ZS-2013-0195, Fire Protection Report, Amendment 13

From kanterella
Jump to navigation Jump to search
Fire Protection Report, Amendment 13
ML13214A372
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 07/31/2013
From: Thurman P
ZionSolutions
To:
Document Control Desk, NRC/FSME
References
ZS-2013-0195
Download: ML13214A372 (129)


Text

ZIONSOLUTIONSLLC An EnergySoiutns Company 10 CFR 50.71 (e)(4) 10 CFR 50.48(f)

July 31, 2013 ZS-2013-0195 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Zion Nuclear Power Station, Units 1 and 2 Facility Operating License Nos. DPR-39 and DPR-48 NRC Docket Nos. 50-295 and 50-304

Subject:

Zion Nuclear Power Station Fire Protection Report, Amendment 13

References:

ZionSolutions, LLC Letter, P. Thurman to U.S. NRC, "Zion Nuclear Power Station Fire Protection Report, Amendment 12," dated July 31, 2011 In accordance with the requirements of 10 CFR 50.71, "Maintenance of records, making of reports," paragraph (e)(4), ZionSolutions, LLC is submitting Amendment 13 to the Fire Protection Report (FPR) for the Zion Nuclear Power Station (ZNPS), Units 1 and 2. This FPR amendment is being submitted within 24 months of the previous ZNPS FPR amendment that was submitted in the referenced letter. The ZNPS FPR is a document incorporated by reference in the ZNPS Defueled Safety Analysis Report. Accordingly, this amendment is due to be submitted by July 31, 2013.

A summary of the changes made to the ZNPS FPR is provided in Attachment 1. These changes reflect the changes that were made through June 1, 2013, under the provisions of 10 CFR 50.48 "Fire protection," paragraph (f). provides the replacement pages for Amendment 13 of the ZNPS FPR as required by 10 CFR 50.71(e) and is accompanied by a list of effective pages and instructions for updating the ZNPS FPR. We have evaluated the FPR changes in accordance with 10 CFR 50.48(f) and concluded the changes do not reduce the effectiveness of fire protection for the facilities, systems and equipment which result in a radiological hazard, taking into account the current decommissioning plant conditions and activities of ZNPS, and do not require prior NRC approval.

This submittal accurately presents changes made since the previous submittal and reflects information and analysis performed under the provisions of 10 CFR 50.48 but not previously submitted to the NRC.

101 Shiloh Boulevard, Zion

  • IL60099 (224) 789-4016
  • Fax: (224) 789-4008
  • www.zionsolutionscompany.com * )4F-

ZionSolutions, LLC ZS-2013-0195 Page 2 of 2 If you have any questions regarding this letter, please contact Mr. Jim Ashley at (847) 379-2978.

ParikS.Tumn, Esq.

Vice President Regulatory Affairs ZionSolutions, LLC Attachments:

1. Summary of Changes - Amendment 13, Fire Protection Report - Zion Station
2. Zion Station Fire Protection Report - Amendment 13, July 2013 cc: John Hickman, U.S. NRC Senior Project Manager Service List

Zion Nuclear Power Station, Unit 1 and 2 License Transfer Service List cc:

Patrick T. Daly Dan Shrum Senior VP and General Manager Senior VP Regulatory Affairs ZionSolutions, LLC EnergySolutions 101 Shiloh Boulevard 423 West 300 South, Ste. 200 Zion, IL 60099 Salt Lake City, UT 84101 Patrick Thurman, Esq. Russ Workman VP Regulatory Affairs, Licensing & General Counsel Document Control EnergySolutions ZionSolutions, LLC 423 West 300 South, Ste. 200 101 Shiloh Boulevard Salt Lake City, UT 84101 Zion, IL 60099 Illinois Department of Nuclear Safety Gary Bouchard Office of Nuclear Facility Safety VP Engineering, Ops & Nuclear Security and 1035 Outer Park Drive Decommissioning Plant Manager Springfield, IL 62704 ZionSolutions, LLC 101 Shiloh Boulevard Kent McKenzie Zion, IL 60099 Emergency Management Coordinator Lake County Emergency Management Alan Parker Agency President Projects Group 1303 N. Milwaukee Avenue EnergySolutions Libertyville, IL 60048-1308 1009 Commerce Park Drive, Ste. 100 Oak Ridge, TN 37830 Regional Administrator U.S. NRC, Region III John Christian 2443 Warrenville Road President of Logistics, Processing and Lisle, IL 60532-4352 Disposal (LP& D) Group EnergySolutions John E. Matthews 1750 Tysons Boulevard, Suite 1500 Morgan, Lewis & Bockius LLP Mclean, VA 22102 1111 Pennsylvania Avenue, NW Washington, DC 20004

ZionSolutions, LLC ZS-2013-0195: Attachment 1 ATTACHMENT 1

SUMMARY

OF CHANGES AMENDMENT 12 OF THE FIRE PROTECTION REPORT - ZION STATION The "affected pages" listed below are the pages revised in Amendment 13.

FPR Revision # 2011-03 Derate select Radiological Controlled Area (RCA) fires barriers. The fire barrier derating is justified by the elimination of significant combustible loads and the quantity of radioactive material remaining in the RCA. Additionally, combustible load information has been updated to reflect the removal of select combustible loads.

Affected pages: 2-5, 2-8, 2-10, 2-12, 2-15, 2-16, 2-20, 2-21, 2-25, 2-26, 2-27, 2-28, 2-29, 2-30, 2-31, 2-32, 2-33, 2-34, 2-40, 2-41, 2-42, 3-1, 3-1a, 3-9, 3-10, 3-16, 3-17, 3-67, 3-69, 3-113, 3-114, 3-116, 3-124, 3-125, 3-127, 3-131, 3-133, 3-135, 3-145, 3-146, 3-218, 3-239, 3-241, 3-251, 3-252, 3-261, 3-266, 3-267, 3-268, 3-269 Affected Figures: 2-1 thru 2-14, 2-17,2-22, 2-23 thru 2-45 FPR Revision # 2011-04 Revise the FPR to reflect the conversion of the FP system standpipes and hose stations inside containment from a wet to a dry system. The change was made to address the potential for freezing select water filled piping.

Affected pages: 3-1, 3-1a FPR Revision 2011-05 This change adds guidance pertaining to the methodology to be used when updating the Fire Hazards Analysis (FHA) Section of the FPR.

Affected pages: 2-7 FPR Revision 2012-01 This revision updates the FPR to reflect the replacement of existing Service Water (SW) pumps with two smaller pumps in support of active decommissioning activities.

Additionally, select Turbine Building (TB) sprinkler systems were removed from service due to the removal of associated combustible loads.

Affected pages: 2-8, 2-9, 2-33, 2-38, 2-40, 2-42, 3-114, 3-116, 3-118, 3-122, 3-125, 3-127, 3-131, 3-133, 3-223, 3-267, 3-268, 3-269

ZionSolutions, LLC ZS-2013-0195: Attachment 1 FPR Revision 2012-02 Remove from service the Quality Assurance (QA) Records Room Carbon Dioxide FP suppression system. The QA Records Room is no longer used and combustible loads have been removed.

Affected pages: 2-9, 2-12, 2-29, 2-38, 3-140, FPR Revision 2012-03 Revise the FPR to reflect the removal of FP system exterior ring header hydrant # 7. The hydrant was removed to facilitate the movement of large equipment near the Fuel Building. An acceptable quantity of exterior hydrants remain available.

Affected pages: 2-8 FPR Revision 2012-04 This FPR change abandons the Diesel driven fire pump and associated support system systems. The pump is no longer required in the current plant configuration.

Affected pages: 2-8, 2-14, 2-33, 2-42, 3-264, 3-265 FPR Revision 2012-05 This FPR revision converts the FP water suppression system into a dual function system that allows Service Water (SW) to flow through the FP piping to supply cooling loads while still providing the required FP flow.

Affected pages: 2-8, 2-13 FPR Revision 2013-01 This FPR change modifies the content of the Pre-Fire Plans to assist the Zion Municipal Fire Department (ZMFD) upon their arrival at the site for firefighting activities.

Affected pages: 2-6, 2-10, 2-11, 2-13 FPR Revision 2013-02 This FPR revision removes fire detection requirements from select areas of the plant. In general, the areas affected had specific equipment that required fire detection to satisfy Appendix R requirements while the plant was operating. The equipment in these areas has been abandoned and de-energized.

Affected pages: 2-37, 2-38, 2-39, 3-92 thru 3-111, 3-149 thru 3-156, 3-162, 3-180, 3-182, 3-186 Figures: 2-15 thru 2-22

ZionSolutions, LLC ZS-2013-0195: Attachment 1 FPR Revision 2013-03 Revise the FPR to reflect the removal of miscellaneous HVAC charcoal filters which results in a reduction of combustible loading. The charcoal filters are no longer required.

Affected pages: 2-31, 2-32, 2-40, 2-41, 3-206, 3-228, 3-229

ZionSolutions, LLC ZS-2013-0195: Attachment 2 ATTACHMENT 2 ZION NUCLEAR POWER STATION FIRE PROTECTION REPORT, AMENDMENT 13 To perform the 2013 Zion Fire Protection Report update, please remove the existing pages and insert Amendment 13 pages as follows:

SECTION REMOVE INSERT Title Page Title Page Title Page List of Effective Pages page i page i List of Effective Pages page ii page ii List of Effective Pages page iii page iii List of Effective Pages page iv Section 2 pages 2-5 thru 2-16 pages 2-5 thru 2-16 Section 2 page 2-20 page 2-20 Section 2 page 2-21 page 2-21 Section 2 pages 2-25 thru 2-34 pages 2-25 thru 2-34 Section 2 pages 2-37 thru 2-42 pages 2-37 thru 2-42 Section 2 Figures 2-1 thru 2-14 Figures 2-1 thru 2-14 Section 2 Figures 2-15 thru 2-45 DELETED Section 3 page 3-1 page 3-1 Section 3 page 3-1 a page 3-1 a Section 3 page 3-9 page 3-9 Section 3 page 3-10 page 3-10 Section 3 page 3-16 page 3-16 Section 3 page 3-17 page 3-17 Section 3 page 3-67 page 3-67 Section 3 page 3-69 page 3-69 Section 3 pages 3-92 thru 3-111 pages 3-92 thru 3-111 Section 3 page 3-113 page 3-113 Section 3 page 3-114 page 3-114 Section 3 page 3-116 page 3-116 Section 3 page 3-118 page 3-118 Section 3 page 3-122 page 3-122 Section 3 page 3-124 page 3-124 Section 3 page 3-125 page 3-125 Section 3 page 3-127 page 3-127

ZionSolutions, LLC ZS-2013-0195: Attachment 2 SECTION REMOVE INSERT Section 3 page 3-131 page 3-131 Section 3 page 3-133 page 3-133 Section 3 page 3-135 page 3-135 Section 3 page 3-140 page 3-140 Section 3 page 3-145 page 3-145 Section 3 page 3-146 page 3-146 Section 3 pages 3-149 thru 3-156 pages 3-149 thru 3-156 Section 3 page 3-162 page 3-162 Section 3 page 3-180 page 3-180 Section 3 page 3-182 page 3-182 Section 3 page 3-186 page 3-186 Section 3 page 3-206 page 3-206 Section 3 page 3-218 page 3-21.8 Section 3 page 3-223 page 3-223 Section 3 page 3-228 page 3-228 Section 3 page 3-229 page 3-229 Section 3 page 3-239 page 3-239 Section 3 page 3-241 page 3-241 Section 3 page 3-251 page 3-251 Section 3 page 3-252 page 3-252 Section 3 page 3-261 page 3-261 Section 3 pages 3-264 thru 3-269 pages 3-264 thru 3-269

ZION STATION FIRE PROTECTION REPORT Amendment 13, July 2013 I

Zion Fire Protection Report Amendment 13 List of Effective Pages Title Page Amendment 13 List of Effective Pages 1 of 4 Amendment 13 2 of 4 Amendment 13 3 of 4 Amendment 13 4 of 4 Amendment 13 Table of Contents 1 through 6 Amendment 9 7 Amendment 11 Section 1 1-1 through 1-3 Amendment 12 Section 2 2-1 through 2-4 Amendment 12 2-5 Amendment 13 2-6 Amendment 13 2-7 Amendment 13 2-8 Amendment 13 2-9 Amendment 13 2-10 Amendment 13 2-11 Amendment 13 2-12 through 2-16 Amendment 13 2-17 Amendment 12 2-18 Amendment 7 2-19 Amendment 12 2-20 Amendment 13 2-20a Amendment 13 2-21 Amendment 13 2-22 Amendment 7 2-23 Amendment 7 2-24 Amendment 12 2-25 through 2-34 Amendment 13 2-35 Amendment 12 2-36 Amendment 8 2-37 Amendment 13 2-38 Amendment 13 2-39 Amendment 13 2-40 through 2-41 Amendment 13 2-42 Amendment 13 Figures 2-1 through 2- 14 Amendment 13 Figures 2-15 thru 2-45 (Deleted) Amendment 13 i

Zion Fire Protection Report

. Amendment 13 List of Effective Pages Section 3 3-1 Amendment 13 3-la Amendment 13 3-2 through 3-8 Amendment 12 3-9 Amendment 13 3-10 Amendment 13 3-11 through 3-15 Amendment 12 3-16 3-17 3-18 through 3-20 Amendment 13 Amendment 13 Amendment 7 I

3-21 Amendment 8 3-22 Amendment 7 3-23 Amendment 11 3-24 Amendment 7 3-25 Amendment 11 3-26 Amendment 7 3-27 Amendment 11 3-28 Amendment 7 3-29 Amendment 11 3-30 through 3-33 Amendment 7 3-34 Amendment 8 3-35 Amendment 7 3-36 Amendment 8

.3-37 through 3-39 Amendment 7 3-40 Amendment 8 3-41 Amendment 7 3-42 Amendment 8 3-43 through 3- 57 Amendment 7 3-58 Amendment 11 3-59 through 3-66 Amendment 7 3-67 Amendment 13 3-68 Amendment 7 3-69 Amendment 13 3-70 thru 3-74 Amendment 7 3-75 Amendment 11 3-76 Amendment 7 3-77 Amendment 7 3-78 Amendment 11 3-79 through 3-91 Amendment 7 3-92 thru 3-111 Amendment 13 3-112 Amendment 7 3-113 Amendment 13 3-114 Amendment 13 3-115 Amendment 7 3-116 Amendment 13 ii

Zion Fire Protection Report Amendment 13 I List of Effective Pages 3-117 Amendment 7 3-118 Amendment 13 3-119 through 3-121 Amendment 7 3-122 Amendment 13 3-123 Amendment 7 3-124 Amendment 13 3-125 Amendment 13 3-126 Amendment 7 3-127 Amendment 13 3-128 Amendment 7 3-.129 Amendment 7 3-130 Amendment 7 3-131 Amendment 13 3-132 Amendment 7 3-133 Amendment 13 3-134 Amendment 7 3-135 Amendment 13 3-136 through 3-139 Amendment 7 3-140 Amendment 13 3-141 thru 144 Amendment 7 3-145 Amendment 13 3-146 Amendment 13 3-147 Amendment 7 3-148 Amendment 11 Amendment 13 3-149 through 3-156 3-157 thru 3-159 3-160 Amendment 7 Amendment 11 I

3-161 Amendment 7 3-162 Amendment 13 3-163 through 3-179 Amendment 7 3-180 Amendment13 3-181 Amendment 7 3-182 Amendment 13 3-183 thru 185 Amendment 7 3-186 Amendment 13 3-187 thru 195 Amendment 7 3-196 Amendment 8 3-197 Amendment 7 3-198 Amendment 8 3-199 Amendment 7 3-200 Amendment 7 3-201 Amendment 11 3-202 Amendment 7 3-203 Amendment 7 3-204 Amendment 7

.3-205 Amendment 7 3-206 Amendment 13 3-207 through 3-217 Amendment 7 3-218. Amendment 13 iii

Zion Fire Protection Report Amendment 13 List of Effective Pages 3-219 Amendment 7 3-220 Amendment 7 3-221 Amendment 11 3-222 Amendment 7

.3-223 Amendment 13 I 3-224 Amendment 7 3-225 Amendment 11 3-226 through 3-227 Amendment 7 3-228 Amendment 13 3-229 Amendment 13 3-230 thru 3-235 Amendment 7 3-236 Amendment 11 3-237 Amendment 7 3-238 Amendment 7 3-239 Amendment 13 3-240 Amendment 7 3-241 Amendment 13 3-242 thru 250 Amendment 7 3-251 Amendment 13 3-252 Amendment 13 3-253 Amendment 7 3-254 Amendment 11 3-255 Amendment 11 3-256 through 3-257 Amendment 8 3-258 Amendment 11 3-259 Amendment 11 3-260 Amendment 7 3-261 Amendment 13 I 3-262 Amendment 12 3-263 Amendment 7 3-264 Amendment 13 3-265 Amendment 13 3-266 Amendment 13 3-267 Amendment 13 3-268 Amendment 13 3-269 Amendment 13 3-270 Amendment 7 3-271 Amendment 11 3-272 Amendment 11 iv

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 2.5.2 Radioactive Contamination Radioactive contamination is present in many Zion Station fire areas, and could be spread by the smoke from a fire in a radiologically contaminated area. To ensure that the risk of spreading contamination is minimized, the plant continues to apply the defense-in-depth concept to those areas where radiological contamination exists. This effort includes:

a. Controlling ignition sources All hot work and transient ignition sources are strictly controlled and monitored by procedure.
b. Controlling the presence, placement and removal of combustibles during decommissioning The storage of transient combustibles in these plant areas is limited in amount, duration and in areas where it can be placed, and is also strictly controlled by procedure.

The removal and storage of combustibles from contaminated areas during decommissioning is controlled to ensure that a Radiological Hazard is not created.

c. Providing suppression for rapid extinguishing of fires Hose stations are available within the RCA; on each elevation of the AB, inside the Containments, and inside the FB.
d. Maintaining fire barriers Internal walls of the RCA that were credited as fire barriers prior to onset of decommissioning will be retained as unrated barriers until the area is dismantled. Fire barriers for areas that contain significant amounts of combustibles are being maintained. Fire barriers are shown on Figures 2-1 to 2-14.
e. Maintaining fire detection Fire detection is provided in the Auxiliary Building and Fuel Building where a fire could Induce a hazardous radiological release. Those fire detection systems that presently protect areas of the plant where a fire could Induce a hazardous radiological release are maintained as functional systems, subject to NFPA and Insurance Company required inspections, tests, and maintenance.
f. Maintaining Emergency Response Capability The Zion Emergency Response Capability utilizes both onsite and offsite fire responders during a fire emergency. The ZMFD and the incipient fire responder(s) are capable of rapid response to manually control any fires that do occur.

2-5

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT

g. Providing control of smoke releases Smoke is controlled during a radiological fire with barriers and ventilation. Fixed, backup, and portable ventilation flow paths minimize the release of smoke.
h. Radiation Protection Personnel Radiation Protection personnel are assigned duty to assist site fire responders during fires.

Radiation Protection personnel provide information, direction, and monitoring as needed to minimize contamination and dose to the firefighters.

i. Pre-Fire Plans The Pre-Fire Plans provide information to the site fire responders about the layout of the plant, routes available to the fire scene, and locations of fire suppression equipment.

By applying the defense-in-depth features described above, Zion Station meets this objective.

2.5.3 Minimizing Release of Radioactive Materials For all decommissioning activities, the amount of radioactivity and combustibles in the associated work areas will be evaluated to minimize the possibility that the consequences of a fire will result in a Radiological Hazard. The current fire loading and the amount of radioactivity for each fire area will be assessed prior to start of any decommissioning work. Combustibles and/or radioactivity will be reduced, when possible, and additional incipient fire responders will be provided as necessary to ensure that radioactive* releases are less than the limits of IOCFR20 in the event of a fire. Administrative controls will be established to control the removal and storage of contaminated combustibles.

