Issue date | Title | |
---|---|---|
ML22326A064 | 31 October 2022 | 4 to the Updated Final Safety Analysis Report, Chapter 2, Site Characteristics (Part 2 of 2) and Chapter 3, Design of Structures, Components, Equipment, and Systems (Part 1 of 7) |
ML22326A120 | 31 October 2022 | 4 to the Updated Final Safety Analysis Report, Chapter 8, Electric Power (Part 3 of 3); Chapter 9, Auxiliary Systems; and Chapter 10, Steam and Power Conversion System (Part 1 of 2) |
ML22116A084 | 5 July 2022 | Issuance of Amendment Nos. 215 and 198, Regarding Revision to Technical Specification 3.7.2, Main Steam Isolation Valves (Msivs) |
NL-21-1015, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System | 13 January 2022 | Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.2 Limiting Condition for Operation to Remove One Main Steam Isolation Valve System |
ML21179A124 | 15 June 2021 | 0 to Updated Final Safety Analysis Report, Chapter 3, Design of Structures, Components, Equipment and Systems, Sections 3.1 Thru 3.7 |
ML21102A240 | 30 March 2021 | 3 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics (Part 2) & Chapter 3, Design of Structures, Components, Equipment, and Systems (Part 1) |
ND-20-0625, Report of 10 CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report | 5 June 2020 | Report of 10 CFR 50.59 Changes, Tests and Experiments and 10 CFR 52 Appendix D Departure Report |
ND-20-0093, Supplement to Request for License Amendment: Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (LAR-19-014S1) | 14 February 2020 | Supplement to Request for License Amendment: Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (LAR-19-014S1) |
ML19338C151 | 18 December 2019 | Regulatory Audit Report (LAR-19-014) |
ML19322C029 | 26 November 2019 | Notice of No Objection for Preliminary Amendment Request for Vogtle Electric Generating Plant Units 3 and 4 (PAR-19-014), Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 |
ND-19-1388, Preliminary Amendment Request (Par): Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (PAR-19-014) | 13 November 2019 | Preliminary Amendment Request (Par): Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (PAR-19-014) |
ML19282E152 | 10 October 2019 | COL Docs - Audit Plan for LAR 19-014 Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 |
ML19283A041 | 10 October 2019 | COL Docs - Audit Plan for LAR 19-014 Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 |
ML19319A011 | 11 September 2019 | Acceptance Letter - Vogtle Electric Generating Plant Units 3 and 4 LAR 19-014, Tornado Missile Protection for Main Steam Vent Stacks and Wall |
ML19238A167 | 27 August 2019 | Request for Withholding Proprietary Information from Public Disclosure for Vogtle Electric Generating Plant Units 3 and 4 (LAR-19-014) |
ND-19-0855, Request for License Amendment: Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (LAR-19-014) - Without Proprietary Enclosure 3 | 16 August 2019 | Request for License Amendment: Tornado Missile Protection for Main Steam Vent Stacks and Wall 11 (LAR-19-014) - Without Proprietary Enclosure 3 |
ML19196A061 | 15 July 2019 | COL Docs - FW: Draft Letter for 7/25/19 Pre-Submittal Meeting |
ML19168A084 | 26 June 2019 | Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: 07/02/2019 |
ML19120A134 | 6 May 2019 | 3/15/19 Summary of Public Meeting with Nuclear Entergy Institute, Duke Energy, and Southern Nuclear Operating Company Post-Pilot Implementation of Tornado Missile Risk Evaluator Methodology at Vogtle, Units 1 and 2 and Shearon Harris, Unit |
ND-19-0340, Transmittal of Proprietary Presentation Slides for NRC Public Meeting on April 11, 2019 Tornado Missile: Turbine Building First Bay Barriers and MSSV Stacks (WEC LAR 221) | 23 April 2019 | Transmittal of Proprietary Presentation Slides for NRC Public Meeting on April 11, 2019 Tornado Missile: Turbine Building First Bay Barriers and MSSV Stacks (WEC LAR 221) |
ML18304A394 | 11 January 2019 | Issuance of Amendment Nos. 198 and 181, Revise Updated Final Safety Analysis Report to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis |
NL-18-1179, Response to NRC Request for Additional Information Tornado Missile Risk Evaluator SNC Supplemental | 14 September 2018 | Response to NRC Request for Additional Information Tornado Missile Risk Evaluator SNC Supplemental |
ML18236A445 | 30 August 2018 | Review of Response to RAI License Amendment Request for Approval to Utilize the Tornado Missile Risk Evaluator to Analyze Tornado Missile Protection Non-Conformances |
NL-18-0815, