==2.0 REFERENCES==
==2.0 REFERENCES==
  ............................................................................................................. 8 2.1 Performance References .............................................................................................. 8 2.2 Developmental References  
  ............................................................................................................. 8  
 
===2.1 Performance===
 
References .............................................................................................. 8 2.2 Developmental References  
........................................................................................... 8 3.0 PRECAUTIONS AND LIMITATIONS ......................................................................... 14  
........................................................................................... 8 3.0 PRECAUTIONS AND LIMITATIONS ......................................................................... 14  


Line 55: Line 59:
===4.1 Preliminar===
===4.1 Preliminar===
y Actions ..................................................................................................... 1 6 4.2 Special Tools, Meas uring and Test Equipment, Parts, and Supplies .......................... 22 4.3 Field Preparations .......................................................................................................
y Actions ..................................................................................................... 1 6 4.2 Special Tools, Meas uring and Test Equipment, Parts, and Supplies .......................... 22 4.3 Field Preparations .......................................................................................................
24 4.4 Approvals and No tifications ........................................................................................ 30 5.0 ACCEPTANCE CRITERIA ......................................................................................... 31 6.0 PERFORMANCE ........................................................................................................ 39 6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOL ER LOGIC .................................... 39 6.2 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOL ER LOGIC .................................... 43 6.3 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER LOGIC ....................................... 46 6.4 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER LOGIC ....................................... 49 6.5 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER LOGIC ...................................... 52 6.6 2-PMCL-30-179-B, SIS PUMP 2B-B ROOM COOLER LOGIC .................................. 55 6.7 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER LOGIC ........................................................................................................ 58 6.8 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER LOGIC ......................................................................................................................... 61 6.9 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A LOGIC .................... 64 6.10 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B LOGIC .................... 69 6.11 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A LOGIC .................... 74 6.12 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B LOGIC .................... 79 WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 4 of 144  
24 4.4 Approvals and No tifications ........................................................................................ 30  
 
===5.0 ACCEPTANCE===
CRITERIA ......................................................................................... 31  
 
===6.0 PERFORMANCE===
........................................................................................................ 39 6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOL ER LOGIC .................................... 39 6.2 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOL ER LOGIC .................................... 43 6.3 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER LOGIC ....................................... 46 6.4 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER LOGIC ....................................... 49 6.5 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER LOGIC ...................................... 52 6.6 2-PMCL-30-179-B, SIS PUMP 2B-B ROOM COOLER LOGIC .................................. 55 6.7 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER LOGIC ........................................................................................................ 58 6.8 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER LOGIC ......................................................................................................................... 61 6.9 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A LOGIC .................... 64 6.10 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B LOGIC .................... 69 6.11 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A LOGIC .................... 74 6.12 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B LOGIC .................... 79 WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 4 of 144  


Table of Contents (continued) 6.13 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A LOGIC .............................. 84 6.14 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B LOGIC .............................. 89 6.15 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER AIR FLOW .............................. 94 6.16 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER AIR FLOW .............................. 95 6.17 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER AIR FLOW ................................. 96 6.18 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER AIR FLOW ................................. 98 6.19 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER AIR FLOW .............................. 100 6.20 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER AIR FLOW .............................. 102 6.21 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER AIR FLOW ....................................................................................................................... 10 4 6.22 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER AIR FLOW ....................................................................................................................... 10 6 6.23 2-PMCL-30-186, PENETRATION ROOM EL 692 COOLER 2A-A AIR FLOW ....................................................................................................................... 10 8 6.24 2-PMCL-30-187, PENETRATION ROOM EL 692 COOLER 2B-B AIR FLOW ....................................................................................................................... 11 0 6.25 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A AIR FLOW ....................................................................................................................... 11 2 6.26 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B AIR FLOW ....................................................................................................................... 11 4 6.27 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A AIR FLOW ...................... 116 6.28 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B AIR FLOW ...................... 118 6.29 HIGH ENERGY LINE BRE AK (HELB) DETECTION. ............................................... 120 6.29.2 CVCS LETDOWN HEAT EXCHANGER ROOM HELB DETECTION ............................................................................................... 122 6.29.3 RHR PUMP ROOM 2A HELB DETECTION ............................................... 125 6.29.4 RHR PUMP ROOM 2B HELB DETECTION ............................................... 127 6.29.5 RHR HEAT EXCHANGER ROOM 2A HELB DETECTION ........................ 129 6.29.6 RHR HEAT EXCHANGER ROOM 2B HELB DETECTION ........................ 131 7.0 POST PERFORMANC E ACTIVITIE S ...................................................................... 133 8.0 RECORDS ................................................................................................................ 13 3
Table of Contents (continued) 6.13 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A LOGIC .............................. 84 6.14 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B LOGIC .............................. 89 6.15 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER AIR FLOW .............................. 94 6.16 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER AIR FLOW .............................. 95 6.17 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER AIR FLOW ................................. 96 6.18 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER AIR FLOW ................................. 98 6.19 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER AIR FLOW .............................. 100 6.20 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER AIR FLOW .............................. 102 6.21 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER AIR FLOW ....................................................................................................................... 10 4 6.22 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER AIR FLOW ....................................................................................................................... 10 6 6.23 2-PMCL-30-186, PENETRATION ROOM EL 692 COOLER 2A-A AIR FLOW ....................................................................................................................... 10 8 6.24 2-PMCL-30-187, PENETRATION ROOM EL 692 COOLER 2B-B AIR FLOW ....................................................................................................................... 11 0 6.25 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A AIR FLOW ....................................................................................................................... 11 2 6.26 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B AIR FLOW ....................................................................................................................... 11 4 6.27 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A AIR FLOW ...................... 116 6.28 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B AIR FLOW ...................... 118 6.29 HIGH ENERGY LINE BRE AK (HELB) DETECTION. ............................................... 120 6.29.2 CVCS LETDOWN HEAT EXCHANGER ROOM HELB DETECTION ............................................................................................... 122 6.29.3 RHR PUMP ROOM 2A HELB DETECTION ............................................... 125 6.29.4 RHR PUMP ROOM 2B HELB DETECTION ............................................... 127 6.29.5 RHR HEAT EXCHANGER ROOM 2A HELB DETECTION ........................ 129 6.29.6 RHR HEAT EXCHANGER ROOM 2B HELB DETECTION ........................ 131 7.0 POST PERFORMANC E ACTIVITIE S ...................................................................... 133  
 
===8.0 RECORDS===
................................................................................................................ 13 3
WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 5 of 144  
WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 5 of 144  


Line 68: Line 81:
==1.0 INTRODUCTION==
==1.0 INTRODUCTION==
1.1 Test Objectives A. Demonstrate the proper operation of the Unit 2 Auxiliary Building Engineered Safety Features (ESF) Room/Area Coolers. B. Demonstrate the proper operation of the Essential Raw Cooling Water (ERCW)
1.1 Test Objectives A. Demonstrate the proper operation of the Unit 2 Auxiliary Building Engineered Safety Features (ESF) Room/Area Coolers. B. Demonstrate the proper operation of the Essential Raw Cooling Water (ERCW)
Flow Control Valves associated with their respective ESF Room/Area Coolers. C. Demonstrate the proper operation of the High E nergy Line Break (HELB) detection equipment and alarms.
Flow Control Valves associated with their respective ESF Room/Area Coolers. C. Demonstrate the proper operation of the High E nergy Line Break (HELB) detection equipment and alarms.  
1.2 Scope A. This test demonstrates the operability of the Unit 2 Auxi liary Building ESF Room/Area Coolers and Fans to ensure the following: 1. The required ESF coolers start upon receipt of their associated room/area Hi-Tem perature signal. 2. The required Unit 2 ESF cooler s start upon receipt of a simulated Auxiliary Building Isolati on (ABI) signal and stop upon reset of ABI signal.  (See also 1.2D) 3. The ESF coolers can be controlled manually by local handswitch.  
 
===1.2 Scope===
 
A. This test demonstrates the operability of the Unit 2 Auxi liary Building ESF Room/Area Coolers and Fans to ensure the following: 1. The required ESF coolers start upon receipt of their associated room/area Hi-Tem perature signal. 2. The required Unit 2 ESF cooler s start upon receipt of a simulated Auxiliary Building Isolati on (ABI) signal and stop upon reset of ABI signal.  (See also 1.2D) 3. The ESF coolers can be controlled manually by local handswitch.  
: 4. The ESF room/area coolers maintain desired air flows. 5. The required Unit 2 Au xiliary Building ESF cooler ERCW supply valves open in a maximum of 10 seconds upon start of their associated cooler.
: 4. The ESF room/area coolers maintain desired air flows. 5. The required Unit 2 Au xiliary Building ESF cooler ERCW supply valves open in a maximum of 10 seconds upon start of their associated cooler.
NOTE ERCW flowrates are verified during perform ance of 2-PTI-067-02, ERCW System Flow Balance. B. The required HELB indications an d annunciations respond appropriately upon reciept of their associated r oom/area Hi-Temper ature signal.
NOTE ERCW flowrates are verified during perform ance of 2-PTI-067-02, ERCW System Flow Balance. B. The required HELB indications an d annunciations respond appropriately upon reciept of their associated r oom/area Hi-Temper ature signal.
Line 76: Line 92:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


1.2 Scope (continued)  
===1.2 Scope===
(continued)  


C. ESF pump room cooler start upon associated Pump Start signal logic is verified when each associated ESF pump is tested as shown below:
C. ESF pump room cooler start upon associated Pump Start signal logic is verified when each associated ESF pump is tested as shown below:
Line 86: Line 103:


==2.0 REFERENCES==
==2.0 REFERENCES==
2.1 Performance References A. SMP-9.0, Rev 0, Conduct of Test B. GTM-05, HVAC Air Balance (Draft)
 
===2.1 Performance===
References A. SMP-9.0, Rev 0, Conduct of Test B. GTM-05, HVAC Air Balance (Draft)
C. 0-SOI-67.01, Essential Raw Cooling Water System (Draft) 2.2 Developmental References A. Final Safety Analysis Report, Amendment 99 1. FSAR Section 9.2.1, Essential Raw Cooling Water (ERCW) 2. FSAR Section 9.4.5.3, Auxiliary Building Safety Features (ESF) Equipment Coolers 3. FSAR Table 14.2-1, S heets 4 & 5, Essential Ra w Cooling Water System Test Summary 4. FSAR Table 14.2-1, S heets 36 & 37, Auxiliary Bu ilding Ventilation System B. Drawings 1. Flow Diagrams a. 2-47W866-8, Rev 0, HEAT ING, COOLING & VENTILATING AIR FLOW DRA 54923-070, Rev 0  
C. 0-SOI-67.01, Essential Raw Cooling Water System (Draft) 2.2 Developmental References A. Final Safety Analysis Report, Amendment 99 1. FSAR Section 9.2.1, Essential Raw Cooling Water (ERCW) 2. FSAR Section 9.4.5.3, Auxiliary Building Safety Features (ESF) Equipment Coolers 3. FSAR Table 14.2-1, S heets 4 & 5, Essential Ra w Cooling Water System Test Summary 4. FSAR Table 14.2-1, S heets 36 & 37, Auxiliary Bu ilding Ventilation System B. Drawings 1. Flow Diagrams a. 2-47W866-8, Rev 0, HEAT ING, COOLING & VENTILATING AIR FLOW DRA 54923-070, Rev 0  


Line 93: Line 112:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


2.2 Developmental References (continued)  
===2.2 Developmental===
References (continued)  
: 2. Electrical  a. 1-45W600-30-4, Rev 26, VENTILATING SYSTEM SCHEMATIC DIAGRAM b. 2-45W600-57-37, SEPERATION &
: 2. Electrical  a. 1-45W600-30-4, Rev 26, VENTILATING SYSTEM SCHEMATIC DIAGRAM b. 2-45W600-57-37, SEPERATION &
MISC AUX RELAYS SCHEMATIC DIAGRAM, [Later]  
MISC AUX RELAYS SCHEMATIC DIAGRAM, [Later]  
Line 121: Line 141:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


2.2 Developmental References (continued)  
===2.2 Developmental===
References (continued)  
: l. 45N1693-4 (AC), Rev, AAB, SEP ERATION AUX RELAY PNL 1-R-78 CONNECTION DIAGRAM m. 45W2770-1, Rev 18, 480V CONT. & AUX BLDG VENT BD 2A1-A CONNECTION DIAGRAM n. 45W2770-2, Rev 6, 480V CONT. & AUX BLDG VENT BD 2A1-A CONNECTION DIAGRAM o. 45W2772-2, Rev 13, 480V CONT. & AUX BLDG VENT BD 2B1-B CONNECTION DIAGRAM p. 45W2772-3, Rev 14, 480V CONT. & AUX BLDG VENT BD 2B1-B CONNECTION DIAGRAM 3. Mechanical a. 2-47W600-188, Rev 0, INSTRUMENTS AND CONTROLS DRA 53788-041, Rev 0  
: l. 45N1693-4 (AC), Rev, AAB, SEP ERATION AUX RELAY PNL 1-R-78 CONNECTION DIAGRAM m. 45W2770-1, Rev 18, 480V CONT. & AUX BLDG VENT BD 2A1-A CONNECTION DIAGRAM n. 45W2770-2, Rev 6, 480V CONT. & AUX BLDG VENT BD 2A1-A CONNECTION DIAGRAM o. 45W2772-2, Rev 13, 480V CONT. & AUX BLDG VENT BD 2B1-B CONNECTION DIAGRAM p. 45W2772-3, Rev 14, 480V CONT. & AUX BLDG VENT BD 2B1-B CONNECTION DIAGRAM 3. Mechanical a. 2-47W600-188, Rev 0, INSTRUMENTS AND CONTROLS DRA 53788-041, Rev 0  


Line 136: Line 157:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


2.2 Developmental References (continued)  
===2.2 Developmental===
References (continued)  
: 5. Other a. 47B601-55-25 (AC), Rev D, ELECTRICAL INSTRUMENT TABULATION b. 2-45B655-6A, Rev 0, MAIN CONTROL ROOM ANNUNCIATOR INPUTS WINDOW BOX XA-55-6A c. 2-45B655-E6A, Rev 0, ANNUN CIATOR WINDOW BOX XA-55-6A ENGRAVING C. Documents a. SMP-4.0, Rev 2, Syst em Completion and Turnover b. SMP-8.0, Rev 3, Administration of Preoperational Test Procedures c. GTM-03, HVAC Gravity Dampers, Fire Dampers, and Fire Doors, (Draft) d. WBN2-30AB-4001, Rev 1, Auxiliar y Building Heating, Ventilation, Air Conditioning System (30, 31, 44) e. WBN2-67-4002, Rev 1, Essential Raw Cooling Water System, System 67 f. G-37, Rev 4, Testing and Balancing of HVAC Systems During Installation, Modification, and Maintenance g. 2-TSD-030A-01, Rev 1, Select Auxiliary Building ESF Coolers and HELB Detection h. 0-PI-OPS-1.1, Rev 3, Jumper Control Process i. 2-PTI-067-02, ERCW System Flow Balance (Draft)  
: 5. Other a. 47B601-55-25 (AC), Rev D, ELECTRICAL INSTRUMENT TABULATION b. 2-45B655-6A, Rev 0, MAIN CONTROL ROOM ANNUNCIATOR INPUTS WINDOW BOX XA-55-6A c. 2-45B655-E6A, Rev 0, ANNUN CIATOR WINDOW BOX XA-55-6A ENGRAVING C. Documents a. SMP-4.0, Rev 2, Syst em Completion and Turnover b. SMP-8.0, Rev 3, Administration of Preoperational Test Procedures c. GTM-03, HVAC Gravity Dampers, Fire Dampers, and Fire Doors, (Draft) d. WBN2-30AB-4001, Rev 1, Auxiliar y Building Heating, Ventilation, Air Conditioning System (30, 31, 44) e. WBN2-67-4002, Rev 1, Essential Raw Cooling Water System, System 67 f. G-37, Rev 4, Testing and Balancing of HVAC Systems During Installation, Modification, and Maintenance g. 2-TSD-030A-01, Rev 1, Select Auxiliary Building ESF Coolers and HELB Detection h. 0-PI-OPS-1.1, Rev 3, Jumper Control Process i. 2-PTI-067-02, ERCW System Flow Balance (Draft)  
: j. 2-PTI-074-01, Residual H eat Removal System (Draft) k. 2-PTI-063-5A, Safety Injection Syst em Pump/Valve Logic Test (Draft) l. 2-PTI-063-5B, Safety Injection Syst em Pump/Valve Logic Test (Draft) m. 2-PTI-062-01, Charging and Letdown Logic Test (Draft) n. 2-PTI-072-01, Containment Spray Pump/Valve Logic Test (Draft)
: j. 2-PTI-074-01, Residual H eat Removal System (Draft) k. 2-PTI-063-5A, Safety Injection Syst em Pump/Valve Logic Test (Draft) l. 2-PTI-063-5B, Safety Injection Syst em Pump/Valve Logic Test (Draft) m. 2-PTI-062-01, Charging and Letdown Logic Test (Draft) n. 2-PTI-072-01, Containment Spray Pump/Valve Logic Test (Draft)
Line 143: Line 165:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


2.2 Developmental References (continued)  
===2.2 Developmental===
References (continued)  
: o. 2-PTI-262-01, Integrated Safeguards Test (Draft) p. 2-PTI-262-02, Integrated Safeguards Test (Draft) q. Scaling and Setpoint Documents (1) SSD-2-TS-30-175, RHR Pump Ro om Cooler Fan A-A, [Later] (2) SSD-2-TS-30-176, RHR Pump Ro om Cooler Fan B-B, [Later] (3) SSD-2-TS-30-177, CS Pump R oom Cooler Fan A-A, [Later] (4) SSD-2-TS-30-178, CS Pump R oom Cooler Fan B-B, [Later] (5) SSD-2-TS-30-179, SIS Pump Ro om Cooler Fan B-B, [Later] (6) SSD-2-TS-30-180, SIS Pump Ro om Cooler Fan A-A, [Later] (7) SSD-2-TS-30-182, Charging Pump Room Cooler Fan B-B, [Later] (8) SSD-2-TS-30-183, Charging Pump Room Cooler Fan A-A, [Later] (9) SSD-2-TS-30-186A, Penetration R oom Cooler, El 692, Fan A-A, [Later] (10) SSD-2-TS-30-186B, Penetration R oom Cooler, El 692, Fan A-A, [Later] (11) SSD-2-TS-30-187A, Penetration R oom Cooler, El 692, Fan B-B, [Later] (12) SSD-2-TS-30-187B, Penetration R oom Cooler, El 692, Fan B-B, [Later] (13) SSD-2-TS-30-196A, Penetration R oom Cooler, El 713, Fan A-A, [Later] (14) SSD-2-TS-30-196B, Penetration R oom Cooler, El 713, Fan A-A, [Later] (15) SSD-2-TS-30-197A, Penetration R oom Cooler, El 713, Fan B-B, [Later] (16) SSD-2-TS-30-197B, Penetration R oom Cooler, El 713, Fan B-B, [Later]
: o. 2-PTI-262-01, Integrated Safeguards Test (Draft) p. 2-PTI-262-02, Integrated Safeguards Test (Draft) q. Scaling and Setpoint Documents (1) SSD-2-TS-30-175, RHR Pump Ro om Cooler Fan A-A, [Later] (2) SSD-2-TS-30-176, RHR Pump Ro om Cooler Fan B-B, [Later] (3) SSD-2-TS-30-177, CS Pump R oom Cooler Fan A-A, [Later] (4) SSD-2-TS-30-178, CS Pump R oom Cooler Fan B-B, [Later] (5) SSD-2-TS-30-179, SIS Pump Ro om Cooler Fan B-B, [Later] (6) SSD-2-TS-30-180, SIS Pump Ro om Cooler Fan A-A, [Later] (7) SSD-2-TS-30-182, Charging Pump Room Cooler Fan B-B, [Later] (8) SSD-2-TS-30-183, Charging Pump Room Cooler Fan A-A, [Later] (9) SSD-2-TS-30-186A, Penetration R oom Cooler, El 692, Fan A-A, [Later] (10) SSD-2-TS-30-186B, Penetration R oom Cooler, El 692, Fan A-A, [Later] (11) SSD-2-TS-30-187A, Penetration R oom Cooler, El 692, Fan B-B, [Later] (12) SSD-2-TS-30-187B, Penetration R oom Cooler, El 692, Fan B-B, [Later] (13) SSD-2-TS-30-196A, Penetration R oom Cooler, El 713, Fan A-A, [Later] (14) SSD-2-TS-30-196B, Penetration R oom Cooler, El 713, Fan A-A, [Later] (15) SSD-2-TS-30-197A, Penetration R oom Cooler, El 713, Fan B-B, [Later] (16) SSD-2-TS-30-197B, Penetration R oom Cooler, El 713, Fan B-B, [Later]
WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 13 of 144  
WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 13 of 144  
Line 149: Line 172:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