2-6

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 2.6 FIRE HAZARDS ANALYSIS AND ENGINEERING DESIGN 2.6.1 Fire Hazards Analysis The Fire Hazards Analysis (FHA) shall be revised to incorporate any: design changes to fire protection equipment, changes to the fire protection capability in fire zones containing structures, systems and components Important to the Defueled Condition, changes to the fire protection capability in fire zones within the RCA, or increases to fire loads where a fire could cause the release or spread of radioactive material. The revision shall:

" Consider potential insitu and transient fire hazards,

  • Determine the consequences of a fire in any location onsite which contains SSC's ITDC, or

" The potential for a fire-caused release or spread of radioactive material.

" Determine the fire induced radiological hazards of a fire in any location in the plant to ensure the risk of such fire Is minimized to the environment, plant personnel and the public.

Revisions to the FHA described above shall be supported by all necessary engineering evaluations, effectiveness reviews, calculations, and/or test results.

During the course of decommissioning, fixed fire loads (i.e., fire loads described in the FHA) will be removed from the designated fire zones. Administrative controls defined in the Transient Combustible Control program and incorporated into work packages will ensure that the process of decommissioning does not result in creating an unmonitored Radiological Hazard from the movement and collection of fire loads. As the intent and process of decommissioning ultimately results in the removal of fixed fire loads, the overall outcome is a reduction in the fire loading as described in the FHA. For the purpose of facilitating decommissioning, the Fire Hazards Analysis assumes that the movement and ultimate removal of fire loads described in the FHA will result in the fire loading to temporarily increase in adjacent fire zones and other fire zones enroute to removal of the fire loads. This assumption is included, in part, as an Administrative Transient Combustible Load. Administrative controls are established to control the amounts, the movement, and temporary storage of these combustibles (General considerations are described in Section 2.8).

Therefore, re-analysis of fire zones to account for a reduction in fixed fire loads is not required for decommissioning to proceed.

2.6.2 Fire Protection Features Desian Criteria Existing fire protection design features were developed using the guidance of the NFPA codes and standards and recognized industry standards in effect at the time of installation. However, justified deviations exist. All future fire protection design features shall be developed using the guidance of the NFPA codes and standards and/or recognized industry standards in effect at the time of installation.

2.6.3 Fire Protection Enaqineerina Evaluations Fire protection engineering evaluations shall be used to evaluate deviations from applicable code or regulatory requirements for new or existing fire protection systems associated with the equipment ITDC and for those areas where a fire could cause the release or spread of radioactive material. The fire protection engineering evaluation shall be performed by a person who is cognizant of the codes, standards, and regulatory requirements that govern the design. The fire protection engineering evaluation shall be reviewed or approved by a person who is qualified by ZionSolutions as a Fire Protection Engineer.

Zion Station can make changes to the Fire Protection Program without NRC approval if these changes do not reduce the effectiveness of fire protection for facilities, systems, and equipment which could result in a radiological hazard, taking into account site conditions and activities. Zion Station shall continue to use the 10CFR50.59 process and an effectiveness review to evaluate changes to the Fire Protection Program.

2-7

Amendment 13, July 2013 I ZION STATION FIRE PROTECTION REPORT 2.6.4 Fire Protection System Description Plant fire protection is provided by a loop fire header distribution system using fire hydrants, fire hose reels, fixed sprinkler or water spray systems, and water deluge systems. Portable fire extinguishers are provided throughout the plant and selected areas are provided with fixed carbon dioxide, dry chemical, or foam extinguishing systems. The automatic suppression systems are listed in Table 2.8.2. Systems and components required to be functional are controlled by the Administrative Technical Requirements (ATRs). All other systems are required in order to meet insurance requirements. Generally, the fire protection systems, to the extent possible, are designed in accordance with Nuclear Electric Insurance Limited (NEIL) guidelines and the applicable NFPA standards.

A 10-inch yard main loop (ring header) encircles the entire plant with fire hydrants spaced at approximately 250-foot intervals. Note that Hydrant #7 has been removed resulting in an approximate 500 foot interval between Hydrants #6 and #8. This yard main loop can be isolated into two segments with each one having an independent supply path source. The turbine building has a 10-inch loop header following the exterior walls of the turbine building. The auxiliary building is supplied by a 10-inch header which is fed from the yard main on both the Unit 1 and Unit 2 sides and from the turbine building header.

The turbine building is fed from the yard main loop and from the cross connection to the auxiliary building mentioned above. The reactor containments and the fuel handling building are fed from the auxiliary building 10-inch header and the crib house is fed directly from the fire pump discharge header. The main headers can be isolated so that water can be supplied to a portion of each building if a break occurs in a header. Hose stations are located throughout the buildings at approximately 100-foot intervals on each floor. Each hose station in the Aux building and Fuel building contains at least 50 feet of hose.

Most areas where oil or other significant amounts of combustible materials may be stored or handled are provided with a fixed fire protection system as described in the fire hazards analysis for each fire zone.

The FP water suppression system is a dual function system that allows SW to flow through the FP piping to supply plant cooling loads, while still providing the required FP flow. The FP water suppression system pressure is normally maintained from one of the SW pumps, with the Motor Driven (MD) Fire Pump in standby. The SW pump also provides flow to various components within the plant through FP piping. The SW pumps are located in the Crib House and are rated at 3000 gpm. The normal operating pressure of the SW pump, and hence the FP system, is-100 psig. In this dual function configuration, SW flow (normally) exists through the fire protection piping to various plant cooling loads. Isolation valves are installed to allow isolation of those components from the FP system. The site required flow demand, as described in NEIL Loss Control Standard 3.2.15.1.1, is the largest single automatic fixed water extinguishing system plus 500 gpm hose stream allowance; 750 gpm plus 500 gpm for a total flow of 1250 gpm. In the event of a fire, the MD Fire Pump has the capacity to supply the required FP demand load including the SW loads. The analysis is documented in Zion Calculation 22R-0-150M-0008.

Whenever the fire protection system header in the crib house falls to "86 psig, the motor-driven fire pump will automatically start and maintain the fire protection system headers at 125-psig to 140-psig pressure.

The fire pump is rated at 2000 gpm at 141 psig, and takes suction directly from the crib house forebay which is supplied by Lake Michigan. The site city water supply can be used to fight fires during a loss of offsite power event when the motor driven fire pump is unavailable. The Zion Fire Department has the capability to connect a pumper truck to an onsite municipal hydrant. The pumper truck discharge can be connected to an adjacent fire protection ring header hydrant and thus provide a water supply to the header.

2-8

Amendment 13. July 2013 ZION STATION FIRE PROTECTION REPORT In the event that the fire pump fails to operate, then water could be supplied to the fire protection system headers from the service water pumps.

The portion of the plant Fire Protection System that is required for the control of radiological fires is controlled by the Administrative Technical Requirements. The major components of that portion are specified in Table 2.6.1. The valves identified in Table 2.6.1 provide the fire suppression flowpaths to the areas that require control of radiological fires; the Auxiliary Building, the Fuel Building and the two Containment Buildings. There are three independent flowpaths to these areas from the underground ring header. Isolation valves are designated to provide isolation in the event of maintenance or leakage to allow continued fire suppression to these areas.

2.6.5 Detection System Description/Desin Features A general description of the placement of the Fire Detection System at Zion Station is shown on Table 2.8.2. Drawings of the fire water protection system are contained in station drawings M-43 and M-513.

Fire detection equipment required to be functional is listed in the ATR's. All other fire detection is present to satisfy insurance requirements.

Detection systems have been designed to provide coverage for one or more of the following situations:

1. General area detection;
2. Specific hazard detection;
3. Specific equipment detection (primary endangered by an exposure fire); and
4. Supplement protection of suppression systems for specific hazards (these detectors are in addition to the heat detectors provided to actuate certain suppression systems).

The Fire Alarm and Detection Systems, where provided, are designed and installed under the general guidance of National Fire Protection Association (NFPA) 72D and 72E. Certain code deviations exist, but these deviations have been evaluated. The number, type and location of detectors was determined generally in accordance with the recommendations of the manufacturers and the guidelines established in NFPA 72E. All fire alarms and fire detectors in radiological areas provide an audible and visual alarm in the Plant Control Room.

2-9

Amendment 13, July 2013 I ZION STATION FIRE PROTECTION REPORT 2.6.6 Electrical Design Features and Criteria The cable tray and conduit penetrations through fire barriers have been sealed and tested.

Cable penetrations entering the main control room from the cable spreading room below are sealed with cellular concrete and covered with Flammastic, Vimasco or an equivalent coating.

All cable Is qualified by flame tests at least as severe as those listed in IEEE-383 - 1974. The cables generally can be considered self-extinguishing and non-flame propagating.

Emergency lights are provided to aid in personnel egress from the plant in case of fire. A complete list of emergency lights can be found in the plant electrical maintenance procedures.

2.6.7 Mechanical Desian Features and Crteteda Insulation on piping was not considered in the heat load calculation because of its low "Btu* content, and the dispersed nature of this loading throughout the station.

The rupture of process piping as a result of fires was not considered. The assumption made was the continued flow would act as a heat sink and contribute to the maintenance of the integrity of the piping.

The grease contained in some motor-operated valves was not considered because of the limited number of these types of valves that contained a significant amount of lubricating grease and their spatial separation within the plant.

Pipe penetrations through fire barriers have been sealed. Fire barrier assemblies include the fire walls, fire doors, fire dampers, and penetration seals that make up a fire barrier.

No new fire barriers were installed to meet the requirements of I OCFR50.48(f) after the plant was permanently shutdown; credit was taken for the location of existing fire barriers in the plant. One of the original primary goals of passive fire barriers was the protection of redundant safe-shutdown trainsithis goal is no longer required. The remaining goal, which is preventing the spread and release of radioactive contamination during a fire which could result in a radiological hazard, is maintained by the existing barriers and ventilation boundaries. As shown by calculation (references i and j), based on the amount of contamination remaining and the type of combustibles present (i.e. mainly cable insulation), a fire that results in a radiological hazard is highly unlikely.

2-10

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 2.6.8 Structural Design Features and Criteria Structural design elements and materials descriptions are as follows:

Concrete was used in the construction of walls, floor slabs, and roof slabs. Fire-resistant covering of steel beams and columns is of a mix which includes a proportion of carbonate-type aggregate. This factor was a consideration in determining the fire resistance of these structural elements.

Hollow concrete blocks used in the construction of walls conform to the applicable requirements of ASTM C-90 for Type I units and for Grade U-I block and are formed from a mix containing lightweight, expanded slag aggregate. Blocks were laid In a standard running-bond pattern with 318-inch-thick horizontal and vertical mortar joints. Heavy-duty steel ladder-type continuous reinforcing ties are provided in the horizontal joints at 16 inches on centers vertically.

Three layers of preformed joint filler, which were used to pack joints in masonry walls, were used throughout the plant; self-expanding cork-type, sponge rubber-type, and polyethylene foam-type. Rubber sealant used to seal the faces of joints in masonry walls which were packed with preformed joint filler is a Type A Thiokol base sealant.

The exterior roof covering, which is referred to as UL Class A roof covering, Is a four-ply built-up pitch, felt, and gravel roofing, System F, with 1-Inch-thick preformed board insulation. This roof covering complies in all respects with the applicable requirements of the Underwriters' Laboratories for Class A rating. This rating applies to roof coverings which are effective against severe fire exposure and under such exposures are not readily flammable and do not carry or communicate fire; afford a fairly high degree of fire protection to the roof deck; do not slip from position; possess no flying brand hazard; and do not require frequent repairs in order to maintain their fire-resistive properties.

Penetrations in a designated fire resistive barrier are protected so that they have an. appropriate fire resistance rating for the hazard present.

2.6.9 HVAC Deeicn Features and Cteria Fire dampers are generally installed in HVAC system ductwork where a duct passes through a designed fire barrier, or other technical justification has been provided.

In the fire hazards analysis portions of this report, the assumption is made that all fire dampers are 1-1/2-hour labeled unless otherwise noted. In areas where total flooding gaseous suppression systems are used, dampers in the ventilation system are automatically closed.

2-11

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 2.6.10 Surveillance Testing/ Maintenance Fire protection test procedures shall be established that:

a. Demonstrate functionality and conformance with design and system readiness requirements,
b. Identify types, frequencies and detailed procedures for testing, C. Properly evaluate and act upon test results.

Test procedure requirements may vary depending upon the categorization of the equipment that the fire protection feature is protecting. The technical requirements for functional system FP test procedures are contained in the ATR's. The test procedures are located in the Zion 200 series periodic tests (PT's).

Preventive maintenance (PM) procedures shall be established for fire protection features. The PM program shall take the following into consideration: manufacturers recommendations, consensus code or insurance guidance, and results from tests and inspections. FP PM procedures are filed in the Zion Maintenance Department. Other PM procedures have been incorporated in Zion 200 series periodic tests where applicable and convenient.

2.6.11 Compliance With NFPA Codes And Standards National Fire Protection Association (NFPA) codes in effect at the time of plant design were used as guidelines in the design of passive fire protection features (e.g., fire doors, and dampers), active fire protection systems (i.e., fire suppression and detection systems), and in the development of administrative controls of fire hazards. Unique situations and configurations that deviate from applicable NFPA codes exist. However, these situations and configurations have been justified or accepted by the insurance carrier (NEIL).

The following list identifies the applicable NFPA codes:

10 -1975 Portable Fire Extinguishers 13-1976 Sprinkler Systems, Installation 13A-1976 Sprinkler Maintenance 14 -1974 Standpipe and Hose System 15 -1973 Water Spray Fixed Systems 20 -1973 Centrifugal Fire Pumps 24 -1973 Outside Protection 30 -1973 Flammable and Combustible Liquid Code 37 -1975 Stationary Combustion Engines and Gas Turbines 51 -1976 Welding and Cutting 69-1973 Explosion Prevention Systems 72D-1975 Proprietary Signaling Systems 72E-1 974 Automatic Fire Detectors 90A-1976 Air Conditioning and Ventilating Systems 194-1974 Fire Hose Connections 600-1986 Industrial Fire Brigades 2-12 '

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 2.6.12 Pre-Fire Plans The Pre-Fire Plans are used as an aid by the site fire responders to fight fires. The Pre-Fire Plans contain the following types of information:

a) Location of fire suppression equipment.

b) Route recommendations.

2-13

Amendment 13, July2013 1 ZION STATION FIRE PROTECTION REPORT TABLE 2.6.1 FIRE SUPPRESSION WATER SYSTEM FIRE PUMPS EQUIPMENT NUMBER Motor-Driven Fire Pump OA OFP008 I

FIRE HEADER ISOLATION VALVES VALVE NUMBER OPERATOR TYPE OFP-0004 MANUAL OFP-0006 MANUAL I OFP-0007 MANUAL OFP-0008 MANUAL OFP-0020 MANUAL OFP-0021 MANUAL OFP-0022 MANUAL OFP-0024 MANUAL OFP-0032 MANUAL OFP-0077 MANUAL OFP-0078 MANUAL OFP-0079 MANUAL OFP-0080 MANUAL OFP-0084 MANUAL OFP-0085 MANUAL OFP-0410 MANUAL OFP-0411 MANUAL 1FP0088 MANUAL 1FP-0167 MANUAL 1FP-0170 MANUAL I FCV-FP0008 DIAPHRAGM 2FP0088 MANUAL 2FP-01 70 MANUAL 2FCV-FP0008 DIAPHRAGM 2-14

Amendment 13, July 2013 I ZION STATION FIRE PROTECTION REPORT 2.7 ADMINISTRATIVE TECHNICAL REQUIREMENTS Fire systems are intended to be operational at all times. Outages of fire systems occur due to impairments, planned maintenance and testing. Administrative Technical Requirements have been established to place administrative controls on fire impairments.

The Administrative Technical Requirements are intended to establish the baseline for system requirements. These requirements are located in the fire protection administration procedures.

These ATRs ensure that proper compensatory measures are established for system outages and that the outage is kept to a minimum length of time. These procedures also outline the reporting requirements for system impairments to the property insurance carrier.

Each surveillance requirement shall be performed within the specified surveillance interval with a maximum allowable extension not exceeding 25 percent of the specified surveillance interval.

As the Plant systems are deactivated and fire hazards are reduced, the associated fire protection systems may be deactivated if they do not reduce the effectiveness of the Fire Protection Program. System deactivation is controlled by Plant procedures. When ATR compliance is not met, the station corrective action program is involved per approved station procedures.

The ATRs can be found in ZAP 900-01.

2.8 FHA ASSUMPTIONS AND METHODOLOGY The fire hazards analysis has been developed with the following assumptions.

a. Fire areas are designated, based on as-built conditions, as those portions of a building which are separated from other areas by physical boundaries whose construction is comparable to that of a rated fire barrier. The intent of physically impeding the spread of a fire is satisfied based on the relatively low fire loading which exists throughout the plant and the adequacy of the barriers due to other design considerations (e.g., radiation shielding, tornado, seismic). Fire barriers that existed during the SAFSTOR period and prior to the onset of decommissioning have been maintained as rated barriers. During decommissioning, fire barriers will be systematically removed to allow for the removal of equipment and debri, Including combustibles. This process will be controlled such that dismantlement of fire areas and the associated removal of combustibles within the Radiological Control Areas (RCA), will not result in a significant increase in equivalent fire severity or the accumulation of combustibles that could result in a radiological hazard. As shown by calculation (Reference 2.8.3.j), without crediting internal fire barriers, the resultant combination of fire loading for all fire zones and areas of each elevation of the AB, does not result in the possibility of a Radiological Hazard. The total equivalent fire severity for all zones combined for each elevation of the AB is shown in Table 2.8.1. Equivalent Fire Severity for the Containments was also calculated as one area. The equivalent fire severity shown for each elevation of the AB is based on all combustibles moved to the general area with the associated internal barriers removed (a typical sequence of activities for decommissioning). Periodic inspections of these fire barriers will be suspended; maintenance of structures that form ventilation barriers between the RCA and the environment will be retained as necessary.

2-15

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT

b. For the purpose of facilitating decommissioning, the fire hazards analysis assumes that the movement and ultimate removal of fire loads described in the FHA will result in the fire loading to temporarily Increase In adjacent fire zones and other fire zones enroute to removal of the fire loads.

This assumption is included as an Administrative Transient Combustible Load. Administrative controls are established to control the amounts, the movement, and temporary storage of these combustibles. General considerations are described below:.

  • Fire loads in non-radiological zones may be moved into other non-radiological zones under the direction of the Fire Marshall and Transient Fire Load administrative guidance. Fire loads in these zones do not present the potential for a Radiological Hazard. The total accumulated fire load will be controlled by administrative requirements under the direction of the Fire Marshall.
  • Fire loads in radiological zones may be moved into other fire zones within the Radiological Control Area (RCA) provided that the resultant fire load and associated contamination does not result in a Radiological Hazard. Administrative controls are established to ensure the amounts, the movement, and temporary storage of contaminated fire loads does not result in a Radiological Hazard. (Reference 2.8.3.j)
c. The calculation of fire loads in a given fire zone is accomplished by calculating the average combustible loading in a fire zone. This provides a quantitative measure of a fire hazard.
d. The design-basis fire is the most severe fire that can credibly occur within a fire area or zone. Fire initiation is assumed along with the failure of existing automatic protection systems, except for those systems that were installed to prevent fire spread between areas. Failure of all cables and equipment within a fire zone or area is postulated.
e. Fire Zones are outlined by the physical barriers that exist for each zone; these zones are defined as:

(1) each elevation of the AB is considered a fire zone, (2) each Containment is considered a fire zone, (3) the FB is considered a fire zone, and (4) other specific fire zones as specified In Table 2.8.1.

f. The gaskets and sealant between joints in the HVAC ductwork contribute less than 2000 Btu/ft2 and have not been considered as a combustible. (Calculation No. 22R-B-217M-003) 2-1 5a I

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT To establish a conservative approach to controlling transient combustibles, an administrative transient combustible load is defined for each fire zone. The administrative transient load applied to most of the fire zones was assumed to be the equivalent of one 55 gallon drum of lube oil per 1000 square feet of floor or 8,525 Btu/ft2 , although larger transient loads are assumed in some areas to allow for decommissioningactivities.

