CORRECTIVE
STEPS TAKEN AND THE RESULTS ACHIEVED The event was reported to the NRC in Licensee Event Report 96-S01 on September 11, 1996, in FPL's 30 day report on the discovery of additional
tampering of key-locked switches on August 14, 1996.CORRECTIVE
STEPS TO AVOID FURTHER VIOLATIONS
A.Security Procedure No.0006125,"Reporting
of Safeguards
Events" was revised to clarify the definition
of"tampering" and the reportability
determinations
for similar events.B.Security event response guidance will be developed to provide for actions in response to an event that resulted from, or is suspected to have resulted from, deliberate
or malicious acts directed against plant safety or security equipment.
This action will be completed by October 31, 1996.5.Full compliance
was achieved on September 11, 1996 with the completion
of Item 3 above.VIOLATION B: Technical Specification
6.8.1.a requires that written procedures
be established, implemented, and maintained
covering the activities
recommended
in Appendix A of Regulatory
Guide 1.33, Revision 2, February 1978.Appendix A, paragraph l.c includes administrative
procedures
for equipment control.Administrative
Procedure No.2-0010123,"Administrative
Control of Valves, Locks and Switches," Revision 73 implements
this requirement
with respect to administratively
controlled
keys.Step 8.2.1 of this procedure states in part that cubicles containing
critical controls in remote locations shall be locked and the keys maintained
under Administrative
Control.Contrary to the above, on August 19, 1996, keys used for the control of Power Operated Relief Valves V1474 and V1475 located in the 2A and 2B electrical
penetration
rooms respectively, were located in the unlocked cubicles which house  
L-96-255 Attachment
Re I to a Notice of Violation these switches.This is a Severity Level IV violation (Supplement
I)RESPONSE: 1.FPL concurs with the violation, as clarified below.2.REASON FOR VIOLATION Re uirements Step 8.1.2.of Administrative
Procedure (AP)No.2-0010123,"Administrative
Control of Valves, Locks and Switches," states, in part, that: A valve, switch or fuse is placed under Administrative
Control by: A.Physically
locking the valve or switch Step 8.2.1.of AP No.2-0010123 states, in part, that: Cubicles and racks containing
critical instrumentation
and controls shall be locked and the keys maintained
under administrative
control.~Back round The power operated relief valve (PORV)electrical
isolation switches are used to electrically
isolate PORV operation from the control room in the event of a fire requiring reactor shutdown and evacuation
of the control room.The electrical
isolation switches are located in the electrical
penetration
room and are key locked switches housed in protective
boxes.Since the electrical
isolation switches themselves
are key locked, the protective
boxes in which the key locked electrical
isolation switches are housed are not required to be locked in accordance
with AP No.2-0010123.
The keys used for the electrical
isolation of the PORVs require administrative
control in accordance
with AP No.2-0010123.
Maintaining
the keys for the PORV electrical
isolation key locked switches in the unsecured switch boxes violated the administrative
control requirements
of AP No.2-0010123.  
L-96-255 Attachment
Re 1 to a Notice of Violation Discussion
The cause of the violation was inadequate
administrative
controls to ensure adequate key accessibility
and while, at the same time, maintaining
key control.The development
and review of the original procedures
for control room inaccessibility
focused only on the ability of the operators to carry out their shutdown functions.
The review was not sufficient
in that, while the procedure assured the accessibility
of keys post-control
room evacuation, it did not ensure that the keys were maintained
under adequate administrative
control.Operating procedure ONOP 2-0030135,"Control Room Inaccessibility," stated that a backup set of the PORV electrical
isolation switch keys are located in the switch boxes in the electrical
penetration
room (one set of keys is also maintained
in the locked key box on the remote shutdown panel).Maintaining