2.2 Developmental References (continued)  
===2.2 Developmental===
References (continued)  


   (17) SSD-2-TS-30-201A, Pipe Chas e Coolers Fan 2A-A, [Later] (18) SSD-2-TS-30-201B, Pipe Chas e Coolers Fan 2A-A, [Later] (19) SSD-2-TS-30-202A, Pipe Chas e Coolers Fan 2B-B, [Later] (20) SSD-2-TS-30-202B, Pipe Chas e Coolers Fan 2B-B, [Later] (21) SSD-2-TS-30-5235A, CVCS Letdown Heat Exchanger Room Hi Temperature, [Later] (22) SSD-2-TS-30-5235B, CVCS Letdown Heat Exchanger Room Hi Temperature, [Later] (23) SSD-2-TS-30-5236A, RHR Pump Room A Hi Temperature, [Later] (24) SSD-2-TS-30-5236B, RHR Pump Room A Hi Temperature, [Later] (25) SSD-2-TS-30-5237A, RHR Pump Room B Hi Temperature, [Later] (26) SSD-2-TS-30-5237B, RHR Pump Room B Hi Temperature, [Later] (27) SSD-2-TS-30-5238A, RHR Heat Exchanger Room A Hi Temperature, [Later] (28) SSD-2-TS-30-5238B, RHR Heat Exchanger Room A Hi Temperature, [Later] (29) SSD-2-TS-30-5239A, RHR Heat Exchanger Room B Hi Temperature, [Later] (30) SSD-2-TS-30-5239B, RHR Heat Exchanger Room B Hi Temperature, [Later]
   (17) SSD-2-TS-30-201A, Pipe Chas e Coolers Fan 2A-A, [Later] (18) SSD-2-TS-30-201B, Pipe Chas e Coolers Fan 2A-A, [Later] (19) SSD-2-TS-30-202A, Pipe Chas e Coolers Fan 2B-B, [Later] (20) SSD-2-TS-30-202B, Pipe Chas e Coolers Fan 2B-B, [Later] (21) SSD-2-TS-30-5235A, CVCS Letdown Heat Exchanger Room Hi Temperature, [Later] (22) SSD-2-TS-30-5235B, CVCS Letdown Heat Exchanger Room Hi Temperature, [Later] (23) SSD-2-TS-30-5236A, RHR Pump Room A Hi Temperature, [Later] (24) SSD-2-TS-30-5236B, RHR Pump Room A Hi Temperature, [Later] (25) SSD-2-TS-30-5237A, RHR Pump Room B Hi Temperature, [Later] (26) SSD-2-TS-30-5237B, RHR Pump Room B Hi Temperature, [Later] (27) SSD-2-TS-30-5238A, RHR Heat Exchanger Room A Hi Temperature, [Later] (28) SSD-2-TS-30-5238B, RHR Heat Exchanger Room A Hi Temperature, [Later] (29) SSD-2-TS-30-5239A, RHR Heat Exchanger Room B Hi Temperature, [Later] (30) SSD-2-TS-30-5239B, RHR Heat Exchanger Room B Hi Temperature, [Later]
Line 156: Line 180:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


3.0 PRECAUTIONS AND LIMITATIONS A. Standard precautions shall be followed for working around energized electrical equipment in accordance with TVA Safety Manual Procedure 1021. B. Steps may be repeated if all components cannot be tested in a step. However, if the test has been exited, prerequi site steps must be re-verified and a Chronological Test Log (CTL) entry made. C. Component tags and labels may differ sli ghtly (abbreviations, punctuation, letter case, etc.) from the description given in this test. If this situation occurs, it shall NOT be considered a test deficiency or procedure deviation. It shall be documented in the CTL and reconciled by way of a plant labeling request or drawing discrepancy or single-line dat e typo change in the procedure as appropriate. D. All wires removed/lifted from a termi nal shall be identified and taped or covered with an insulator to prevent personnel or equipment hazard and possible spurious initiations. The wires shoul d be grouped together and labeled with the work implementing document number that required them to be lifted if left unattended. E. All open problems are to be tracked by a corrective action document and entered on the appropriate system punchlist. F. Problems identified during the test s hall be annotated on the Chronological Test Log (CTL) from SMP-9.0 including a descr iption of the problem, the procedure step when/where the problem was identified, corrective action steps taken to resolve the problem, and the number of the corrective action document, if one was required. G. Observe all Radiation Protection (RP) requirements when working in or near contaminated areas. H. All terminal points and connections are to be considered energized.
===3.0 PRECAUTIONS===
AND LIMITATIONS A. Standard precautions shall be followed for working around energized electrical equipment in accordance with TVA Safety Manual Procedure 1021. B. Steps may be repeated if all components cannot be tested in a step. However, if the test has been exited, prerequi site steps must be re-verified and a Chronological Test Log (CTL) entry made. C. Component tags and labels may differ sli ghtly (abbreviations, punctuation, letter case, etc.) from the description given in this test. If this situation occurs, it shall NOT be considered a test deficiency or procedure deviation. It shall be documented in the CTL and reconciled by way of a plant labeling request or drawing discrepancy or single-line dat e typo change in the procedure as appropriate. D. All wires removed/lifted from a termi nal shall be identified and taped or covered with an insulator to prevent personnel or equipment hazard and possible spurious initiations. The wires shoul d be grouped together and labeled with the work implementing document number that required them to be lifted if left unattended. E. All open problems are to be tracked by a corrective action document and entered on the appropriate system punchlist. F. Problems identified during the test s hall be annotated on the Chronological Test Log (CTL) from SMP-9.0 including a descr iption of the problem, the procedure step when/where the problem was identified, corrective action steps taken to resolve the problem, and the number of the corrective action document, if one was required. G. Observe all Radiation Protection (RP) requirements when working in or near contaminated areas. H. All terminal points and connections are to be considered energized.
Instrumentation must be used to determi ne if the circuits are de-energized. I. Retermination of lifted leads requires that their restored bend radius is equal to or greater than the as found condition. J. Vibration testing will be performed dur ing performance of GTM-05, HVAC Air Balance. K. Backdraft damper testing will be perf ormed during performance of GTM-03, HVAC Gravity Dampers, Fire Dampers, and Fire Doors.
Instrumentation must be used to determi ne if the circuits are de-energized. I. Retermination of lifted leads requires that their restored bend radius is equal to or greater than the as found condition. J. Vibration testing will be performed dur ing performance of GTM-05, HVAC Air Balance. K. Backdraft damper testing will be perf ormed during performance of GTM-03, HVAC Gravity Dampers, Fire Dampers, and Fire Doors.
WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 15 of 144  
WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 15 of 144  
Line 162: Line 187:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


3.0 PRECAUTIONS AND LIMI TATIONS (continued)
===3.0 PRECAUTIONS===
AND LIMI TATIONS (continued)
L. During the performance of this procedure visual observation of air handlers and ductwork is required. This includes steady-state and transient operations with visual confirmation that vibration and motor temperatures are not excessive. M. Transients include fan star ts and stops, water hammers or other fluid transients.
L. During the performance of this procedure visual observation of air handlers and ductwork is required. This includes steady-state and transient operations with visual confirmation that vibration and motor temperatures are not excessive. M. Transients include fan star ts and stops, water hammers or other fluid transients.
Verification that transient conditions ar e not causing excessive vibration may be accomplished by observation during the tran sient or verification subsequent to the transient that result ant damage has not occurred. N. If the vibration is determined to be excessive the Test Engineer shall initiate a Test Deficiency Notice (TDN) and notify Nuclear Engineering (NE). O. Portions of this test will simulate a high ambient room temperature using an electric heatgun. This activity shall be performed slowly to prevent damage to the temperature switch sensing bulb. P. Test personnel should exercise cauti on to prevent damage to the cooling coil fins. Q. Portions of this test will require valve stroke timing locally at the valve. Local stroke valve timing begins with the initiating signal and is concluded with the completion of valve stem movement.
Verification that transient conditions ar e not causing excessive vibration may be accomplished by observation during the tran sient or verification subsequent to the transient that result ant damage has not occurred. N. If the vibration is determined to be excessive the Test Engineer shall initiate a Test Deficiency Notice (TDN) and notify Nuclear Engineering (NE). O. Portions of this test will simulate a high ambient room temperature using an electric heatgun. This activity shall be performed slowly to prevent damage to the temperature switch sensing bulb. P. Test personnel should exercise cauti on to prevent damage to the cooling coil fins. Q. Portions of this test will require valve stroke timing locally at the valve. Local stroke valve timing begins with the initiating signal and is concluded with the completion of valve stem movement.
Line 169: Line 195:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.0 PREREQUISITE ACTIONS 4.1 Preliminary Actions NOTE Prerequisite action steps may be performed in any order with Test Director approval.  
===4.0 PREREQUISITE===
ACTIONS 4.1 Preliminary Actions NOTE Prerequisite action steps may be performed in any order with Test Director approval.  
  [1] VERIFY the test/performance copy of this Preoperational Test Instruction (PTI) is the curr ent revision and as needed, each test person assisting in this test has the current revision. ________  
  [1] VERIFY the test/performance copy of this Preoperational Test Instruction (PTI) is the curr ent revision and as needed, each test person assisting in this test has the current revision. ________  
[2] OBTAIN copies of the applicable forms from the latest revision of SMP-9.0, AND ATTACH to this PTI for use during the performance of this PTI. ________  
[2] OBTAIN copies of the applicable forms from the latest revision of SMP-9.0, AND ATTACH to this PTI for use during the performance of this PTI. ________  
Line 178: Line 205:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.1 Preliminary Actions (continued)  
===4.1 Preliminary===
Actions (continued)  


   [5] EVALUATE open punch list items on Watts Bar Integrated Task Equipment List (WITEL), AND ENSURE that they will NOT adver sely affect the test performance. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   
   [5] EVALUATE open punch list items on Watts Bar Integrated Task Equipment List (WITEL), AND ENSURE that they will NOT adver sely affect the test performance. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   
Line 186: Line 214:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.1 Preliminary Actions (continued)  
===4.1 Preliminary===
Actions (continued)  


   [6] ENSURE required Component Test ing has been completed prior to start of test. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   
   [6] ENSURE required Component Test ing has been completed prior to start of test. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   
Line 194: Line 223:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.1 Preliminary Actions (continued)  
===4.1 Preliminary===
Actions (continued)  


   [7] ENSURE outstanding Design Change Notices (DCNs), Engineering Document Construction Releases (EDCRs) or  
   [7] ENSURE outstanding Design Change Notices (DCNs), Engineering Document Construction Releases (EDCRs) or  
Line 204: Line 234:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.1 Preliminary Actions (continued)  
===4.1 Preliminary===
Actions (continued)  


   [8] ENSURE a review of outstanding Clearances has been coordinated with Operations for impact to the test performance, AND RECORD in Appendix B, Temporary Condition Log, if required. ________  
   [8] ENSURE a review of outstanding Clearances has been coordinated with Operations for impact to the test performance, AND RECORD in Appendix B, Temporary Condition Log, if required. ________  
Line 217: Line 248:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.1 Preliminary Actions (continued)  
===4.1 Preliminary===
Actions (continued)  


   [13] PERFORM a pretest walkdown on equipment to be tested to ensure no conditions exist that will impact test performance. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   
   [13] PERFORM a pretest walkdown on equipment to be tested to ensure no conditions exist that will impact test performance. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   
Line 226: Line 258:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.2 Special Tools, Measuring and Test Equipment, Parts, and Supplies [1] OBTAIN the following M&TE or equivalent, AND COMPLETE the following table: DESCRIPTION MINIMUM RANGE ACTUAL RANGE REQUIRED ACCURACY M&TE ID NUMBER CALIBRATION DUE DATE Digital Thermometer with surface  
===4.2 Special===
Tools, Measuring and Test Equipment, Parts, and Supplies [1] OBTAIN the following M&TE or equivalent, AND COMPLETE the following table: DESCRIPTION MINIMUM RANGE ACTUAL RANGE REQUIRED ACCURACY M&TE ID NUMBER CALIBRATION DUE DATE Digital Thermometer with surface  


Temperature Probe 0-200 F  3 F  Stopwatch N/A  0.5 seconds
Temperature Probe 0-200 F  3 F  Stopwatch N/A  0.5 seconds
Line 236: Line 269:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.2 Special Tools, Measuring and Test Equipment, Parts, and Supplies (continued)  
===4.2 Special===
Tools, Measuring and Test Equipment, Parts, and Supplies (continued)  
   [3] ENSURE M&TE calibration due dates will support the completion of this test performance. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   
   [3] ENSURE M&TE calibration due dates will support the completion of this test performance. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   


Line 243: Line 277:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.3 Field Preparations  
===4.3 Field===
Preparations  
[1] ENSURE applicable portions of Append ix D, Electrical Lineup, have been performed. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   
[1] ENSURE applicable portions of Append ix D, Electrical Lineup, have been performed. SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14  SubSection 6.15  SubSection 6.16  SubSection 6.17  SubSection 6.18  SubSection 6.19  SubSection 6.20  SubSection 6.21  SubSection 6.22  SubSection 6.23  SubSection 6.24  SubSection 6.25  SubSection 6.26  SubSection 6.27  SubSection 6.28  SubSection 6.29   


Line 250: Line 285:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.3 Field Preparations (continued)  
===4.3 Field===
Preparations (continued)  


   [2] ENSURE applicable portions of A ppendix E, Switch Lineup, have been performed: SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14   
   [2] ENSURE applicable portions of A ppendix E, Switch Lineup, have been performed: SubSection 6.1  SubSection 6.2  SubSection 6.3  SubSection 6.4  SubSection 6.5  SubSection 6.6  SubSection 6.7  SubSection 6.8  SubSection 6.9  SubSection 6.10  SubSection 6.11  SubSection 6.12  SubSection 6.13  SubSection 6.14   
Line 258: Line 294:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.3 Field Preparations (continued)  
===4.3 Field===
Preparations (continued)  


   [3] VERIFY there is no Auxiliary Building Isol ation (ABI) or High Radiation in Refuel Area Signals present by: A. The ABI window NOT lit on either the TR-A or TR-B Master Isolation Signal Status Panels (Window 5 on  
   [3] VERIFY there is no Auxiliary Building Isol ation (ABI) or High Radiation in Refuel Area Signals present by: A. The ABI window NOT lit on either the TR-A or TR-B Master Isolation Signal Status Panels (Window 5 on  
Line 268: Line 305:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.3 Field Preparations (continued)  
===4.3 Field===
Preparations (continued)  


NOTES 1) Any Annunciator points associated wit h 2-MUX-55-12 and 2-MUX-55-13 ONLY have master switches at the bottom of each terminal strip. 2) All points associated with 2-TBK-55-25, 2-TBK-55-26, 2-TBK-55-27, and 2-TBK-55-28 will not have individual switc hes or a master switch.  
NOTES 1) Any Annunciator points associated wit h 2-MUX-55-12 and 2-MUX-55-13 ONLY have master switches at the bottom of each terminal strip. 2) All points associated with 2-TBK-55-25, 2-TBK-55-26, 2-TBK-55-27, and 2-TBK-55-28 will not have individual switc hes or a master switch.  
Line 281: Line 319:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.3 Field Preparations (continued)  
===4.3 Field===
Preparations (continued)  


NOTE The following ERCW valves are electrically disconnected and locked open:  2-FCV-67-188, RHRP ROOM COOLER 2A-A ERCW SUP FLOW CNTL  2-FCV-67-190, RHRP ROOM COOLER 2B-B ERCW SUP FLOW CNTL  2-FCV-67-168, CCP ROOM COOLER 2A-A ERCW SUP FLOW CNTL  2-FCV-67-170, CCP ROOM COOLER 2B-B ERCW SUP FLOW CNTL  
NOTE The following ERCW valves are electrically disconnected and locked open:  2-FCV-67-188, RHRP ROOM COOLER 2A-A ERCW SUP FLOW CNTL  2-FCV-67-190, RHRP ROOM COOLER 2B-B ERCW SUP FLOW CNTL  2-FCV-67-168, CCP ROOM COOLER 2A-A ERCW SUP FLOW CNTL  2-FCV-67-170, CCP ROOM COOLER 2B-B ERCW SUP FLOW CNTL  
Line 290: Line 329:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.3 Field Preparations (continued)  
===4.3 Field===
Preparations (continued)  


   [7] ENSURE ERCW system is ali gned per 0-SOI-67.01 as applicable to support test performance. ________  
   [7] ENSURE ERCW system is ali gned per 0-SOI-67.01 as applicable to support test performance. ________  
Line 301: Line 341:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


4.4 Approvals and Notifications  
===4.4 Approvals===
and Notifications  
[1] OBTAIN permission of the Preoperational St artup Manager to start the test. Preoperational St artup Manager Signature  Date [2] OBTAIN the Unit 2 Supervisor's (US/
[1] OBTAIN permission of the Preoperational St artup Manager to start the test. Preoperational St artup Manager Signature  Date [2] OBTAIN the Unit 2 Supervisor's (US/
SRO) or Shift Manager's (SM) authorization. U-2 US/SRO/SM Signature  Date  
SRO) or Shift Manager's (SM) authorization. U-2 US/SRO/SM Signature  Date  
Line 310: Line 351:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


5.0 ACCEPTANCE CRITERIA A. Auxiliary Building Engineered Safety Features (ESF) Room/Area Coolers function in accordance wit h design requirements. [1] The controls and interlocks for the ESF Coolers function properly. [1.1] Each ESF Cooler STARTS automatically upon receipt of an associated room Hi-Temper ature signal. 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.1[8]) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.2[8]) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.3[8])
===5.0 ACCEPTANCE===
CRITERIA A. Auxiliary Building Engineered Safety Features (ESF) Room/Area Coolers function in accordance wit h design requirements. [1] The controls and interlocks for the ESF Coolers function properly. [1.1] Each ESF Cooler STARTS automatically upon receipt of an associated room Hi-Temper ature signal. 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.1[8]) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.2[8]) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.3[8])
2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER (Step 6.4[8])
2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER (Step 6.4[8])
2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER (Step 6.5[8])
2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER (Step 6.5[8])
Line 319: Line 361:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


5.0 ACCEPTANCE CRITERIA (continued)  
===5.0 ACCEPTANCE===
CRITERIA (continued)  


   [1.2] The following ESF Coolers STAR T automatically upon receipt of a simulated Auxiliary Building Isolati on (ABI) signal AND stop when the ABI signal is reset. 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A (Step 6.9[20], 6.9[22]) 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B (Step 6.10[20], 6.10[22]) 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A (Step 6.11[20], 6.11[22]) 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B (Step 6.12[20], 6.12[22]) 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A (Step 6.13[20], 6.13[22]) 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B (Step 6.14[20], 6.14[22])  
   [1.2] The following ESF Coolers STAR T automatically upon receipt of a simulated Auxiliary Building Isolati on (ABI) signal AND stop when the ABI signal is reset. 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A (Step 6.9[20], 6.9[22]) 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B (Step 6.10[20], 6.10[22]) 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A (Step 6.11[20], 6.11[22]) 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B (Step 6.12[20], 6.12[22]) 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A (Step 6.13[20], 6.13[22]) 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B (Step 6.14[20], 6.14[22])  
Line 327: Line 370:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


5.0 ACCEPTANCE CRITERIA (continued)  
===5.0 ACCEPTANCE===
CRITERIA (continued)  


   [1.3] Each ESF Cooler can be cont rolled manually by local handswitch. 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.1[4]A, 6.1[5]A,V6.1[10.1]) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.2[4]A, 6.2[5]A,V6.2[10.1]) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.3[4]A, 6.3[5]A, 6.3[10.1]) 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER (Step 6.4[4]A, 6.4[5]A, 6.4[10.1]) 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER (Step 6.5[4]A, 6.5[5]A, 6.5[10.1]) 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER (Step 6.6[4]A 6.6[5]A, 6.6[10.1]) 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER (Step 6.7[4]A, 6.7[5]A, 6.7[10.1]) 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER (Step 6.8[4]A, 6.8[5]A, 6.8[10.1]) 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A (Step 6.9[4]A, 6.9[5]A, 6.9[10.1], 6.9[16.1]) 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B (Step 6.10[4]A, 6.10[5]A, 6.10[10.1], 6.10[16.1]) 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A (Step 6.11[4]A, 6.11[5]A, 6.11[10.1], 6.11[16.1]) 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B (Step 6.12[4]A, 6.12[5]A, 6.12[10.1], 6.12[16.1]) 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A (Step 6.13[4]A, 6.13[5]A, 6.13[10.1], 6.13[16.1]) 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B (Step 6.14[4]A, 6.14[5]A, 6.14[10.1], 6.14[16.1])
   [1.3] Each ESF Cooler can be cont rolled manually by local handswitch. 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.1[4]A, 6.1[5]A,V6.1[10.1]) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.2[4]A, 6.2[5]A,V6.2[10.1]) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.3[4]A, 6.3[5]A, 6.3[10.1]) 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER (Step 6.4[4]A, 6.4[5]A, 6.4[10.1]) 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER (Step 6.5[4]A, 6.5[5]A, 6.5[10.1]) 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER (Step 6.6[4]A 6.6[5]A, 6.6[10.1]) 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER (Step 6.7[4]A, 6.7[5]A, 6.7[10.1]) 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER (Step 6.8[4]A, 6.8[5]A, 6.8[10.1]) 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A (Step 6.9[4]A, 6.9[5]A, 6.9[10.1], 6.9[16.1]) 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B (Step 6.10[4]A, 6.10[5]A, 6.10[10.1], 6.10[16.1]) 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A (Step 6.11[4]A, 6.11[5]A, 6.11[10.1], 6.11[16.1]) 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B (Step 6.12[4]A, 6.12[5]A, 6.12[10.1], 6.12[16.1]) 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A (Step 6.13[4]A, 6.13[5]A, 6.13[10.1], 6.13[16.1]) 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B (Step 6.14[4]A, 6.14[5]A, 6.14[10.1], 6.14[16.1])
Line 334: Line 378:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