2.8.1 FIRE ZONE AND FIRE SEVERITY IDENTIFICATION The Radiologically Controlled Area (RCA) of Zion Station (the AB, Containments and FB) is subdivided Into 9 major fire zones. The major fire zones are Identified as: each elevation (6) of the AB, the FB, and the 2 Containments. These fire zones were previously identified as fire areas with the identification of their boundaries based on the substantial natural separation and/or structural barriers present. Due to the onset of decommissioning, all Interior structural barriers that were previously rated as fire barriers will no longer be maintained (except those barriers retained as shown in Figures 2-1 through 2-14). The rooms previously identified as a fire area are now considered a fire zone although the physical structure of the barriers still exist As denoted in Table 2.8.1 and shown on Figures 2-1 through 2-14, some fire barriers are being retained during decommissioning until combustibles and/or the potential for the spread of a fire is reduced.

All fire barriers have been derated within the TB. The description in the FHA analysis presented in Section 3 has not been revised to delineate between fire areas and fire zones. This is purposely done to Identify those structural barriers that were previously considered rated fire barriers.

The following sections describe the criteria and methodology used to identify fire areas and fire zones for Zion Station. The methodology used to develop the equivalent fire severities for each zone of a fire area is also discussed.

2-16

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 2.8.1.2 Identification of Fire Areas and Fire Zones Prior to permanent shutdown, the plant had been subdivided into major fire areas based on existing features of construction. Based on the definition for fire area and the criteria contained in Generic Letter 83-33, 48 interior and 5 exterior fire areas were identified at Zion Station. These 53 fire areas are made up of 133 interior and 5 exterior fire zones, either individually or in combination. The fire areas were separated either by distance or by noncombustible, unrated fire barriers. These divisions were generally retained during the SAFSTOR period. With the onset of decommissioning, all fire areas have been redesignated as fire zones.

Based on the amount and type of combustibles, many of the previously designated fire zones within the RCA have been combined into one fire zone with the Equivalent Fire Severity recalculated for that combination of zones. The original Fire Zone identifier has been retained for simplicity. Fire Zones that have been combined are identified with the original designation in parenthesis. For example, Fire Zone 11.1 is the 542' elevation of the AB; (11.1 A-1) designates the RHR pump room within Fire Zone 11.1.

The main criterion for downgrading fire barriers (that were previously maintained during SAFSTOR) inside the RCA to unrated barriers Is based on the floor area and the type of combustibles present. As most of the combustible load within interior rooms is cable insulation, the propagation of a fire from those areas Is highly unlikely. This is due to the IEEE 383 requirement for the insulation to be self extinguishing. The areas within the RCA that contain relatively significant amounts of combustibles, based on fire load and severity, other than cable are: (1) the general floor areas of the AB and the Containments, which are very large areas and combustibles are significantly spread out, (2) the U1 & U2 Containment Purge Equipment Rooms, and (3) the RP Offices & Lab areas. The fire severities of these areas are each less than 32 minutes. Maintenance and inspections of some of the barriers associated with these areas and other specific areas will remain in effect until the associated fire load has been sufficiently reduced such that the onset and spread of a fire across the unrated barriers is highly unlikely. Figures 2-1 through 2-14 identify fire barriers that are being maintained.

Exterior walls of the RCA serve as a ventilation boundary. As such, most of the exterior walls will remain intact until final demolition of the building.

The fire zones are listed in Table 2.8.1. The fire detection and suppression systems are also identified and listed in Table 2.8.2 on a zone-by-zone basis.

2.8.1.3 Equivalent Fire Severities The equivalent fire severities and combustible loadings for each zone of the fire areas listed in Table 2.8.1 are based on an inventory of exposed cable insulation (i.e., not in conduit), paper, wood, lubricating oil, diesel fuel, charcoal filters, and maintenance supplies (up to 1000 Btu/ib). The 16th edition of the National Fire Protection Association's Fire Protection Handbook provides guidance on converting weights of various materials into estimated minutes of bum time.

2-20

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Equivalent fire severity in minutes is calculated by multiplying fire load in Btu/ft2 by 7.5 x 104 min/Btulft2 and rounding to the nearest minute to give the equivalent fire severity on the ASTM E-1 19 standard time-temperature curve assuming total combustion of the fuels. In areas where the equivalent fire severity is greater than 180 minutes, it will be restated as >3 hours.

Fire areas and zones, along with a description of fire protection features and combustible loads, are listed in Table 2.8.1.

For example, the equivalent fire severity resulting from the total consumption of 2000 lb of charcoal (with a heat of combustion of 15,000 BtuMlb) located in a fire zone with a floor area of 200 ft2 would be:

2000 lb / 200 ft x 15,000 Btu/lb =

150,000 Btu/tt2 which has an equivalent fire severity of:

150.000 Btu/I/ 1333 Btuft2/minute =

113 minutes (It should be noted that the value of 1333 Btu/ft 2/minute is linear for equivalent fire severities of up to 4.5 hours5.787037e-5 days <br />0.00139 hours <br />8.267196e-6 weeks <br />1.9025e-6 months <br /> in duration.)

This analysis has been performed for each interior fire zone in Table 2.8.1, with the equivalent fire severities Wsted in the table. The above procedure was used in developing and documenting the fire loading and fire severity in each fire zone/fire area.

2-20a I

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 2.8.1.4 Assumptions The combustible materials and their location within each fire zone have been identified by reviewing design drawings and vendor drawings data. Field verification has been performed as needed. The following assumptions were used in developing combustible loads:

a. Combustibles associated with the insulation and lubrication of bearings inside each motor are negligible and were not considered.
b. Combustibles associated with cable insulation of conductors that are in rigid conduit are negligible and were not considered.
c. The only combustibles considered in any of the control panels, switchgear, and motor control centers is the cable insulation. Any other combustibles that may be present in these panels, etc., are considered negligible and, therefore, were not considered.
d. Insulation of cables contained in each section of 480-V MCCs and 4160-V switchgear shall be estimated to weigh 20 pounds.
e. Insulation of cables contained in each 20 inches of lateral length of a control panel shag be estimated to weigh 50 pounds. Insulation of cables contained in each 20 inches of lateral length of local miscellaneous panels (excluding instrument racks) shall be estimated to weigh 32 pounds.

Insulation of cables contained In each 20 inches of lateral length of an instrumentation or computer panel shall be estimated to weigh 30 pounds.

f. Insulation of cables contained in each section of 480-V switchgear is estimated to weigh 40 pounds.
g. The combustion characteristics of both the cable Insulation and jacketing materials are the same.
h. Using the defined fire zones, the cable tray fire loading has been determined as follows:
1. Tabulate all of the. routing points which run through the fire zone/fire area being analyzed.

This tabulation shall include the routing points for all power, control, and instrumentation tray, covered or uncovered, horizontal tray or riser.

2. Determine the number of cables passing through the routing point and the length of each routing point.
3. For each fire zone, provide a volume in ftW of cable insulation for power, control cables, and also for instrumentation cables using conversion factors.

2-21

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT 2.

8.3 REFERENCES

a. Code of Federal Regulations 10CFR50.48(f)
b. Zion Quality Assurance Program
c. Zion Fire Protection Report (Historical), including Amendment 5 dated July 1997.
d. Regulatory Guide 1.191, Fire Protection Program For Nuclear Power Plants During Decommissioning And Permanent Shutdown, dated May 2001
e. NEIL Members Manual Supporting Documents
f. Zion Series 200 Periodic Test Procedures
g. Zion Series 900 Administrative Procedures
h. Zion Calculation No. 22R-B-217M-003, Combustible Loading Calculation
i. Zion Calculation No. 22N-0-1 50M-003, Calculation of Radiation Dose Due to Fire, dated 2009 I. Zion Calculation No. 22N-0-1 50M-004, Calculation of Radiation Dose Due to Contaminated Combustibles, dated 2010 2-25

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION FIRE ZONEE SEVERITY FIRE LOAD LOADING LIMIT FIRE LOADING (NOTE 1)

I (minutes) (Btu/t) AREA (fet) (Btufte) (Btuflte) (Btu/ft2)

Unit I Containment (RCA) 1.0-1 9 12.029 25,888 8.525 20,554 Reactor Cavity (1.1-1) 10,680 347 N/A Annular Area (1.2-i) 30,385 6.566 N/A Steam Gen. & RCP (1.3-1) 8.483 6,709 N/A Operating Floor (1.4-1) 4,182 12,266 N/A Unit 2 Containment (RCA) 1.0-2 9.5 12,633 25,888 8,525 21,158 Reactor Cavity (1.1-2) 10,680 347 WA Annular Area (1.2-2) 30,774 6,566 N/A Steam Gen. & RCP (1.3-2) 9,003 6,709 N/A Operating Floor (1.4-2) 4.968 12,266 N/A Main Control Room Complex Main Control Rm 2.0-0 59 78.882 5,062 8,525 87,407 67,859 Unit 1 Plant Computer Rm 4.0-1 74 98,036 770 11,766 109,802 N/A Unit 2 Plant Computer Rm 4.0-2 58 77,727 770 11,766 89,493 N/A Prime Computer Rm 4.1-1 116 154,193 796 11,382 165,575 N/A Auxiliary Building Kitchen 18.6-1 28 37,356 630 8,525 45,881 N/A Work Control Center 18.6-2 125 166,079 1,476 8.525 174,604 N/A Unit 1 Outer Cable Spreading Rm 3.1-1 81 107,777 10.048 8.525 116,302 N/A 2-26

Amendment 13, July2013 1 ZION STATION FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION FIRE ZONI SEVERITY FIRE LOAD LOADING LIMIT FIRE LOADING (NOTE 1)

I (minutes) (Btu/lt) AREA (ft?) (Btu/e) (Btul/tt) (Btuto)

Unit 2 Outer Cable Spreading Am 3.1-2 74 97,814 9,969 8,525 106,339 NIA Unit 1 Stairwell Enclosure 1116A-11 90 119,754 447 0 128,279 N/A Unit 2 Stairwell Enclosure 18.6A-2 6 7,617 656 8,525 16,142 N/A Unit 1 Inner Cable Spreading Am 3.2-1 90 119,430 2,784 8,525 127,955 N/A

  • Unit 2 Inner Cable Spreading Rm 3.2-2 84 112,107 2,784 8,525 120,632 N/A Unit 1 South Penetration Vault 3.3-1 33 44,328 622 8,525 52,853 N/A Unit 2 North Penetration Vault 3.3-2 30 39,466 622 8,525 47,991 N/A Unil I North Penetration Vault 3.4-1 27 35,995 813 8,525 44,520 N/A Unit 2 South Penetration Vault 3.4-2 26 34,709 813 8,525 43,234 N/A Unit 1 EDG 1B SWGR Rm 5.1-1 26 34,106 1,364 8.525 42,631 N/A Unit 2 EDG 28 SWGR Rm 5.1-2 24 32,521 1,365 8,525 41,046 N/A

- Unit 1 EDG 1A SWGR Am 5.2-1 25 33,223 1.365 8,525 41,748 N/A Unit 2 EDG 2A SWGR Rm 5.2-2 28 37.398 1.365 8,525 45,923 N/A Unit 1 EDG 0 SWGR Rm 5.3-1 29 38.474 1,365 8.525 46,999 N/A Unit 2 EDG 0 SWGR Rm 5.3-2 21 27.822 1,365 8,525 36,347 N/A Unit 1 NON-ESS SWGR Am 5.4-1 3 4,457 2,653 8,525 12,982 N/A Unit 2 NON-ESS SWGR Rm 5.4-2 3 4,444 2,653 8,525 12,969 N/A Unit I Rod Drive MG Set Rm 5.5-1 8 10,030 784 8.525 18,555 N/A Unit 2 Rod Drive MG Set Rm 5.5-2 8 10,174 784 8,525 18,699 N/A 2-27

Amendment 13, July2013 I

. ZION STATION FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION FIRE ZONI LOADING LIMIT FIRE LOADING (NOTE 1)

SEVERITY FIRE LOAD (minutes) (BtuWt) 2 AREA (ft ) (Btu/fe) (Btu/Ht2) (Btu/ft2 )

I Unit 1 Aux Electric Equip Rm 5.6-1 73 97.389 2.221 0 97,389 147,000 Unit 2 Aux Electric Equip Rm 5.6-2 74 98,740 2,221 0 98,740 121,000 Unit 1 Div IS DC Dist. Phi 5,6A-1 13 17,147 156 8,525 25,672 N/A Unit 2 Div 28 DC Dist. Pni 5.6A-2 12 16,406 156 8,525 24,931 N/A Div 17/27 DC Bat. & Dist. Rm 7.0-0 18 24,036 560 8.525 32,561 N/A Unit 1 Div. 19 Battery Rm 7.1-1 35 46,861 209 8,525 55.386 N/A Unit 2 Div. 29 Battery Rm 7.1-2 35 46,861 209 8,525 55,386 N/A Unit 1 Div. 18 Battery Rm 7.2-1 35 47,087 208 8,525 55,612 N/A Unit 2 Div. 28 Battery Rm 7.2-2 35 47,087 208 8.525 55,612 N/A Unit 1 EDG 1B Rm 9.1-1 11 14,270 1,428 8,525 22,795 N/A Uni 2 EDG 2B Rm 9.1-2 11.5 15.280 1,428 8.525 23,805 N/A Unit I EDG IA Rm 9.2-1 10 13.302 1.419 8,525 21,827 N/A Unit.2 EDG 2A Rm 9.2-2 11 14,750 1.419 8,525 23,275 N/A Unit 1 EDG 0 Rm 9.3-1 11.3 15,053 1,428 8.525 23,578 N/A Unit 1 EDG 1B Diesel Fuel Stor 10.1-1 0 0 995 0 0 N/A Unit 2 EDOG 2B Diesel Fuel Stor 10.1-2 0 0 995 0 0 NIA Unit 1 EDG 1A Diesel Fuel Stor 10.2-1 0 0 975 0 0 N/A Unit 2 EDG 2A Diesel Fuel Stor 10.2-2 0 0 975 0 0 N/A Unit 1 EDG 0 Diesel Fuel Stor 103-1 0 0 995 0 0 N/A 2-28

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION LOADING LIMIT FIRE LOADING (NOTE 1)

FIRE ZONE SEVERITY FIRE LOAD (BtuftW)

(minutes) (Btu/ft 2) AREA (fI) (BtUlft2 ) (Btufft?)

Turbine Building Turbine Oil Rm 8.1-0 0 0 6,166 1,200 0 8,525 0

14.691 N/A N/A I

Unit 1 TB Basement 8.2-1 5 20,420 Unit 2 TB Basement 8.2-2 4 4,474 20,420 8,525 12,999 N/A Sampling Rm 8.3-0 13 16,887 1,073 8,525 25,412 N/A Auxiliary Heating Boiler Rm 8.4-0 6 7,405 1.128 8.525 15,930 N/A Unit 1 TB Elev. 592' 8.5-1 6.6 8,758 50,875 8.525 17,283 N/A Unit 2 TB Elev. 592' 8.5-2 7 9,886 56,138 8,525 18.411 N/A BOP Battery Rooms 8,5A-0 31 41,833 600 8.525 50,358 NtA Unit 1 TB Mezz. Floor 8.6-1 8 10,680 48,880 8,525 19,205 N/A Unit 2 TB Mezz. Floor 8.6-2 6 8,120 55,120 8,525 16,645 N/A TB Operating Floor 8.7-0 4.7 6310 97,940 8,525 14,835 N/A Future Unit 2 Dies. Fuel Stor 10.3-2 0 < 1000 995 8,525 9,525 N/A QA Storage Rm and Operating Offices 13.0-0 18 24,060 2,400 8,525 32,585 WA Unit 1 Steam Pipe Tunnel 18.5-1 57 7,613 8,525 8,582 N/A East Lower MS Isolation Valve House U-1 18.5-1 <1 110 654 14,220 14,330 22,711 West Lower MS Isolation Valve House U-1 18.5-1 110 654 14,220 14,330 22,711

<1 Unil 2 Steam Pipe Tunnel 18.5-2 57 7,613 8,525 8,582 N/A

<1 East Lower MS Isolation Valve House U-2 18.5-2 110 654 14,220 14,330 22,711 2-29

ZION STATION Amendment 13, July 2013 I FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION FIRE ZONEE SEVERITY FIRE LOAD LOADING LIMIT FIRE LOADING (NOTE 1)

(Btul/t 2 ) I (minutes) (Btu/ff) AREA (ft) (Btu/f12) (Btu/fte)

. West Lower MS Isolation Valve House U-2 18.5-2 <1 110 654 14,220 14,330 22,711 Auxiliary Building (RCA)

Auxiliary Bldg. 542' Level 11.1 5.2 6,914 25.682 8.525 15,439 Auxiliary Bldg. 542' Level General Area (11.1-0) 9,336 18,458 17,949 (Note 2)

Unit 1 RHR 1A Pump Rm (11.1A-1) <100 211.5 1,191 Unit 2 RHR 2A Pump Rm (11.1A-2) <100 211.5 1,191 Unit 1 RHR 1B Pump Rm (11.1B-i) 100 224.5 1,122 Unit 2 RHR 28 Pump Rm (11.1B-2) <100 224.5 1,122 Unlt 1 Pipe Tunnel (11.1C-1) < 100 895 Negligible Unit 2 Pipe Tunnel (11.1C-2) <100 895 Negligible Unit 1 & 2 Holdup Tank Rm (11.1D-0) < 100 2,312 NA Gas Decay Tanks Area (14.1-0) 2,336 2,250 Negligible Auxiliary Bldg. 560' Level 11.2 17 22,279 21,520 8,525 30,804 Auxiliary Bldg 560' Level General Area (111.2-0)1 26,600 17,064 55,022 Unit I SI Pump 1A Rm (11.2A-1) <100 328 2,363 Unit 2 SI Pump 2A Rm (11 .2A-2) <100 328 2,363 Unit 1 SI Pump 1B Rm (11.28-1) <100 340 2,280 Unit 2 SI Pump 28 Rm (11,28-2) <100 340 2,280 Unit 1 RHR Heat Ex 1A Rm (11.2C-1) < 100 185 Negligible Unit 2 RHR Heat Ex 2A Rm(1 1.2C-2) < 100 185 Negligible Unit 1 RHR Heat Ex IB Rm (11,2D-1) <100 185 Negligible Unit 2 RHR Heat Ex 2B Rm (11.2D-2) < 100 185 Negligible 2-30

Amendment 13,July2013 I

. ZION STATION FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION FIRE ZONEE SEVERITY FIRE LOAD LOADING LIMIT FIRE LOADING (NOTE 1)

(Btu/ft2) (Btu/f1 2) (Btu/ft2) I (minutes) (Btulft 2 ) AREA (ft2)