a set of keys in the switch boxes was intended to ensure that the keys were accessible
to support control room evacuation.
Procedure AP No.2-0010123, in step 8.1.2.A, lists one means of administrative
control for switches to be the physical locking of the switch.Placing the keys inside the unsecured switch boxes, in accordance
with ONOP 2-0030135, violated the administrative
control requirements
of AP No.2-0010123.
3.CORRECTIVE
STEPS TAKEN AND THE RESULTS ACHIEVED A.The Unit 2 PORV electrical
isolation switch keys were removed from the unsecured switch boxes.Control of the PORV electrical
isolation switch keys was assigned to a utility nonlicensed
operator, the senior nuclear plant operator (SNPO).B.The requirement
for the PORV electrical
isolation switch keys to be kept in the unsecured switch boxes was deleted from ONOP 2-0030135.
This action was completed by August 29, 1996.CORRECTIVE
STEPS TO AVOID FURTHER VIOLATIONS
A.Physical custody of the PORV electrical
isolation switch keys was assigned to the SNPO, who maintains them on the watchstanding
shift key ring.This was done to ensure both the control of the keys as well as their availability
to operate the switches in a timely manner, if required.This resolves the previous conflict between the operating procedure and administrative
procedure.
The chain of custody for the keys is maintained
by the SNPO acknowledging
custody of the keys, via his signature, on Check Sheet 2, Nuclear Plant  
L-96-255 Attachment
Re I to a Notice of Violation 0 erator/SNPO
Turnover Check Sheet of AP No.0010120, Conduct of~Oeretioos.
B.Procedures
AP No.1-0010123 and AP No.2-0010123 (for Units 1 and 2, respectively)
will be revised to add to each procedure a list of key rings and keys held by each watchstander.
This will also ensure the periodic performance
of a key inventory.
The procedure revisions will be completed by October 31, 1996.C.The potential for additional
previously
unrecognized
procedural
conflicts in Unit 2 procedures
AP No.2-0010123 and ONOP 2-0030135 concerning
key and lock control was reviewed and no additional
conflicts were identified.
D.The potential for previously
unrecognized
procedural
conflicts in Unit 1 procedures
AP No.1-0010123,"Administrative
Control of Valves, Locks and Switches," and ONOP 1-0030135,"Control Room Inaccessibility," concerning
key and lock control was reviewed and no additional
conflicts were identified.
E.Programmatic
improvements
to the St.Lucie Plant's administrative
control of keys will be made.The changes being considered
include: 1)Stricter shift controls and accountability
for keys checked out by the operating crew during the operating shift;2)A review of the key control log at shift turnover meetings to confirm shift to shift control of administratively
controlled
keys;3)Changes to the Operations
and Security procedures
to define actions and notifications
to be taken in the event of loss of control of administratively
controlled
keys;and, 4)The establishment
of a site-wide numbering system for controlled
keys to ensure better response to missing or lost key events.The evaluation
and implementation
of changes determined
to be required will be completed by November 29, 1996.The quality of St.Lucie Plant procedures, and revisions to those procedures, as well as the quality of procedures
being developed to implement plant process  
L-96-255 Attachment
Re 1 to a Notice of Violation improvements, are the focus of management
attention and action.In order to ensure that plant procedures
are of consistent
quality, St.Lucie Plant has formed the Procedures
Development
Group within the Information
Services Department.
It is intended that this group will ultimately
be responsible
for the development
of, and revisions to, plant procedures.
The focused accountability
for the development, maintenance, and administration
of plant procedures
will help to ensure that procedural
conflicts such as the one identified
by this violation will be prevented from occurring for new procedures, and systematically
identified
and corrected, if present in existing procedures.
5.Full compliance
was achieved on August 29, 1996, with the completion
the actions identified
in Item 3 above.
}}