5.0 ACCEPTANCE CRITERIA (continued)  
===5.0 ACCEPTANCE===
CRITERIA (continued)  


NOTE The Acceptance Criteria in the followin g steps have been adjusted to account for  10% of design/rated flow for nontducted, freestandi ng air coolers as delineated in G-37. [2] Each ESF Room Cooler maintains design air flow: 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.15[5]) 6,925 CFM  (6,233 - 7,617) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.16[5]) 6,925 CFM  (6,233 - 7,617) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.17[7])
NOTE The Acceptance Criteria in the followin g steps have been adjusted to account for  10% of design/rated flow for nontducted, freestandi ng air coolers as delineated in G-37. [2] Each ESF Room Cooler maintains design air flow: 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.15[5]) 6,925 CFM  (6,233 - 7,617) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.16[5]) 6,925 CFM  (6,233 - 7,617) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.17[7])
Line 344: Line 389:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


5.0 ACCEPTANCE CRITERIA (continued)  
===5.0 ACCEPTANCE===
CRITERIA (continued)  


   [3] Essential Raw Cooling Water System Valves. [3.1] The following ERCW valves OPEN upon start of their associated ESF Cooler: 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.3[4]C) 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.4[4]C) 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.5[4]C) 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.6[4]C) 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.9[4]C) 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.10[4]C) 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.11[4]C) 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.12[4]C) 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.13[4]C) 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.14[4]C)  
   [3] Essential Raw Cooling Water System Valves. [3.1] The following ERCW valves OPEN upon start of their associated ESF Cooler: 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.3[4]C) 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.4[4]C) 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.5[4]C) 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.6[4]C) 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.9[4]C) 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.10[4]C) 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.11[4]C) 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.12[4]C) 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.13[4]C) 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.14[4]C)  
Line 352: Line 398:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


5.0 ACCEPTANCE CRITERIA (continued)  
===5.0 ACCEPTANCE===
CRITERIA (continued)  


   [3.2] The following ERCW valves OPEN in  10 seconds: 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.17[4]) 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.18[4]) 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.19[4]) 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.20[4]) 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.23[4]) 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.24[4]) 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.25[4]) 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.26[4]) 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.27[4]) 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.28[4])  
   [3.2] The following ERCW valves OPEN in  10 seconds: 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.17[4]) 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.18[4]) 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.19[4]) 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.20[4]) 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.23[4]) 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.24[4]) 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.25[4]) 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.26[4]) 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.27[4]) 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.28[4])  
Line 360: Line 407:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


5.0 ACCEPTANCE CRITERIA (continued)  
===5.0 ACCEPTANCE===
CRITERIA (continued)  


   [4] High Energy Line Break (HELB) Detection [4.1] The following HELB Indicator Lights come ON upon receipt of an associated room Hi-Te mperature signal. 2-XI-30-5235A, LETDOWN HX PIPE BREAK (Step 6.29.2[3]C) 2-XI-30-5235B, LETDOWN HX PIPE BREAK (Step 6.29.2[7]C) 2-XI-30-5236A, RHR PMP RM A PIPE BREAK (Step 6.29.3[3]C) 2-XI-30-5236B, RHR PMP RM A PIPE BREAK (Step 6.29.3[7]C) 2-XI-30-5237A, RHR PMP RM B PIPE BREAK (Step 6.29.4[3]C) 2-XI-30-5237B, RHR PMP RM B PIPE BREAK (Step 6.29.4[7]C) 2-XI-30-5238A, RHR HX A ROOM PIPE BREAK (Step 6.29.5[3]C) 2-XI-30-5238B, RHR HX A ROOM PIPE BREAK (Step 6.29.5[7]C) 2-XI-30-5239A, RHR HX B ROOM PIPE BREAK (Step 6.29.6[3]C) 2-XI-30-5239B, RHR HX B ROOM PIPE BREAK (Step 6.29.6[7]C)  
   [4] High Energy Line Break (HELB) Detection [4.1] The following HELB Indicator Lights come ON upon receipt of an associated room Hi-Te mperature signal. 2-XI-30-5235A, LETDOWN HX PIPE BREAK (Step 6.29.2[3]C) 2-XI-30-5235B, LETDOWN HX PIPE BREAK (Step 6.29.2[7]C) 2-XI-30-5236A, RHR PMP RM A PIPE BREAK (Step 6.29.3[3]C) 2-XI-30-5236B, RHR PMP RM A PIPE BREAK (Step 6.29.3[7]C) 2-XI-30-5237A, RHR PMP RM B PIPE BREAK (Step 6.29.4[3]C) 2-XI-30-5237B, RHR PMP RM B PIPE BREAK (Step 6.29.4[7]C) 2-XI-30-5238A, RHR HX A ROOM PIPE BREAK (Step 6.29.5[3]C) 2-XI-30-5238B, RHR HX A ROOM PIPE BREAK (Step 6.29.5[7]C) 2-XI-30-5239A, RHR HX B ROOM PIPE BREAK (Step 6.29.6[3]C) 2-XI-30-5239B, RHR HX B ROOM PIPE BREAK (Step 6.29.6[7]C)  
Line 368: Line 416:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


5.0 ACCEPTANCE CRITERIA (continued)  
===5.0 ACCEPTANCE===
CRITERIA (continued)  


   [4.2] Annunciator window 2-XA-55-6A-113B, RHR/CVCS PIPE BREAK, ALARMS upon reciept of any HELB room Hi-Temperature signal. 2-TS-30-5235A, CVCS LETDOWN HT EXCH RM HI TEMP SW (Step 6.29.2[3]A) 2-TS-30-5235B, CVCS LETDOWN HT EXCH RM HI TEMP SW (Step 6.29.2[7]A) 2-TS-30-5236A, RHR PUMP RM A HI TEMP SW (Step 6.29.3[3]A) 2-TS-30-5236B, RHR PUMP RM A HI TEMP SW (Step 6.29.3[7]A) 2-TS-30-5237A, RHR PUMP RM B HI TEMP SW (Step 6.29.4[3]A) 2-TS-30-5237B, RHR PUMP RM B HI TEMP SW (Step 6.29.4[7]A) 2-TS-30-5238A, RHR HT EXCH A ROOM HI TEMP SW (Step 6.29.5[3]A) 2-TS-30-5238B, RHR HT EXCH A ROOM HI TEMP SW (Step 6.29.5[7]A) 2-TS-30-5239A, RHR HT EXCH B ROOM HI TEMP SW (Step 6.29.6[3]A) 2-TS-30-5239B, RHR HT EXCH B ROOM HI TEMP SW (Step 6.29.6[7]A)  
   [4.2] Annunciator window 2-XA-55-6A-113B, RHR/CVCS PIPE BREAK, ALARMS upon reciept of any HELB room Hi-Temperature signal. 2-TS-30-5235A, CVCS LETDOWN HT EXCH RM HI TEMP SW (Step 6.29.2[3]A) 2-TS-30-5235B, CVCS LETDOWN HT EXCH RM HI TEMP SW (Step 6.29.2[7]A) 2-TS-30-5236A, RHR PUMP RM A HI TEMP SW (Step 6.29.3[3]A) 2-TS-30-5236B, RHR PUMP RM A HI TEMP SW (Step 6.29.3[7]A) 2-TS-30-5237A, RHR PUMP RM B HI TEMP SW (Step 6.29.4[3]A) 2-TS-30-5237B, RHR PUMP RM B HI TEMP SW (Step 6.29.4[7]A) 2-TS-30-5238A, RHR HT EXCH A ROOM HI TEMP SW (Step 6.29.5[3]A) 2-TS-30-5238B, RHR HT EXCH A ROOM HI TEMP SW (Step 6.29.5[7]A) 2-TS-30-5239A, RHR HT EXCH B ROOM HI TEMP SW (Step 6.29.6[3]A) 2-TS-30-5239B, RHR HT EXCH B ROOM HI TEMP SW (Step 6.29.6[7]A)  
Line 377: Line 426:
Data Package:  Page ____ of ____    Date ________  
Data Package:  Page ____ of ____    Date ________  


6.0 PERFORMANCE NOTES 1) SubSections 6.1 through 6.29 may be perform ed in any order or in parallel provided the steps within are perf ormed in the order written unless otherwise noted. 2) All verifications (fan starts, fan stops, valve position, etc) are to be done by local observation unless otherwise noted. 3) IF/THEN steps may be marked N/A if stated condition does not exist.
===6.0 PERFORMANCE===
 
NOTES 1) SubSections 6.1 through 6.29 may be perform ed in any order or in parallel provided the steps within are perf ormed in the order written unless otherwise noted. 2) All verifications (fan starts, fan stops, valve position, etc) are to be done by local observation unless otherwise noted. 3) IF/THEN steps may be marked N/A if stated condition does not exist.
6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER LOGIC  
6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER LOGIC  
[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.1 have been completed. ________  
[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.1 have been completed. ________  
Line 1,474: Line 1,525:


7.0 POST PERFORMANCE ACTIVITIES  
7.0 POST PERFORMANCE ACTIVITIES  
[1] NOTIFY the Unit 2 US/SRO of t he test completion and system alignment. ________
[1] NOTIFY the Unit 2 US/SRO of t he test completion and system alignment. ________  
8.0 RECORDS A. QA Records Completed Test Package. B. Non-QA Records  
 
===8.0 RECORDS===
 
A. QA Records Completed Test Package. B. Non-QA Records  


None WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 134 of 144 Appendix A (Page 1 of 4) TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW Data Package:  Page ____ of ____    Date ________
None WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 134 of 144 Appendix A (Page 1 of 4) TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW Data Package:  Page ____ of ____    Date ________

Revision as of 02:14, 14 October 2018

Watt Bar, Unit 2 - Submittal of Pre-op Test Instruction Startup 2-PTI-030A-01, Auxiliary Building ESF Coolers
ML102420679
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 08/30/2010
From: Bajestani M, Kenneth Jones
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
2-PTI-030A-01
Download: ML102420679 (146)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 August 30, 2010 ATTN: Document Control Desk U.S.Nuclear Regulatory Commission Washington, D.C.20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No.50-391

Subject:

Watts Bar Nuclear Plant (WBN)Unit2-Submittal of Pre-op Test Instruction The following approved Watts Bar Unit 2 Pre-op Test Instruction is enclosed: PTI NUMBER Rev.TITLE 2-PTI-030A-01 0 Unit 2 Auxiliary Building ESF Coolers If you have any questions, please contact Pete Olson at (423)365-3294.Sincerely, Masoud Ba" tani Watts Bar it2Vice President

U.S. Nuclear Regulatory Commission Page 2 August 30, 2010 cc (Enclosures):

U. S. Nuclear Regulatory Commission

Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257

NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

WA TIS BAR NUCLEAR PLANT UNIT 2 STARTUP TITLE: Unit 2 Auxiliary Building ESF Coolers Instruction No: 2-PTI-030A-01 Revision No:

_PREPARED BY: Keith JonesDATE 7-Z'l-/O REVIEWED BY:__.._.._...._..._._.......

._PR.'.N_

..A_J'------.---=--

..0-PRINT NAME!SIGt4ATURE INSTRUCTION APPROVAL 2-/0-00J>JTGCHAIRMA

.

APPROVED BY:DATEl.l.d)0 PREOPERATIONAL STARTUP MANAGER TEST RESULTS APPROVAL_________DATE___________

DATE_JTG MEETING NO:_JTG CHAIRMAN: APPROVED BY: PREOPERATIONAL STARTUP MANAGER SMP-8.0, R3, AdministratIon of PreoperatIonal Test InstructIons, AppendIx B WBN Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Unit2 Rev.0000 Page 2 of 144 Revision log Revision Affected or Change Effective Page Number Date Numbers Description of Revision/Change 0000 g!d-.U I, 0 ALL This procedure is written using the Unit 1 PTI-030C-01 Rev 0 as a guide.Turbine Driven Auxiliary Feedwater Pump Room Exhaust Fan tests moved to new instruction 2-PTI-030D-01.

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 3 of 144

Table of Contents

1.0 INTRODUCTION

.......................................................................................................... 6 1.1 Test Objectives ...........................................................................................................

.. 6 1.2 Scope

............................................................................................................................ 6

2.0 REFERENCES

............................................................................................................. 8

2.1 Performance

References .............................................................................................. 8 2.2 Developmental References

........................................................................................... 8 3.0 PRECAUTIONS AND LIMITATIONS ......................................................................... 14

4.0 PREREQUISI

TE ACTIONS ........................................................................................ 16

4.1 Preliminar

y Actions ..................................................................................................... 1 6 4.2 Special Tools, Meas uring and Test Equipment, Parts, and Supplies .......................... 22 4.3 Field Preparations .......................................................................................................

24 4.4 Approvals and No tifications ........................................................................................ 30

5.0 ACCEPTANCE

CRITERIA ......................................................................................... 31

6.0 PERFORMANCE

........................................................................................................ 39 6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOL ER LOGIC .................................... 39 6.2 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOL ER LOGIC .................................... 43 6.3 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER LOGIC ....................................... 46 6.4 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER LOGIC ....................................... 49 6.5 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER LOGIC ...................................... 52 6.6 2-PMCL-30-179-B, SIS PUMP 2B-B ROOM COOLER LOGIC .................................. 55 6.7 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER LOGIC ........................................................................................................ 58 6.8 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER LOGIC ......................................................................................................................... 61 6.9 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A LOGIC .................... 64 6.10 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B LOGIC .................... 69 6.11 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A LOGIC .................... 74 6.12 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B LOGIC .................... 79 WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 4 of 144

Table of Contents (continued) 6.13 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A LOGIC .............................. 84 6.14 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B LOGIC .............................. 89 6.15 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER AIR FLOW .............................. 94 6.16 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER AIR FLOW .............................. 95 6.17 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER AIR FLOW ................................. 96 6.18 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER AIR FLOW ................................. 98 6.19 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER AIR FLOW .............................. 100 6.20 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER AIR FLOW .............................. 102 6.21 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER AIR FLOW ....................................................................................................................... 10 4 6.22 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER AIR FLOW ....................................................................................................................... 10 6 6.23 2-PMCL-30-186, PENETRATION ROOM EL 692 COOLER 2A-A AIR FLOW ....................................................................................................................... 10 8 6.24 2-PMCL-30-187, PENETRATION ROOM EL 692 COOLER 2B-B AIR FLOW ....................................................................................................................... 11 0 6.25 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A AIR FLOW ....................................................................................................................... 11 2 6.26 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B AIR FLOW ....................................................................................................................... 11 4 6.27 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A AIR FLOW ...................... 116 6.28 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B AIR FLOW ...................... 118 6.29 HIGH ENERGY LINE BRE AK (HELB) DETECTION. ............................................... 120 6.29.2 CVCS LETDOWN HEAT EXCHANGER ROOM HELB DETECTION ............................................................................................... 122 6.29.3 RHR PUMP ROOM 2A HELB DETECTION ............................................... 125 6.29.4 RHR PUMP ROOM 2B HELB DETECTION ............................................... 127 6.29.5 RHR HEAT EXCHANGER ROOM 2A HELB DETECTION ........................ 129 6.29.6 RHR HEAT EXCHANGER ROOM 2B HELB DETECTION ........................ 131 7.0 POST PERFORMANC E ACTIVITIE S ...................................................................... 133

8.0 RECORDS

................................................................................................................ 13 3

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 5 of 144

Table of Contents (continued) Appendix A: TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW ................................................................................................... 134 Appendix B: TEMPORARY CONDITION LOG ............................................................. 138 Appendix C: PERMANENT PLANT INSTRUMENTATION LOG .................................. 139 Appendix D: ELECTRIC AL LINEUP ............................................................................. 142 Appendix E: SWIT CH LINEUP ..................................................................................... 144

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 6 of 144

Data Package: Page ____ of ____ Date ________

1.0 INTRODUCTION

1.1 Test Objectives A. Demonstrate the proper operation of the Unit 2 Auxiliary Building Engineered Safety Features (ESF) Room/Area Coolers. B. Demonstrate the proper operation of the Essential Raw Cooling Water (ERCW)

Flow Control Valves associated with their respective ESF Room/Area Coolers. C. Demonstrate the proper operation of the High E nergy Line Break (HELB) detection equipment and alarms.

1.2 Scope

A. This test demonstrates the operability of the Unit 2 Auxi liary Building ESF Room/Area Coolers and Fans to ensure the following: 1. The required ESF coolers start upon receipt of their associated room/area Hi-Tem perature signal. 2. The required Unit 2 ESF cooler s start upon receipt of a simulated Auxiliary Building Isolati on (ABI) signal and stop upon reset of ABI signal. (See also 1.2D) 3. The ESF coolers can be controlled manually by local handswitch.

4. The ESF room/area coolers maintain desired air flows. 5. The required Unit 2 Au xiliary Building ESF cooler ERCW supply valves open in a maximum of 10 seconds upon start of their associated cooler.

NOTE ERCW flowrates are verified during perform ance of 2-PTI-067-02, ERCW System Flow Balance. B. The required HELB indications an d annunciations respond appropriately upon reciept of their associated r oom/area Hi-Temper ature signal.

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 7 of 144

Data Package: Page ____ of ____ Date ________

1.2 Scope

(continued)

C. ESF pump room cooler start upon associated Pump Start signal logic is verified when each associated ESF pump is tested as shown below:

Pump Room Cooler Instruction Testing Cooler Auto Start upon Pump Start RHR Pump 2A-A Room Cooler 2-PTI-074-01 RESIDUAL HEAT REMOVAL SYSTEM RHR Pump 2B-B Room Cooler SIS Pump 2A-A Room Cooler 2-PTI-063-5A SAFETY INJECTION SYSTEM PUMP/VALVE LOGIC TEST SIS Pump 2B-B Room Cooler 2-PTI-063-5B SAFETY INJECTION SYSTEM PUMP/VALVE LOGIC TEST CCP 2A-A Room Cooler 2-PTI-062-01 CHARGING AND LETDOWN LOGIC TEST CCP 2B-B Room Cooler CS Pump 2A-A Room Cooler 2-PTI-072-01 CONTAINMENT SPRAY PUMP/VALVE LOGIC TEST CS Pump 2B-B Room Cooler D. To ensure sufficient test overlap, ESF cooler start upon Auxiliary Building Isolation signal is performed in the In tegrated Safeguards Tests as shown below: Room Cooler Instruction Testing Cooler Auto Start upon ABI 692 Penetration Room Cooler 2A-A 2-PTI-262-01 INTEGRATED SAFEGUARDS TEST 713 Penetration Room Cooler 2A-A Pipe Chase Cooler 2A-A 692 Penetration Room Cooler 2B-B 2-PTI-262-02 INTEGRATED SAFEGUARDS TEST 713 Penetration Room Cooler 2B-B Pipe Chase Cooler 2B-B

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 8 of 144

Data Package: Page ____ of ____ Date ________

2.0 REFERENCES

2.1 Performance

References A. SMP-9.0, Rev 0, Conduct of Test B. GTM-05, HVAC Air Balance (Draft)

C. 0-SOI-67.01, Essential Raw Cooling Water System (Draft) 2.2 Developmental References A. Final Safety Analysis Report, Amendment 99 1. FSAR Section 9.2.1, Essential Raw Cooling Water (ERCW) 2. FSAR Section 9.4.5.3, Auxiliary Building Safety Features (ESF) Equipment Coolers 3. FSAR Table 14.2-1, S heets 4 & 5, Essential Ra w Cooling Water System Test Summary 4. FSAR Table 14.2-1, S heets 36 & 37, Auxiliary Bu ilding Ventilation System B. Drawings 1. Flow Diagrams a. 2-47W866-8, Rev 0, HEAT ING, COOLING & VENTILATING AIR FLOW DRA 54923-070, Rev 0

DRA 54923-071, Rev 0 b. 1-47W845-7, Rev 14, FLOW DIAGRAM - ESSENTIAL RAW COOLING WATER SYSTEM c. 2-47W845-7, Rev 0, FLOW DIAGRAM - ESSENTIAL RAW COOLING WATER SYSTEM WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 9 of 144

Data Package: Page ____ of ____ Date ________

2.2 Developmental

References (continued)

2. Electrical a. 1-45W600-30-4, Rev 26, VENTILATING SYSTEM SCHEMATIC DIAGRAM b. 2-45W600-57-37, SEPERATION &

MISC AUX RELAYS SCHEMATIC DIAGRAM, [Later]

DRA 54172-177, Rev 0

DRA 54172-178, Rev 0

DRA 54172-179, Rev 0

DRA 54172-464, Rev 0

DRA 54172-465, Rev 0

DRA 54172-466, Rev 0 FCR 55967-A, Rev 0 c. 2-45W756-1, Rev 0, 480V CONT

& AUX BLDG VT BD 2A1-A SINGLE LINE d. 2-45W756-5, Rev 0, 480V CONT

& AUX BLDG VT BD 2B1-A SINGLE LINE e. 2-45W760-30-17, Rev 0, VENTILATION SYSTEM SCHEMATIC DIAGRAM f. 2-45W760-30-18, Rev 0, VENTILATION SYSTEM SCHEMATIC DIAGRAM

DRA 53290-049, Rev 0

DRA 53290-066, Rev 0 g. 2-45W760-30-19, Rev 0, VENTILATION SYSTEM SCHEMATIC DIAGRAM h. 2-45W760-30-20, Rev 0, VENTILATION SYSTEM SCHEMATIC DIAGRAM

