MONTHYEARML24220A2742024-08-15015 August 2024 Request for Additional Information Clarification Call Regarding Three Mile Island Station, Unit 2, Amended Post-Shutdown Decommissioning Activities Report, Rev. 6 ML24157A3672024-06-13013 June 2024 Updated Post-Shutdown Decommissioning Activities Report Request for Additional Information Transmittal Letter ML24011A2352024-01-11011 January 2024 Eco Request for Additional Information for 2023 License Amendment Request 1-11-24 ML23187A0202023-06-29029 June 2023 TMI Unit 2 – RAI Related to the Amended Post-Shutdown Decommissioning Activities Report ML23187A0332023-06-29029 June 2023 TMI Unit 2, PSDAR Rev. 5 RAIs ML23082A3432023-03-31031 March 2023 Enclosure - RAI - Three Mile Island, Unit 2 - Acceptance Review and Request for Additional Information for the Historic and Cultural Resources License Amendment Request - EPID: 2023-LLA-0026 ML22357A0142022-12-22022 December 2022 NRC Request for Additional Information Related to the TMI-2 Pdms Transition License Amendment Request ML22210A0882022-07-29029 July 2022 Enclosure - Three Mile Island, Unit No. 2 - Request for Additional Information for Requested Licensing Action Regarding Decommissioning Technical Specifications ML22143A8902022-05-23023 May 2022 Request for Additional information- TMI-1 ISFSI Only Physical Security License Amendment Request ML22125A0122022-04-28028 April 2022 Clarification RAI Partial Response Email from C Smith to a Snyder ML22110A0202022-04-19019 April 2022 Unit 1 Request for Additional Information ML22038A9362022-02-0707 February 2022 TMI2 Accident Analyses Questions ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML20164A0902020-06-10010 June 2020 Request for Additional Information Related to TMI-1 License Amendment Request to Delete Permanently Defueled Technical Specification 3/4.1.4 (L-2019-LLA-0250) ML19319B2082019-11-15015 November 2019 NRR E-mail Capture - Request for Additional Information Related to TMI-1 Request for Exemption from Portions of 10 CFR 50.47 and Part 50 Appendix E (L-2019-LLA-0216) ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML18220A7832018-08-0707 August 2018 NRR E-mail Capture - Request for Additional Information Related to TMI Fall 2017 Steam Generator Tube Inspection Report ML18212A2712018-07-31031 July 2018 NRR E-mail Capture - Request for Additional Information Related to Amendment Regarding Decommissioning ERO Staffing Changes ML17285B1962017-10-27027 October 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. ML17062A4912017-03-0303 March 2017 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative to RPV Threads in Flange Examination (CAC Nos. MF8712-MF8729) ML16356A4802016-12-21021 December 2016 NRR E-mail Capture - RAIs on TMI License Amendment Request for Approval of Changes to the Three Mile Island Nuclear Station Emergency Plan Related to Staffing ML16337A0072016-12-0101 December 2016 NRR E-mail Capture - Draft RAIs Three Mile Island Nuclear Station, Units 1 and 2, License Amendment Request for Approval of Changes to the Three Mile Island Nuclear Station Emergency Plan Related to Staffing ML16287A4042016-10-11011 October 2016 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML15230A5332015-08-18018 August 2015 Draft Request for Additional Information ML15020A7372015-03-0808 March 2015 Request for Additional Information Regarding Related to December 22, 2014, Report Submitted Pursuant to 10 CFR 50.46 ML14307A1172014-11-14014 November 2014 Request for Additional Information Regarding Relief Request RR-14-01 Concerning Alternative Root Mean Square Depth Sizing Requirements ML14240A4122014-09-0404 September 2014 Request for Additional Information Regarding License Amendment Request to Eliminate Certain Technical Specification Reporting Requirements (Tac MF0628) ML14134A3222014-05-22022 May 2014 Request for Additional Information Regarding Review of Three Mile Island Nuclear Station Unit 1 Cycle 20 Core Operating Limits Report ML14134A1722014-05-14014 May 2014 Draft RAIs in Support of NRC Staff Review of TMI Cycle 20 COLR ML14052A2592014-02-27027 February 2014 Request for Additional Information Regarding Proposed License Amendment Request to Revise Technical Specification Reporting Requirements ML14030A5832014-01-29029 January 2014 Draft Request for Additional Information Proposed Revision to Technical Specifications Reporting Requirements Exelon Generation Company, LLC Three Mile Island Nuclear Station, Unit 1 ML13266A2852013-10-21021 October 2013 Request for Additional Information on Three Mile Island Nuclear Station Unit 2 - post-shutdown Decommissioning Activities Report ML13276A6492013-10-0303 October 2013 Notification of Conduct of a Triennial Fire Protection Baseline Inspection ML13269A1792013-09-25025 September 2013 Draft Request for Additional Information ML13253A2252013-09-10010 September 2013 Draft Request for Additional Information ML13249A2072013-09-0505 September 2013 Draft Request for Additional Information ML13193A1752013-07-22022 July 2013 Request for Additional Information Regarding Revision to Pressure and Temperature Limit Curves and Exemption Request for Initial Reference Temperature Values ML13196A3382013-07-15015 July 2013 2013 Decommissioning Fund Report RAI ML13193A1452013-07-12012 July 2013 Electronic Transmission, Draft Request for Additional Information Regarding Proposed Revision to Pressure and Temperature Limit Curves and Exemption Request for Initial Reference Temperature Values (TAC Nos. MF0425 & MF0426) ML13176A4702013-06-26026 June 2013 Request for Additional Information Regarding Overall Integrated Plan in Response to Order Number EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13177A3902013-06-26026 June 2013 Electronic Transmission, Draft Request for