Line 12: Line 12:
| document type = Letter, Request for Additional Information (RAI)
| document type = Letter, Request for Additional Information (RAI)
| page count = 5
| page count = 5
| project =
| stage = RAI
}}
}}



Revision as of 09:50, 30 April 2019

Letter to Mr. Lash Three Mile Island Nuclear Station Unit 2-2011 Decommissioning Funding Status Report - Request for Additional Information License
ML112630451
Person / Time
Site: Three Mile Island Constellation icon.png
Issue date: 10/05/2011
From: Buckley J T
NRC/FSME/DWMEP/DURLD/RDB
To: Lash J H
GPU Nuclear
John Buckley 415-6607
References
Download: ML112630451 (5)


Text

October 5, 2011

Mr. James H. Lash Chief Nuclear Officer GPU Nuclear Inc. Three Mile Island Nuclear Station Route 441 South Post Office Box 480 Middletown, PA 17057-0480

SUBJECT:

THREE MILE ISLAND NUCLEAR STATION UNIT 2 - 2011 DECOMMISSIONING FUNDING STATUS REPORT - REQUEST FOR ADDITIONAL INFORMATION, LICENSE: DPR-73, DOCKET: 50-320

Dear Mr. Lash:

On March 30, 2011, GPU Nuclear, Inc. (GPU) submitted to the U.S. Nuclear Regulatory Commission (NRC) the 2011 Decommissioning Funding Status (DFS) report for Three Mile Island Nuclear Station, Unit 2 (TMI 2), (ADAMS Accession No. ML110950371) pursuant to 10 CFR 50.75(f)(1). The NRC has completed its initial review of the Decommissioning Funding Status (DFS) report and requests the following information to complete its analysis:

RAI #1: Decommissioning Costs Provide the amount of decommissioning funds estimated to be required under 10 CFR 50.75(c).

Basis: Per 10 CFR 50.75(f)(1), GPU's DFS report must include, at a minimum the amount of decommissioning funds estimated to be required under 10 CFR 50.75(b) and (c). The DFS report did not include the amount of funds estimated to be required based on the formula in 10 CFR 50.75(c). GPU's submittal states that the decommissioning fund estimate, pursuant to 10 CFR 50.75(b) and (c) is based upon a site specific decommissioning cost study, Decommissioning Cost Analysis for Three Mile Island Unit 2, dated January 2009 and escalated to 2010 dollars.

J. Lash 2 GPU should provide a response within 30 days from the date of this letter. If you have any questions regarding this letter, please contact John Buckley, at (301) 415-6607, or by e-mail at John.Buckley@nrc.gov Sincerely, /RA/ John T. Buckley, Senior Project Manager Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs

Docket No.: 50-320 License No.: DPR-73 cc: TMI-2 Distribution List

J. Lash 2 GPU should provide a response within 30 days from the date of this letter. If you have any questions regarding this letter, please contact John Buckley, at (301) 415-6607, or by e-mail at John.Buckley@nrc.gov. Sincerely, /RA/

John T. Buckley, Senior Project Manager Decommissioning and Uranium Recovery Licensing Directorate Division of Waste Management and Environmental Protection Office of Federal and State Materials and Environmental Management Programs

Docket No.: 50-320 License No.: DPR-73 cc: TMI-2 Distribution List

DISTRIBUTION: DWMEP r/f CRegan SHarwell LKauffman ML112630451 OFFICE: DWMEP DWMEP NRR DWMEP DWMEP NAME: JBuckley CHolston SHarwell BWatson JBuckley DATE: 09/ 22/2011 09/27/2011 10/03/2011 10/03/2011 10/05/2011 OFFICIAL RECORD COPY Three Mile Island - Unit 2 Service List cc: Mr. Danny L. Pace President, GPU Nuclear Inc. FirstEnergy Corporation Mail Stop: A-WAC-A3 341 White Pond Drive Akron, OH 44320 Mr. Greg Halnon Director, Regulatory Affairs FirstEnergy Corporation Mail Stop: A-WAC-A3 341 White Pond Drive Akron, OH 44320 Mr. Eric Epstein EFMR Monitoring Group 4100 Hillsdale Road Harrisburg, PA 17112 Mr. Wythe Keever The Patriot 812 Market Street Harrisburg, PA 17105 U.S. Environmental Protection Agency Region III Office ATTN: Mr. B. Hoffman EIS Coordinator 3ES30 1650 Arch Street Philadelphia, PA 17103 Ms. Jane Lee 183 Valley Road Etters, PA 17319

Mr. Walter W. Cohen, Consumer Advocate Department of Justice Strawberry Square, 14 th Floor Harrisburg, PA 17127 Mr. Mark E. Ford Manager PDMS Exelon Generation Company LLC P.O. Box 480 Middletown, PA 17057 Mr. Jerome Boyd PDMS Supervisor Exelon Generation Company LLC P.O. Box 480 Middletown, PA 17057 Mr. Glen E. Chick Site Vice President, TMI-1 Exelon Generation Company LLC P.O. Box 480 Middletown, PA 17057 Mr. David W. Jenkins, Esq. First Energy Legal Department 76 South Main St. Akron, OH 44308 Chairperson Dauphin County Board of Commissioners Dauphin County Courthouse Front and Market Streets Harrisburg, PA 17120 Mr. Ad Crable Lancaster New Era 8 West King Street Lancaster, PA 17601 Director Bureau of Radiation Protection Department of Environmental Protection 13 th Floor, Rachel Carson State Office Bldg. P. O. Box 8469 Harrisburg, PA 17105-8469

Senior Resident Inspector (TMI-1) U.S. Nuclear Regulatory Commission P.O. Box 311 Middletown, PA 17057 Dr. Judith H. Johnsrud Environmental Coalition on Nuclear Power 433 Orlando Avenue State College, PA 16803-3477

Mr. Dave Atherholt Site Regulatory Assurance Manager, TMI-1 Exelon Generation Company LLC P. O. Box 480 Middletown, PA 17057

Mr. Kevin L. Ostrowski Vice President GPU Nuclear Fleet Oversight Mail Stop: A-WAC-A3 341 White Pond Drive Akron, OH 44320 Mr. Michael J. Casey GPU Nuclear Responsible Engineer TMI-2 FirstEnergy Nuclear Operating Company Mail Stop: A-WAC-A3 341 White Pond Drive Akron, OH 44320