DRA 53290-051, Rev 0

DRA 53290-067, Rev 0 i. 45N1688-1 (AC), Rev MM, SEPERATION AUX RELAY PNL 1-R-73 CONNECTION DIAGRAM j. 45N1688-4 (AC), Rev AAD, SEPE RATION AUX RELAY PNL 1-R-73 CONNECTION DIAGRAM k. 45N1693-1 (AC), Rev SS, SEPERATION AUX RELAY PNL 1-R-78 CONNECITON DIAGRAM WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 10 of 144

Data Package: Page ____ of ____ Date ________

2.2 Developmental

References (continued)

l. 45N1693-4 (AC), Rev, AAB, SEP ERATION AUX RELAY PNL 1-R-78 CONNECTION DIAGRAM m. 45W2770-1, Rev 18, 480V CONT. & AUX BLDG VENT BD 2A1-A CONNECTION DIAGRAM n. 45W2770-2, Rev 6, 480V CONT. & AUX BLDG VENT BD 2A1-A CONNECTION DIAGRAM o. 45W2772-2, Rev 13, 480V CONT. & AUX BLDG VENT BD 2B1-B CONNECTION DIAGRAM p. 45W2772-3, Rev 14, 480V CONT. & AUX BLDG VENT BD 2B1-B CONNECTION DIAGRAM 3. Mechanical a. 2-47W600-188, Rev 0, INSTRUMENTS AND CONTROLS DRA 53788-041, Rev 0

DRA 53788-042, Rev 0

DRA 53788-043, Rev 0

DRA 53788-044, Rev 0

DRA 53788-045, Rev 0

DRA 53788-046, Rev 0 DRA 53788-047, Rev 0 b. 47W920-1 (AC), Rev Y, HEATING, VENTILATING AND AIR CONDITIONING c. 47W920-2 (AC), Rev R, HEATING, VENTILATING AND AIR CONDITIONING d. 47W920-4 (AC), Rev S, HEATING VENTILATING AND AIR CONDITIONING 4. Logic/Control a. 2-47W611-65-1, Rev 2, EL ECTRICAL LOGIG DIAGRAM EMERGENCY GAS TREATMENT SYSTEM WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 11 of 144

Data Package: Page ____ of ____ Date ________

2.2 Developmental

References (continued)

5. Other a. 47B601-55-25 (AC), Rev D, ELECTRICAL INSTRUMENT TABULATION b. 2-45B655-6A, Rev 0, MAIN CONTROL ROOM ANNUNCIATOR INPUTS WINDOW BOX XA-55-6A c. 2-45B655-E6A, Rev 0, ANNUN CIATOR WINDOW BOX XA-55-6A ENGRAVING C. Documents a. SMP-4.0, Rev 2, Syst em Completion and Turnover b. SMP-8.0, Rev 3, Administration of Preoperational Test Procedures c. GTM-03, HVAC Gravity Dampers, Fire Dampers, and Fire Doors, (Draft) d. WBN2-30AB-4001, Rev 1, Auxiliar y Building Heating, Ventilation, Air Conditioning System (30, 31, 44) e. WBN2-67-4002, Rev 1, Essential Raw Cooling Water System, System 67 f. G-37, Rev 4, Testing and Balancing of HVAC Systems During Installation, Modification, and Maintenance g. 2-TSD-030A-01, Rev 1, Select Auxiliary Building ESF Coolers and HELB Detection h. 0-PI-OPS-1.1, Rev 3, Jumper Control Process i. 2-PTI-067-02, ERCW System Flow Balance (Draft)
j. 2-PTI-074-01, Residual H eat Removal System (Draft) k. 2-PTI-063-5A, Safety Injection Syst em Pump/Valve Logic Test (Draft) l. 2-PTI-063-5B, Safety Injection Syst em Pump/Valve Logic Test (Draft) m. 2-PTI-062-01, Charging and Letdown Logic Test (Draft) n. 2-PTI-072-01, Containment Spray Pump/Valve Logic Test (Draft)

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 12 of 144

Data Package: Page ____ of ____ Date ________

2.2 Developmental

References (continued)

o. 2-PTI-262-01, Integrated Safeguards Test (Draft) p. 2-PTI-262-02, Integrated Safeguards Test (Draft) q. Scaling and Setpoint Documents (1) SSD-2-TS-30-175, RHR Pump Ro om Cooler Fan A-A, [Later] (2) SSD-2-TS-30-176, RHR Pump Ro om Cooler Fan B-B, [Later] (3) SSD-2-TS-30-177, CS Pump R oom Cooler Fan A-A, [Later] (4) SSD-2-TS-30-178, CS Pump R oom Cooler Fan B-B, [Later] (5) SSD-2-TS-30-179, SIS Pump Ro om Cooler Fan B-B, [Later] (6) SSD-2-TS-30-180, SIS Pump Ro om Cooler Fan A-A, [Later] (7) SSD-2-TS-30-182, Charging Pump Room Cooler Fan B-B, [Later] (8) SSD-2-TS-30-183, Charging Pump Room Cooler Fan A-A, [Later] (9) SSD-2-TS-30-186A, Penetration R oom Cooler, El 692, Fan A-A, [Later] (10) SSD-2-TS-30-186B, Penetration R oom Cooler, El 692, Fan A-A, [Later] (11) SSD-2-TS-30-187A, Penetration R oom Cooler, El 692, Fan B-B, [Later] (12) SSD-2-TS-30-187B, Penetration R oom Cooler, El 692, Fan B-B, [Later] (13) SSD-2-TS-30-196A, Penetration R oom Cooler, El 713, Fan A-A, [Later] (14) SSD-2-TS-30-196B, Penetration R oom Cooler, El 713, Fan A-A, [Later] (15) SSD-2-TS-30-197A, Penetration R oom Cooler, El 713, Fan B-B, [Later] (16) SSD-2-TS-30-197B, Penetration R oom Cooler, El 713, Fan B-B, [Later]

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 13 of 144

Data Package: Page ____ of ____ Date ________

2.2 Developmental

References (continued)

(17) SSD-2-TS-30-201A, Pipe Chas e Coolers Fan 2A-A, [Later] (18) SSD-2-TS-30-201B, Pipe Chas e Coolers Fan 2A-A, [Later] (19) SSD-2-TS-30-202A, Pipe Chas e Coolers Fan 2B-B, [Later] (20) SSD-2-TS-30-202B, Pipe Chas e Coolers Fan 2B-B, [Later] (21) SSD-2-TS-30-5235A, CVCS Letdown Heat Exchanger Room Hi Temperature, [Later] (22) SSD-2-TS-30-5235B, CVCS Letdown Heat Exchanger Room Hi Temperature, [Later] (23) SSD-2-TS-30-5236A, RHR Pump Room A Hi Temperature, [Later] (24) SSD-2-TS-30-5236B, RHR Pump Room A Hi Temperature, [Later] (25) SSD-2-TS-30-5237A, RHR Pump Room B Hi Temperature, [Later] (26) SSD-2-TS-30-5237B, RHR Pump Room B Hi Temperature, [Later] (27) SSD-2-TS-30-5238A, RHR Heat Exchanger Room A Hi Temperature, [Later] (28) SSD-2-TS-30-5238B, RHR Heat Exchanger Room A Hi Temperature, [Later] (29) SSD-2-TS-30-5239A, RHR Heat Exchanger Room B Hi Temperature, [Later] (30) SSD-2-TS-30-5239B, RHR Heat Exchanger Room B Hi Temperature, [Later]

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 14 of 144

Data Package: Page ____ of ____ Date ________

3.0 PRECAUTIONS

AND LIMITATIONS A. Standard precautions shall be followed for working around energized electrical equipment in accordance with TVA Safety Manual Procedure 1021. B. Steps may be repeated if all components cannot be tested in a step. However, if the test has been exited, prerequi site steps must be re-verified and a Chronological Test Log (CTL) entry made. C. Component tags and labels may differ sli ghtly (abbreviations, punctuation, letter case, etc.) from the description given in this test. If this situation occurs, it shall NOT be considered a test deficiency or procedure deviation. It shall be documented in the CTL and reconciled by way of a plant labeling request or drawing discrepancy or single-line dat e typo change in the procedure as appropriate. D. All wires removed/lifted from a termi nal shall be identified and taped or covered with an insulator to prevent personnel or equipment hazard and possible spurious initiations. The wires shoul d be grouped together and labeled with the work implementing document number that required them to be lifted if left unattended. E. All open problems are to be tracked by a corrective action document and entered on the appropriate system punchlist. F. Problems identified during the test s hall be annotated on the Chronological Test Log (CTL) from SMP-9.0 including a descr iption of the problem, the procedure step when/where the problem was identified, corrective action steps taken to resolve the problem, and the number of the corrective action document, if one was required. G. Observe all Radiation Protection (RP) requirements when working in or near contaminated areas. H. All terminal points and connections are to be considered energized.

Instrumentation must be used to determi ne if the circuits are de-energized. I. Retermination of lifted leads requires that their restored bend radius is equal to or greater than the as found condition. J. Vibration testing will be performed dur ing performance of GTM-05, HVAC Air Balance. K. Backdraft damper testing will be perf ormed during performance of GTM-03, HVAC Gravity Dampers, Fire Dampers, and Fire Doors.

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 15 of 144

Data Package: Page ____ of ____ Date ________

3.0 PRECAUTIONS

AND LIMI TATIONS (continued)

L. During the performance of this procedure visual observation of air handlers and ductwork is required. This includes steady-state and transient operations with visual confirmation that vibration and motor temperatures are not excessive. M. Transients include fan star ts and stops, water hammers or other fluid transients.

Verification that transient conditions ar e not causing excessive vibration may be accomplished by observation during the tran sient or verification subsequent to the transient that result ant damage has not occurred. N. If the vibration is determined to be excessive the Test Engineer shall initiate a Test Deficiency Notice (TDN) and notify Nuclear Engineering (NE). O. Portions of this test will simulate a high ambient room temperature using an electric heatgun. This activity shall be performed slowly to prevent damage to the temperature switch sensing bulb. P. Test personnel should exercise cauti on to prevent damage to the cooling coil fins. Q. Portions of this test will require valve stroke timing locally at the valve. Local stroke valve timing begins with the initiating signal and is concluded with the completion of valve stem movement.

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 16 of 144

Data Package: Page ____ of ____ Date ________

4.0 PREREQUISITE

ACTIONS 4.1 Preliminary Actions NOTE Prerequisite action steps may be performed in any order with Test Director approval.

[1] VERIFY the test/performance copy of this Preoperational Test Instruction (PTI) is the curr ent revision and as needed, each test person assisting in this test has the current revision. ________

[2] OBTAIN copies of the applicable forms from the latest revision of SMP-9.0, AND ATTACH to this PTI for use during the performance of this PTI. ________

[3] ENSURE changes to the references listed on "Test Procedures/Instructions Referenc e Review," Appendix A, have been reviewed and determined NOT to adversely affect the test performance. ________

[4] VERIFY current revisions and change paper for referenced drawings have been reviewed and determined NOT to adversely affect the test performance, AND ATTACH documentation of current drawing revision numbers and change paper that were reviewed to the data package. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 17 of 144

Data Package: Page ____ of ____ Date ________

4.1 Preliminary

Actions (continued)

[5] EVALUATE open punch list items on Watts Bar Integrated Task Equipment List (WITEL), AND ENSURE that they will NOT adver sely affect the test performance. SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14 SubSection 6.15 SubSection 6.16 SubSection 6.17 SubSection 6.18 SubSection 6.19 SubSection 6.20 SubSection 6.21 SubSection 6.22 SubSection 6.23 SubSection 6.24 SubSection 6.25 SubSection 6.26 SubSection 6.27 SubSection 6.28 SubSection 6.29

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 18 of 144

Data Package: Page ____ of ____ Date ________

4.1 Preliminary

Actions (continued)

[6] ENSURE required Component Test ing has been completed prior to start of test. SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14 SubSection 6.15 SubSection 6.16 SubSection 6.17 SubSection 6.18 SubSection 6.19 SubSection 6.20 SubSection 6.21 SubSection 6.22 SubSection 6.23 SubSection 6.24 SubSection 6.25 SubSection 6.26 SubSection 6.27 SubSection 6.28 SubSection 6.29

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 19 of 144

Data Package: Page ____ of ____ Date ________

4.1 Preliminary

Actions (continued)

[7] ENSURE outstanding Design Change Notices (DCNs), Engineering Document Construction Releases (EDCRs) or

Temporary Alterations (TAs) do NOT adversely impact testing. SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14 SubSection 6.15 SubSection 6.16 SubSection 6.17 SubSection 6.18 SubSection 6.19 SubSection 6.20 SubSection 6.21 SubSection 6.22 SubSection 6.23 SubSection 6.24 SubSection 6.25 SubSection 6.26 SubSection 6.27 SubSection 6.28 SubSection 6.29

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 20 of 144

Data Package: Page ____ of ____ Date ________

4.1 Preliminary

Actions (continued)

[8] ENSURE a review of outstanding Clearances has been coordinated with Operations for impact to the test performance, AND RECORD in Appendix B, Temporary Condition Log, if required. ________

[9] ENSURE GTM-05, HVAC Air Balance, has been submitted to the JTG for concurrence that it adequately satisfies the requirements of this instruction. JTG Meeting: ________ ________

[10] ATTACH completed GTM-05 HVAC Air Balance package for system 30A. ________

[11] ENSURE plant instruments required for test performance, listed on Appendix C, Permanent Plant Instrumentation Log, have been placed in service and are within their calibration

interval. SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14 SubSection 6.29

[12] ENSURE components contained within the boundaries of this test are under the jurisdicti onal control of Preoperational Startup Engineering (PSE) in accordance with SMP-4.0. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 21 of 144

Data Package: Page ____ of ____ Date ________

4.1 Preliminary

Actions (continued)

[13] PERFORM a pretest walkdown on equipment to be tested to ensure no conditions exist that will impact test performance. SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14 SubSection 6.15 SubSection 6.16 SubSection 6.17 SubSection 6.18 SubSection 6.19 SubSection 6.20 SubSection 6.21 SubSection 6.22 SubSection 6.23 SubSection 6.24 SubSection 6.25 SubSection 6.26 SubSection 6.27 SubSection 6.28 SubSection 6.29

[14] CONDUCT a pretest briefing wit h Test and Operations personnel in accordance with SMP-9.0. ________

[15] ENSURE that communications are available for areas where testing is to be conducted. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 22 of 144

Data Package: Page ____ of ____ Date ________

4.2 Special

Tools, Measuring and Test Equipment, Parts, and Supplies [1] OBTAIN the following M&TE or equivalent, AND COMPLETE the following table: DESCRIPTION MINIMUM RANGE ACTUAL RANGE REQUIRED ACCURACY M&TE ID NUMBER CALIBRATION DUE DATE Digital Thermometer with surface

Temperature Probe 0-200 F 3 F Stopwatch N/A 0.5 seconds

________

[2] ENSURE the following are available: A. Handheld Jumper ________

B. Clean cloth soaked in cool water (to cool temperature elements) ________ C. Electric heat gun (to heat temperature elements) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 23 of 144

Data Package: Page ____ of ____ Date ________

4.2 Special

Tools, Measuring and Test Equipment, Parts, and Supplies (continued)

[3] ENSURE M&TE calibration due dates will support the completion of this test performance. SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14 SubSection 6.15 SubSection 6.16 SubSection 6.17 SubSection 6.18 SubSection 6.19 SubSection 6.20 SubSection 6.21 SubSection 6.22 SubSection 6.23 SubSection 6.24 SubSection 6.25 SubSection 6.26 SubSection 6.27 SubSection 6.28 SubSection 6.29

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 24 of 144

Data Package: Page ____ of ____ Date ________

4.3 Field

Preparations

[1] ENSURE applicable portions of Append ix D, Electrical Lineup, have been performed. SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14 SubSection 6.15 SubSection 6.16 SubSection 6.17 SubSection 6.18 SubSection 6.19 SubSection 6.20 SubSection 6.21 SubSection 6.22 SubSection 6.23 SubSection 6.24 SubSection 6.25 SubSection 6.26 SubSection 6.27 SubSection 6.28 SubSection 6.29

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 25 of 144

Data Package: Page ____ of ____ Date ________

4.3 Field

Preparations (continued)

[2] ENSURE applicable portions of A ppendix E, Switch Lineup, have been performed: SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 26 of 144

Data Package: Page ____ of ____ Date ________

4.3 Field

Preparations (continued)

[3] VERIFY there is no Auxiliary Building Isol ation (ABI) or High Radiation in Refuel Area Signals present by: A. The ABI window NOT lit on either the TR-A or TR-B Master Isolation Signal Status Panels (Window 5 on

1-XX-55-6C and 1-XX-55-6D) on 1-M-6. SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14 B. No high rad alarm for 0-RM-90-102 and -103, annunciator window 184B on 0-M-12. SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 27 of 144

Data Package: Page ____ of ____ Date ________

4.3 Field

Preparations (continued)

NOTES 1) Any Annunciator points associated wit h 2-MUX-55-12 and 2-MUX-55-13 ONLY have master switches at the bottom of each terminal strip. 2) All points associated with 2-TBK-55-25, 2-TBK-55-26, 2-TBK-55-27, and 2-TBK-55-28 will not have individual switc hes or a master switch.

[4] ENSURE System 55, Annuncia tor and Sequential Events Recording System, applicable TBK switches are ON, the applicable Master switches are ON, and window software

input(s) are ENABLED for the following Annunciator windows: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK (SubSection 6.29) ________

[5] VERIFY the following systems are operational and have been placed in service to the extent necessary to perform this test: A. System 214, C & A Bldg Vent Boards (480V AC). ________ B. System 032, Control Air ________

C. System 235, 120V AC Vital Instrument Power Boards ________ D. System 55, Annunciator and Sequential Events Recording System ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 28 of 144

Data Package: Page ____ of ____ Date ________

4.3 Field

Preparations (continued)

NOTE The following ERCW valves are electrically disconnected and locked open: 2-FCV-67-188, RHRP ROOM COOLER 2A-A ERCW SUP FLOW CNTL 2-FCV-67-190, RHRP ROOM COOLER 2B-B ERCW SUP FLOW CNTL 2-FCV-67-168, CCP ROOM COOLER 2A-A ERCW SUP FLOW CNTL 2-FCV-67-170, CCP ROOM COOLER 2B-B ERCW SUP FLOW CNTL

[6] VERIFY the following system 67 ERCW valves are available to support test activities: 2-FCV-67-188, RHRP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (SubSection 6.1) 2-FCV-67-190, RHRP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (SubSection 6.2) 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTRL (SubSection 6.3) 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTRL (SubSection 6.4) 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTRL (SubSection 6.5) 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTRL (SubSection 6.6) 2-FCV-67-168, CCP ROOM COOLER 2A-A ERCW SUP FLOW CNTRL (SubSection 6.7) 2-FCV-67-170, CCP ROOM COOLER 2B-B ERCW SUP FLOW CNTRL (SubSection 6.8) 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTRL (SubSection 6.9) 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTRL (SubSection 6.10) 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTRL (SubSection 6.11) 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTRL (SubSection 6.12) 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTRL (SubSection 6.13) 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTRL (SubSection 6.14)

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 29 of 144

Data Package: Page ____ of ____ Date ________

4.3 Field

Preparations (continued)

[7] ENSURE ERCW system is ali gned per 0-SOI-67.01 as applicable to support test performance. ________

[8] VERIFY no other work or test activities are in progress on or near ESF pumps which could cause unexpected pump room

cooler starts. SubSection 6.1 SubSection 6.2 SubSection 6.3 SubSection 6.4 SubSection 6.5 SubSection 6.6 SubSection 6.7 SubSection 6.8 SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 30 of 144

Data Package: Page ____ of ____ Date ________

4.4 Approvals

and Notifications

[1] OBTAIN permission of the Preoperational St artup Manager to start the test. Preoperational St artup Manager Signature Date [2] OBTAIN the Unit 2 Supervisor's (US/

SRO) or Shift Manager's (SM) authorization. U-2 US/SRO/SM Signature Date

[3] NOTIFY Unit 1 Operations that performace of the following sections requres access into the Unit 1 R-panels fo r placement of handheld jumpers. SubSection 6.9 SubSection 6.10 SubSection 6.11 SubSection 6.12 SubSection 6.13 SubSection 6.14

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 31 of 144

Data Package: Page ____ of ____ Date ________

5.0 ACCEPTANCE

CRITERIA A. Auxiliary Building Engineered Safety Features (ESF) Room/Area Coolers function in accordance wit h design requirements. [1] The controls and interlocks for the ESF Coolers function properly. [1.1] Each ESF Cooler STARTS automatically upon receipt of an associated room Hi-Temper ature signal. 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.1[8]) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.2[8]) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.3[8])

2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER (Step 6.4[8])

2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER (Step 6.5[8])

2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER (Step 6.6[8])

2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER (Step 6.7[8]) 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER (Step 6.8[8]) 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A (Step 6.9[8], 6.9[14]) 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B (Step 6.10[8], 6.10[14]) 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A (Step 6.11[8], 6.11[14]) 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B (Step 6.12[8], 6.12[14]) 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A (Step 6.13[8], 6.13[14]) 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B (Step 6.14[8], 6.14[14])

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 32 of 144

Data Package: Page ____ of ____ Date ________

5.0 ACCEPTANCE

CRITERIA (continued)