Revision as of 15:43, 17 August 2019

Responds to Violations Noted in Insp Repts 50-335/96-16 & 50-389/96-16.Corrective Actions:Revised Security Procedure 0006125, Reporting of Safeguards Events, & Will Develop Security Event Response Guidance
ML17229A088
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 10/18/1996
From: Plunkett T
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
L-96-255, NUDOCS 9610250150
Download: ML17229A088 (13)


Text

CATEGORY j.REGULATORY INFORMATION-DISTRIBUTION SYSTEM (RIDS)*ACCESSION'NBR:9610250150 DOC.DATE: 96/10/18 NOTARIZED:

NO FACIL:50-335 St.Lucie Plant, Unit 1, Florida Power a Light Co.50-389 St.Lucie Plant, Unit 2, Florida Power 6 Light Co.AUTH.NAME AUTHOR AFFILIATION PLUNKETT,T.F.

Florida Power a Light Co.RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)

SUBJECT:

Responds to violations noted in insp repts 50-335/96-16 a 50-389/96-16.Corrective actions:revised security procedure 0006125,"Reporting of Safeguards Events," 6 will develop security event response guidance.DISTRIBUTION CODE: IE01D COPIES RECEIVED:LTR ENCL SIZE: TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES: DOCKET g 05000335 05000389 RECIPIENT ID CODE/NAME PD2-3 PD INTERNAL: ACRS C FIL CENTER NRR DRC HHFB NRR/DRPM/PERB OE DIR RGN2 FILE 01 EXTERNAL: LITCO BRYCE,J H NRC PDR COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 RECIPIENT ID CODE/NAME WIENS,L.AEOD/SPD/RAB DEDRO NRR/DISP/PIPB NRR/DRPM/PECB NUDOCS-ABSTRACT OGC/HDS3 NOAC COPIES LTTR ENCL 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 D E N T'OTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE.TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)ON EXTENSION 415-2083 TOTAL NUMBER OF COPIES REQUIRED: LTTR 19 ENCL 19 Florida Power 5 Light Company, P.O.Box 14000, Juno Beach, FL 33408.0420 OCT18$996 L-96-255 10 CFR 2.201 U.S.Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C.20555 Re: St.Lucie Units 1 and 2 Docket No.50-335 and 50-389 Reply to a Notice of Violation NRC S ecial Ins ection Re ort 96-16 Florida Power and Light Company has reviewed the subject Notice of Violation and, pursuant to 10 CFR 2.201, the responses to the violations are attached.Very truly yours, T.F.Plunkett President Nuclear Division TFP/JAS/EJW Attachment cc: Stewart D.Ebneter, Regional Administrator, USNRC Region II Senior Resident Inspector, USNRC, St.Lucie Plant~.,'r j/l~9trr f 0250i 50 5000335 0 96i018 pDR ADOCK 0 6 an FPL Group company

~~L-96-255 Attachment Re I to a Notice of Violation VIOLATION A: 10 CFR 73.71, Reporting of Safeguards Events, Appendix G, (a)(3)"Reportable Safeguards Events," requires the licensee to report to the NRC within one hour following discovery, followed by a written report within 30 days, events which cause interruption of normal operations through tampering with controls including the security system.The licensee's Security Procedure, SP-0006125, Reporting of Safeguards Events, Revision 9, dated April 20, 1995, Paragraph 8.2 (I)defines one of those specific events as being a"confirmed tampering of suspicious origin with safety or security equipment." Contrary to the above on July 29, 1996, the licensee failed to report the confirmed tampering with security equipment (locks)within one hour to the NRC.This is a Severity Level IV violation (Supplement ID)RESPONSE: 1.FPL concurs with the violation.

2.REASON FOR VIOLATION The reason for the violation was personnel error in that the event was not correctly identified as involving tampering.

A contributing factor to the error was inadequate procedural guidance.The security event reporting procedure in use on July 26, 1996, did not provide a clear definition of tampering nor clear guidance for making reportability determinations for tampering events.On July 26, 1996, glue was discovered in the lock core of an entry door to the Unit 2 Control Element Drive Mechanism Control System (CEDMCS)room.Further inspection revealed that several padlock/door lock sets (a total of eleven locks)on both units had been similarly vandalized.