  • Unit i Cont, Spray Pump Rm (1 .2E-1) 11,037 792 41,021
  • Unit 2 Cont. Spray Pump Rm (11.2E-2) 22,096 792 49,268
  • Unit 1 Pipe Chase (11.2F-1) <100 398 Negligible
  • Unit 2 Pipe Chase (11.2F-2) .< 100 398 Negligible Auxiliary Bldg 579' Level 11.3 12 16,111 23,372 8,525 24,636 Auxiliary Bldg 579' Level General Area (11.3-0) 22,202 12,490 48,423 Unit 1 Charg Pump 1A Rm(l1.3A-1) <1000 313 25,750 Unit 2 Charg Pump 2A Rm (11.3A-2) <1000 313 25,750 Unit 1 Charg Pump 1B Rm (11.31-1) <1000 302 26.700 Unit 2 Charg Pump 2B Rm (11.3B-2) <1000 302 26.700 Unit i Charg Pump 1C Rm (11.3C-1) <1000 279 30,600 Unit 2 Charg Pump 2C Rm (11.3C-2) <1000 279 30,600 Unit 1 RWST Rm (11.313-1) < 1000 1,369 Negligible Unit 2 RWST Rm (11.3D-2) <1000 1,369 Negligible Unit I Ppe Chase (11.3E-1) 12,220 1.787 16,900 Unit 2 Pipe Chase (11.3E-2) 11,172 2,403 12,035 Crystallizer (14.2A-0) 23,346 2,166 N/A Auxiliary Bldg 592' Level 11.4 16 20.350 25,896 8.525 28,875

- Auxiliary Bldg 592' Level General Area (11.4-0) 25,079 19,945 41,145

- Unit 1 Letdown Heat Ex Rm (11AA-1) 20.305 256 20,305 2-31

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION FIRE ZONE SEVERITY FIRE LOAD LOADING LIMIT FIRE LOADING (NOTE 1) I (minutes) 2 (Btu/ft ) AREA (it) (BtU/ft2) 2 (Btultt ) (Btu/*)

Unit 2 Letdown Heat Ex Rm (11.4A-2) 1,061 256 4,875 Unit 1 Seal Wtr Heat Ex Rm (11.4-.1) 18.834 276 18,834 Unit 2 Seal Wtr Heat Ex Rm (11 .4B-2) 984 276 4,520 Unit 1 Pipe Chase (1 1.4C-1) <100 375 Negligible Unit 2 Pipe Chase )11.4C-2) <100 375 Negligible DAW Storage (11.4D-0) 458 960 25,000 25,458 15,700 Dry Active Waste Storage (1 4.3A-0) 6,945 1,987 18,591 Drum Filling (14.3B-0) 1.357 1,190 1.357 Radwaste Annex Truck Ldg (not Included with the 14.3C-0 2 3,194 1,879 8,525 11,719 Negligible General Area)

Auxiliary Bldg 617' Level 11.5 25 32,920 19,879 8,525 41,445

. Auxiliary Bldg 617: Level General Area (11.5.0) 39,507 7,867 55,841

  • HVAC Equipment Rm (Note 3) (not Included with 11.5A-0 14 18,738 4,034 8,525 27,263 81,904 the General Area)

Unit 1 VCT Rm (11.51-1) 74,793 169 74,793 Unit 2 VCT Rm (11.6B-2) 54.231 169 54,231 Unit 1 Pipe Chase (1 1.5C-1) <.100 427 Negligible Unit 2 Pipe Chase (1 1.5C-2) <100 427 Negligible Rad Prot. Office & Lab (Note 3) 11.5D-0 31 41,706 5,776 8,525 50,231 41,799 Unit 1 Cont Purge Air Equip (Note 3) 11.6-1 16 21,158 1,420 8,525 29,683 23,059 Unit 2 Cont Purge Air Equip (Note 3) 11.6-2 21 27,096 1,420 8,525 35,621 28,997 Tool Crib (14.4A-0) 3,972 720 4,120 2-32

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION FIRE ZONI SEVERITY FIRE LOAD LOADING LIMIT FIRE LOADING (NOTE 1)

(minutes) (Btu/fte) AREA (ft) (Btu/ft2) (Baulft2) (Btuffi)

  • Waste Gas Rm (14.4B-0) i0,510 917 42,385
  • Radwaste Evaporator Rm (14.4C-0)
  • 100 350 Negligible Spent Resin Storage Area (14.40-0)
  • 100 217 Negligible Auxiliary Bldg 642' Level (Note 3) 11.7-0 20 26,372 6,880 8.525 34.897 57.033 Fuel Handling Building (RCA) (Note 3) 12.0-0 6 8.479 6.180 8,525 17.004 N/A TSC Building 18.3-0 2.6 3,402 6,171 0 3402 N/A East Service Building 18.7-0 592' 28 37,404 10,856 8,525 45,929 N/A 608'-3" 19 25,404 13,448 8.525 33,929 N/A 624' 24 31.214 13,448 8,525 39,739 NIA 636' 25 33,261 13,448 8,525 41.786 NIA 648' 25 33,639 13,544 8.525 42,164 N/A 660' 26 33.874 13,544 8,525 42,399 N/A Outer Crib House 1&4A-0 13 17,118 9,125 8,525 25,643 23,250 Inner Crib House 18.4B-0 5 7.016 4.316 8,525 15,541 33,230 Fuel Oil Tank Area 18.6-0 0 0 0 0 0 N/A Unit 1 Transformers 18.9-1 54 72,058 1.902 0 72,058 N/A Unit 2 Transformers 18.9-2 54 72.058 1,902 0 72,058 N/A 2-33

Amendment 13, July 2013 I ZION STATION FIRE PROTECTION REPORT TABLE 2.8.1 COMBUSTIBLE LOADING

SUMMARY

FIXED ADMIN EQUIVALENT TRANSIENT TOTAL 1993 SER FIRE ACTUAL FIXED COMBUSTIBLE COMBUSTIBLE VALUE AREA DESCRIPTION FIRE ZONE SEVERITY FIRE LOAD LOADING LIMIT FIRE LOADING (NOTE 1)

I (minutes) (Btu/ft2 ) AREA (f12) (Btute) (Btute) 2 (Btuft)

Waste Water Treatment Center 15.0-0 13 17.558 4,800 8,525 26,083 W/A West Service Building 18.2-0 Ground Floor Machine Shop 3 3,600 9.284 8,525 12,125 N/A Ground Floor Storeroom 9 12.174 3.721 8,525 20,699 N/A Ground Floor Paint/Oil Storeroom 544 7,249 x I 318 8,525 733,425 N/A Ground Floor Offices 5 7,239 1.577 8,525 15,764 N/A Ground Floor Tool Area 0 0 913 8.525 8,525 WA Ground Floor Locker Area 0 0 8060 8,525 8,525 N/A Third Floor General Area 4 5,573 5,722 8,525 14,098 N/A Third Floor Central File 15 19,590 1,924 8,525 28.115 N/A Third Floor Men's Locker 0 0 4,865 8,525 8,525 WA Third Floor VTIP Room 20 26,084 521 8,525 34.609 N/A Third Floor Reference Center 13 17,565 1,630 8,525 26,090 N/A Third Floor Storage Area 8 10,644 2.111 8,525 19,169 N/A Fourth Floor Meeting Room 1,909 2,084 8,525 10,434 N/A Note 1: The values in this column reflect the fixed combustible loadings reviewed by the NRC for preparation of Its SER, dated 08/31/93, which provided approval of revised combustible loadings.

The exemption requests were revised by ComEd in 1992 to reflect Increases infixed combustible loading that had occurred since the 1982 and 1987 exemption request submittals. In the SER, the NRC stated that although the fixed combustible loading had increased, revised exemptions were not required because the basis for acceptance of the original exemptions had not changed. The SER does not specifically quote all the values listed in this column; however, the SER states that the NRC review was based on combustible loading values staled In the FPR dated 09/15/92, Therefore, the values in this column reflect those listed in the 09/15/92 FPR.

Note 2: General Area 11.1-0 Includes combustibles from areas 11.1E-1, 11.1E-2, 11.1F-1. 11.1F-2. 11.IG-1, 11.1G-2, 11.1H-1 and 11.1H-2 as depictedIn reference"h". The fire load and severity shown for the General Area of the 542' elevation of the AB 11.1-0 Include these areas. I Note 3: Fire Barriers are being maintained In these zones due to the type of combustibles present and/or the potential for a fire to spread Into the RCA. The HVAC Equipment Rm (11 .5A-0) Is not part of the RCA.

2-34

Amendment 13, July 2013 I ZION STATION FIRE PROTECTION REPORT TABLE 2.8.2 FIRE PROTECTION FEATURES

SUMMARY

FIRE AUTOMATIC AUTOMATIC SUPPRESSION ATR REQUIRED AREAWZONE FIRE FIRE SYSTEM SUPPRESSION AREA DESCRIPTION DETECTION SUPPRESSION TYPE (NOTE 1)

  • Unit 2 Div 28 0C Dist. PnI 5.6A-2 YES NO
  • Div 17/27 DC Bat. & Dist. Rm 7.0-0 YES NO

. Unit 1 Div. 19 Battery Rm 7.1-1 YES NO

  • Unit 2 Div. 29 Battery Rm 7.1-2 YES NO
  • Unit 1 Div. 18 Battery Rm 7.2-1 YES NO
  • Unit 2 Div. 28 Battery Rm 7.2-2 YES NO
  • Unit I EDG 1B Rm 9.1-1 NO NO Unit 2 EDG 2B Rm 9.1-2 NO NO Unit I EDG IA Rm 9.2-1 NO NO
  • Unit 2 EDG 2A Rm 9.2-2 NO NO
  • Unit 1 EDG 0 Rm 9.3-1 NO NO
  • Unit I EOG I B Diesel Fuel Slotr 10.11- NO NO
  • Unit 2 EDG 2B Diesel Fuel Stor 1011-2 NO NO
  • Unit 1 EDG IA Diesel Fuel Stor 10.2-1 NO NO

-Unit 2 EDG 2A Diesel Fuel Stor 10.2-2 NO NO Unit I EDG 0 Diesel Fuel Stor 10.3-1 NO NO 2-37

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT TABLE 2.8.2 FIRE PROTECTION FEATURES

SUMMARY

FIRE AUTOMATIC AUTOMATIC SUPPRESSION ATR REQUIRED AREA/ZONE FIRE FIRE SYSTEM SUPPRESSION AREA DESCRIPTION DETECTION SUPPRESSION TYPE (NOTE 1)

  • Turbine Building

-Turbine Oil Rm 8.1-0 NO NO NO

  • Unit 1 TB Basement 8.2-1 NO NO NO
  • Unit 2 TB Basement 8.2-2 NO NO NO

. Sampling Rm 8.3-0 NO NO

  • Auxilary Heating Boiler Rm 8.4-0 NO NO NO
  • Unit 1 TB Elev. 592' 8.5-1 YES NO NO Unit 2 TB Elev, 592' 8.5-2 YES NO NO BOP Battery Rooms 8.5A-0 YES NO
  • Unit I TB Mezz. Floor 16-11 NO NO NO
  • Unit 2 TB Mezz. Floor 8.6-2 NO NO NO

- TB Operating Floor 8.7-0 NO NO

  • Future Unit 2 Dies. Fuel Stor 10.3-2 NO NO OA Storage Rm and Operating Offices O 13.0-0 NO NO NO
  • Unit 1 Steam Pipe Tunnel 18.5-1 NO NO

- East Lower MS Isolation Valve House U-1 18.5-1 NO NO West Lower MS Isolation Valve House U-1 18.5-1 NO NO Unit 2 Steam Pipe Tunnel 18.5-2 NO NO

  • East Lower MS Isolation Valve House U-2 18.5-2 NO NO
  • West Lower MS Isolation Valve House U-2 18.5-2 NO NO

- Auxiliary Building

  • Auxiliary Bldg 542' Level 11.1-0 YES NO

.Unit I RHR 1A Pump Rm 11.1A-1 NO NO

  • Unit 2 RHR 2A Pump Rm 11.1A-2 NO NO

.Uni I1 RHR 1B Pump Rm 11.1B-1 NO NO 2-38

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT TABLE 2.8.2 FIRE PROTECTION FEATURES

SUMMARY

FIRE AUTOMATIC AUTOMATIC SUPPRESSION ATR REQUIRED AREArZONE FIRE FIRE SYSTEM SUPPRESSION AREA DESCRIPTION DETECTION SUPPRESSION TYPE (NOTE 1)

  • Auxiliary Building (cont'd)
  • Unit 2 RHR 2B Pump Rm 11.1-2 NO NO
  • Unit I Pipe Tunnel 11.IC-1 NO NO
  • Unit 2 Pipe Tunnel 11.1C-2 NO NO
  • Gas Decay Tanks Area 14.1-0 NO NO
  • Auxiliary Bldg 560 Level 11.2-0 YES NO
  • Unit I SI Pump 1A Rm 11.2A-1 NO NO
  • Unit 2 Sl Pump 2A Rm 11.2A-2 NO NO
  • Until SI Pump 1B Rm 11.21-1 NO NO
  • Unit 2 SI Pump 2B Rm 11.21-2 NO NO
  • Unit I1 RHR Heat Ex 1A Rm 11.2C-1 NO NO
  • Unit 2 RHR Heat Ex 2A Rm 11.2C-2 NO NO
  • Unit I1 RHR Heat Ex 1B Rm 11.2D-1 NO NO
  • Unit 2 RHR Heat Ex2B Rm 11.2D-2 NO NO Unit I Coni. Spray Pump 11.2E-1 NO NO Unit 2 Cont. Spray Pump
  • .Unlt I Pipe Chase 11.2E-2 11.2F-1 NO NO NO NO

.I

  • Unit 2 Pipe Chase 11.2F-2 NO NO
  • Auxiliary Bldg 579' Level 11 3-0 YES NO
  • Unit 1 Charg. Pump IA Rm 11.3A-1 NO NO
  • Unit 2 Charg. Pump 2A Rm 11.3A-2 NO NO
  • Unit 1 Charg. Pump IB Rm 11.3B.1 NO NO
  • Unit2 Charg. Pump 2B Rm 11.38-2 NO NO

-Unit 1 Charg. Pump 1C Rm 11.3C-1 NO NO

  • Unit 2 Charg. Pump 2C Rm 11.3C-2 NO NO

-Unit I1 RWST Rm 11.3D-1 NO NO

-Unit 2 RWST Rm 11.3D-2 NO NO 2-39

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT TABLE 2.8.2 FIRE PROTECTION FEATURES

SUMMARY

FIRE AUTOMATIC AUTOMATIC SUPPRESSION ATR REQUIRED AREA(ZONE FIRE FIRE SYSTEM SUPPRESSION AREA DESCRIPTION DETECTION SUPPRESSION TYPE (NOTE 1)

  • Auxiliary Building (cont'd)
  • Unit 1 Pipe Chase 11.3E-1 NO NO
  • Unit 2 Pipe Chase 11.3E-2 NO NO
  • Hold up Tanks 11.1D-0 NO NO
  • Crystallizer 14.2A-0 NO NO Auxiliary Bldg 592' Level 11.4-0 YES NO NO I
  • Unit 1 Letdown Heat Ex Rm 11.4A-1 NO NO
  • Unit 2 Letdown Heat Ex Rm 11.4A-2 NO NO
  • Unit 1 Seal Wtr Heal Ex Rm 11.4B-1 NO NO
  • Unit 2 Seal Wir Heat Ex Rm 11,41-2 NO NO
  • Unit 1 Pipe Chase 11,4C-1 NO NO

. Unit 2 Pipe Chase 11.4(-2 NO NO

  • Dry Active Waste Storage
  • Drum Filfng 14.3A-0 14.38-0 NO NO NO NO I
  • Raolwaste Annex Truck Ldg 14.3C-0 NO NO I
  • DAW Storage 11.4D-0 YES NO 2-40

Amendment 13, July 2013 I ZION STATION FRRE PROTECTION REPORT TABLE 2.8.2 FIRE PROTECTION FEATURES

SUMMARY

FIRE AUTOMATIC AUTOMATIC SUPPRESSION ATR REQUIRED AREANZONE FIRE FIRE SYSTEM SUPPRESSION AREA DESCRIPTION DETECTION SUPPRESSION TYPE (NOTE 1)

Auxillary Bldg 617 Level 11.5-0 YES NO

  • HVAC Equipment Rm 11.5A-0 YES NO NO
  • Unit I1VCT Rm 11.5B-1 NO NO
  • Unit 2 VCT Rm 11.51-2 NO NO
  • Unit 1 Pipe Chase 11.5C-1 NO NO
  • Unit 2 Pipe Chase 11.5C-2 NO NO Rad Prot. Office & Lab R 11.5D-0 NO NO
  • Unit 1 Cont Purge Air Equp 11.6-1 NO NO NO
  • Unit 2 Cont Purge Air Equp 11.6-2 NO NO
  • Tool Crib 14.4A-0 NO NO
  • Waste Gas Rm 14.41-0 NO NO
  • Radwaste Evaporator Rm 14,4C-0 NO NO
  • Spent Resin Storage Area 144D-0 NO NO 2-41

Amendment 13, July 2013 I ZION STATION FRE PROTECTION REPORT TABLE 2.8.2 FIRE PROTECTION FEATURES

SUMMARY

FIRE AUTOMATIC AUTOMATIC SUPPRESSION ATR REQUIRED AREA/ZONE FIRE FIRE SYSTEM SUPPRESSION AREA DESCRIPTION DETECTION SUPPRESSION TYPE (NOTE 1)

Audliary BSlg 642' Level 11.7-0 YES NO

  • Fuel Handing Building 12.0-0 YES NO
  • West Service Building 18.2-0 YES (PARTIAL) YES (PARTIAL) Wet Pipe Sprinklers/ NO Deluge

- TSC 18.3-0 NO NO

- East Service Building 18.7-0 NO NO Wet Pipe Sprinklers NO Note 2 592' 608-3" 624' 636' 648' 660' Outer Crib House 18.4A-0 NO NO Inner Crib House 18.4B-0 YES NO NO Fuel Oil Tank Area 18.8-0 NO NO Unit I Transformers - MPT/UAT REMOVED 18.9-1 NO NO NO SAT DRAINED Unit 2 Transformers - MPT/UAT REMOVED 18.9-2 NO NO NO SAT DRAINED

-Waste Water Treatment Center 15,0-0 NO NO

-ILL Dept. of Nuclear Safely Rm NO NO NOTE 1: These systems are required to be controlled per the Zion Administrative Technical Requirements (ATRs). The systems have been Installed to minimize radiological hazards by providing rapid suppression, A description of the specific areas protected by these systems Is provided In Section 3.0 (FHA) for the applicable tire zones.

NOTE 2: Sprinkler System Drained. Provision in place to manually connect water supply to system located on south end of building.

2-42

a 49

~h1 RIt-

1 TIM it, L-tr

K-W T =

I Fin smwap es

LI FIGSR 2-2

'st-a a

-mL

'Ao

'S.~. / T4 _ Ujf I

U ~LL.. I 41 11 -Y~!AIII I

--I L--

1 L",IA, (vr 4

-HI; I,,I 4 ýIýn

~-

'p (o mvcUg AM wu' KATu, S.... am t man wumm

$Nw S.." s~ 31 d ow I* ft x

t a 9 a t B 9 U le 4- +4 I

0I-1.n is

,A-=-

"blanom Lcpmr--.-

F-- I NIPCA* tOMi O

- mma im m 6t&wnu iý-

I, Nlý I T----

91 I

'1 aT

~ ~ _________I FTM a.

16 1.1 ol 11.1

....I'IU L 4.

U T~W C,.