[1.2] The following ESF Coolers STAR T automatically upon receipt of a simulated Auxiliary Building Isolati on (ABI) signal AND stop when the ABI signal is reset. 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A (Step 6.9[20], 6.9[22]) 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B (Step 6.10[20], 6.10[22]) 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A (Step 6.11[20], 6.11[22]) 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B (Step 6.12[20], 6.12[22]) 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A (Step 6.13[20], 6.13[22]) 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B (Step 6.14[20], 6.14[22])

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 33 of 144

Data Package: Page ____ of ____ Date ________

5.0 ACCEPTANCE

CRITERIA (continued)

[1.3] Each ESF Cooler can be cont rolled manually by local handswitch. 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.1[4]A, 6.1[5]A,V6.1[10.1]) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.2[4]A, 6.2[5]A,V6.2[10.1]) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.3[4]A, 6.3[5]A, 6.3[10.1]) 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER (Step 6.4[4]A, 6.4[5]A, 6.4[10.1]) 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER (Step 6.5[4]A, 6.5[5]A, 6.5[10.1]) 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER (Step 6.6[4]A 6.6[5]A, 6.6[10.1]) 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER (Step 6.7[4]A, 6.7[5]A, 6.7[10.1]) 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER (Step 6.8[4]A, 6.8[5]A, 6.8[10.1]) 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A (Step 6.9[4]A, 6.9[5]A, 6.9[10.1], 6.9[16.1]) 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B (Step 6.10[4]A, 6.10[5]A, 6.10[10.1], 6.10[16.1]) 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A (Step 6.11[4]A, 6.11[5]A, 6.11[10.1], 6.11[16.1]) 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B (Step 6.12[4]A, 6.12[5]A, 6.12[10.1], 6.12[16.1]) 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A (Step 6.13[4]A, 6.13[5]A, 6.13[10.1], 6.13[16.1]) 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B (Step 6.14[4]A, 6.14[5]A, 6.14[10.1], 6.14[16.1])

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 34 of 144

Data Package: Page ____ of ____ Date ________

5.0 ACCEPTANCE

CRITERIA (continued)

NOTE The Acceptance Criteria in the followin g steps have been adjusted to account for 10% of design/rated flow for nontducted, freestandi ng air coolers as delineated in G-37. [2] Each ESF Room Cooler maintains design air flow: 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER (Step 6.15[5]) 6,925 CFM (6,233 - 7,617) 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER (Step 6.16[5]) 6,925 CFM (6,233 - 7,617) 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER (Step 6.17[7])

12,200 CFM (10,980 - 13,420) 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER (Step 6.18[7])

12,200 CFM (10,980 - 13,420) 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER (Step 6.19[7]) 7,850 CFM (7,065 - 8,635) 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER (Step 6.20[7]) 7,850 CFM (7,065 - 8,635) 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER (Step 6.21[5]) 9,200 CFM (8,280 - 10,120) 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER (Step 6.22[5]) 9,200 CFM (8,280 - 10,120) 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A (Step 6.23[7])4,250 CFM (3,825 - 4,675) 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B (Step 6.24[7])4,250 CFM (3,825 - 4,675) 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A (Step 6.25[7])3,950 CFM (3,555 - 4,345) 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B (Step 6.26[7])3,950 CFM (3,555 - 4,345) 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A (Step 6.27[7]) 5,400 CFM (4,860 - 5,940) 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B (Step 6.28[7]) 5,400 CFM (4,860 - 5,940)

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 35 of 144

Data Package: Page ____ of ____ Date ________

5.0 ACCEPTANCE

CRITERIA (continued)

[3] Essential Raw Cooling Water System Valves. [3.1] The following ERCW valves OPEN upon start of their associated ESF Cooler: 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.3[4]C) 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.4[4]C) 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.5[4]C) 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.6[4]C) 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.9[4]C) 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.10[4]C) 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.11[4]C) 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.12[4]C) 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.13[4]C) 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.14[4]C)

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 36 of 144

Data Package: Page ____ of ____ Date ________

5.0 ACCEPTANCE

CRITERIA (continued)

[3.2] The following ERCW valves OPEN in 10 seconds: 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.17[4]) 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.18[4]) 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.19[4]) 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.20[4]) 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.23[4]) 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.24[4]) 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.25[4]) 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.26[4]) 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL (Step 6.27[4]) 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL (Step 6.28[4])

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 37 of 144

Data Package: Page ____ of ____ Date ________

5.0 ACCEPTANCE

CRITERIA (continued)

[4] High Energy Line Break (HELB) Detection [4.1] The following HELB Indicator Lights come ON upon receipt of an associated room Hi-Te mperature signal. 2-XI-30-5235A, LETDOWN HX PIPE BREAK (Step 6.29.2[3]C) 2-XI-30-5235B, LETDOWN HX PIPE BREAK (Step 6.29.2[7]C) 2-XI-30-5236A, RHR PMP RM A PIPE BREAK (Step 6.29.3[3]C) 2-XI-30-5236B, RHR PMP RM A PIPE BREAK (Step 6.29.3[7]C) 2-XI-30-5237A, RHR PMP RM B PIPE BREAK (Step 6.29.4[3]C) 2-XI-30-5237B, RHR PMP RM B PIPE BREAK (Step 6.29.4[7]C) 2-XI-30-5238A, RHR HX A ROOM PIPE BREAK (Step 6.29.5[3]C) 2-XI-30-5238B, RHR HX A ROOM PIPE BREAK (Step 6.29.5[7]C) 2-XI-30-5239A, RHR HX B ROOM PIPE BREAK (Step 6.29.6[3]C) 2-XI-30-5239B, RHR HX B ROOM PIPE BREAK (Step 6.29.6[7]C)

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 38 of 144

Data Package: Page ____ of ____ Date ________

5.0 ACCEPTANCE

CRITERIA (continued)

[4.2] Annunciator window 2-XA-55-6A-113B, RHR/CVCS PIPE BREAK, ALARMS upon reciept of any HELB room Hi-Temperature signal. 2-TS-30-5235A, CVCS LETDOWN HT EXCH RM HI TEMP SW (Step 6.29.2[3]A) 2-TS-30-5235B, CVCS LETDOWN HT EXCH RM HI TEMP SW (Step 6.29.2[7]A) 2-TS-30-5236A, RHR PUMP RM A HI TEMP SW (Step 6.29.3[3]A) 2-TS-30-5236B, RHR PUMP RM A HI TEMP SW (Step 6.29.3[7]A) 2-TS-30-5237A, RHR PUMP RM B HI TEMP SW (Step 6.29.4[3]A) 2-TS-30-5237B, RHR PUMP RM B HI TEMP SW (Step 6.29.4[7]A) 2-TS-30-5238A, RHR HT EXCH A ROOM HI TEMP SW (Step 6.29.5[3]A) 2-TS-30-5238B, RHR HT EXCH A ROOM HI TEMP SW (Step 6.29.5[7]A) 2-TS-30-5239A, RHR HT EXCH B ROOM HI TEMP SW (Step 6.29.6[3]A) 2-TS-30-5239B, RHR HT EXCH B ROOM HI TEMP SW (Step 6.29.6[7]A)

[4.3] Unit 2 Alarm Events Display Scr een indicates the correct alarm upon reciept of each HELB r oom Hi-Temperat ure signal. 2-TS-30-5235A, CVCS LETDOWN HT EXCH RM HI TEMP SW (Step 6.29.2[3]B) 2-TS-30-5235B, CVCS LETDOWN HT EXCH RM HI TEMP SW (Step 6.29.2[7]B) 2-TS-30-5236A, RHR PUMP RM A HI TEMP SW (Step 6.29.3[3]B) 2-TS-30-5236B, RHR PUMP RM A HI TEMP SW (Step 6.29.3[7]B) 2-TS-30-5237A, RHR PUMP RM B HI TEMP SW (Step 6.29.4[3]B) 2-TS-30-5237B, RHR PUMP RM B HI TEMP SW (Step 6.29.4[7]B) 2-TS-30-5238A, RHR HT EXCH A ROOM HI TEMP SW (Step 6.29.5[3]B) 2-TS-30-5238B, RHR HT EXCH A ROOM HI TEMP SW (Step 6.29.5[7]B) 2-TS-30-5239A, RHR HT EXCH B ROOM HI TEMP SW (Step 6.29.6[3]B) 2-TS-30-5239B, RHR HT EXCH B ROOM HI TEMP SW (Step 6.29.6[7]B)

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 39 of 144

Data Package: Page ____ of ____ Date ________

6.0 PERFORMANCE

NOTES 1) SubSections 6.1 through 6.29 may be perform ed in any order or in parallel provided the steps within are perf ormed in the order written unless otherwise noted. 2) All verifications (fan starts, fan stops, valve position, etc) are to be done by local observation unless otherwise noted. 3) IF/THEN steps may be marked N/A if stated condition does not exist.

6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.1 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-175, RHR PUMP 2A-A ROOM COOLER, at 2-JB-292-2506-A, [A11W/676], is in AUTO, AND ENSURE Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-17 5, 480V C&A BUILDING VENT BD 2A1-A, Compartment 9A, Red Light is OFF. ________ B. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 13, FCV-67-188 RHR PMP 2A-A ROOM CLR OPEN, is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 40 of 144

Data Package: Page ____ of ____ Date ________

6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER LOGIC (continued)

[4] PLACE Handswitch 2-HS-30-175, RHR PUMP 2A-A ROOM COOLER, to START, AND VERIFY the following: A. Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-175-A, 480V C&A BUILDING VENT BD 2A1-A, Compartment 9A, Red Light is ON. ________

[5] PLACE Handswitch 2-HS-30-175, RHR PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER 2A-A, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 5, 480V C&A BUILDING VENT BD 2A1-A, Compartment 9A, Red Light is OFF. ________

[6] PLACE Handswitch 2-HS-30-175, RHR PUMP 2A-A ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER 2A-A, remains OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 41 of 144

Data Package: Page ____ of ____ Date ________

6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER LOGIC (continued)

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS 175, RHR PUMP 2A-A ROOM COOLER TEMP, [A11W/676], sensing bulb to a temperature greater than 95 F. [8] VERIFY Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

[10] MAINTAIN Temperature Swit ch 2-TS-30-175, RHR PUMP 2A-A ROOM COOLER TEMP, sensing bulb at a temperature greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-175, RHR PUMP 2A-A ROOM COOLER, to STOP, AND '

VERIFY Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-175, RHR PUMP 2A-A ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-175, RHR PUMP 2A-A ROOM COOLER TEMP, sensing bulb to a temperature less than 90F. ________

[12] VERIFY Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, STOPS. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 42 of 144

Data Package: Page ____ of ____ Date ________

6.1 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER LOGIC (continued)

[13] IF no further testing is to be performed on Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 43 of 144

Data Package: Page ____ of ____ Date ________

6.2 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.2 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-176, RHR PUMP 2B-B ROOM COOLER, at 2-JB-292-2505-B, [A11V/676], is in AUTO, AND ENSURE Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-17 6, 480V C&A BUILDING VENT BD 2B1-B, Compartment 9A, Red Light is OFF. ________ B. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 18, FCV-67-190 RHR PMP 2B-B ROOM CLR OPEN, is ON. ________

[4] PLACE Handswitch 2-HS-30-176, RHR PUMP 2B-B ROOM COOLER, to START, AND VERIFY the following: A. Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 6, 480V C&A BUILDING VENT BD 2B1-B, Compartment 9A, Red Light is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 44 of 144

Data Package: Page ____ of ____ Date ________

6.2 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-176, RHR PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 6, 480V C&A BUILDING VENT BD 2B1-B, Compartment 9A, Red Light is OFF. ________

[6] PLACE Handswitch 2-HS-30-176, RHR PUMP 2B-B ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, remains OFF. ________

CAUTION The following steps will simulate a high am bient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS 176, RHR PUMP 2B-B ROOM COOLER TEMP [A11V

/676], sensing bulb to a temperature greater than 95F. ________

[8] VERIFY Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 45 of 144

Data Package: Page ____ of ____ Date ________

6.2 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER LOGIC (continued)

[10] MAINTAIN Temperature Swit ch 2-TS-30-176, RHR PUMP 2B-B ROOM COOLER TEMP, sensing bulb at a temperature greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-176, RHR PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-176, RHR PUMP 2B-B ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-176, RHR PUMP 2B-B ROOM COOLER TEMP, sensing bulb to a temperature less than 90F. ________

[12] VERIFY Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER STOPS. ________

[13] IF no further testing is to be performed on Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 46 of 144

Data Package: Page ____ of ____ Date ________

6.3 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.3 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-177, CS PUMP 2A-A ROOM COOLER, at 2-JB-292-2502-A, [A10U/676], is in AUTO, AND ENSURE Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-17 7, 480V C&A BUILDING VENT BD 2A1-A, Compartment 3C, Red Light is OFF. ________ B. Valve 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, [A10U/676], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 12, FCV-67-184 CS PMP 2A-A ROOM CLR OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-177, CS PUMP 2A-A ROOM COOLER, to START, AND VERIFY the following: A. Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 7, 480V C&A BUIILDING VENT BD 2A1-A, Compartment 3C, Red Light is ON. ________ C. Valve 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 12, FCV-67-184 CS PMP 2A-A ROOM CLR OPEN, is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 47 of 144

Data Package: Page ____ of ____ Date ________

6.3 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-177, CS PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 7, 480V C&A BUILDING VENT BD 2A1-A, Compartment 3C, Red Light is OFF. ________ C. Valve 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 12, FCV-67-184 CS PMP 2A-A ROOM CLR OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-177, CS PUMP 2A-A ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS 177, CS PUMP 2A-A ROOM COOLER TEMP, [A11U/

676], sensing bulb to a temperature greater than 95F. ________

[8] VERIFY Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 48 of 144

Data Package: Page ____ of ____ Date ________

6.3 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS 177, CS PUMP 2A-A ROOM COOLER TEMP, sensing bul b at a temperature greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-177, CS PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-177, CS PUMP 2A-A ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-177, CS PUMP 2A-A ROOM COOLER TEMP, sensing bulb to a temperature less than 90F. ________

[12] VERIFY Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, STOPS.

[13] IF no further testing is to be performed on Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 49 of 144

Data Package: Page ____ of ____ Date ________

6.4 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.4 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-178, CS PUMP 2B-B ROOM COOLER, at 2-JB-292-2501-B, [A11U/676], is in AUTO, AND ENSURE Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-17 8, 480V C&A BUILDING VENT BD 2B1-B, Compartment 3C, Red Light is OFF. ________ B. Valve 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, [A10U/676], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 19, FCV-67-186 CS PMP 2B-B ROOM CLR OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-178, CS PUMP 2B-B ROOM COOLER, to START, AND VERIFY the following: A. Cooler 2-PMCL-30-17B, CS PUMP 2B-B ROOM COOLER, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 8, 480V C&A BUILDING VENT BD 2B1-B, Compartment 3C, Red Light is ON. ________ C. Valve 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 19, FCV-67-186 CS PMP 2B-B ROOM CLR OPEN, is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 50 of 144

Data Package: Page ____ of ____ Date ________

6.4 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-178, CS PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 8, 480V C&A BUILDING VENT BD 2B1-B, Compartment 3C, Red Light is OFF. ________ C. Valve 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 19, FCV-67-186 CS PMP 2B-B ROOM CLR OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-178, CS PUMP 2B-B ROOM COOLER to AUTO, AND VERIFY Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS 178, CS PUMP 2B-B ROOM COOLER TEMP, [A11T/676

], to a temperature greater than 95F. ________

[8] VERIFY Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 51 of 144

Data Package: Page ____ of ____ Date ________

6.4 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS 178, CS PUMP 2B-B ROOM COOLER TEMP, sensing bul b at a temperature greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-178, CS PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-178, CS PUMP 2B-B ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-178, CS PUMP 2B-B ROOM COOLER TEMP, sensing bulb to a temperature less than 90F. ________

[12] VERIFY Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, STOPS. ________

[13] IF no further testing is to be performed on Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 52 of 144

Data Package: Page ____ of ____ Date ________

6.5 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.5 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-180, SIS PUMP 2A-A ROOM COOLER, at 2-JB-292-1197-A, [A10V/692], is in AUTO, AND ENSURE Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-18 0, 480V C&A BUILDING VENT BD 2A1-A, Compartment 8A, Red Light is OFF. ________ B. Valve 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, [A9V/692], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 1, FCV-67-176 SIP 2A-A ROOM CLR OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-180, SIS PUMP 2A-A ROOM COOLER, to START, AND VERIFY the following: A. Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-18 0, 480V C&A BUILDING VENT BD 2A1-A, Compartment 8A, Red Light is ON. ________ C. Valve 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 1, FCV-67-176 SIP 2A-A ROOM CLR OPEN, is

ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 53 of 144

Data Package: Page ____ of ____ Date ________

6.5 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-180, SIS PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-18 0, 480V C&A BUILDING VENT BD 2A1-A, Compartment 8A, Red Light is OFF. ________ C. Valve 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 1, FCV-67-176 SIP 2A-A ROOM CLR OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-180, SIS PUMP 2A-A ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS 180, SIS PUMP 2A-A ROOM COOLER TEMP, [A10V

/692], sensing bulb to a temperature greater than 95F. ________

[8] VERIFY Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 54 of 144

Data Package: Page ____ of ____ Date ________

6.5 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS 180, SIS PUMP 2A-A ROOM COOLER TEMP, sensing bul b at a temperature greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-180, SIS PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-180, SIS PUMP 2A-A ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, STARTS. ________

[11] COOL Temperature Switch 2-TS 180, SIS PUMP 2A-A ROOM COOLER TEMP, sensing bulb to a temperature less than 90F. ________

[12] VERIFY Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, STOPS. ________

[13] IF no further testing is to be performed on Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 55 of 144

Data Package: Page ____ of ____ Date ________

6.6 2-PMCL-30-179-B, SIS PUMP 2B-B ROOM COOLER LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.6 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-179, SIS PUMP 2B-B ROOM COOLER, at 2-JB-292-1198-B, [A10U/692], is in AUTO, AND ENSURE Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-17 9, 480V C&A BUILDING VENT BD 2B1-B, Compartment 8A, Red Light is OFF. ________ B. Valve 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, [A9V/692], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 10, FCV-67-182 SIP 2B-B ROOM CLR OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-179, SIS PUMP 2B-B ROOM COOLER, to START, AND VERIFY the following: ________ A. Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 9, 480V C&A BUILDING VENT BD 2B1-B, Compartment 8A, Red Light is ON. ________ C. Valve 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 10, FCV-67-182 SIP 2B-B ROOM CLR OPEN, is

ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 56 of 144

Data Package: Page ____ of ____ Date ________

6.6 2-PMCL-30-179-B, SIS PUMP 2B-B ROOM COOLER LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-179, SIS PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-17 9, 480V C&A BUILDING VENT BD 2B1-B, Compartment 8A, Red Light is OFF. ________ C. Valve 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTRL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 10, FCV-67-182 SIP 2B-B ROOM CLR OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-179, SIS PUMP 2B-B ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS 179, SIS PUMP 2B-B ROOM COOLER TEMP, [A9U

/692], sensing bulb to a temperature greater than 95F. ________

[8] VERIFY Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 57 of 144

Data Package: Page ____ of ____ Date ________

6.6 2-PMCL-30-179-B, SIS PUMP 2B-B ROOM COOLER LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS 179, SIS PUMP 2B-B ROOM COOLER TEMP, sensing bul b at a temperature greater than 95 F. [10.1] PLACE Handswitch 2-HS-30-179, SIS PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-179, SIS PUMP 2B-B ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, STARTS. ________

[11] COOL Temperature Switch 2-TS 179, SIS PUMP 2B-B ROOM COOLER TEMP, sensing bulb to a temperature less than 90F. ________

[12] VERIFY Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, STOPS.