The affected locks were determined not to adversely impact plant operations or the Physical Security Plan.Based on this determination, it was incorrectly interpreted that this event did not constitute"tampering" as described in St.Lucie Plant Security Procedure No.0006125,"Reporting of Safeguards Events." The procedure required

~~~~L-96-255 Attachment Re 1 to a Notice of Violation"confirmed tampering of suspicious origin with safety or security equipment" to be reported as a Safeguards Event.Failure to identify this incident as"tampering with security/safety equipment" resulted in utility personnel not reporting the incident to the Nuclear Regulatory Commission (NRC)within one hour, as required.3.CORRECTIVE STEPS TAKEN AND THE RESULTS ACHIEVED The event was reported to the NRC in Licensee Event Report 96-S01 on September 11, 1996, in FPL's 30 day report on the discovery of additional tampering of key-locked switches on August 14, 1996.CORRECTIVE STEPS TO AVOID FURTHER VIOLATIONS A.Security Procedure No.0006125,"Reporting of Safeguards Events" was revised to clarify the definition of"tampering" and the reportability determinations for similar events.B.Security event response guidance will be developed to provide for actions in response to an event that resulted from, or is suspected to have resulted from, deliberate or malicious acts directed against plant safety or security equipment.

This action will be completed by October 31, 1996.5.Full compliance was achieved on September 11, 1996 with the completion of Item 3 above.VIOLATION B: Technical Specification 6.8.1.a requires that written procedures be established, implemented, and maintained covering the activities recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978.Appendix A, paragraph l.c includes administrative procedures for equipment control.Administrative Procedure No.2-0010123,"Administrative Control of Valves, Locks and Switches," Revision 73 implements this requirement with respect to administratively controlled keys.Step 8.2.1 of this procedure states in part that cubicles containing critical controls in remote locations shall be locked and the keys maintained under Administrative Control.Contrary to the above, on August 19, 1996, keys used for the control of Power Operated Relief Valves V1474 and V1475 located in the 2A and 2B electrical penetration rooms respectively, were located in the unlocked cubicles which house L-96-255 Attachment Re I to a Notice of Violation these switches.This is a Severity Level IV violation (Supplement I)RESPONSE: 1.FPL concurs with the violation, as clarified below.2.REASON FOR VIOLATION Re uirements Step 8.1.2.of Administrative Procedure (AP)No.2-0010123,"Administrative Control of Valves, Locks and Switches," states, in part, that: A valve, switch or fuse is placed under Administrative Control by: A.Physically locking the valve or switch Step 8.2.1.of AP No.2-0010123 states, in part, that: Cubicles and racks containing critical instrumentation and controls shall be locked and the keys maintained under administrative control.~Back round The power operated relief valve (PORV)electrical isolation switches are used to electrically isolate PORV operation from the control room in the event of a fire requiring reactor shutdown and evacuation of the control room.The electrical isolation switches are located in the electrical penetration room and are key locked switches housed in protective boxes.Since the electrical isolation switches themselves are key locked, the protective boxes in which the key locked electrical isolation switches are housed are not required to be locked in accordance with AP No.2-0010123.

The keys used for the electrical isolation of the PORVs require administrative control in accordance with AP No.2-0010123.

Maintaining the keys for the PORV electrical isolation key locked switches in the unsecured switch boxes violated the administrative control requirements of AP No.2-0010123.

L-96-255 Attachment Re 1 to a Notice of Violation Discussion The cause of the violation was inadequate administrative controls to ensure adequate key accessibility and while, at the same time, maintaining key control.The development and review of the original procedures for control room inaccessibility focused only on the ability of the operators to carry out their shutdown functions.