Vv-AOM

')*

- ~I'~.U-~ ~Ham r--- -

I, m

N

""Now$ni I.

m LL*m U I J - - - - I ml I

m E Eýl

~-- -

~iIx'~ -- e - sMs it J m m

~ - p - ~-i~mm~ U

1J I ~'i" I T
  • '...- anwIwa :r $n do mslm II

~. .14-' LU I r T-T 0 L. WAQTPý 1'J~ -ZM swm um? I a 2 I~.3-1 1.4 U-7 t so L

1 Z

2

  1. VKAiNIki

.Af FACILITY - 30X P 3

l

JSS.1+/-2w ICAM wo $KAM

.!M an "a 4" 0 =mo

2_

J.g ,

17 IA

.r _L Ell

I ii

? - I- -- ~ ~- - -

I ' II I i It -

1 P - P P 9 9 7 ' -

I I I !

I 4~ ~

t ~ ~ t!

ft m " ono" 4 I ...~

t ,I1 i

T a

a T I

I- .ini a . I in a mm. *- u mm. mu i *T1

  • f
  • Jill" I ~ -

.-- +~,I~::rl~ I --

- u~q we.

m I

=--

4-- h

~uil

-, aI~~

I--i 4~

U

~" I l

U ms IS i an in~r 101 ,-14" RM -im.,Lao Now.

_-3 C

  • a-..-- -~ ~

War- I U - I U - ~m- U

  • I t6-AfvtA, t L¶K~ ej' 1 l 1-.....-

114=0 I C!Jit~

49 17 t I1 P-.

IL-Aje rV6)

I I

""i"M'li'lI

[77 It debi - i ~

..,,,. iisin II P  ! I ltillI Il TTI i *'- i II lti U1 I tI - Eli

  • mImES 'i L~ *1 i

~I '-a P U, I w..

.frX

  1. %*on Mrl N-.

.ML~ - iAtNOWNo M u Flom

=6 i

.... . _ - . ....... . .. . . . .. * -L,

aliý",.

i-0" 08~ e, 1 .- p "l 1, I *.~

'-I r Im A eman o m*

TT

'V tizW, CONDITION OF ORIGINAL DRAWING - *(l -- RPP*RflltrTif PleI nnrr h. aO

w 1tWqw4 flu InlID row

  • T iI t

. 10bw

  • Lw WUCSM WIMM *KA~

d -*A ONOWCM10

eamm -p-I rp

- .1 MRiM~

WOWIA LMI U Nom a" uno OUN F&

LvI

- - - - - - - "m o" N a*ma sm~ -

S m

U It* 16" Eli-i -~

tI:,

! I I'.'t low~ r I El' u... ~ -' - 4h.~4~4 3 ~ httt 3~

=10 H I.

]

tI; -4

~J~-4.--- ---

4 I

Ii

~iIm ~.

r~ -

I ~

~

I~i~i/~~ I I p -

H m

I -

J W 1 - -

1.!

ear INM--I.-..-

Ii -~

i~L~

B e~ M-14

,~ '4~ J4*~ ~ - I,~ It~

r '~' '~'

~

U A I Mu E R t *rt*-

. emrA

0 0

hFim- - - --- - - - - -

009 iH"Lx~ -- --- -- --- --

Eo pF1t 1-0

.4-r4 9-wit

~k~I am NIoeA Sa Omaw Iý -m " mSONi FIH "4

Amendment 13, July2013 i ZION STATION FIRE PROTECTION REPORT 3.0 FIRE HAZARD ANALYSIS The FHA analysis presented in this section refers to fire barriers that existed prior to the onset of decommissioning. Based on the amount and type of combustibles present within the interior rooms of the RCA, and the low amount of combustibles outside of the RCA, the existing fire barriers of most areas have be downgraded to unrated barriers. Actual removal of barriers will not occur until the onset of decommissioning for the associated zone.

In summary, areas previously designated as Fire Areas will be designated as Fire Zones due to the suspension of maintenance and periodic inspections of fire barriers except as denoted in Tables 2.8.1 and Figures 2-1 through 2-14. All previous designations of Fire Zones will remain the same; Fire Zones and fire barriers are shown on Figures 2-1 to 2-14.

3.0.a Containment Buildings The primary containment for each unit is considered a fire zone and has been divided into four segments for the assessment of fire loading. The following discussion applies to the fire analysis of the entire containment structure for each unit.

Each primary containment building is a closed concrete cylinder with structural reinforced base slab, walls, and a domed roof slab. These elements vary In thickness from 32 inches for the roof to 108 inches for the base slab. The roof slab and walls have been post-tensioned by means of steel tendons. The inside face of the entire building is lined with a 14-inch thick steel plate liner.

During decommissioning, access to the containment building will be through the 222-inch-diameter steel "equipment" air lock which leads to the Auxiliary Building at elevation 617 feet 0 inch. Each containment has a Construction door installed for bringing in equipment and removal of debris. With the exception of these entry points, the base slab, walls, and roof slab carry a minimum fire rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

Electrical cable penetrations and mechanical piping penetrations are provided. These penetrations have not been tested as fire barriers but would prevent the propagation of any fire likely to start into or out of the primary containment.

Radiological Hazard Potential Radiation and contaminants are present in all areas of the containment. The release of airborne radioactivity is controlled by maintaining the containment atmosphere negative in pressure with respect to the outside environment's atmospheric pressure. This negative pressure is maintained by the AB Ventilation system and/or Containment Purge system. Air can be exhausted from containment through the Containment Purge Exhaust Fans. Air can also be extracted from the containment through the equipment hatch to the AB. The AB Exhaust Fans can maintain the AB and the containments negative in pressure when the construction doors are closed. Administrative controls maintain the Containment Purge exhaust fan in operation when the construction doors are open. The AB Ventilation and the Containment Purge system use prefilters and HEPA filters to filter out any high radiation contaminants.

The exhaust air is routed to the vent stacks and is monitored for gaseous and particulate radioactive via radiation monitors. Portable CO 2 or dry chemical extinguishers are recommended for any fire in this zone due to radiation conditions. Manual fire suppression is also available via hose stations located inside the containments.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in the containments is important to the defueled condition:

Containment Purge System 3-1

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Fire Protection Criteria and Measures There are no automatic suppression or detection systems in the Containments. However, manual fire suppression equipment Including portable fire extinguishers and dry standpipe hose stations are available for fire responder use. The dry standpipe hose stations will be made ready for use for the ZMFD by the Local Operator (or the Shift Supervisor) in the event of a fire. Access routes are available to fire response personnel responding to a fire in this fire area. Smoke removal capability can be provided by the containment purge system through HEPA filters.

Design-Basis Fire The design-basis fire would result if cable insulation in a zone burned. It could also spread to the other zones inside the containment since the walls and floors separating these zones are not designated as fire barriers. The fire would not spread beyond the containment due to the containment walls and the large separation from combustibles outside of the containments.

The design-basis fire is unlikely for the following reasons:

  • Hot work associated with the dismantlement and removal of equipment inside the containments will be reviewed by the Fire Marshall for Fire Watch requirements. Combustibles will be removed as part of the dismantlement.
  • No significant quantities of combustible material that is easily ignited are stored in this area. Most of the combustibles material is cable insulation that meets the IEEE 383 criteria for cable fire tests.

" The fire zones have a low fire loading and the combustibles present are not evenly distributed, making the likelihood of a fire spreading to the other zones within the containments small.

3.0.1 Unit 1 Containment 1.0-1 This fire zone is comprised of the following segments:

1.1-1 Unit 1 reactor cavity, 1.2-1 Unit 1 Annular area, elevations 590 ft and 568 ft, 1.3-1 Unit 1 steam generator and reactor coolant pump area, and 1.4-1 Unit 1 operating floor, elevation 617 ft.

3-1a

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material in this fire area consisted of 104 gallons of lube oil (which has been drained),

about 420 lb of cable Insulation In trays and cabinets, about 48 ft of nuclear instrumentation cable, about 35 lb of flexible connectors (HVAC), 18 modules each of HEPA and pre-fihters, and 2688 lb of wood. With a floor area of 12,266 ft2 and a total heat content of 5.129 x 107 Btu, the average fire loading in this area is about 4.182 x 10 3 Btu/ft2 with an equivalent fire severity of 3 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft 2.

3-9

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT 3.0.2 Unit 2 Containment 1.0-2 This fire zone is comprised of the following segments:

1.1-2 Unit 2 reactor cavity,

.1.2-2 Unit 2 Annular area, elevations 590 ft and 568 ft.

1.3-2 Unit 2 steam generator and reactor coolant pump area, and 1.4-2 Unit 2 operating floor, elevation 617 ft.

3.0.2.1 Unit 2 Reactor Cavity (1.2-1 Fire Barrier Description A structural reinforced concrete cylinder surrounds the rough reactor cavity. Access to the steam generator area at elevation 568 feet 0 inch from the reactor cavity is through a solid door to a tunnel. Both the rough tunnel and rough reactor cavity are provided with 'A-inch-thick steel liner plate.

A. Floor The structural reinforced concrete slab below this cylinder, which Is the base slab of the containment building, is 53 feet 0 inch in diameter, and 108 inches thick. There are no floor drains in the reactor cavity or tunnel floor. A stainless steel sump with pump is located in the tunnel floor for the purpose of removing water to another sump on the reactor floor at elevation 568 feet 0 inch.

B. Ceiling The domed roof slab is constructed of structurally reinforced concrete.

C. Wall A structural reinforced concrete cylinder with an inside diameter of 21 feet 0 inch and walls 16 feet 0 inch thick surround the rough reactor cavity from elevation 539 feet 0 inch up to elevation 565 feet 0 inch.

The rough tunnel walls are structural reinforced concrete 36 inches thick.

Over the rough structural concrete described above are placed 24-inch-thick (reactor cavity walls), 30-inch-thick (reactor cavity and tunnel floor), and 15-inch-thick (tunnel walls) structural reinforced concrete finish slabs.

From elevation 565 feet 0 inch to elevation 580 feet 6 inches, a structural reinforced concrete cylinder with an inside diameter of 17 feet 1 inch and walls 101 inches thick surround the reactor cavity.

From elevation 580 feet 6 inches to elevation 590 feet 5-1/2 inches or elevation 589 feet 5-1/2 inches, a structural reinforced concrete cylinder of 25 feet 0 inch inside diameter and 54 inches thick surrounds the reactor cavity.

Finish concrete 8 inches thick is placed over the structural reinforced concrete to elevation 590 feet 5-1/2 inches or elevation 589 feet 5-1/2 inches.

A 1-foot-0-inch thick concrete cylinder of inside diameter 18 feet 6 inches is placed around the circumference of the reactor at elevation 591 feet 1-1/2 inches. Between this cylinder and the structural reinforced concrete cylinder at elevation 591 feet 1.1/2 inches are eight access panels of 12-gauge steel-plate covered with bricks made of shielding material.

Penetrations through the structure surrounding the reactor vessel for steam and feedwater piping are sealed with noncombustible material. The tunnel opening to the steam generator area at elevation 508 feet 0 inch is provided with non-fire-rated doors.

These walls, ceiling, and floor are not designated as fire area barriers.

3-10

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.2.4 Unit 2 oeratirn Floor. Elevation 617 (1.4-21 Fire Barrier Description This zone includes the entire containment building from elevation 617 feet 0 inch up to the domed roof slab at elevation 779 feet 8 inches, and the refueling cavity from elevation 581 feet 0 inch up to elevation 617 feet 0 inch. This zone is constructed of reinforced concrete with open stairwells and grated openings to the level below.

A. Floor The floor at elevation 617 feet 0 inch is a 36-inch structural reinforced concrete slab in the portion over the steam generator and reactor coolant pump area and has a number of penetrations for equipment. The remaining portion, which Is over an annular area, is steel grating supported on exposed steel framing.

Floor drains are routed to a sump at elevation 568 feet 0 inch.

B. Ceiling A domed roof slab constructed of structural reinforced concrete covers this zone.

C. Wall The 9-foot-0-inch high by 30-inch-thick structural reinforced concrete walls completely surround the top portion of the four steam generators that project above the floor slab at elevation 617 feet 0 inch. In addition, the pressurizer is enclosed by 12-inch-thick structural reinforced concrete walls that are capped by a removable 12-inch-thick structural reinforced concrete roof slab at elevation 655 feet 8 inches. HVAC ducts are not provided with fire dampers.

Radiological Hazard Potential Radiation and contaminants are present in this area. Air is exhausted from containment through prefilters and HEPA filters to filter out any high radiation contaminants. The air is then routed to the vent stacks via exhaust fans. Portable C02 or dry chemical extinguishers are recommended for any fire in this zone due to radiation conditions and distances from hose stations. Personnel doses should be monitored in this area.

3-16

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material in this fire area consisted of cable insulation in trays and cabinets, nuclear instrumentation cable, flexible connectors (HVAC), HEPA and pre-filters, wood, plastic battery casings.

With a floor area of 12,266 ft2 and a total heat content of 6.09 x 107 Btu, the average fire loading in this area is about 4.968 Btu/ft2 with an equivalent fire severity of 4 minutes. The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2 .

Fire Protection Criteria and Measures This fire zone has no general area automatic fire suppression or detection.

Manual fire suppression equipment including portable fire extinguishers and hose stations are available at containment entry for fire responder use. Access routes to this fire zone are available for responding fire response personnel.

Design-Basis Fire The design-basis fire would result if the combustible materials in this zone burned. This fire could spread to other zones in the containment, since the zone boundaries are not designated as fire barriers, but it would not spread out of the containment building.

The design-basis fire is unlikely, since this zone has a low fire loading, and the combustibles present are not evenly distributed, making the likelihood of a fire spreading rather small.

Any fire likely to start in this zone would remain confined to a small area, and would not cause any major damage.

3-17

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

4160-V SWGR 1LP084 1RIA-PR49 Buses: Isokinetic U1 Containment 141: lAP001 Flow Panel Rad Monitor 142:1AP002 143:1AP003 144: 1AP004 4160-V SWGR Bus 145: 1AP005 Combustible Material and Fire Loading The combustible material in this fire area consists of about 1067 lb of cable insulation, 8 lb of flexible connectors (HVAC), and 1.8 lbs of plastic battery casings. With a floor area of 2653 ft2 and a total heat load of 1.182 x 107 Btu, the average fire loading in this area is 4.457 x 103 Btu/ft 2, with an equivalent fire severity of 3 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

Fire Protection Criteria and Measures This fire area contains no automatic suppression systems, but fire detection in this fire area is provided by ionization smoke detectors that alarm in the control room.

Manual fire suppression equipment in the form of a portable fire extinguisher is available in this fire area, and hose stations are available in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this area. Communications equipment/smoke removal capability are available in this area as described in the pre-fire plan.

Design-Basis Fire The design-basis fire is the fire that bums all the cable insulation in the switchgear in this room. Due to the small amount of combustible material present, and the resulting small fire loading (less than a fire of Y2-hour severity), there are no serious consequences. A fire in this room would be quickly detected by the ionization detectors, and annunciated in the control room.

3-67

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

4160-V SWGR 2LP084 2RIA-PR49 Buses: Isokinetic AB/U2 Containment 241: 2AP001 Flow Panel Rad Monitor 242:2AP002 243:2AP003 244:2AP004 4160-V SWGR Bus 245: 2AP005 Combustible Material and Fire Loading The combustible material in this fire area consists of 1067 lb of cable insulation, 3 lb of flexible connectors (HVAC), and 1.8 lbs of plastic battery casings. With a floor area of 2653 ft and a total heat load of 1.179 x 10 Btu, the average fire loading in this area is 4.444 x i03 Btu/ft 2, with an equivalent fire severity of 3 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

Fire Protection Criteria and Measures This fire area contains no automatic suppression systems, but fire detection in this fire area is provided by ionization smoke detectors that alarm in the control room.

Manual fire suppression equipment in the form of a portable fire extinguisher Is available in this fire area, and hose stations are available in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this area. Communications equipment/smoke removal capability are available in this area as described in the pre-fire plan.

Design-Basis Fire The design-basis fire is the fire that bums all the cable insulation in the switchgear in this room. Due to the small amount of combustible material present, and the resulting small fire loading (less than a fire of 1/2k-hour severity), there are no serious consequences. A fire in this room would be quickly detected by the ionization detectors, and annunciated in the control room.

3-69

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.33 Unit I EDG 15 Room (9.1-11 This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is constructed of reinforced concrete with three-hour doors in the east wall. The ducts through the ceiling and the vents in the east wall are fire-dampered. The diesel air intake duct does not have a fire damper. Vertical ducts penetrating horizontal fire barriers have two fire dampers in series, each rated as 1-1/2 hours. All piping and electrical penetrations are sealed.

A. Floor The floor slab at elevation 592 feet 0 inch, which is the roof of the diesel fuel oil storage room 1B, is of 42-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating. There are two floor drains provided to remove water or oil from the diesel-generator room.

B. Ceiling The roof slab at elevation 617 feet 0 inch, which is the floor of the diesel-generator 1B switchgear room, is of 6-inch-thick structural reinforced concrete supported by structural steel framing which is supported by steel columns. The roof assembly carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

C. North Wall The north wall of the diesel-generator room is of 12-inch-thick structural reinforced concrete. Diesel-generator room 1B includes an air intake fan area which is located in the northwest corner of the diesel-generator room. This wall carries a 3-hour fire-resistance rating.

D. South Wall The south wall is of 24-inch-thick structural reinforced concrete. This wall carries a 3-hour fire-resistance rating.

E. East Wall The east wall is of 18-inch-thick structural reinforced concrete having two Label A fire doors and frames.

This wall carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. Also located on the east wall is an 8-foot-0-inch-wide-by-12-foot-high area of wall which is of 18-inch-thick concrete block. This will be used as a removal area if diesel-generator repair is required.

F. West Wall The west wall is of 24-inch-thick structural reinforced concrete. This wall contains a door that provides access into the EDG vent system chase area. The west exterior louvered wall bounding the EDG vent system chase area is a fire area boundary.

3-92

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is important to the defueled condition:

None Combustible Material and Fire Loading The combustible material in this fire area consists of approximately 40 gallons of lube oil, 1278 lb of cable insulation, 5.46 lb of flexible connectors (HVAC), and 3.6 lbs of plastic battery casings. With a floor area of 1428 ft2 and a total load of 2.04 x 107 Btu, the average fire loading in this area/zone is 14,270 Btu/fte, with an equivalent fire severity of less than 11 minutes. The administrative transient combustible load limit for this fire zone is 8,525 Btu/h.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones. An access route is available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles. A fire would not affect adjacent rooms.

3-93

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 3.0.34 Unit 2 EDG 2B Room (9.1-2)

This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is constructed of reinforced concrete with three-hour doors in the east wall. The ducts through the ceiling and the vents in the east wall are fire-dampered. Unrated dampers are also installed in the east wall in the same opening as the fire dampers. All piping and electrical penetrations are sealed.

A. Floor The floor slab at elevation 592 feet 0 inch, which is the roof of the diesel fuel oil storage room 1B, is of 42-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating. There are two floor drains provided to remove water or oil from the diesel-generator room.

B. Ceilina The roof slab at elevation 617 feet 0 inch, which is the floor of the diesel-generator 1B switchgear room, is of 6-inch-thick structural reinforced concrete supported by structural steel framing which is supported by steel columns. The roof assembly carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. All the ceiling beams, except one, are covered with concrete.

C. North Wall The north wall of the diesel-generator room is of 24-inch-thick structural reinforced concrete, except in the air intake fan area which is located in the northwest comer of the diesel-generator room. This wall carries a 3-hour fire-resistance rating.

D. South Wall The south wall is of 11-5/8-inch-thick reinforced hollow concrete. This wall carries a 3-hour fire-resistance rating.