[13] IF no further testing is to be performed on Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 58 of 144

Data Package: Page ____ of ____ Date ________

6.7 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.7 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, at 2-JB-292-1191-A,

[A12T/692], is in AUTO, AND ENSURE Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, is OFF. ________

[3] VERIFY the following: ________ A. Breaker 2-BKR-30-183, 480V C&A BUILDLING VENT BD 2A1-A, Compartment 10A, Red Light is OFF. ________ B. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 3, FCV-67-168 CCP 2A-A ROOM CLR OPEN, is

ON. ________

[4] PLACE Handswitch 2-HS-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, to START, AND VERIFY the following: A. Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-183, 480V C&A BUILDLING VENT BD 2A1-A, Compartment 10A, Red Light is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 59 of 144

Data Package: Page ____ of ____ Date ________

6.7 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, to STOP AND VERIFY: A. Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-183, 480V C&A BUILDLING VENT BD 2A1-A, Compartment 10A, Red Light is OFF. ________

[6] PLACE Handswitch 2-HS-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS-30-183, CENT CHARGING PUMP 2A-A RM COOLER TEMP, [A12T/692], sensing bulb to a temperature greater than 95F. ________

[8] VERIFY Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM C OOLER, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 60 of 144

Data Package: Page ____ of ____ Date ________

6.7 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS-30-183, CENT CHARGING PUMP 2A-A RM COOL ER TEMP, sensing bulb at a temperature greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-183, CENT CHARGING PUMP 2A-A RM COOLER TEMP, sensing bulb to a temperature less than 90F. ________

[12] VERIFY Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, STOPS. ________

[13] IF no further testing is to be performed on Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM

COOLER, THEN SECURE Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 61 of 144

Data Package: Page ____ of ____ Date ________

6.8 2-PMCL-30-182, CENT CHARGIN G PUMP 2B-B ROOM COOLER LOGIC [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.8 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, at 2-JB-292-1192-B,

[A11U/692], is in AUTO, AND ENSURE Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-18 2, 480V C&A BUILDING VENT BD 2B1-B, Compartment 10A, Red Light is OFF. ________ B. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 8, FCV-67-170 CCP 2B-B ROOM CLR OPEN, is

ON. ________

[4] PLACE Handswitch 2-HS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, to START, AND VERIFY the following: A. Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-18 2, 480V C&A BUILDING VENT BD 2B1-B, Compartment 10A, Red Light is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 62 of 144

Data Package: Page ____ of ____ Date ________

6.8 2-PMCL-30-182, CENT CHARGIN G PUMP 2B-B ROOM COOLER LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-18 2, 480V C&A BUILDING VENT BD 2B1-B, Compartment 10A, Red Light is OFF. ________

[6] PLACE Handswitch 2-HS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER TEMP, [A11U/692], sensing bulb to a temperatur e greater than 95F. ________

[8] VERIFY Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM C OOLER, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 63 of 144

Data Package: Page ____ of ____ Date ________

6.8 2-PMCL-30-182, CENT CHARGIN G PUMP 2B-B ROOM COOLER LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER TEMP, sensing bulb at a temperatur e greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, to AUTO, AND VERIFY Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER TEMP, sensing bulb to a temperature less than 90F. ________

[12] VERIFY Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, STOPS. ________

[13] IF no further testing is to be performed on Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM

COOLER, THEN SECURE Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 64 of 144

Data Package: Page ____ of ____ Date ________

6.9 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A LOGIC [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.9 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, at 2-JB-292-1553-A, [A12U/693], is in

AUTO, AND ENSURE Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-18 6, 480V C&A BUILDING VENT BD 2A1-A, Compartment 2C, Red Light is OFF. ________ B. Valve 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, [A12U/692], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 23, FCV-67-346 PENT ROOM CLR 2 A1 OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to START, AND VERIFY the following: A. Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-18 6, 480V C&A BUILDING VENT BD 2A1-A, Red Light is ON. ________ C. Valve 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 23, FCV-67-346 PENT ROOM CLR 2 A1 OPEN, is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 65 of 144

Data Package: Page ____ of ____ Date ________

6.9 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-18 6, 480V C&A BUILDING VENT BD 2A1-A, Red Light is OFF. ________ C. Valve 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 23, FCV-67-346 PENT ROOM CLR 2 A1 OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to AUTO, AND VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS-30-186A, PENETRATION ROOM EL 692 COOLER 2A-A TEMP, [A12U/692], sensing bulb to a temperatur e greater than 85F. ________

[8] VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 105 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 66 of 144

Data Package: Page ____ of ____ Date ________

6.9 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS-30-186A PENETRATION ROOM EL 692 COOLER 2A-A TEMP, sensing bulb at a tem perature greater than 85F. ________

[10.1] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to STOP, AND VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to AUTO, AND VERIFY Cooler 2-CLR-30-186-A, PENETRATION ROOM EL 692 COOLER 2A-A, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-186A, PENETRATION ROOM EL 692 COOLER 2A-A TE MP, sensing bulb, until it resets, AND VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STOPS. ________

[12] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to STANDBY, AND VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[13] HEAT Temperature Switch 2-TS-30-186B, PENETRATION ROOM EL 692 COOLER 2A-A TEMP, [A12U/692], sensing bulb to a temperatur e greater than 90F. ________

[14] VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STARTS. (Acc Crit) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 67 of 144

Data Package: Page ____ of ____ Date ________

6.9 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A LOGIC (continued)

[15] IF temperature of the s ensing bulb reaches 110 F, THEN STOP applying heat to the sensing bulb. ________

[16] MAINTAIN Temperature Switch 2-TS-30-186B, PENETRATION ROOM EL 692 COOLER 2A-A TEMP, sensing bulb at a tem perature greater than 90F. ________

[16.1] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A to STOP, AND VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STOPS. (Acc Crit) ________

[16.2] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to STANDBY, AND VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STARTS. ________

[17] COOL Temperature Switch 2-TS-30-186B, PENETRATION ROOM EL 692 COOLER 2A-A TEMP, sensing bulb until it

resets, AND VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STOPS. ________

[18] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to AUTO, AND VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, remains OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 68 of 144

Data Package: Page ____ of ____ Date ________

6.9 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A LOGIC (continued)

NOTE The following step will simulate an Auxiliary Building Isolation (ABI) Signal by placing a jumper across terminal points in Auxiliary Rela y panel 1-R-73.

[19] PLACE and HOLD a handheld jumper at TB 339, between Pt.

10 and Pt. 11 in Auxiliary Relay Panel 1-R-73. ________ 1st

________

CV [20] VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STARTS. (Acc Crit) ________

[21] REMOVE handheld jumper at TB 339 between Pt. 10 and Pt.

11 in Auxiliary Relay Panel 1-R-73. ________ 1st

________

CV [22] VERIFY Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STOPS. (Acc Crit) ________

[23] IF no further testing is to be performed on Cooler 2-CLR-30-186, PENETRATION ROOM EL 692

COOLER 2A-A, THEN SECURE Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 69 of 144

Data Package: Page ____ of ____ Date ________

6.10 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B LOGIC [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.10 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B at, 2-JB-292-1554-B, [A12V/692], is in AUTO, AND ENSURE Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-18 7, 480V C&A BUILDING VENT BD 2B1-B, Compartment 8B, Red Light is OFF. ________ B. Valve 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, [A12V/692], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 26, FCV-67-348 PENT ROOM CLR 2 B1 OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, to START, AND VERIFY the following: A. Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-18 7, 480V C&A BUILDING VENT BD 2B1-B, Compartment 8B, Red Light is ON. ________ C. Valve 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 26, FCV-67-348 PENT ROOM CLR 2 B1 OPEN,is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 70 of 144

Data Package: Page ____ of ____ Date ________

6.10 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-18 7, 480V C&A BUILDING VENT BD 2B1-B, Red Light is OFF. ________ C. Valve 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 26, FCV-67-348 PENT ROOM CLR 2 B1 OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS-30-187A, PENETRATION ROOM EL 692 COOLER 2B-B TEMP, [A12V/692], sensing bulb to a temperatur e greater than 85F. ________

[8] VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 105 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 71 of 144

Data Package: Page ____ of ____ Date ________

6.10 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS-30-187A, PENETRATION ROOM EL 692 COOLER 2B-B TEMP, sensing bulb at a tem perature greater than 85F. ________

[10.1] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B to STOP, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-187-B, PENETRATION ROOM EL 692 COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-187A, PENETRATION ROOM EL 692 COOLER 2B-B TEMP, sensing bulb until it

resets, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STOPS. ________

[12] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, to STANDBY, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[13] HEAT Temperature Switch 2-TS-30-187B, PENETRATION ROOM EL 692 COOLER 2B-B TEMP, [A12V/692], sensing bulb to a temperatur e greater than 90F. ________

[14] VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STARTS. (Acc Crit) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 72 of 144

Data Package: Page ____ of ____ Date ________

6.10 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B LOGIC (continued)

[15] IF temperature of the s ensing bulb reaches 110 F, THEN STOP applying heat to the sensing bulb. ________

[16] MAINTAIN Temperature Switch 2-TS-30-187B, PENETRATION ROOM EL 692 COOLER 2B-B TEMP, sensing bulb at a tem perature greater than 90F. ________

[16.1] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, to STOP, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STOPS. (Acc Crit) ________

[16.2] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, to STANDBY, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STARTS. ________

[17] COOL Temperature Switch 2-TS-30-187B, PENETRATION ROOM EL 692 COOLER 2B-B TEMP, sensing bulb until it

resets, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STOPS. ________

[18] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, remains OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 73 of 144

Data Package: Page ____ of ____ Date ________

6.10 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B LOGIC (continued)

NOTE The following step will simulate an Auxiliary Building Isolation (ABI) Signal by placing a jumper across terminal points in Auxiliary Rela y panel 1-R-78.

[19] PLACE and HOLD a handheld jumper at TB 838, between Pt. 1 and Pt. 2 in Auxiliary Relay Panel 1-R-78. ________

1st

________

CV [20] VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STARTS. (Acc Crit) ________

[21] REMOVE handheld jumper at TB 838 between Pt. 1 and Pt. 2 in Auxiliary Relay Panel 1-R-78. ________

1st

________

CV [22] VERIFY Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STOPS. (Acc Crit) ________

[23] IF no further testing is to be performed on Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER

2B-B, THEN SECURE Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 74 of 144

Data Package: Page ____ of ____ Date ________

6.11 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A LOGIC [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.11 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, at 2-JB-292-1503-A, [A14V/713], is in

AUTO, AND ENSURE Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-19 6, 480V C&A BUILDING VENT BD 2A1-A, Compartment 10B, Red Light is OFF. ________ B. Valve 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, [A14V/713], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 24, FCV-67-350 PENT ROOM CLR 2 A2 OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, to START, AND VERIFY the following: A. Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 2A-A, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-19 6, 480V C&A BUILDING VENT BD 2A1-A, Compartment 10B, Red Light is ON. ________ C. Valve 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 24, FCV-67-350 PENT ROOM CLR 2 A2 OPEN, is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 75 of 144

Data Package: Page ____ of ____ Date ________

6.11 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-19 6, 480V C&A BUILDING VENT BD 2A1-A, Compartment 10B, Red Light is OFF. ________ C. Valve 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 24, FCV-67-350 PENT ROOM CLR 2 A2 OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-19A, PENETRATION ROOM EL 713 COOLER 2A-A, to AUTO AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS-30-196A, PENETRATION ROOM EL 713 COOLER 2A-A TEMP SWITCH, [A14V/713], sensing bulb to a tem perature greater than 90F. ________

[8] VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 110 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 76 of 144

Data Package: Page ____ of ____ Date ________

6.11 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS-30-196A, PENETRATION ROOM EL 713 COOLER 2A-A TEMP SWITCH, sensing bulb at a temperature greater than 90F. ________

[10.1] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, to STOP, AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, to AUTO, AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-196A, PENETRATION ROOM EL 713 COOLER 2A-A TEMP SWITCH, sensing bulb

until it resets, AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STOPS. ________

[12] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, to STANDBY, AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[13] HEAT Temperature Switch 2-TS-30-196B, PENETRATION ROOM EL 713 COOLER 2A-A TEMP SWITCH, [A14V/713], sensing bulb to a tem perature greater than 95F. ________

[14] VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STARTS. (Acc Crit) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 77 of 144

Data Package: Page ____ of ____ Date ________

6.11 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A LOGIC (continued)

[15] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

[16] MAINTAIN Temperature Switch 2-TS-30-196B, PENETRATION ROOM EL 713 COOLER 2A-A TEMP SWITCH, sensing bulb at a temperature greater than 95F. ________

[16.1] PLACE Handswitch 2-HS-30-196, EL 713 PENT ROOM COOLER 2A-A, to STOP, AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STOPS. (Acc Crit) ________

[16.2] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, to STANDBY, AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STARTS. ________

[17] COOL Temperature Switch 2-TS-30-196B, PENETRATION ROOM EL 713 COOLER 2A-A TEMP SWITCH, sensing bulb

until it resets, AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STOPS. ________

[18] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, to AUTO, AND VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, remains OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 78 of 144

Data Package: Page ____ of ____ Date ________

6.11 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A LOGIC (continued)

NOTE The following step will simulate an Auxiliary Building Isolation (ABI) Signal by placing a jumper across terminal points in Auxiliary Rela y panel 1-R-73.

[19] PLACE and HOLD a handheld jumper at TB 340, between Pt.

11 and Pt. 12 in Auxiliary Relay Panel 1-R-73. ________ 1st

________

CV [20] VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STARTS. (Acc Crit) ________

[21] REMOVE handheld jumper at TB 340 between Pt. 11 and Pt.

12 in Auxiliary Relay Panel 1-R-73. ________ 1st

________

CV [22] VERIFY Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STOPS. (Acc Crit) ________

[23] IF no further testing is to be performed on Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER

2A-A, THEN SECURE Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 79 of 144

Data Package: Page ____ of ____ Date ________

6.12 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B LOGIC [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.12 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, at 2-JB-292-1505-B, [A14V/713], is in

AUTO, AND ENSURE Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-19 7, 480V C&A BUILDING VENT BD 2B1-B, Compartment 2C, Red Light is OFF. ________ B. Valve 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, [A14V/713], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 27, FCV-67-352 PENT ROOM CLR 2 B2 OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to START, AND VERIFY the following: A. Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-19 7, 480V C&A BUILDING VENT BD 2B1-B Compartment 2C, Red Light is ON. ________ C. Valve 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 27, FCV-67-352 PENT ROOM CLR 2 B2 OPEN, is ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 80 of 144

Data Package: Page ____ of ____ Date ________

6.12 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-19 7, 480V C&A BUILDING VENT BD 2B1-B, Compartment 2C, Red Light is OFF. ________ C. Valve 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 27, FCV-67-352 PENT ROOM CLR 2 B2 OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS-30-197A, PENETRATION ROOM EL 713 COOLER 2B-B TEMP SWITCH, [A14V/713], sensing bulb to a tem perature greater than 90F. ________

[8] VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 110 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 81 of 144

Data Package: Page ____ of ____ Date ________

6.12 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS-30-197A, PENETRATION ROOM EL 713 COOLER 2B-B TEMP SWITCH, sensing bulb at a temperature greater than 90F. ________

[10.1] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to STOP, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-197A, PENETRATION ROOM EL 713 COOLER 2B-B TEMP SWITCH, sensing bulb

until it resets, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STOPS. ________

[12] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to STANDBY, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, remains OFF. ________

CAUTION The following steps will simulate a high am bient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[13] HEAT Temperature Switch 2-TS-30-197B, PENETRATION ROOM EL 713 COOLER 2B-B TEMP SWITCH, [A14V/713], sensing bulb to a tem perature greater than 95F. ________

[14] VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STARTS. (Acc Crit) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 82 of 144

Data Package: Page ____ of ____ Date ________

6.12 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B LOGIC (continued)

[15] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

[16] MAINTAIN Temperature Switch 2-TS-30-197B, PENETRATION ROOM EL 713 COOLER 2B-B TEMP SWITCH, sensing bulb at a temperature greater than 95F. ________

[16.1] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to STOP, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STOPS. (Acc Crit) ________

[16.2] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to STANDBY, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STARTS. ________

[17] COOL Temperature Switch 2-TS-30-197B, PENETRATION ROOM EL 713 COOLER 2B-B TEMP SWITCH, sensing bulb

until it resets, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STOPS. ________

[18] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, remains OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 83 of 144

Data Package: Page ____ of ____ Date ________

6.12 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B LOGIC (continued)

NOTE The following step will simulate an Auxiliary Building Isolation (ABI) Signal by placing a jumper across terminal points in Auxiliary Rela y panel 1-R-78.

[19] PLACE and HOLD a handheld jumper at TB 838, between Pt. 3 and Pt. 4 in Auxiliary Relay Panel 1-R-78. ________

1st

________

CV [20] VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STARTS. (Acc Crit) ________

[21] REMOVE handheld jumper at TB 838 between Pt. 3 and Pt. 4 in Auxiliary Relay Panel 1-R-78. ________

1st

________

CV [22] VERIFY Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STOPS. (Acc Crit) ________

[23] IF no further testing is to be performed on Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER

2B-B, THEN SECURE Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 84 of 144

Data Package: Page ____ of ____ Date ________

6.13 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.13 have been completed. ________

[2] ENSURE Handswitch 2-HS 201, AB EL 692 PIPE CHASE COOLER 2A-A at 2-JB-292-1555-A, [A15U/692], is in AUTO, AND ENSURE Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-20 1, 480V C&A BUILDING VENT BD 2A1-A, Compartment 10C, Red Light is OFF. ________ B. Valve 2-FCV-67-342, PI PE CHASE COOLER 2A-A ERCW SUP FLOW CNTL, [A15U/692], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27A, Window 22, FCV-67-342 PIPE CHASE CLR 2 A OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to START, AND VERIFY the following: A. Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-20 1, 480V C&A BUILDING VENT BD 2A1-A, Compartment 10C, Red Light is ON. ________ C. Valve 2-FCV-67-342, PI PE CHASE COOLER 2A-A ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27A, Window 22, FCV-67-342 PIPE CHASE CLR 2 A OPEN, is

ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 85 of 144

Data Package: Page ____ of ____ Date ________

6.13 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-20 1, 480V C&A BUILDING VENT BD 2A1-A, Compartment 10C, Red Light is OFF. ________ C. Valve 2-FCV-67-342, PI PE CHASE COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27A, Window 22, FCV-67-342 PIPE CHASE CLR 2 A OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to AUTO, AND VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS-30-201A, AB EL 692 PIPE CHASE COOLER 2A-A TEMP, [A12U

/692], sensing bulb to a temperature greater than 95F. ________

[8] VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 86 of 144

Data Package: Page ____ of ____ Date ________

6.13 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A LOGIC (continued)

[10] MAINTAIN Temperature Switch 2-TS-30-201A, AB EL 692 PIPE CHASE COOLER 2A-A TEMP, sensing bulb at a temperature greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to STOP, AND VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to AUTO, AND VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-201A, AB EL 692 PIPE CHASE COOLER 2A-A TEMP, sensing bulb until it resets, AND VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STOPS. ________

[12] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to STANDBY, AND VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, remains OFF. ________

CAUTION The following steps will simulate a high am bient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[13] HEAT Temperature Switch 2-TS-30-201B, AB EL 692 PIPE CHASE COOLER 2A-A TEMP, [A12U

/692], sensing bulb to a temperature greater than 100F. ________

[14] VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STARTS. (Acc Crit) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 87 of 144

Data Package: Page ____ of ____ Date ________

6.13 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A LOGIC (continued)

[15] IF temperature of the s ensing bulb reaches 120 F, THEN STOP applying heat to the sensing bulb. ________

[16] MAINTAIN Temperature Switch 2-TS-30-201B, AB EL 692 PIPE CHASE COOLER 2A-A TEMP, sensing bulb at a temperature greater than 100F. ________

[16.1] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to STOP, AND VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STOPS. (Acc Crit) ________

[16.2] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to STANDBY, AND VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STARTS. ________

[17] COOL Temperature Switch 2-TS-30-201B, AB EL 692 PIPE CHASE COOLER 2A-A TEMP, sensing bulb until it resets, AND VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STOPS. ________

[18] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to AUTO, AND VERIFY Cooler 2-CLR-30-201-A, AB EL 692 PIPE CHASE COOLER 2A-A, remains OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 88 of 144

Data Package: Page ____ of ____ Date ________

6.13 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A LOGIC (continued)

NOTE The following step will simulate an Auxiliary Building Isolation (ABI) Signal by placing a jumper across terminal points in Auxiliary Rela y panel 1-R-73.

[19] PLACE and HOLD a handheld jumper at TB 340, between Pt. 9 and Pt. 10 in Auxiliary Relay Panel 1-R-73. ________

1st

________

CV [20] VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STARTS. (Acc Crit) ________

[21] REMOVE handheld jumper at TB 340 between Pt. 9 and Pt.