Additional Information Regarding Overall Integrated Plan in Response to Order Number EA-12-051, Reliable Spent Fuel Pool Instrumentation ML13066A2442013-03-19019 March 2013 Request for Additional Information Regarding Fifth Inservice Test Interval Relief Request PR-01 Nuclear Services Closed Cooling Water Flow Measurement ML13066A1262013-03-0707 March 2013 Electronic Transmission, Draft Request for Additional Information Regarding Fifth Inservice Test Interval Relief Request PR-01 Nuclear Services Closed Cooling Water Flow Measurement ML13044A3212013-03-0505 March 2013 Request for Additional Information Regarding 30-Day Report for Emergency Core Cooling System Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML13045A6432013-02-25025 February 2013 Request for Additional Information Regarding Relief Request VR-01, Associated with the Fifth Inservice Testing Interval ML13051A3852013-02-25025 February 2013 Request for Additional Information Regarding End-of-Interval Relief Request RR-12-01, Pressure Nozzle-to-Head Weld Exams ML13050A6362013-02-20020 February 2013 Draft RAI Memo ML13044A3122013-02-13013 February 2013 Electronic Transmission, Draft Request for Additional Information Regarding 30-Day Report for Emergency Core Cooling System Model Changes Pursuant to the Requirements of 10 CFR 50.46 ML13044A6652013-02-13013 February 2013 Electronic Transmission, Draft Request for Additional Information Regarding Relief Request VR-01, Associated with the Fifth Inservice Testing Interval 2024-08-15
[Table view] |
Text
February 2022 TMI2 Accident Analyses Questions The licensee is seeking to use revised accident analyses to develop what systems, components, controls, and actions are necessary to safely move into a decommissioning phase at TMI2 from the PDMS. The PDMS is more of a static configuration whereas decommissioning will involve numerous activities to remove residual reactivity that remains following the 1979 accident.
NRC staff agree that non-mechanistic or incredible scenarios may not be useful unless the results of technical analyses are below established safety limits. However, conservative scenarios may be used to account for uncertainties. Because TMI2 represents a one-of-a-kind situation, uncertainties may be larger than for other reactor decommissioning sites.
The following questions and comments were developed as part of the initial review to determine if sufficient information is available to complete the acceptance review. The comments should not be viewed as comprehensive and additional comments may be provided as part of the acceptance review or after the acceptance review.
Overall, the staff will be looking for a description of the analyses that will allow the staff to verify the licensee results. Staff will be looking for the source term that is assumed including the concentrations and quantities of radionuclides that were included. The staff would look for a basis for radionuclides that are known to be present and not have been included. For example, the licensee could identify Table(s) X, Y, Z of references A, B, C as providing the source term information and provide the references in the submittal. Next, describe the release fractions, leakage pathway factors, airborne release fractions that are used. Then, what is the release point and release type (puff, continual). Finally, what is the atmospheric information that was used to translate concentrations at the release point to the receptor (X/Q, etc.) and where is the receptor located and for how long. NRC staff can piece together the information from historical references if that is what is relied upon but it is likely to be less efficient and involve potentially more questions than if this information is provided by the licensee.
- 1) What is the source term (radionuclides) analyzed in terms of characterization data and in what references (Table #s) is this information found? What is the uncertainty in the source term data?
- 2) The reactor building fire appears to be most limiting of the currently analyzed scenarios.
Is credit being taken for the reactor building or not? If the doors are open would this analyzed scenario be most limiting?
- 3) Where are the fuel and energy sources that will be introduced during decommissioning described? Can any of these result in a new more limiting scenario?
- 4) What radioactive material is located outside of the reactor building? Do all of those locations have HEPA filtration? Would a fire outside of the reactor building with different material and a different release point be bound by scaling the reactor building fire result to account for no HEPA filter?
- 5) References cite the source term uncertainty as plus or minus 50%. Given the 97 mrem dose result is very close to the 100 mrem limit, how has uncertainty in the source term been accounted for?
- 6) The ratios of the results for different radionuclides may require further explanation. For some scenarios one would expect the ratio of key fission products (Sr, Cs) to actinides (Pu) would be fairly similar but some are substantially different.
- 7) The radionuclides evaluated for different scenarios are different. One usually starts with the complete list of known radioactivity and then performs some sort of screening to eliminate isotopes with low contribution to dose.
- 8) The revised document discussed a normalized composite mix. Please provide documentation describing what this is and how it was calculated.
- 9) Please provide the reference Reactor Building Fire Analysis.
- 10) It is good to establish limits (dose rate cutoffs) substantially below the regulations to allow for a factor of safety and account for uncertainties. NRC staff would like to be able to establish how those limits were derived.