E. East Wall The east wall Is of 18-inch-thick structural reinforced concrete having two Label A fire doors and frames.

This wall carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. Also located on the east wall is an 8-foot-0-inch-wide-by-12-foot-high area of wall which is of 18-inch-thick concrete block. This will be used as a removal area if diesel-generator repair is required.

F. West Wall The west wall is of 24-inch-thick structural reinforced concrete. This wall contains a door that provides access into the EDG vent system chase area. The west exterior louvered wall bounding the EDG vent system chase area is not a fire area boundary.

3-94

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is Important to the defueled condition:

None Combustible Material and Fire Loading The combustible material in this fire area consists of approximately 40 gallons of lube oil, 1412 lb of cable insulation, 2.75 lb of flexible connectors (HVAC), and 3.6 lbs of plastic battery casings. With a floor area of 1428 ft2 and a total heat load of 2.18 x 10 Btu, the average fire loading in this area is 15,280 Btu/ft ,

7 with an equivalent fire severity of less than 12 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2 .

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones. Access routes are available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles. A fire would not affect adjacent rooms.

3-95

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 3.0.35 Unit 1 EDG 1A Room (9.2-1)

This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is constructed of reinforced concrete with three-hour doors In the east wall. The ducts through the ceiling and the vents in the east wall are fire-dampered. Unrated dampers are also installed in the east wall in the same opening as the fire dampers. All piping and electrical penetrations are sealed.

A. Floor The floor slab at elevation 592 feet 0 inch, which is the roof of the diesel fuel oil storage room 1A, is of 42-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating. There are two floor drains provided to remove water or oil from the diesel-generator room.

B. Ceilina The roof slab at elevation 617 feet 0 inch, which is the floor of the diesel-generator IA switchgear room, is 6-inch-thick structural reinforced concrete supported by structural steel framing which is supported by steel columns. The roof assembly carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

C. North Wall The north wall of the diesel-generator room is of 12-inch-thick structural reinforced concrete. Diesel-generator room 1A includes an air intake tan area which is located in the southwest comer of the diesel-generator room. This wall carries a 3-hour fire-resistance rating.

D. South Wall The south wall is of 12-inch-thick structural reinforced concrete. This wall carries a 3-hour fire-resistance rating.

E. East Wall The east wall Is of 18-inch-thick structural reinforced concrete having two Label A fire doors and frames.

This wall carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. Also located on the east wall is an 8-foot-0-inch-wide-by-1 2-foot-high area of wall which is of 18-inch-thick concrete block. This will be used as a removal area if diesel-generator repair is required.

F. West Wall The west wall is of 24-inch-thick structural reinforced concrete. This wall contains a door that provides access into the EDG vent system chase area. The west exterior louvered wall bounding the EDG vent system chase area is a fire area boundary.

3-96

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is important to the defueled condition:

None Combustible Material and Fire Loading The combustible material in this fire area consists of approximately 40 gallons of lube oil, 1141.4 lb of cable insulation, 5.46 lb of flexible connectors (HVAC), and 3.6 lbs of plastic battery casings. With a floor area of 1419 ft2 and a total heat load of 1.88 x 107 Btu, the average fire loading in this area is 13,302 Btu/ft2, with an equivalent fire severity of less than 10 minutes. The administrative transient combustible load limit for this fire zone is 8,525 Btu/ftO.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones. Access routes are available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles. A fire would not affect adjacent rooms.

3-97

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 3.0.36 Unit 2 EDO 2A Room (9.2-2)

This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is constructed of reinforced concrete with three-hour doors in the east wall. The ducts through the ceiling and the vents in the east wall are fire-dampered. Unrated dampers are also installed in the east wall in the same opening as the fire dampers.

A. Floor The floor slab at elevation 592 feet 0 inch, which is the roof of the diesel fuel oil storage room 2A, is of 42-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating. There are two floor drains provided to remove water or oil from the diesel-generator room.

B. Ceilina The roof slab at elevation 617 feet 0 inch, which is the floor of the diesel-generator 2A switchgear room, is of 6-inch-thick structural reinforced concrete supported by structural steel framing which is supported by steel columns. The roof assembly carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

C. North Wall The north wall of the diesel-generator room is of 12-Inch-thick structural reinforced concrete. Diesel-generator room 2A includes an air intake fan area which is located in the northwest comer of the diesel-generator room. This wall carries a 3-hour fire-resistance rating.

D. South Wall The south wall is of 11-5/8-inch-thick reinforced hollow concrete. This wall carries a 3-hour fire-resistance rating.

E. East Wall The east wall is of 18-inch-thick structural reinforced concrete having two Label A fire doors and frames.

This wall carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. Also located on the east wall is an 8-foot-0-inch-wide-by-i 2-foot-high area of wall which is of 18-inch-thick concrete block. This will be used as a removal area if diesel-generator repair is required.

F. West Wall The west wall is of 24-inch-thick structural reinforced concrete. This wall contains a door that provides access into the EDG vent system chase area. The west exterior louvered wall bounding the EDG vent system chase area is a fire area boundary.

3-98

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is important to the defueled condition:

None Combustible Material and Fire Loading The combustible material in this fire area consists approximately 40 gallons of lube oil, 1,237 lb of cable insulation, 2.75 lb of flexible connectors (HVAC), and 3.6 lbs of plastic battery casings. With a floor area of 1419 ft 2 and a total heat load of 2.093 x 107 Btu, the average fire loading in this area/zone is 14,750 Btu/t, with an equivalent fire severity of less than 11 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btulft2 .

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones. Access routes are available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles. A fire would not affect adjacent rooms.

3-99

Amendment 13, July 201.3 ZION STATION FIRE PROTECTION REPORT 3.0.37 Unit I EDG 0 Room (9.3-1)

This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is constructed of reinforced concrete with three-hour doors in the east wall. The ducts through the ceiling and the vents in the east wall are fire-dampered. Unrated dampers are also installed in the east wall in the same opening as the fire dampers. All piping and electrical penetrations are sealed.

A. Floor The floor slab at elevation 592 feet 0 inch, which is the roof of the diesel fuel oil storage room (10.3-1), is of 42-inch-thick structural reinforced concrete and cardes a 3-hour fire-resistance rating. Floor drains are provided to remove water or oil from the diesel-generator room.

B. Ceilina The roof slab at elevation 617 feet 0 Inch, which is the floor of the diesel-generator (5.3-1) switchgear room, is of 6-inch-thick structural reinforced concrete supported by structural steel framing which is supported by steel columns. The roof assembly carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.

C. North Wall The north wall of the diesel-generator room is of 24-inch-thick structural reinforced concrete. This wall carries a 3-hour fire-resistance rating.

D. South Wall The south wall is of 11-5/8-inch-thick structural reinforced concrete. This wall carries a 3-hour fire-resistance rating.

E. East Wall The east wall is of 18-inch-thick structural reinforced concrete having two Label A fire doors and frames.

This wall carries a fire-resistance rating of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />. Also located on the east wall is an 8-foot-0-inch-wide-by-1 2-foot-high area of wall which is of 18-inch-thick concrete block. This will be used as a removal area if diesel-generator repair is required.

F. West Wall The west wall is of 24-inch-thick structural reinforced concrete. The portion of west wall covered by the air intake fan is 12 inches thick. This wall contains a door that provides access into the EDG vent system chase area. The west exterior louvered wall bounding the EDG vent system chase area is a fire area boundary.

3-100

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area Is important to-the defueled condition:

None Combustible Material and Fire Loading The combustible material in this fire area consists of approximately 40 gallons of lube oil, 1374 lb of cable insulation, 5.46 lb of flexible connectors (HVAC), and 3.6 lbs of plastic battery casings. With a floor area of 1428 fe and a total heat load of 2.15 x 107 Btu, the average fire loading in this area is 15,053 Btu/t, with an equivalent fire severity of less than 12 minutes. The administrative transient combustible load limit for this fire zone is 8,525 Btu/t.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones. Access routes are available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles.

A fire would not affect adjacent rooms.

3-101

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT 3.0.38 Unit I EDG 1B Diesel Fuel Oil Storaae Room (10.1-1)

This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is of reinforced concrete construction. All walls and slabs are 3-hour fire rating. All electrical and piping penetrations are sealed. HVAC penetrations are 1-1/2 hour rated fire dampers.

A. Floor The base slab at elevation 567 feet 6 Inches is 24 inches thick. Two floor drains are located in this area.

B. Ceiling The roof slab at elevation 592 feet 0 inches is 42 inches thick.

C. South Wall The south wall is of 36-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch.

D. North Wall The north wall is of 24-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the north wall that leads to diesel oil storage room 1A. The doors are located 7 feet 0 inch above the floor line to contain oil in the room In the event of a tank rupture. A grating stair and platform are provided at each door.

E. East Wall The east wall is of 18-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the wall that leads to the turbine building basement.

F. West Wall The west wall is of 36-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

3-102

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition:

Combustible Material and Fire Loading The combustible material in this fire area is negligible.

The administrative transient combustible load limit for this fire area Is zero.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose station is available in adjacent fire areas/zones.

Access routes are available to fire rresponse members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles.

3-103

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.39 Unit 2 EDG 2B Diesel Fuel Oil Storage Room (10.1-21 This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is of reinforced concrete construction and all walls and slabs are 3-hour fire rating. All electrical and piping penetrations are sealed. Two floor drains are provided to remove fire protection water and oil.

A. Ceiling The roof slab is 42 inches thick and Is the diesel-generator room floor.

B. Floor The base slab at elevation 567 feet 6 inches is 24 inches thick. Two floor drains are located in this area.

C. South Wall The south wall is of 24-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door In the south wall that leads to the adjacent diesel oil storage room.

D. North Wall The north wall Is of 36-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and Is dowelled into the roof slab at elevation 592 feet 0 inch.

E. East Wall The east wall is of 18-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the wall that leads to the turbine building basement.

F. West Wall The west wall is of 36-Inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

3-104

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition:

Combustible Material and Fire Loading The combustible material in this fire area is negligible.

The administrative transient combustible load limit for this fire area is zero.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available In adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles in the area.

3-105

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.40 Unit 1 EDG 1A Diesel Fuel Oil Storage Room (10.2-11 This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is of reinforced concrete construction and all walls and slabs are 3-hour fire rating. All electrical and piping penetrations are sealed. Two floor drains are provided to remove fire protection water and oil.

A. Ceiling The roof slab is 42 inches thick and is the diesel-generator room floor.

B. Floor The base slab at elevation 567 feet 6 inches is 24 Inches thick. Two floor drains are located in this area.

C. South Wall The south wall is of 24-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the south wall that leads to the adjacent diesel oil storage room.

D. North Wall The north wall is of 24-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the north wall that leads to diesel oil storage room 1A. The doors are located 7 feet 0 inch above the floor line to contain oil in the room in the event of a tank rupture. A grating stair and platform are provided at each door.

E. EMst Wall The east wall is of 18-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the wall that leads to the turbine building basement.

F. West Wall The west wall is of 36-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

3-106

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition:

Combustible Material and Fire Loading The combustible material in this fire area is negligible.

The administrative transient combustible load limit for this fire area is zero.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles in the area.

3-107

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.41 Unit 2 EDG 2A Diesel Fuel Oil Storage Room (10.2-2)

This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is of reinforced concrete construction and all walls and slabs are 3-hour fire rating. Doors are 3-hour fire-rated and the vent ducts, located in the east wall, are fire dampered.

All electrical and piping penetrations are sealed. Two floor drains are provided to remove fire protection water and oil.

A. Ceiling The roof slab is 42 inches thick and is the diesel-generator room floor.

B. Floor The base slab at elevation 567 feet 6 inches Is 24 inches thick. Two floor drains are located in this area.

C. South Wall The south wall is of 36-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The waNl extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch.

0. North Wall The north wall is of 24-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the north wall that leads to diesel oil storage room 2B. The doors are located 7 feet 0 inch above the floor line to contain oil in the room in the event of a tank rupture. A grating stair and platform are provided at each door.

E. East Wall The east wall is of 18-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the wall that leads to the turbine building basement.

F. West Wall The west wall is of 36-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

3-108

Amendment 13, July 2013 1 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition:

Combustible Material and Fire Loading The combustible material in this fire area is negligible.

The administrative transient combustible load limit for this fire area Is zero.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles in the area.

3-109

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 3.0.42 Unit I EDG 0 Diesel Fuel Oil Stora-ae Room (10.3-1)

This fire area has not been subdivided into fire zones.

Fire Barrier Description This area is of reinforced concrete construction. Doors are 3-hour fire-rated and ventilation ducts in the east wall are fire-dampered. All electrical and piping penetrations are sealed. Two floor drains are provided to remove fire protection water and oil.

A. Ceiling The roof slab is 42 inches thick and is the diesel-generator room floor.

B. Floor The base slab at elevation 567 feet 6 inches is 24 Inches thick. Two floor drains are located in this area.

C. South Wall The south wall is of 36-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door on the south wall that leads to diesel oil storage room IA. The doors are located 7 feet 0 inch above the floor line to contain oil in the room in the event of a tank rupture. A grating stair and platform are provided at each door.

D. North Wall The north wall is of 24-inch-thick structural reinforced concrete and carries a 3-hour fire-resistance rating.

The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch.

E. East Wall The east wall is of 18-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch. There is a UL Label A (3-hour) fire door in the wall that leads to the turbine building basement.

F. West Wall The west wall is of 36-inch-thick structural reinforced concrete. The wall extends up to and is dowelled into the roof slab at elevation 592 feet 0 inch.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination.

3-110

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition:

Combustible Material and Fire Loading The combustible material in this fire area Is negligible.

The administrative transient combustible load limit for this fire area is zero.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this area.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles in the area.

3-111

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.43.1 Turbine Oil Room (8.1-0)

Fire Barrier Description A. Floor The base slab at elevation 560 feet 0 inch consists of an 8-inch concrete finish over a 14-foot-O-inch structural reinforced concrete slab. Two floor drains and two equipment drains are provided.

B. Ceiling The roof slab at elevation 592 feet 0 inch, which is also the floor slab of the secondary sampling room is structural reinforced concrete slab. The slab is supported by steel beams, which are protected by plaster.

C. South Wall The south wall is of 48-Inch-thick structural reinforced concrete and carries a 3-hour fire rating.

D. North Wall The north wall is of 4-foot-0-inch-thick concrete. The north wall carries a 3-hour fire rating.

E. East Wall The east wall Is of 48-inch-thick reinforced concrete and carries a 3-hour fire rating.

F. West Wall The west wall is of 48-inch-thick concrete. In the west wall are two UL Label A (3-hour) doors. The doors are located 4 feet 6 inches above the floor line to contain the oil in the room in case of a tank rupture. Fire damper is provided In ventilation opening.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition. The following is the major equipment in the area:

Turbine (Dirty) Turbine (Clean) Dirty Oil Tank Oil Transfer Oil Transfer (20,000 gal)

Pump 0TO012 Pump 0T0013 DRAINED Clean Oil Tank (20,000 gal)

DRAINED 3-113

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material in this fire zone consists of remnants of lube oil.

The administrative transient combustible load limit for this fire area is zero.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this zone.

Design-Basis Fire The design-basis fire for this room is insignificant. The Turbine Oil Rooms are located on the east side of the Turbine Building, far from any radiological areas. Since no equipment important to the defueled condition is located in this room, the ability to cool the spent fuel pool would not be affected by this fire.

This fire will also not result in any radiological hazard.

3-114

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition. The following is the major equipment in the area:

480-V TB MCC Dirty Oil Room Dirty Oil Room 1323A and B Vent Fan OB Vent Fan OA 1AP018 & 1AP084 0TV015 OTV014 TB Equipment Fire Sump Pumps ORT-PR35 Drain Sump Pumps OA, OB, OC Fire Sump 1A and 1B Rad Monitor Combustible Material and Fire Loading The combustible material in this fire zone consists of lube oil, cable insulation, flexible connections (HVAC), and plastic battery casings. With a floor area of 20,420 ft and a total heat load of 1.259 x 108 Btu, the average fire loading in this zone is 6,166 Btu/ft2, with an equivalent fire severity of about 5 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire areas/zones. Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability are available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all the combustibles in the area ignited and burned. This fire could spread to other elevations of the turbine building. It is unlikely that the fire would spread throughout this zone or to other elevations of the turbine building since the combustibles are spread out over a large floor area. .Since there is no equipment important to the defueled condition In this area, the ability to cool the spent fuel pool would not be affected. This fire will also not result in any radiological hazard.

3-116

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition. The following is the major equipment in the area:

480-V TB MCC TB Equipment Drains Sump Drains Sump Pumps 2A & 2B Pumps 2A & 2B Combustible Material and Fire Loading The combustible material in this fire zone consists of lube oil, cable insulation, rubber, flexible connectors (HVAC), and plastic battery casings. With a floor area of 20,420 ft2 and a total heat load of 9.13 x 107 the average fire loading in this zone is 4,474 Btu/ft2, with an equivalent fire severity of about 4 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/fe.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability are available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all the combustibles in the area ignited and burned. It is unlikely that the fire would spread throughout this zone or to other elevations of the turbine building since the combustibles are spread out over the large floor area. Since there is no equipment important to the defueled condition in this area, the ability to cool the spent fuel pool would not be affected. This fire will also not result in any radiological hazard.

3-118

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material in this fire zone consists of 4.25 gallons of lube oil and 700 lb of cable insulation.

With a floor area of 1128 ft 2 and a total heat load of 8.352 x 106 Btu, the average fire loading in this zone is 7.405 x 108 Btu/ft, with an equivalent fire severity of 6 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones. Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability are available In this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would damage or destroy all of the equipment in this room. This fire would not affect the ability to cool the spent fuel pool. This fire will also not result in any radiological hazard.

3-122

Amendment 13, July 2013 I ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITOC)

There is no equipment in this area important to the defueled condition. The following major equipment is in the area:

MCC 1322 480-V MCC 1353 480-V Instrument Air 1AP017 1AP028 Receiver Service Air Compressors 1A and 18 Service Air Receiver MCC 1354A and B CO 2 Storage 480-V 1AP029 Tank and I AP095 Refrigerator 15,000 Gallon Turbine Oil Reservoir DRAINED Combustible Material and Fire Loading The combustible material in this fire zone consists of lube oil, plastic, paper, rubber, wood, acetylene, cable insulation, and plastic battery casings. With a floor area of 50,875 ft2 and a total heat load of 4.456 x 108 Btu, the average loading in this zone is 8,758 Btu/ft2, with an equivalent fire severity of 6.6 minutes.

The administrative transient combustible load limit for this fire zone Is 8,525 Btu/ft2 .

3-124

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Fire .Protection Criteria and Measures The Turbine Building Elevator shaft is provided with a locally alarming heat detection device. Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire area/zones. Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability are available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all the combustibles ignited. This fire would not likely spread throughout this zone or to other elevations of the turbine buiding since the combustibles are spread out over the large floor area. Since no equipment ITDC is located in this zone, the ability to cool the spent fuel pool would not be affected. This fire will also not result in any radiological hazard.

3-125

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition. The following major equipment is in the area:

MCC 2322 MCC 2353 MCC 2354A and 480-V 480-V 2354B 480-V 2AP01 7 2AP028 2AP029 and 2AP095 Service Air Service Air Compressor 2A Receiver 2A Instrument Air Receivers 2A, and 0B Instrument Air 15,000-gal Lube Dehydrator Oil Reservoir (empty)

Combustible Material and Fire Loading The combustible material In this fire zone consists of approximately 560 gallons of lube oil, 51.2 lb of panel, 163 lb of wood, 22 lb of compressed 10% methane, 100 lb of rubber, 1,650 lb of paper, 925 lb of plastic, approximately 36,400 lb of cable insulation, and 18 lbs of plastic battery casings. With a floor area of 56,138 ft 2 and a total heat load of 5.55 x 108 Btu, the average loading in this zone is 9.886 x 103 Btu/ft2 ,

with an equivalent fire seventy of 7 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2 .