10 in Auxiliary Relay Panel 1-R-73. ________ 1st

________

CV [22] VERIFY Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STOPS. (Acc Crit) ________

[23] IF no further testing is to be performed on Cooler 2-CLR-30-201, AB EL 692 PI PE CHASE COOLER 2A-A, THEN SECURE Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A.. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 89 of 144

Data Package: Page ____ of ____ Date ________

6.14 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B LOGIC

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.14 have been completed. ________

[2] ENSURE Handswitch 2-HS 202, AB EL 692 PIPE CHASE COOLER 2B-B, at 2-JB-292-1556-B, [A14U/692], is in AUTO, AND ENSURE cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, is OFF. ________

[3] VERIFY the following: A. Breaker 2-BKR-30-20 2, 480V C&A BUILDING VENT BD 2B1-B, Compartment 3B, Red Light is OFF. ________ B. Valve 2-FCV-67-344, PI PE CHASE COOLER 2B-B ERCW SUP FLOW CNTL, [A14U/692], is CLOSED. ________ C. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 29, FCV-67-344 PIPE CHASE CLR 2 B OPEN, is OFF. ________

[4] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to START, AND VERIFY the following: A. 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STARTS. (Acc Crit) ________ B. Breaker 2-BKR-30-20 2, 480V C&A BUILDING VENT BD 2B1-B, Compartment 3B, Red Light is ON. ________ C. Valve 2-FCV-67-344, PI PE CHASE COOLER 2B-B ERCW SUP FLOW CNTL, is OPEN. (Acc Crit) ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 29, FCV-67-344 PIPE CHASE CLR 2 B OPEN, is

ON. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 90 of 144

Data Package: Page ____ of ____ Date ________

6.14 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B LOGIC (continued)

[5] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STOPS. (Acc Crit) ________ B. Breaker 2-BKR-30-20 2, 480V C&A BUILDING VENT BD 2B1-B, Compartment 3B, Red Light is OFF. ________ C. Valve 2-FCV-67-344, PI PE CHASE COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED. ________ D. On Panel 0-M-27A, CLRS ERCW SUP, 0-XX-55-27B, Window 29, FCV-67-344 PIPE CHASE CLR 2 B OPEN, is OFF. ________

[6] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[7] HEAT Temperature Switch 2-TS-30-202A, AB EL 692 PIPE CHASE COOLER 2B-B TEMP, [A12U

/692], sensing bulb to a temperature greater than 95F. ________

[8] VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STARTS. (Acc Crit) ________

[9] IF temperature of the s ensing bulb reaches 115 F, THEN STOP applying heat to the sensing bulb. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 91 of 144

Data Package: Page ____ of ____ Date ________

6.14 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B LOGIC (continued)

[10] MAINTIAN Temperature Switch 2-TS-30-202A, AB EL 692 PIPE CHASE COOLER 2B-B TEMP, sensing bulb at a temperature greater than 95F. ________

[10.1] PLACE Handswitch 2-HS-30-20B, AB EL 692 PIPE CHASE COOLER 2B-B, to STOP, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STOPS. (Acc Crit) ________

[10.2] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STARTS. ________

[11] COOL Temperature Switch 2-TS-30-202A, AB EL 692 PIPE CHASE COOLER 2B-B TEMP, sensing bulb until it resets, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STOPS. ________

[12] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to STANDBY, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, remains OFF. ________

CAUTION The following steps will simulate a high ambi ent room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[13] HEAT Temperature Switch 2-TS-30-202B, AB EL 692 PIPE CHASE COOLER 2B-B TEMP, [A12U

/692], sensing bulb to a temperature greater than 100F. ________

[14] VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STARTS. (Acc Crit) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 92 of 144

Data Package: Page ____ of ____ Date ________

6.14 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B LOGIC (continued)

[15] IF temperature of the s ensing bulb reaches 120 F, THEN STOP applying heat to the sensing bulb. ________

[16] MAINTAIN Temperature Switch 2-TS-30-202B, AB EL 692 PIPE CHASE COOLER 2B-B TEMP, sensing bulb at a temperature greater than 100F. ________

[16.1] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to STOP, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STOPS. (Acc Crit) ________

[16.2] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to STANDBY, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STARTS. ________

[17] COOL Temperature Switch 2-TS-30-202B, AB EL 692 PIPE CHASE COOLER 2B-B TEMP, sensing bulb until it resets, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STOPS. ________

[18] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to AUTO, AND VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, remains OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 93 of 144

Data Package: Page ____ of ____ Date ________

6.14 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B LOGIC (continued)

NOTE The following step will simulate an Auxiliary Building Isolation (ABI) Signal by placing a jumper across terminal points in Auxiliary Rela y panel 1-R-78.

[19] PLACE and HOLD a handheld jumper at TB 837, between Pt. 9 and Pt. 10 in Auxiliary Relay Panel 1-R-78. ________

1st

________

CV [20] VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STARTS. (Acc Crit) ________

[21] REMOVE handheld jumper at TB 837 between Pt. 9 and Pt.

10 in Auxiliary Relay Panel 1-R-78. ________ 1st

________

CV [22] VERIFY Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STOPS. (Acc Crit) ________

[23] IF no further testing is to be performed on Cooler 2-CLR-30-202, AB EL 692 PI PE CHASE COOLER 2B-B, THEN SECURE Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 94 of 144

Data Package: Page ____ of ____ Date ________

6.15 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER AIR FLOW

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.15 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-175, RHR PUMP 2A-A ROOM COOLER, at 2-JB-292-2506-A [A11W/676], is in START, AND ENSURE Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, is ON. ________

[3] OBSERVE operation of Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, AND VERIFY that it is in a steady state condition. ________

[4] ENSURE Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, air flow measurement has been performed using

GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[5] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 6,925 CFM (6,233 - 7,617) ________

[6] PLACE Handswitch 2-HS-30-175, RHR PUMP 2A-A ROOM COOLER to STOP, AND VERIFY that Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER STOPS. ________

[7] IF no further testing is to be performed on Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-175, RHR PUMP 2A-A ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 95 of 144

Data Package: Page ____ of ____ Date ________

6.16 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER AIR FLOW

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.16 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-176, RHR PUMP 2B-B ROOM COOLER, at 2-JB-292-2505-B, [A11V/676], is in START, AND ENSURE Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, is ON. ________

[3] OBSERVE operation of Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, AND VERIFY that it is in a steady state condition. ________

[4] ENSURE Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, air flow measurement has been performed using

GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[5] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 6,925 CFM (6,233 - 7,617) ________

[6] PLACE Handswitch 2-HS-30-176, RHR PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY that Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, STOPS. ________

[7] IF no further testing is to be performed on Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-176, RHR PUMP 2B-B ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 96 of 144

Data Package: Page ____ of ____ Date ________

6.17 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER AIR FLOW

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.17 have been completed. ________

[2] ENSURE Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, is OFF, AND ENSURE Valve 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, [A10U/676], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-177, CS PUMP 2A-A ROOM COOLER, at 2-JB-292-2502-A, [A10U/676], to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, AND VERIFY that it is in a steady state condition. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 97 of 144

Data Package: Page ____ of ____ Date ________

6.17 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER AIR FLOW (continued)

[6] ENSURE Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, air flow measurement has been performed using

GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 12,200 CFM (10,980 - 13,420) ________

[8] PLACE Handswitch 2-HS-30-177, CS PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, STOPS. ________ B. Valve 2-FCV-67-184, CSP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-177, CS PUMP 2A-A ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 98 of 144

Data Package: Page ____ of ____ Date ________

6.18 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER AIR FLOW

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.18 have been completed. ________

[2] ENSURE Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, is OFF, AND ENSURE Valve 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, [A10U/676], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-178, CS PUMP 2B-B ROOM COOLER, at 2-JB-292-2501-B, [A11U/676], to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, AND VERIFY that it is in a steady state condition. ________

[6] ENSURE Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, air flow measurement has been performed using

GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 99 of 144

Data Package: Page ____ of ____ Date ________

6.18 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER AIR FLOW (continued)

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 12,200 CFM (10,980 - 13,420) ________

[8] PLACE Handswitch 2-HS-30-178, CS PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, STOPS. ________ B. Valve 2-FCV-67-186, CSP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED ________

[9] IF no further testing is to be performed on Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-178, CS PUMP 2B-B ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 100 of 144

Data Package: Page ____ of ____ Date ________

6.19 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER AIR FLOW

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.19 have been completed. ________

[2] ENSURE Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, is OFF, AND ENSURE Valve 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, [A9V/692], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-180, SIS PUMP 2A-A ROOM COOLER, at 2-JB-292-1197-A, [A10V/692], to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, AND VERIFY that it is in a steady state condition. ________

[6] ENSURE Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, air flow measurement has been performed using

GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 101 of 144

Data Package: Page ____ of ____ Date ________

6.19 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER AIR FLOW (continued)

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 7,850 CFM (7,065 - 8,635) ________

[8] PLACE Handswitch 2-HS-30-180, SIS PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, STOPS. ________ B. Valve 2-FCV-67-176, SIP ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-180, SIS PUMP 2A-A ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 102 of 144

Data Package: Page ____ of ____ Date ________

6.20 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER AIR FLOW

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.20 have been completed. ________

[2] ENSURE Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, is OFF, AND ENSURE Valve 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, [A9V/692], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-179, SIS PUMP 2B-B ROOM COOLER, at 2-JB-292-1198-B, [A10U/692], to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, AND VERIFY that it is in a steady state condition. ________

[6] ENSURE Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, air flow measurement has been performed using

GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 103 of 144

Data Package: Page ____ of ____ Date ________

6.20 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER AIR FLOW (continued)

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 7,850 CFM (7,065 - 8,635) ________

[8] PLACE Handswitch 2-HS-30-179, SIS PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY the following: A. Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER STOPS. ________ B. Valve 2-FCV-67-182, SIP ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER, THEN SECURE Cooler 2-PMCL-30-179, SIS PUMP 2B-B ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 104 of 144

Data Package: Page ____ of ____ Date ________

6.21 2-PMCL-30-183, CENT CHARGIN G PUMP 2A-A ROOM COOLER AIR FLOW [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.21 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, at 2-JB-292-1191-A, [A12T/692], is in START, AND ENSURE Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, is ON. ________

[3] OBSERVE operation of Cooler 2-PMCL-30-183-A, CENT CHARGING PUMP 2A-A ROOM COOLER, AND VERIFY that it is in a steady state condition. ________

[4] ENSURE Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, ai r flow measurement has been performed using GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[5] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 9,200 CFM (8,280 - 10,120) ________

[6] PLACE Handswitch 2-HS-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER, STOPS. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 105 of 144

Data Package: Page ____ of ____ Date ________

6.21 2-PMCL-30-183, CENT CHARGIN G PUMP 2A-A ROOM COOLER AIR FLOW (continued)

[7] IF no further testing is to be performed on Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM

COOLER, THEN SECURE Cooler 2-PMCL-30-183, CENT CHARGING PUMP 2A-A ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 106 of 144

Data Package: Page ____ of ____ Date ________

6.22 2-PMCL-30-182, CENT CHARGIN G PUMP 2B-B ROOM COOLER AIR FLOW [1] VERIFY prerequisites listed in Sect ion 4.0 for SubSection 6.22 have been completed. ________

[2] ENSURE Handswitch 2-HS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, at 2-JB-292-1192-B,

[A11U/692], is in START, AND ENSURE Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, is ON. ________

[3] OBSERVE operation of Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, AND VERIFY that it is in a steady state condition. ________

[4] ENSURE Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, ai r flow measurement has been performed using GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[5] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 9,200 CFM (8,280 - 10,120) ________

[6] PLACE Handswitch 2-HS-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, to STOP, AND VERIFY Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER, STOPS. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 107 of 144

Data Package: Page ____ of ____ Date ________

6.22 2-PMCL-30-182, CENT CHARGIN G PUMP 2B-B ROOM COOLER AIR FLOW (continued)

[7] IF no further testing is to be performed on Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM

COOLER, THEN SECURE Cooler 2-PMCL-30-182, CENT CHARGING PUMP 2B-B ROOM COOLER. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 108 of 144

Data Package: Page ____ of ____ Date ________

6.23 2-PMCL-30-186, PENETRATION ROOM EL 692 COOLER 2A-A AIR FLOW [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.23 have been completed. ________

[2] ENSURE Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A is OFF, AND ENSURE Valve 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, [A12U/692], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, at 2-JB-292-1553-A, [A12U/692],

to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 109 of 144

Data Package: Page ____ of ____ Date ________

6.23 2-PMCL-30-186, PENETRATION ROOM EL 692 COOLER 2A-A AIR FLOW (continued)

[5] OBSERVE operation of Cool er 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, AND VERIFY that it is in a steady state condition. ________

[6] ENSURE Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, air flow measurement has been

performed using GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 4,250 CFM (3,825 - 4,675) ________

[8] PLACE Handswitch 2-HS-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A, STOPS. ________ B. Valve 2-FCV-67-346, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER

2A-A, THEN SECURE Cooler 2-CLR-30-186, PENETRATION ROOM EL 692 COOLER 2A-A. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 110 of 144

Data Package: Page ____ of ____ Date ________

6.24 2-PMCL-30-187, PENETRATION ROOM EL 692 COOLER 2B-B AIR FLOW [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.24 have been completed. ________

[2] ENSURE Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B is OFF, AND ENSURE Valve 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, [A12V/692], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, at 2-JB-292-1554-B, [A12V/692],

to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cool er 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, AND VERIFY that it is in a steady state condition. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 111 of 144

Data Package: Page ____ of ____ Date ________

6.24 2-PMCL-30-187, PENETRATION ROOM EL 692 COOLER 2B-B AIR FLOW (continued)

[6] ENSURE Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, air flow measurement has been

performed using GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 4,250 CFM (3,825 - 4,675) ________

[8] PLACE Handswitch 2-HS-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, to STOP, AND VERIFY the following A. Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B, STOPS. ________ B. Valve 2-FCV-67-348, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER

2B-B, THEN SECURE Cooler 2-CLR-30-187, PENETRATION ROOM EL 692 COOLER 2B-B. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 112 of 144

Data Package: Page ____ of ____ Date ________

6.25 2-CLR-30-196, PENETRATION R OOM EL 713 COOLER 2A-A AIR FLOW [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.25 have been completed. ________

[2] ENSURE Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, is OFF, AND ENSURE Valve 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, [A14V/713], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, at 2-JB-292-1503-A, [A14V/713],

to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cool er 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, AND VERIFY that it is in a steady state condition. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 113 of 144

Data Package: Page ____ of ____ Date ________

6.25 2-CLR-30-196, PENETRATION R OOM EL 713 COOLER 2A-A AIR FLOW (continued)

[6] ENSURE Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, air flow measurement has been

performed using GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 3,950 CFM (3,555 - 4,345) ________

[8] PLACE Handswitch 2-HS-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A, STOPS. ________ B. Valve 2-FCV-67-350, PENT ROOM COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER

2A-A, THEN SECURE Cooler 2-CLR-30-196, PENETRATION ROOM EL 713 COOLER 2A-A. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 114 of 144

Data Package: Page ____ of ____ Date ________

6.26 2-CLR-30-197, PENETRATION R OOM EL 713 COOLER 2B-B AIR FLOW [1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.26 have been completed. ________

[2] ENSURE Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, is OFF, AND ENSURE Valve 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, [A14V/713], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, at 2-JB-292-1505-B, [A14V/713],

to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cool er 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, AND VERIFY that it is in a steady state condition. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 115 of 144

Data Package: Page ____ of ____ Date ________

6.26 2-CLR-30-197, PENETRATION R OOM EL 713 COOLER 2B-B AIR FLOW (continued)

[6] ENSURE Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, air flow measurement has been

performed using GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 3,950 CFM (3,555 - 4,345) ________

[8] PLACE Handswitch 2-HS-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B, STOPS. ________ B. Valve 2-FCV-67-352, PENT ROOM COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER

2B-B, THEN SECURE Cooler 2-CLR-30-197, PENETRATION ROOM EL 713 COOLER 2B-B. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 116 of 144

Data Package: Page ____ of ____ Date ________

6.27 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A AIR FLOW

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.27 have been completed. ________

[2] ENSURE Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, is OFF, AND ENSURE Valve 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL, [A15U/692], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, at 2-JB-292-155 5-A, [A15U/692], to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-342, PIPE CHASE COOLER 2A-A ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, AND VERIFY that it is in a steady state condition. ________

[6] ENSURE Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, air flow m easurement has been performed using GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 117 of 144

Data Package: Page ____ of ____ Date ________

6.27 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A AIR FLOW (continued)

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 5,400 CFM (4,860 - 5,940) ________

[8] PLACE Handswitch 2-HS-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A, STOPS. ________ B. Valve 2-FCV-67-342, PI PE CHASE COOLER 2A-A ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-CLR-30-201, AB EL 692 PI PE CHASE COOLER 2A-A, THEN SECURE Cooler 2-CLR-30-201, AB EL 692 PIPE CHASE COOLER 2A-A. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 118 of 144

Data Package: Page ____ of ____ Date ________

6.28 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B AIR FLOW

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.28 have been completed. ________

[2] ENSURE Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, is OFF, AND ENSURE Valve 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL, [A14U/692], is CLOSED. ________

NOTE The following steps require valve stroke timing locally at the valve. Local valve stroke timing begins with the initiating signal and is concluded with the completion of valve stem movement.

[3] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, at 2-JB-292-155 6-B, [A14U/692], to START, AND MEASURE the stroke OPEN time of Valve 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL. ________

[4] RECORD stroke OPEN time of Valve 2-FCV-67-344, PIPE CHASE COOLER 2B-B ERCW SUP FLOW CNTL, AND VERIFY it meets acceptance criteria.

seconds M&TE:

Acc Crit: 10 seconds maximum _______ [5] OBSERVE operation of Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, AND VERIFY it is in a steady state condition. ________

[6] ENSURE Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, air flow m easurement has been performed using GTM-05, AND ENSURE completed GTM-05 data sheets are attached. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 119 of 144

Data Package: Page ____ of ____ Date ________

6.28 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B AIR FLOW (continued)

[7] RECORD the air flow measurement below, AND VERIFY it meets acceptance criteria.

CFM Acc Crit: 5,400 CFM (4,860 - 5,940) ________

[8] PLACE Handswitch 2-HS-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, to STOP, AND VERIFY the following: A. Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B, STOPS. ________ B. Valve 2-FCV-67-344, PI PE CHASE COOLER 2B-B ERCW SUP FLOW CNTL, is CLOSED. ________

[9] IF no further testing is to be performed on Cooler 2-CLR-30-202, AB EL 692 PI PE CHASE COOLER 2B-B, THEN SECURE Cooler 2-CLR-30-202, AB EL 692 PIPE CHASE COOLER 2B-B. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 120 of 144

Data Package: Page ____ of ____ Date ________

6.29 HIGH ENERGY LINE BREAK (HELB) DETECTION.

[1] ENSURE prerequisites listed in Section 4.0 for SubSection 6.29 have been completed. ________

[2] VERIFY 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, is CLEAR (NOT LIT). ________

[3] VERIFY the Unit 2 Alarm Events Display Screen on Panel 2-M-16A indicates the following inputs are in

NORMAL (Green): A. 113-B CVC LTDN HX RM HI TEMP PIPE BREAK (TS-30-5235 A/B) ________ B. 113-B RHR PUMP RM A HI TEMP PIPE BREAK (TS-30-5236 A/B) ________ C. 113-B RHR PUMP RM B HI TEMP PIPE BREAK (TS-30-5237 A/B) ________ D. 113-B RHR HX RM A HI TEMP PIPE BREAK (TS-30-5238 A/B) ________ E. 113-B RHR HX RM B HI TEMP PIPE BREAK (TS-30-5239 A/B) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 121 of 144

Data Package: Page ____ of ____ Date ________

6.29 HIGH ENERGY LINE BREAK (HELB) DETECTION. (continued)

[4] VERIFY The following Indicating Light s on Panel 2-M-6, are OFF: A. 2-XI-30-5235A, LETDOWN HX PIPE BREAK ________

B. 2-XI-30-5235B, LETDOWN HX PIPE BREAK ________

C. 2-XI-30-5236A, RHR PMP RM A PIPE BREAK ________ D. 2-XI-30-5236B, RHR PMP RM A PIPE BREAK ________ E. 2-XI-30-5237A, RHR PMP RM B PIPE BREAK ________ F. 2-XI-30-5237B, RHR PMP RM B PIPE BREAK ________ G. 2-XI-30-5238A, RHR HX A RM PIPE BREAK ________ H. 2-XI-30-5238B, RHR HX A RM PIPE BREAK ________ I. 2-XI-30-5239A, RHR HX B RM PIPE BREAK ________ J. 2-XI-30-5239B, RHR HX B RM PIPE BREAK ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 122 of 144

Data Package: Page ____ of ____ Date ________

NOTE SubSections 6.29.2 through 6.29.6 may be perf ormed in any order provided the steps within are performed in the order written.

6.29.2 CVCS LETDOWN HEAT EXCHANGER ROOM HELB DETECTION CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[1] HEAT Temperature Switch 2-TS-30-5235A, CVCS LETDOWN HT EXCH RM HI TEMP SW, on Panel 2-L-730A, [A10U/737], sensing bulb to a tem perature greater than 144F. ________

[2] IF temperature of the s ensing bulb reaches 165 F, THEN STOP applying heat to the sensing bulb. ________

[3] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B CVC LTDN HX RM HI TEMP PIPE BREAK (TS-30-5235 A/B),

is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI 5235A, LETDOWN HX PIPE BREAK, is ON. (Acc Crit) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 123 of 144

Data Package: Page ____ of ____ Date ________

6.29.2 CVCS LETDOWN HEAT EXCHANGER ROOM HELB DETECTION (continued)

[4] COOL Temperature Switch 2-TS 5235A, CVCS LETDOWN HT EXCH RM HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B CVC LTDN HX RM HI TEMP PIPE BREAK (TS-30-5235 A/B),

is NORMAL (Green). ________ C. Indicating Light 2-XI 5235A, LETDOWN HX PIPE BREAK, is OFF. ________

CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[5] HEAT Temperature Switch 2-TS-30-5235B, CVCS LETDOWN HT EXCH RM HI TEMP SW, on Panel 2-L-730B, [A10U/737], sensing bulb to a tem perature greater than 144F. ________

[6] IF temperature of the s ensing bulb reaches 165 F, THEN STOP applying heat to the sensing bulb. ________

[7] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B CVC LTDN HX RM HI TEMP PIPE BREAK (TS-30-5235 A/B),

is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI 5235B, LETDOWN HX PIPE BREAK, is ON. (Acc Crit) ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 124 of 144

Data Package: Page ____ of ____ Date ________

6.29.2 CVCS LETDOWN HEAT EXCHANGER ROOM HELB DETECTION (continued)

[8] COOL Temperature Switch 2-TS 5235A, CVCS LETDOWN HT EXCH RM HI TEMP SW, sensing bulb until resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B CVC LTDN HX RM HI TEMP PIPE BREAK (TS-30-5235 A/B),

is NORMAL (Green). ________ C. Indicating Light 2-XI 5235B, LETDOWN HX PIPE BREAK, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 125 of 144

Data Package: Page ____ of ____ Date ________

6.29.3 RHR PUMP ROOM 2A HELB DETECTION CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[1] HEAT Temperature Switch 2-TS-30-5236A, RHR PUMP RM A HI TEMP SW, on Panel 2-L-731A, [A10W/676], sensing bulb to a temperature greater than 144F. ________

[2] IF temperature of the s ensing bulb reaches 165 F, THEN STOP applying heat to the sensing bulb. ________

[3] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR PUMP ROOM A HI TEMP PIPE BREAK (TS-30-5236 A/B), is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI-30-5236A, RHR PMP RM A PIPE BREAK, is ON. (Acc Crit) ________

[4] COOL Temperature Switch 2-TS-30-5236A, RHR PUMP RM A HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR PUMP ROOM A HI TEMP PIPE BREAK (TS-30-5236 A/B), is NORMAL (Green). ________ C. Indicating Light 2-XI-30-5236A, RHR PMP RM A PIPE BREAK, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 126 of 144

Data Package: Page ____ of ____ Date ________

6.29.3 RHR PUMP ROOM 2A HE LB DETECTION (continued)

CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe..