The review was not sufficient in that, while the procedure assured the accessibility of keys post-control room evacuation, it did not ensure that the keys were maintained under adequate administrative control.Operating procedure ONOP 2-0030135,"Control Room Inaccessibility," stated that a backup set of the PORV electrical isolation switch keys are located in the switch boxes in the electrical penetration room (one set of keys is also maintained in the locked key box on the remote shutdown panel).Maintaining a set of keys in the switch boxes was intended to ensure that the keys were accessible to support control room evacuation.

Procedure AP No.2-0010123, in step 8.1.2.A, lists one means of administrative control for switches to be the physical locking of the switch.Placing the keys inside the unsecured switch boxes, in accordance with ONOP 2-0030135, violated the administrative control requirements of AP No.2-0010123.

3.CORRECTIVE STEPS TAKEN AND THE RESULTS ACHIEVED A.The Unit 2 PORV electrical isolation switch keys were removed from the unsecured switch boxes.Control of the PORV electrical isolation switch keys was assigned to a utility nonlicensed operator, the senior nuclear plant operator (SNPO).B.The requirement for the PORV electrical isolation switch keys to be kept in the unsecured switch boxes was deleted from ONOP 2-0030135.

This action was completed by August 29, 1996.CORRECTIVE STEPS TO AVOID FURTHER VIOLATIONS A.Physical custody of the PORV electrical isolation switch keys was assigned to the SNPO, who maintains them on the watchstanding shift key ring.This was done to ensure both the control of the keys as well as their availability to operate the switches in a timely manner, if required.This resolves the previous conflict between the operating procedure and administrative procedure.

The chain of custody for the keys is maintained by the SNPO acknowledging custody of the keys, via his signature, on Check Sheet 2, Nuclear Plant

L-96-255 Attachment Re I to a Notice of Violation 0 erator/SNPO Turnover Check Sheet of AP No.0010120, Conduct of~Oeretioos.

B.Procedures AP No.1-0010123 and AP No.2-0010123 (for Units 1 and 2, respectively) will be revised to add to each procedure a list of key rings and keys held by each watchstander.

This will also ensure the periodic performance of a key inventory.

The procedure revisions will be completed by October 31, 1996.C.The potential for additional previously unrecognized procedural conflicts in Unit 2 procedures AP No.2-0010123 and ONOP 2-0030135 concerning key and lock control was reviewed and no additional conflicts were identified.

D.The potential for previously unrecognized procedural conflicts in Unit 1 procedures AP No.1-0010123,"Administrative Control of Valves, Locks and Switches," and ONOP 1-0030135,"Control Room Inaccessibility," concerning key and lock control was reviewed and no additional conflicts were identified.

E.Programmatic improvements to the St.Lucie Plant's administrative control of keys will be made.The changes being considered include: 1)Stricter shift controls and accountability for keys checked out by the operating crew during the operating shift;2)A review of the key control log at shift turnover meetings to confirm shift to shift control of administratively controlled keys;3)Changes to the Operations and Security procedures to define actions and notifications to be taken in the event of loss of control of administratively controlled keys;and, 4)The establishment of a site-wide numbering system for controlled keys to ensure better response to missing or lost key events.The evaluation and implementation of changes determined to be required will be completed by November 29, 1996.The quality of St.Lucie Plant procedures, and revisions to those procedures, as well as the quality of procedures being developed to implement plant process

L-96-255 Attachment Re 1 to a Notice of Violation improvements, are the focus of management attention and action.In order to ensure that plant procedures are of consistent quality, St.Lucie Plant has formed the Procedures Development Group within the Information Services Department.

It is intended that this group will ultimately be responsible for the development of, and revisions to, plant procedures.

The focused accountability for the development, maintenance, and administration of plant procedures will help to ensure that procedural conflicts such as the one identified by this violation will be prevented from occurring for new procedures, and systematically identified and corrected, if present in existing procedures.

5.Full compliance was achieved on August 29, 1996, with the completion the actions identified in Item 3 above.