Fire Protection Criteria and Measures Ionization detection is provided in the uninterruptable power supply (UPS) equipment rooms.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability are available in this zone as described in the pre-f ire plan.

Design-Basis Fire The design-basis fire would result if all the combustibles in the area ignited and burned. It is unlikely that the fire would spread throughout this zone or to other elevations of the turbine building since the combustibles are spread out over the large floor area. The ability to cool the spent fuel pool would not be affected. This fire will also not result in any radiological hazard.

3-127

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition. The following major equipment is in the area:

480-V SWGR Bus 480-V SWGR Bus H2 Seal Oil 132:1AP009 135: 1AP012 Unit Drained 480-V TB MCC 1352: 1AP027 480-V Tank 4160/480-V Tank Heating MCC Heating Transformer 135-11: 135-1: IAP040 480-V TB MCC 480-V TB MCC 1321A and 1321B 1351A and 1351B 1AP016 and 1AP083 1AP026 and 1AP094 Combustible Material and Fire Loading The combustible material in this fire zone consists of lube oil, paper, plastic, cable insulation, cloth, HVAC filters, lining, and plastic battery casings. With a floor area of 48,880 ft2 and a total heat load of 5220 x 108, the average fire loading in this zone is 10,680 Btu/ft2, with an equivalent fire severity of approximately 8 minutes. The administrative transient combustible load limit for this fire zone is 8,525 Btu/ftr.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone andlor in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability is available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all the combustibles in the area ignited and burned. It is unlikely that the fire would spread throughout this zone or to other elevations of the turbine building since the combustibles are spread out over the large floor area. Because no equipment important to the defueled condition is located in this zone, the ability to cool the spent fuel pool would not be affected. This fire will also not result in any radiological hazard.

3-131

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition. The following major equipment is in the area:

480-V SWGR Bus 480-V SWGR Bus H2 SeaI Oil 232: 2AP009 235:2AP012 Unit (empty) 480-V TB MCC 2352: 2AP027 I 480-V Tank 4160/480-V Tank Heating MCC Heating Transformer 235-11: 235-2: 2AP040 480-V TB MCC 480-V TB MCC 2321A and 2321 B: 2351: 2AP026 2AP01 6 and 2AP083 Combustible Material and Fire Loading The combustible material in this fire zone consists of lube oil, plastic, wood, rubber, clothing, flexible connections (HVAC), duct insulation, pre-filter, paper, cable insulation, and plastic battery casings. With a floor area of 55,120 f 2 and a total heat load of 4.48 x 10e, the average fire loading in this zone is 8,120 Btu/ft2 , with an equivalent fire severity of less than 7 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2 .

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability are available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result ifall the combustibles in the area ignited and burned. It is unlikely that the fire would spread throughout this zone or to other elevations of the turbine building since the combustibles are spread out over the large floor area. Because no equipment important to the defueled condition is located in this zone, the ability to cool the spent fuel pool would not be affected. This fire will also not result in any radiological hazard.

3-133

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

Diesel Fuel Oil 480-V TB MCC Exhaust Fan 1A 1324: 1AP049 1TV012 and 1AP085 Refrigeration Unit OA Refrigeration Unit OB I Diesel Fuel Oil 480-V TB MCC Diesel Fuel Oil Exhaust Fan 1B 1356: 1AP050 Exhaust Fan 2A 1TV013 and 1AP096 2TV012 Diesel Fuel Oil Return Air Fans Return Air Fans Exhaust Fan 2B OSVO04 & 0SV01I1 OSVO03 & 0SV010 2TV013 Service Bldg.

HVAC System A/H 0SV001 Service Bldg.

HVAC System ANH OSVO02 Heating System Boiler & XFRM I Heating System Service Bldg.

Expansion Tank HVAC System (1500 gallons) OSVO09 Combustible Material and Fire Loading The combustible material in this fire zone consists of lube oil, carpet, cable insulation, grease, flexible connectors (HVAC), clothing, wood, plastic, acetylene, filter modules, HEPA filter modules, charcoal, cabinet lining, internal duct lining, duct insulation, rubber, paper, fiberglass, polyester, nylon, polyurethane, flexible duct, mix box blanket materials, and plastic battery casings. With a floor area of 97,940 ft2 and a total heat load of 6.177 x 108 Btu, the average fire loading in this zone is 6,307 Btu/ft2 , with an equivalent fire severity of 4.7 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

Fire Protection Criteria and Measures This fire zone contains no automatic suppression systems.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability are available in the zone as described in the pre-fire plan.

3-135

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material In this fire zone consists of about 80 lb of wall base materials, 227 lb of duct insulation (HVAC), 21.5 lb of flexible duct,'5,000 lb of paper, 500 lb of plastic, and 1.8 lbs of plastic battery casings. With a floor area of 2400 ft2 and a total heat load of 1.030 x 108 Btu, the average fire loading in this zone is 2.406 x 104 Btu/ft2 , with an equivalent fire severity of 18 minutes. f The administrative transient combustible load limit for this fire zone Is 8,525 Btu/ft2.

Fire Protection Criteria and Measures No automatic suppression or fire detection is provided in QA storage room. Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and with additional extinguishers and fire hose In adjacent fire areas/zones. An access route is available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability are available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all of the paper stored in this room burned. Since no equipment important to the defueled condition is located in either this room, or in the surrounding turbine building, this fire would not have any effect on plant safety. This fire will also not result in any radiological hazard.

3-140

Amendment 13, July 2013 I ZION STATION FIRE PROTECTION REPORT 3.0.44 Radiological Control Area of the Auxiliary Buildina This building has been subdivided into the following six fire zones. Each elevation of the Auxiliary Building is considered one fire zone. Rooms and enclosures of each elevation were previously considered separate fire zones have been combined as one fire zone except as denoted. The original fire zone identifier has been retained in parenthesis () for information. The fire barriers separating these zones will be left in place for the most part during decommissioning until the building is demolished.

Zone 11.1 Auxiliary Building, 542' Level,

" (11.1-0) 542' Level General Area

  • (11.1A-1) Unit I RHR Pump 1A Room,

" (11.1A-2) Unit 2 RHR Pump 2A Room,

  • (11.1B-1) Unit I RHR Pump 1B Room,
  • (11.1B-2) Unit 2 RHR Pump 2B Room,

" (11.1C-1) Unit 1 Pipe Tunnel,

" (11.1C-2) Unit 2 Pipe Tunnel,

" (11.1D-0) Hold up Tanks,

  • (14.1-0) Gas Decay Tanks Area, Zone 11.2 Auxiliary Building, 560' Level,
  • (11.2-0) 560' Level General Area 0 (11.2A-1) Unit 1 Safety Injection Pump 1A Room,
  • (1 1.2A-2) Unit 2 Safety Injection Pump 2A Room,
  • (11.2B-1) Unit 1 Safety Injection Pump 1B Room.
  • (11.28-2) Unit 2 Safety Injection Pump 2B Room,
  • (11.2C-1) Unit 1 RHR Heat Exchanger 1A Room,
  • (11.2C-2) Unit 2 RHR Heat Exchanger 2A Room,
  • (11.2D-1) Unit 1 RHR Heat Exchanger 1B Room,
  • (11.2D-2) Unit 2 RHR Heat Exchanger 2B Room,
  • (11.2F-2) Unit 2 Pipe Zone 11.3 Auxiliary Building, 579' Level, 0 (11.3-0) 579' Level General Area
  • (1 1.3A-1) Unit 1 Centrifugal Charging Pump 1A Room,
  • (1 1.3A-2) Unit 2 Centrifugal Charging Pump 2A Room,
  • (11.31-1) Unit 1 Centrifugal Charging Pump 1B Room, 0 (11.3B-2) Unit 2 Centrifugal Charging Pump 2B Room, 0 (11.3C-1) Unit I Reciprocating Charging Pump 1C Room,
  • (11.3C-2) Unit 2 Reciprocating Charging Pump 2C Room,
  • (11.3D-1) Unit 1 Refueling Water Storage Tank Room,
  • (11.3D-2) Unit 2 Refueling Water Storage Tank Room, 0 (11.3E-1) Unit 1 Pipe Chase,
  • (11.3E-2) Unit 2 Pipe Chase,
  • (14.2A-0) Crystallizer, 3-145

Amendment 13, July2013 1 ZION STATION FIRE PROTECTION REPORT Zone 11.4 Auxiliary Building, 592' Level, (11.4-0) 592' Level General Area 0 (11.4A-1) Unit 1 Letdown Heat Exchanger Room, (11.4A-2) Unit 2 Letdown Heat Exchanger Room, 0 (11.4B-1) Unit 1 Seal Water Heat Exchanger Room, 0 (11.4B-2) Unit 2 Seal Water Heat Exchanger Room, 0 (11.4C-1) Unit 1 Pipe Chase, S (11.40-2) Unit 2 Pipe Chase, 0 (14.3A-0) Dry Active Waste Storage, 0 (14.38-0) Drum Filling, 0 (14.3C-0) Radwaste Annex Truck Loading Zone, 0 (11.4D-0) DAW Storage, Zone 11.5 Auxiliary Building, 617' Level,

  • (11.5-0) 617' Level General Area
  • (11.5B-1) Unit 1 Volume Control Tank Room,
  • (11.5B-2) Unit 2 Volume Control Tank Room,
  • (11.5C-1) Unit 1 Pipe Chase,
  • (11.5C-2) Unit 2 Pipe Chase,
  • (11.5D-0) Radiation Protection Offices and Labs, Fire Barriers Maintained
  • (11.6-1) Unit I Containment Purge Air Equipment Room, Fire Barriers Maintained
  • (11.6-2) Unit 2 Containment Purge Air Equipment Room, Fire Barriers Maintained
  • (14.4A-0) Tool Crib,
  • (14.4B-0) Waste Gas Room,
  • (14.4C-0) Radwaste Evaporator Room,
  • (14.4D-0) Spent Resin Storage Area.

Zone 11.7 Auxiliary Building, 642' Level Fire Barriers Maintained I 3-146

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 3.0.44.2 Unit I RHR Pump 1A Room M11.1A-1)

Fire Barrier Description This zone is constructed of reinforced concrete. Electrical and piping penetrations of the room boundaries are sealed. A hollow metal door provides access to the zone. The vent duct to the redundant RHR pump cubicle is fire-dampered, while the vents located above the door are not.

A. Floor The floor at elevation 542 feet 0 inch is an 8-inch concrete finish slab on a 60-inch concrete base slab.

The floor has a 3-hour fire rating. There are a number of floor drains in this zone to remove water and oil and which are routed to the auxiliary building sump at this floor.

B. Ceilina The roof slab at elevation 560 feet 0 inch varies In thickness from 24 inches to 42 inches.

C. South Wall The south wall is 24-inch-thick structural reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

D. North Wall The north wall is 24-inch-thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

E. East Wall The east wall is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

F. West Wall The west wall is 24-Inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

Radiological Hazard Potential Radiation and contaminants are present in this area. Airborne contamination is likely as well. Personnel doses should be monitored in this area.

3-149

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is important to the defueled condition:

None.

Combustible Material and Fire Loading Negligible.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/.t 2.

Fire Protection Criteria and Measures This fire zone contains no automatic suppression systems.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

An access route Is available to fire response members responding to a fire In this zone.

Design-Basis Fire The design-basis fire is highly unlikely for the following reasons:

No significant quantities of combustible materials are stored in this room.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-150

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 3.0.44.3 Unit 2 RHR Pump 2A Room0 (11.1A-2)

Fire Barrier Description This zone is constructed of reinforced concrete. Electrical and piping penetrations of the room boundaries are sealed. A hollow metal door provides access to the zone. The vent duct to the redundant RHR pump cubicle is fire-dampered, while the vents located above the door are not.

A. Floor The floor at elevation 542 feet 0 inch is an 8-inch concrete finish slab on a 60-inch concrete base slab.

The floor has a 3-hour fire rating. There are a number of floor drains in this zone to remove water and oil and which are routed to the auxiliary building sump at this floor.

B. Ceilina The roof slab at elevation 560 feet 0 inch varies in thickness from 24 inches to 42 inches.

C. South Wall The south wall is 24-inch-thick structural reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

D. North Wall The north wall is 24-inch thick reinforced concrete and extends up to and Is dowelled into the roof slab at elevation 560 feet 0 inch.

E. East Wall The east wall Is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

F. West Wall The west wall Is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

Radiological Hazard Potential Radiation and contaminants are present in this area. Airborne contamination is likely as well. Personnel doses should be monitored in this area.

3-151

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is important to the defueled condition:

None.

Combustible Material and Fire Loading Negligible The administrative transient combustible load limit for this fire zone is 8,525 Btulft2 .

Fire Protection Criteria and Measures This fire zone contains no automatic suppression systems.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this zone.

Design-Basis Fire The design-basis fire is highly unlikely for the following reasons:

No significant quantities of combustible materials are stored In this room.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-152

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.44.4 Unit 1 RHR Pump 1B Room (11.1 B-1)

Fire Barrier Description This zone is constructed of reinforced concrete. Electrical and piping penetrations of the room boundaries are sealed. A hollow metal door provides access to the zone. The vent duct to the redundant RHR pump cubicle is fire-dampered, while the vents located above the door are not.

A. Floor The floor at elevation 542 feet 0 inch is an 8-inch concrete finish slab on a 60-inch concrete base slab.

The floor has a 3-hour fire rating. There are a number of floor drains in this zone to remove water and oil and which are routed to the auxiliary building sump at this floor.

B. Celfina The roof slab at elevation 560 feet 0 inch varies in thickness from 24 inches to 42 inches.

C. South Wall The south wall is 24-inch-thick structural reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

D. North Wall The north wall is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

E. East Wall The east wall is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

F. West Wall The west wall is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

Radiological Hazard Potential Radiation and contaminants are present in this area. Airborne contamination is likely as well. Personnel doses should be monitored in this area.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is important to the defueled condition:

None.

3-153

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading Negligible.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

Fire Protection Criteria and Measures This fire zone contains no automatic suppression systems.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this zone.

Design-Basis Fire The design-basis fire is highly unlikely for the following reasons:

No significant quantities of combustible materials are stored in this room.

A fire In this area does not cause a radiological hazard in the Auxiliary Building.

3-154

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.44.5 Unit 2 RHR Pump 2B Room 111.1 B-2)

Fire Barrier Description This zone is constructed of reinforced concrete. Electrical and piping penetrations of the room boundaries are sealed. A hollow metal door provides access to the zone. The vent duct to the redundant RHR pump cubicle is fire-dampered, while the vents located above the door are not.

A. Floor The floor at elevation 542 feet 0 inch is an 8-inch concrete finish slab on a 60-inch concrete base slab.

The floor has a 3-hour fire rating. There are a number of floor drains in this zone to remove water and oil and which are routed to the auxiliary building sump at this floor.

B. Ceiling The roof slab at elevation 560 feet 0 inch varies in thickness from 24 inches to 42 inches.

C. South Wall The south wall is 24-inch-thick structural reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

D. North Wall The north wall is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

E. East Wall The east wall is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet.

F. West Wall The west wall is 24-inch thick reinforced concrete and extends up to and is dowelled into the roof slab at elevation 560 feet 0 inch.

Radiological Hazard Potential Radiation and contaminants are present in this area. Airborne contamination is likely as well. Personnel doses should be monitored in this area.

3-155

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is important to the defueled condition:

None.

Combustible Material and Fire Loading Negligible.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/t 2 .

Fire Protection Criteria and Measures This fire zone contains no automatic suppression systems.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this zone.

Design-Basis Fire The design-basis fire is highly unlikely for the following reasons:

No significant quantities of combustible materials are stored in this room.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-156

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

480V AB ESS 480V AB ESS 480V AB ESS MCC 1383A & B MCC 1393A, B & C MCC 2383A 1AP035 and 1AP091 1AP036, 1AP092 2AP035 1AP093 480V AB MCC 2342 480V AB MCC 1342 2AP023 1AP023 480V AB ESS 480V AB ESS MCC 1333A & B MCC 2333A & B 1AP021 and 1AP088 2AP021, 2AP088 Combustible Material and Fire Loading The combustible material in this fire zone consists of lube oil, plastic, paper, and cable insulation, mostly in trays, and plastic battery casings. With a floor area of 17,064 ft2 and a total heat load of 4.532 x 10i Btu, the average fire loading in this zone is 26,600 Btu/ft2, with an equivalent fire severity of about 20 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

Fire Protection Criteria and Measures Fire detection in this zone is provided by ionization smoke detectors that alarm in the control room.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire areas/zones. Access routes are available to fire response members responding to a fire in this zone.

I Design-Basis Fire The design-basis fire would result if all the combustible material in this zone burned. The fire loading is small (equivalent to a fire of less than /2-hour severity). The air would be filtered before it is discharged.

The design-basis fire is highly unlikely, since the majority of combustible material normally present is cable insulation, which meets the IEEE-383 criteria for cable fire test.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-162

Amendment 13, July 2013 I ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material in this fire zone consists of 795.4 lb of cable insulation. With a floor area of 792 ft2 and a total heat load of 8.74 x I0' Btu, the average fire loading in this zone is 11,037 Btu/ft2 , with an equivalent fire severity of about 8 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft 2.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available I in this fire zone and/or in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire In this zone.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles.

Adequate means are provided to extinguish any fire likely to start in this room. I A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-180

Amendment 13, July2013 I ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material in this fire zone consists of 1,592.4 lb of cable insulation. With a floor area of 792 ft2 and a total heat load of 1.75 x I Btu, the average fire loading in this zone is 22,096 Btu/ft2 , with an equivalent fire severity of less than 17 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2 .

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this zone.

Design-Basis Fire The design-basis fire is highly unlikely due to the low amount of combustibles. I Adequate means are provided to extinguish any fire likely to start in this room. I A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-182

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

Concentrates 480-V AB Refueling Water Holding Tank Radwaste Annex Purification Transfer Pumps MCC 1344: IAP150 Pump: Pump 0 480V Aux Bldg.

ESS MCC 2383B:

2AP092 Combustible Material and Fire Loading The combustible material in this fire zone consists of about 1 gallon of lube oil, 25,137 lb of cable insulation, mostly in trays and 48.6 lbs of plastic battery casings. With a floor area of 12,490 fe, and a total heat load of 2.77 x 10e Btu, the average fire loading in this zone is 2.22 x 104 Btu/fte, with an equivalent fire severity of less than 17 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/fl2 .

Fire Protection Criteria and Measures Fire detection in this fire zone is provided by ionization smoke detectors that alarm in the control room.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire areas/zones. Access routes are available to fire response members responding to a fire in this zone.

Design-Basis Fire The design-basis fire would result if all of the cable insulation in the room burned. Control of equipment located in rooms would be lost. Since all of the rooms on the floor are either sealed or contain negligible amounts of combustible materials, the fire would not enter those areas. The air would be filtered before it is released. The design-basis fire could spread to other floors, since the floor and ceiling do not qualify as fire barriers.

The design-basis fire is highly unlikely, since most of the combustible material present is cable insulation.

In addition, the cables are separated in cable trays by function and division.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-186

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Radiological Hazard Potential Radiation and contaminants are present in this area. Airborne contamination is likely as well. Air is exhausted directly to a bank of HEPA filters. The filtered air is then exhausted up the Auxiliary Building vent stacks. Personnel doses should be monitored In this area.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

480-V AB MCC 480-V AB MCC Boric Acid 1332: IAP020 2332: 2AP020 Pumps: 1A, 1B.