[5] HEAT Temperature Switch 2-TS-30-5236B, RHR PUMP RM A HI TEMP SW, on Panel 2-L-731B, [A10W/676], sensing bulb to a temperature greater than 144F. ________

[6] IF temperature of the s ensing bulb reaches 165 F, THEN STOP applying heat to the sensing bulb. ________

[7] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR PUMP ROOM A HI TEMP PIPE BREAK (TS-30-5236 A/B), is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI-30-5236B, RHR PMP RM A PIPE BREAK, is ON. (Acc Crit) ________

[8] COOL Temperature Switch 2-TS-30-5236B, RHR PUMP RM A HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR PUMP ROOM A HI TEMP PIPE BREAK (TS-30-5236 A/B), is NORMAL (Green). ________ C. Indicating Light 2-XI-30-5236B, RHR PMP RM A PIPE BREAK, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 127 of 144

Data Package: Page ____ of ____ Date ________

6.29.4 RHR PUMP ROOM 2B HELB DETECTION CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[1] HEAT Temperature Switch 2-TS-30-5237A, RHR PUMP RM B HI TEMP SW, on Panel 2-L-732A, [A10V/676], sensing bulb to a temperature greater than 144F. ________

[2] IF temperature of the s ensing bulb reaches 165 F, THEN STOP applying heat to the sensing bulb. ________

[3] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR PUMP ROOM B HI TEMP PIPE BREAK (TS-30-5237 A/B), is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI-30-5237A, RHR PMP RM B PIPE BREAK, is ON. (Acc Crit) ________

[4] COOL Temperature Switch 2-TS-30-5236A, RHR PUMP RM B HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR PUMP ROOM B HI TEMP PIPE BREAK (TS-30-5237 A/B), is NORMAL (Green). ________ C. Indicating Light 2-XI-30-5237A, RHR PMP RM B PIPE BREAK, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 128 of 144

Data Package: Page ____ of ____ Date ________

6.29.4 RHR PUMP ROOM 2B HE LB DETECTION (continued)

CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[5] HEAT Temperature Switch 2-TS-30-5237B, RHR PUMP RM B HI TEMP SW, on Panel 2-L-732B, [A10V/676], sensing bulb to a temperature greater than 144F. ________

[6] IF temperature of the s ensing bulb reaches 165 F, THEN STOP applying heat to the sensing bulb. ________

[7] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR PUMP ROOM B HI TEMP PIPE BREAK (TS-30-5237 A/B), is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI-30-5237B, RHR PMP RM B PIPE BREAK, is ON. (Acc Crit) ________

[8] COOL Temperature Switch 2-TS-30-5237B, RHR PUMP RM B HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR PUMP ROOM B HI TEMP PIPE BREAK (TS-30-5237 A/B), is NORMAL (Green). ________ C. Indicating Light 2-XI-30-5237B, RHR PMP RM B PIPE BREAK, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 129 of 144

Data Package: Page ____ of ____ Date ________

6.29.5 RHR HEAT EXCHANGER ROOM 2A HELB DETECTION CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[1] HEAT Temperature Switch 2-TS-30-5238A, RHR HEAT EXCH A ROOM HI TEMP SW , on 2-L-733A, [A10V/713], sensing bulb to greater than 134F. ________

[2] IF temperature of the s ensing bulb reaches 155 F, THEN STOP applying heat to the sensing bulb. ________

[3] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR HX ROOM A HI TEMP PIPE BREAK (TS-30-5238 A/B), is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI-30-5238A, RHR HX A RM PIPE BREAK, is ON. (Acc Crit) ________

[4] COOL Temperature Switch 2-TS-30-5238A, RHR HEAT EXCH A ROOM HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR HX ROOM A HI TEMP PIPE BREAK (TS-30-5238 A/B), is NORMAL (Green). ________ C. Indicating Light 2-XI-30-5238A, RHR HX A RM PIPE BREAK, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 130 of 144

Data Package: Page ____ of ____ Date ________

6.29.5 RHR HEAT EXCHANGER ROOM 2A HELB DETECTION (continued)

CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[5] HEAT Temperature Switch 2-TS-30-5238B, RHR HEAT EXCH A ROOM HI TEMP SW , on 2-L-733B, [A10W/713], sensing bulb to greater than 134F. ________

[6] IF temperature of the s ensing bulb reaches 155 F, THEN STOP applying heat to the sensing bulb. ________

[7] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR HX ROOM A HI TEMP PIPE BREAK (TS-30-5238 A/B), is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI-30-5238B, RHR HX A RM PIPE BREAK, is ON. (Acc Crit) ________

[8] COOL Temperature Switch 2-TS-30-5238B, RHR HEAT EXCH A ROOM HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR HX ROOM A HI TEMP PIPE BREAK (TS-30-5238 A/B), is NORMAL (Green). ________ C. Indicating Light 2-XI-30-5238B, RHR HX A RM PIPE BREAK, is OFF. ________ Indicating Light 2-XI-30-5237A-A, RHR HEAT EXCH A ROOM HI TEMP IND LT, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 131 of 144

Data Package: Page ____ of ____ Date ________

6.29.6 RHR HEAT EXCHANGER ROOM 2B HELB DETECTION CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[1] HEAT Temperature Switch 2-TS-30-5239A, RHR HEAT EXCH B ROOM HI TEMP SW , on 2-L-734A, [A10V/713], sensing bulb to greater than 134F. ________

[2] IF temperature of the s ensing bulb reaches 155 F, THEN STOP applying heat to the sensing bulb. ________

[3] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR HX ROOM B HI TEMP PIPE BREAK (TS-30-5239 A/B), is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI-30-5239A, RHR HX B RM PIPE BREAK, is ON. (Acc Crit) ________

[4] COOL Temperature Switch 2-TS-30-5239A, RHR HEAT EXCH B ROOM HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR HX ROOM B HI TEMP PIPE BREAK (TS-30-5239 A/B), is NORMAL (Green). ________ C. Indicating Light 2-XI-30-5239A, RHR HX B RM PIPE BREAK, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 132 of 144

Data Package: Page ____ of ____ Date ________

6.29.6 RHR HEAT EXCHANGER ROOM 2B HELB DETECTION (continued)

CAUTION The following step will simulate a high ambient room temperature using an electric heatgun. Heat the temperature switch sensing bulb SLOWLY while monitoring the bulb temperature with a surface temperature probe.

[5] HEAT Temperature Switch 2-TS-30-5239B, RHR HEAT EXCH B ROOM HI TEMP SW , on 2-L-734B, [A10U/713], sensing bulb to greater than 134F. ________

[6] IF temperature of the s ensing bulb reaches 155 F, THEN STOP applying heat to the sensing bulb. ________

[7] VERIFY the following A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, ALARMS. (Acc Crit) ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR HX ROOM B HI TEMP PIPE BREAK (TS-30-5239 A/B), is in ALARM (Red). (Acc Crit) ________ C. Indicating Light 2-XI-30-5239B, RHR HX B RM PIPE BREAK, is ON. (Acc Crit) ________

[8] COOL Temperature Switch 2-TS-30-5239B, RHR HEAT EXCH B ROOM HI TEMP SW, sensing bulb until it resets, AND VERIFY the following: A. 2-XA-55-6A-113B, RHR/CVCS HI TEMP PIPE BREAK, CLEARS. ________ B. Unit 2 Alarm Events Display Screen indicates 113-B RHR HX ROOM B HI TEMP PIPE BREAK (TS-30-5239 A/B), is NORMAL (Green). ________ C. Indicating Light 2-XI-30-5239B, RHR HX B RM PIPE BREAK, is OFF. ________

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 133 of 144

Data Package: Page ____ of ____ Date ________

7.0 POST PERFORMANCE ACTIVITIES

[1] NOTIFY the Unit 2 US/SRO of t he test completion and system alignment. ________

8.0 RECORDS

A. QA Records Completed Test Package. B. Non-QA Records

None WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 134 of 144 Appendix A (Page 1 of 4) TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW Data Package: Page ____ of ____ Date ________

NOTES 1) Additional copies of this table may be made as necessary. 2) Initial and date indicates review has been completed for impact PROCEDURE/ INSTRUCTION REVISION/CHANGES IMPACT Yes/No INITIAL AND DATE (N/A for no change) SMP-4.0 SMP-8.0 SMP-9.0 0-SOI-67.01 GTM-05 GTM-03 2-TSD-030A-01 FSAR Section 9.2.1 Section 9.4.5.3 Table 14.2-1 Shts 4 & 5, 36 & 37 of 90 2-PTI-067-02 2-PTI-062-01 2-PTI-063-5A 2-PTI-063-05B 2-PTI-072-01 2-PTI-074-01 2-PTI-262-01 2-PTI-262-02 G-37 0-PI-OPS-1.1 WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 135 of 144 Appendix A (Page 2 of 4) TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW

Data Package: Page ____ of ____ Date ________

PROCEDURE/ INSTRUCTION REVISION/CHANGES IMPACT Yes/No INITIAL AND DATE (N/A for no change) WBN2-30AB-4001 WBN2-67-4002 WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 136 of 144 Appendix A (Page 3 of 4) TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW

Data Package: Page ____ of ____ Date ________

PROCEDURE/ INSTRUCTION REVISION/CHANGES IMPACT Yes/No INITIAL AND DATE (N/A for no change) SSD-2-TS-30-175 SSD-2-TS-30-176 SSD-2-TS-30-177 SSD-2-TS-30-178 SSD-2-TS-30-179 SSD-2-TS-30-180 SSD-2-TS-30-182 SSD-2-TS-30-183 SSD-2-TS-30-186A SSD-2-TS-30-186B SSD-2-TS-30-187A SSD-2-TS-30-187B SSD-2-TS-30-196A SSD-2-TS-30-196B SSD-2-TS-30-197A SSD-2-TS-30-197B SSD-2-TS-30-201A SSD-2-TS-30-201B SSD-2-TS-30-202A SSD-2-TS-30-202B WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 137 of 144 Appendix A (Page 4 of 4) TEST PROCEDURES/INSTRUCTIONS REFERENCE REVIEW

Data Package: Page ____ of ____ Date ________

PROCEDURE/ INSTRUCTION REVISION/CHANGES IMPACT Yes/No INITIAL AND DATE (N/A for no change) SSD-2-TS-30-5235A SSD-2-TS-30-5235B SSD-2-TS-30-5236A SSD-2-TS-30-5236B SSD-2-TS-30-5237A SSD-2-TS-30-5237B SSD-2-TS-30-5238A SSD-2-TS-30-5238B SSD-2-TS-30-5239A SSD-2-TS-30-5239B

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 138 of 144 Appendix B (Page 1 of 1)

TEMPORARY CONDITION LOG Data Package: Page ____ of ____ Date ________

NOTE These steps will be N/A'd if no temporary condition existed. Additional copies of this table may be made as necessary.

ITEM No. TEMPORARY CONDITION DESCRIPTION PERFORMED RETURNED TO NORMAL Step No. Performed By/Date CV By/Date Step No. Returned By/Date CV By/Date WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 139 of 144 Appendix C (Page 1 of 3) PERMANENT PLANT INSTRUMENTATION LOG Data Package: Page ____ of ____ Date ________

INSTRUMENT OR INSTRUMENT LOOP # CAL DUE DATE FILLED AND VENTED 1 PLACED IN SERVICE 1 USED FOR QUANTITATIVE ACC CRIT POST-TEST CAL DATE 2 POST-TEST CALIBRATION ACCEPTABLE 2 INITIAL/DATE INIT/DATE INIT/DATE YES NO 2-TS-30-175 N/A N/A NO N/A N/A 2-TS-30-176 N/A N/A NO N/A N/A 2-TS-30-177 N/A N/A NO N/A N/A 2-TS-30-178 N/A N/A NO N/A N/A 2-TS-30-179 N/A N/A NO N/A N/A 2-TS-30-180 N/A N/A NO N/A N/A 2-TS-30-182 N/A N/A NO N/A N/A 2-TS-30-183 N/A N/A NO N/A N/A WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 140 of 144 Appendix C (Page 2 of 3) PERMANENT PLANT INSTRUMENTATION LOG

Data Package: Page ____ of ____ Date ________

INSTRUMENT OR INSTRUMENT LOOP # CAL DUE DATE FILLED AND VENTED 1 PLACED IN SERVICE 1 USED FOR QUANTITATIVE ACC CRIT POST-TEST CAL DATE 2 POST-TEST CALIBRATION ACCEPTABLE 2 INITIAL/DATE INIT/DATE INIT/DATE YES NO 2-TS-30-186A N/A N/A NO N/A N/A 2-TS-30-186B N/A N/A NO N/A N/A 2-TS-30-187A N/A N/A NO N/A N/A 2-TS-30-187B N/A N/A NO N/A N/A 2-TS-30-196A N/A N/A NO N/A N/A 2-TS-30-196B N/A N/A NO N/A N/A 2-TS-30-197A N/A N/A NO N/A N/A 2-TS-30-197B N/A N/A NO N/A N/A 2-TS-30-201A N/A N/A NO N/A N/A 2-TS-30-201B N/A N/A NO N/A N/A 2-TS-30-202A N/A N/A NO N/A N/A 2-TS-30-202B N/A N/A NO N/A N/A WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 141 of 144 Appendix C (Page 3 of 3) PERMANENT PLANT INSTRUMENTATION LOG

Data Package: Page ____ of ____ Date ________

INSTRUMENT OR INSTRUMENT LOOP # CAL DUE DATE FILLED AND VENTED 1 PLACED IN SERVICE 1 USED FOR QUANTITATIVE ACC CRIT POST-TEST CAL DATE 2 POST-TEST CALIBRATION ACCEPTABLE 2 INITIAL/DATE INIT/DATE INIT/DATE YES NO 2-TS-30-5235A N/A N/A NO N/A N/A 2-TS-30-5235B N/A N/A NO N/A N/A 2-TS-30-5236A N/A N/A NO N/A N/A 2-TS-30-5236B N/A N/A NO N/A N/A 2-TS-30-5237A N/A N/A NO N/A N/A 2-TS-30-5237B N/A N/A NO N/A N/A 2-TS-30-5238A N/A N/A NO N/A N/A 2-TS-30-5238B N/A N/A NO N/A N/A 2-TS-30-5239A N/A N/A NO N/A N/A 2-TS-30-5239B N/A N/A NO N/A N/A 1 These items may be initialed and dated by personnel performing the task. Instrumentation not required to be filled and vented may be identified as Not Applicable. (N/A) 2 May be identified as Not Applicable (N/A) if instrument was not used to verify/record quantitative acceptance criteria data.

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 142 of 144 Appendix D (Page 1 of 2)

ELECTRICAL LINEUP Data Package: Page ____ of ____ Date ________

SECTIONS IDENTIFICATION DESCRIPTION LOCATION POSITION INIT 6.1, 6.15 2-BKR-30-175 RHR PUMP 2A-A RM COOLER C&A Building Vent BD 2A1-A Compartment 9A ON (CLOSED) 6.2, 6.16 2-BKR-30-176 RHR PUMP 2B-B RM COOLER C&A Building Vent BD 2B1-B Compartment 9A ON (CLOSED) 6.3, 6.17 2-BKR-30-177 CS PUMP 2A-A RM COOLER C&A Building Vent BD 2A1-A Compartment 3C ON (CLOSED) 6.4, 6.18 2-BKR-30-178 CS PUMP 2B-B RM COOLER C&A Building Vent BD 2B1-B Compartment 3C ON (CLOSED) 6.5, 6.19 2-BKR-30-180 SIS PUMP 2A-A RM COOLER C&A Building Vent BD 2A1-A Compartment 8A ON (CLOSED) 6.6, 6.20 2-BKR-30-179 SIS PUMP 2B-B RM COOLER C&A Building Vent BD 2B1-B Compartment 8A ON (CLOSED) 6.7, 6.21 2-BKR-30-183 CENT CHG PUMP 2A-A RM COOLER C&A Building Vent BD 2A1-A Compartment 10A ON (CLOSED) 6.8, 6.22 2-BKR-30-182 CENT CHG PUMP 2B-B RM COOLER C&A Building Vent BD 2B1-B Compartment 10A ON (CLOSED) 6.9, 6.23 2-BKR-30-186 PENT RM EL 692 CLR 2A-A C&A Building Vent BD 2A1-A Compartment 2C ON (CLOSED) 6.10, 6.24 2-BKR-30-187 PENT RM EL 692 CLR 2B-B C&A Building Vent BD 2B1-B Compartment 8B ON (CLOSED)

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 143 of 144 Appendix D (Page 2 of 2)

ELECTRICAL LINEUP

Data Package: Page ____ of ____ Date ________

SECTIONS IDENTIFICATION DESCRIPTION LOCATION POSITION INIT 6.11, 6.25 2-BKR-30-196 PENT RM EL 713 CLR 2A-A C&A Building Vent BD 2A1-A Compartment 10B ON (CLOSED) 6.12, 6.26 2-BKR-30-197 PENT RM EL 713 CLR 2B-B C&A Building Vent BD 2B1-B Compartment 2C ON (CLOSED) 6.13, 6.27 2-BKR-30-201 AB EL 692 PIPE CHASE CLR 2A-A C&A Building Vent BD 2A1-A Compartment 10C ON (CLOSED) 6.14, 6.28 2-BKR-30-202 AB EL 692 PIPE CHASE CLR 2B-B C&A Building Vent BD 2B1-B Compartment 3B ON (CLOSED) 6.29 2-BKR-235-1/11-D AUX RELAY RACK A BUS TO PANEL 2-R-75 120V AC Vital Inst Pwr BD 2-I ON (CLOSED) 6.29 2-BKR-235-2/9-E AUX RELAY RACK B BUS TO PANEL 2-R-75 120V AC Vital Inst Pwr BD 2-II ON (CLOSED) 6.29 2-BKR-235-2/10-E AUX RELAY RACK 2-R-75 BUS C 120V AC Vital Inst Pwr BD 2-II ON (CLOSED) 6.29 2-BKR-235-3/30-F SEPERATION AUX RELAY PANELS 2-R-73/2-R-74 120V AC Vital Inst Pwr BD 2-III ON (CLOSED) 6.29 2-BKR-235-4/39-G SEPERATION AUX RELAY PANELS 2-R-77/2-R-78 120V AC Vital Inst Pwr BD 2-IV ON (CLOSED)

WBN Unit 2 Unit 2 Auxiliary Building ESF Coolers 2-PTI-030A-01 Rev. 0000 Page 144 of 144 Appendix E (Page 1 of 1) SWITCH LINEUP Data Package: Page ____ of ____ Date ________

SECTION SWITCH NUMBER SWITCH LOCATION NOMENCLATURE POSITION VERIFIED BY INITIALS 6.1 2-HS-30-175 2-JB-292-2506-A [A11W/676] RHR PUMP 2A-A ROOM COOLER AUTO after STOP 6.2 2-HS-30-176 2-JB-292-2505-B

[A11V/676] RHR PUMP 2B-B ROOM COOLER AUTO after STOP 6.3 2-HS-30-177 2-JB-292-2502-A [A10U/676] CS PUMP 2A-A ROOM COOLER AUTO after STOP 6.4 2-HS-30-178 2-JB-292-2501-B [A11U/676] CS PUMP 2B-B ROOM COOLER AUTO after STOP 6.5 2-HS-30-180 2-JB-292-1197-A

[A10V/692]

SIS PUMP 2A-A ROOM COOLER AUTO after STOP 6.6 2-HS-30-179 2-JB-292-1198-B [A10U/692]

SIS PUMP 2B-B ROOM COOLER AUTO after STOP 6.7 2-HS-30-183 2-JB-292-1191-A [A12T/692] CENT CHARGING PUMP 2A-A ROOM COOLER AUTO after STOP 6.8 2-HS-30-182 2-JB-292-1192-B [A11U/692] CENT CHARGING PUMP 2B-B ROOM COOLER AUTO after STOP 6.9 2-HS-30-186 2-JB-292-1553-A [A12U/692] PENETRATION ROOM EL 692 COOLER 2A-A AUTO after STOP 6.10 2-HS-30-187 2-JB-292-1554-B

[A12V/692] PENETRATION ROOM EL 692 COOLER 2B-B AUTO after STOP 6.11 2-HS-30-196 2-JB-292-1503-A

[A14V/713] PENETRATION ROOM EL 713 COOLER 2A-A AUTO after STOP 6.12 2-HS-30-197 2-JB-292-1505-B

[A14V/713] PENETRATION ROOM EL 713 COOLER 2B-B AUTO after STOP 6.13 2-HS-30-201 2-JB-292-1555-A [A15U/692]

AB EL 692 PIPE CASE COOLER 2A-A AUTO after STOP 6.14 2-HS-30-202 2-JB-292-1556-B [A14U/692]

AB EL 692 PIPE CASE COOLER 2B-B FLOW AUTO after STOP