2A, and 2B Monitor Tank Monitor Tank Boron Sample Panels Drain Pump Drain Pump OB: 0VC044 OA: 0VC043 Combustible Material and Fire Loading The combustible material in this fire zone consists of lube oil, cable insulation, mostly in trays, compressed hydrogen, pre-filter and HEPA filter modules, plastic, panel insulation and plastic battery casings. With a floor area of 19,945 ft and a total heat load of 5.002 x 108 Btu, the average fire loading in this zone is 25,079 Btu/ft 2, with an equivalent fire severity of 19 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2 .

Fire Protection Criteria and Measures Fire detection in this fire zone is provided by ionization smoke detectors that alarm in the control room.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and/or in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability is available in this zone as described in the pre-fire plan.

Design- Basis Fire The design basis fire would result if all of the combustibles In the area burned, including the cable Insulation, and flammable liquids. All of the equipment in the open floor area would be destroyed. Control of equipment in rooms would be lost. Since all of the rooms on the floor are either sealed, or contain negligible amounts of combustible materials, the fire would not enter those areas. The air is filtered before being released to the atmosphere.

A fire in this area does not cause a radiological hazard In the Auxiliary Building.

3-206

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material in this fire zone consists of about 2,413 lb of cable insulation mostly in trays, 4 modules each of pre-filters and HEPA filters. With a floor area of 1987 ft2 and a total heat load of 1.38 x 107 Btu, the average fire loading in this zone is 6.945 x 104 Btu/ft2 , with an equivalent fire severity of 10 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft 2.

Fire Protection Criteria and Measures Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

Access routes are available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability is available In this zone as described in the pre fire plan.

Design-Basis Fire A design basis fire could result if all of the combustible load in the room burned. However, a design basis fire is unlikely for the following reasons:

a. No significant quantities of combustibles.
b. Area suppression present.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-218

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Combustible Material and Fire Loading The combustible material in this fire zone consists of about 40 lb of cable insulation and transient material.

With a floor area of 960 ft2 and a negligible heat load, the average fixed fire loading in this zone Is negligible.

The administrative transient combustible load limit for this fire zone is 25,000 Btu/ft 2 .

Fire Protection Criteria and Measures Fire detection in this fire zone is provided by ionization smoke detectors that alarm in the control room.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this area.

Design-Basis Fire Due to the relatively light fire loading in this area, the design basis fire consequences is negligible.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-223

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition. The following is major equipment in the area:

Control Room Control Room Control Room Ventilation Air-Handling Return Air Filters: OPV001 Unit OA: Fan OB:

and OPV002 OPV009 OPV012 Control Room Control Room Computer and Misc.

Odor Filters: Air-Handling Rooms Return OPV003 and OPV004 Unit 0B: 0PV010 Air Fan OB: 0OV004 Control Room Control Room Computer and Misc.

Makeup Air Return Air Rooms Refrigeration Filters: OPV005 Fan OA: OPV01 1 Unit OA: 0OV005 Computer and Misc. Control Room Computer and Misc.

Rooms HVAC System Refrigeration Rooms Refrigeration Panel: OLP020 Unit OA OPV013 Unit OB: 0OV006 Computer and Misc. Control Room Computer and Misc.

Rooms HVAC Sys. Refrigeration Rooms HVAC System Exhaust Fan OA: Unit OB: Panel: OLP021 0OV007 OPV014 Computer and Misc. Control Room Computer and Misc.

Rooms HVAC Sys. Charcoal Unit Rooms Air-Handling Exhaust Fan OB: Fan OA Unit OA: OOV001 0OV008 Computer and Misc. Control Room Computer and Misc.

Rooms Filters Charcoal Unit Rooms Air-Handling 0OV009 Fan OB Unit OB: 0OV002 Computer and Misc. Control Room Computer and Misc.

Rooms Filters HVAC System Rooms Return Air 0OV010 Panel: OLP018 Fan OA: 0OV003 Computer and Misc. Control Room Rooms Mixing Box HVAC System 0OV018, 0OV021, Panel: OLP019 and 0OV025 Combustible Material and Fire Loading The combustible material in this fire zone consists of about 5,072 lb of cable insulation mostly in trays, about 69 lb of flexible connectors (HVAC), 50 modules each of pre-filter and HEPA filters, about 1812 lb of external duct insulation, about 23 lb of mixing box blanket material, and about 1047 lb of internal duct lining. With a floor area of 4034 ft and a total heat load of 7.559 x le Btu, the average fire loading in this zone Is 1.874 x 104 Btu/ft 2, with an equivalent fire severity of 14 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

3-228

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Fire Protection Criteria and Measures Fire detection in this fire zone is provided by ionization smoke detectors (12 in area and 6 in ducts) that alarm in the control room.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones. A hose station is available in this area.

An access route is available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability is available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all the combustible materials in the room burned. The HVAC equipment in the zone would be damaged. Due to the isolated low fire loading in this room, the fire would be confined to this room. The ability cool the spent fuel pool would not be affected. No radiological hazard will result from this fire.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-229

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

Purge Supply Purge Supply Purge Exhaust Fan 1A Fan 1B Fan 1A Purge Exhaust Fan 1B Combustible Material and Fire Loading The combustible material in this fire zone consists of 200 lb of cable insulation, about 39 lb of flexible connectors (HVAC), 84 modules each of pre-filters and HEPA filters and about 16 lb of internal duct lining.

With a floor area of 1420 ft2 and a total heat load of 3.004 x 107 Btu, the average fire loading in this zone is 2.11 x 104 Btu/ft2, with an equivalent fire severity of 16 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/fe.

Fire Protection Criteria and Measures This fire zone contains no automatic suppression or detection systems, but manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones. An access route is available to fire response members responding to a fire in this zone.

Communications equipment/smoke removal capability are available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all of the combustible material in the room burned. The HVAC equipment in the room would be damaged. The insignificant amount of radioactive substances generated when the HEPA filter bums will be exhausted to the atmosphere through the main stacks. The ability to cool the spent fuel pool would not be affected. Due to the small fire loading, equivalent to a fire of much less than one-half hour severity, the fire would be contained in the room.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-239

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

Purge Supply Purge Supply Purge Exhaust Fan 2A Fan 2B Fan 2A Purge Exhaust Fan 2B Combustible Material and Fire Loading The combustible material in this fire zone consists of 269 lb of cable insulation, 47 lb of flexible connectors (HVAC), 90 modules each of pre-filters and HEPA filters and about 305 lb of internal duct lining. With a floor area of 1420 ft2 and a total heat load of 3.848 x 107 Btu, the average fire loading in this zone is 2.7096 x 104 Btu/ft2, with an equivalent fire severity of 21 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft2.

Fire Protection Criteria and Measures This fire zone contains no automatic suppression or detection systems, but manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability is available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all of the combustible material in the room burned. The HVAC equipment in the room would be damaged. The insignificant amount of radioactive substances generated when the HEPA filter bums will be exhausted to the atmosphere through the main stacks. The ability to cool the spent fuel pool would not be affected. Due to the small fire loading, equivalent to a fire of much less than one-half hour severity, the fire would be contained in the room.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-241

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is important to the defueled condition:

AB Vent Supply AB Vent Supply Fan OA Fan OC AB Vent System AB Exhaust Fans:

Panel: OLP17 OD, OE, OF Combustible Material and Fire Loading The combustible material in this fire zone consists of 96 gallons of lube oil, 368.5 lb of cable insulation, 420 lb of duct insulation, 109 lb of flexible connectors (HVAC), 499 HEPA filter modules, 481 pre-filter modules, and 18 lbs of plastic battery casings. With a floor area of 6880 ft2 and a total heat load of 1.814 x 100 Btu the average fire loading in this zone is 2.63 x 104 Btu/ft2 , with an equivalent fire severity of less than 20 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/ft 2.

Fire Protection Criteria and Measures Fire detection in this fire zone is provided by heat and ionization smoke detectors that alarm in the control room.

Manual fire suppression equipment in the form of portable fire extinguishers and hose stations is available in this fire zone and in adjacent fire areas/zones.

An access route is available to fire response members responding to a fire in this zone. Communications equipment/smoke removal capability Is available in this zone as described in the pre-fire plan.

Design-Basis Fire The design-basis fire would result if all the combustible materials in this zone burned. The radioactive substances released when the HEPA filters are burned will be exhausted to the atmosphere through the main stacks. The ability to cool the spent fuel pool would not be affected.

A fire in this area does not cause a radiological hazard in the Auxiliary Building.

3-251

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 3.0.45 Fuel Handlina Buildina (12.0-0)

Fire Barrier Description This zone is constructed of reinforced concrete with unprotected steel supporting the roof. Electrical and piping penetrations are sealed. The fire area is supplied by AB Ventilation system.

The walls of the security access are hollow concrete blocks and vary in thickness from 8 inches to 12 inches. The walls of new fuel storage rooms vary in thickness from 18 inches to 72 inches structural reinforced concrete. Fire dampers in the horizontal ducts are 1-1/2-hour fire-rated. At elevation 576 feet 0 inch, there is the spent fuel storage pool that extends up to elevation 617 feet 0 inch and is open to the operating floor at elevation 617 feet 0 inch. Walls and floor slabs of pool are structural reinforced concrete. The thickness of the walls varies from 72 inches to 84 inches, and the thickness of the floor slab varies from 41 inches to 66 inches. A continuous stainless steel liner plate Is anchored to the floor slab and walls of the pool.

For the floor level at elevation 592 feet 0 inch, the following areas are included:

a. Heat exchanger area with walls of 18 inches thick structural reinforced concrete and floor slab of 8-inch finish over the 36-inch-thick structural reinforced concrete base slab.
b. Decontamination area with walls varying in thickness from 18 inches to 21 inches structural reinforced concrete and floor slab of 44-inch-thick structural reinforced concrete. A continuous stainless steel plate is anchored to the floor slab and walls of the decontamination area. The north, east, and west walls extend up to elevation 612 feet 0 inch. The decontamination area is open to the operating area at elevation 617 feet 0 inch.
c. The remaining area at elevation 592 feet 0 inch, for unloading fuel, has a floor slab of 44-Inch-thick structural reinforced concrete.

At elevation 592 feet 0 inch in the heat exchanger area and in the fuel unloading area, floor drains are provided. They are routed to the heat exchanger area sump which in turn is pumped to the radwaste building.

A. Floor For the operating floor at elevation 617 feet 0 inch, the floor slab of structural reinforced concrete varies in thickness from 8 inches to 42 inches. In the area from columns P-R and from rows 17-23, the floor slab is supported by steel beams protected by a 2-inch-thick minimum cover of concrete and by unprotected steel columns. The floor slab in this area will provide a fire resistance of 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br /> to the passage of fire from the fuel-handling building to the auxiliary building at 592 feet 0 inch level. The base slab at elevation 576 feet 0 inch varies in thickness from 48 inches to 72 inches. The base slab at elevation 592 feet 0 inch varies in thickness from 36 inches to 44 inches. In some areas at elevation 592 feet 0 inch, an 8-inch concrete finish is provided over the base slab.

The intermediate floor level at elevation 608 feet 2 inches, which is the roof of the spent fuel pit pump area at elevation 592 feet 0 inch, is a 28-inch structural reinforced concrete slab. For the intermediate floor level at elevation 602 feet 0 inch, the floor slab is 36-inch-thick structural reinforced concrete, and is the roof of the heat exchanger area.

3-252

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT E. East Wall The east wall, lower level, is a minimum 24-inch thick structural reinforced concrete. At elevation 592 feet 0 inch, the wall is constructed of 11-5/8-inch hollow concrete blocks. There are a number of plastic glazed windows in the east wall.

F. West Wall The west wall, lower level, is a minimum 24-inch thick structural reinforced concrete. At elevation 592 feet 0 inch, the wall is constructed of 11-5/8-inch hollow concrete blocks. A portion of the wall above and below the window in the west wall is Insulated metal siding instead of concrete block. There are a number of plastic glazed windows in the west wall. Six pneumatic-operated louvers are provided in this wall.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition. The following is major equipment in the area:

480-V Crib House 480-V Crib House MCC 1334: 1AP024 MCC 2334:2AP024 Combustible Material and Fire Loading The combustible material in this fire area consists of about 746.5 gallons of lube oil, about 26 lb of flexible connectors, 3,662 lb of cable insulation, mostly in cable trays, and 3.6 lbs of plastic battery casings. With a floor area of 9125 ft2 and a total heat load of 1.562 xl0 Btu, the average fire loading is 1.712 x 10W Btu/ft2, with an equivalent fire severity of 13 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/f?.

3-261

Amendment 13, July2013 1 ZION STATION FIRE PROTECTION REPORT Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

D and D 480-V Crib House Service Water Pumps:

ESS MCC 1382:

1AP082 1B:1SW002A 1C:1 SW003A 480-V Crib House 480-V Crib House ESS MCC 1392: ESS MCC 2382:

1AP034 2AP032 480-V Crib House ESS MCC 2392:

2AP034 Motor-Driven Fire Pump OA I Crib House Vent System Panel 0LP022 and 0LP023 I

Combustible Material and Fire Loading The combustible material in this fire area consists of 6 gallons of lube oil, 2,644.4 lb of cable insulation, and 26.25 pounds of flexible connectors (HVAC). Lube oil is contained in the D and D service water pumps (3 gallon), motor-driven (2 gallons) fire pump, and air compressors (1 gallon). A negligible quantity of lube oil is contained in strainers. With a floor area of 4,316 ft and a total heat content of 3.028 x 107 Btu, the average fire loading in this fire area is 7.016 x 103 Btu/ft2 with an equivalent fire severity of 5 minutes.

The administrative transient combustible load limit for this fire zone is 8,525 Btu/fte.

3-264

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT Fire Protection Criteria and Measures Fire detection is provided in this fire area by ionization type smoke detectors designed to alarm in the control room.

No automatic suppression systems are provided in this fire area.

Manual fire suppression equipment is available in or near this fire area. Portable C02 fire extinguishers are strategically located in the area. Access routes are available to the fire responders responding to a fire in this fire area. Smoke removal capability is available through portable smoke ejector equipment.

Design-Basis Fire A design basis fire could result if all combustible loads in the area burned.

The design-basis fire for this fire area would activate fire detection alarms in the control room.

A fire in this fire area cannot affect Fire Area 18.4A-0 (Outer Crib House) because of the presence of a complete three-hour fire barrier for Fire Area 18.4B-0. No other fire areas share a boundary with this fire area.

3-265

Amendment 13, July2013 ZION STATION FIRE PROTECTION REPORT 3.0.51 Fuel Oil Tank Area (18.8-)

This fire area has not been divided into fire zones.

Fire Area Description This tank is located outside approximately 90 feet from the East Service Building and 255 feet from the crib house. The tank is surrounded by a berm which can contain the entire 150,000 gal of the tank.

All diesel fuel oil has been removed from the tank.

A flammable compressed gas tank farm is located approximately halfway between the fuel oil tank area and the turbine building. Another compressed gas cylinder storage area is located between the fuel oil tank area and the crib house.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITDC)

There is no equipment in this area important to the defueled condition:

Fuel Oil Tank Compressed Gas Hydrogen and (150,000 gal) Storage Area Nitrogen Tank Farm DRAINED Removed Combustible Material and Fire Loading The combustible material in this fire area/zone is negligible.

The administrative transient combustible load limit set for this area is zero.

Fire Protection Criteria and Measures Automatic suppression and detection are not provided in this area. The fuel oil tank installation meets the requirements of NFPA 30.

Design-Basis Fire 3-266

Amendment 13, July 2013 ZION STATION FIRE PROTECTION REPORT 3.0.52 Unit I Transformers (118.9-1)

This fire area has not been divided into fire zones.

Fire Barrier Description The two main power transformers and the Unit Aux transformer for Unit 1 have been removed and replaced with a new 34 KV to 4 KV transformer. The new transformer is located outside and is approximately 15 feet from the Auxiliary Building at the closest point and is greater than 25 feet from the Turbine Building. The transformer is filled with" 1010 gallons of Envirotemp FR3, a non-petroleum, fire resistant fluid. The transformer is located on a base filled with crushed stone to prevent the spread of any spilled oil.

The system auxiliary transformer has been drained of the oil and is no longer in service.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

Unit I System Unit 1 34KV Transformer 142 Transformer DRAINED Combustible Material and Fire Loading Although Envirotemp FR3 is considered a self-extinguishing fluid, the combustible load is calculated assuming it as transformer mineral oil. The combustible material in this fire area consists of 1,010 gallons of transformer oil. With a floor area of 1902 ft and a total heat load of 1.37 x 108 Btu, the average fire loading in this area is 72,058 Btu per ft2, with an equivalent fire severity greater of 54 minutes..

The administrative transient combustible load limit set for this area is zero.

Fire Protection Criteria and Measures No automatic suppression or detection is provided in this fire area. Fire hydrants are located in the adjacent area for manual suppression.

Access routes are available to fire response members responding to a fire in this area. Communications equipment is available for this area.

3-267

Amendment 13,July2013 ZION STATION FIRE PROTECTION REPORT Design-Basis Fire The design-basis fire would occur if the oil in a transformer ignited and burned. It could spread to the turbine building, west service building and auxiliary building.

If a fire started in a transformer, it would be extinguished by manual fire fighting using the outside fire hydrants. It is unlikely that it would spread to the turbine building, since the transformer is located greater than 25 feet away.The portion of the Auxiliary Building adjacent to the transformer is not a radiological area. Loss of this transformer would not affect the ability to cool the spent fuel pool. A fire in this area does not result in a radiological hazard.

3-268

Amendment 13, July 2013 1 ZION STATION FIRE PROTECTION REPORT 3.0.53 Unit 2 Transformer (18.9-2)

This fire area has not been divided into fire zones.

Description The System Auxiliary Transformer (SAT) is near the northwest comer of the Unit 2 turbine building, however has been drained of oil.

A new 34KV to 4KV transformer has been installed for decommissioning. The new transformer is located outside and is greater than 25 feet from the Turbine Building and Auxiliary Building. The transformer is filled witli 1010 gallons of Envirotemp FP3, a non-petroleum, fire resistant fluid. The transformer is located on a base filled with crushed stone to prevent the spread of any spilled oil.

Radiological Hazard Potential A fire in this area would not create a radiological hazard for the following reasons:

This area contains no significant radiological material or contamination. This area is separated from radiological areas by fire barriers.

Equipment Important to the Defueled Condition (ITDC)

The following equipment in this area is either important to the defueled condition or major equipment in the area:

Unit 2 System Unit 2 34KV Transformer 242 Transformer DRAINED Combustible Material and Fire Loading Although Envirotemp FR3 is considered a self extinguishing fluid, the combustible load is calculated assuming it as transformer mineral oil. The combustible material in this fire area/zone consists of 1,010 gallons of transformer oil. With a floor area of 1902 ft2 and a total heat load of 1.37 x 108 Btu, the average fire loading in this area is 72,058 Btu per ft2, with an equivalent fire severity greater of 54 minutes.

The administrative transient combustible load limit set for this area is zero.

Fire Protection Criteria and Measures No automatic suppression or detection Is provided in this fire area. Fire hydrants are located in the adjacent area for manual suppression. Access routes are available to fire response members responding to a fire in this area. Communications equipment is available for this area/zone.

Design-Basis Fire The design-basis fire would occur if the oil In the transformer ignited and burned. It could also spread to the turbine and auxiliary buildings. If a fire started in a transformer, it would be extinguished by the manual suppression using the outside fire hydrants. It is unlikely that it would spread to the turbine building or auxiliary building, since the transformer is located greater than 25 feet away. Loss of this transformer would not affect the ability to cool the spent fuel pool, and no radiological hazard will result as a result of this fire.

3-269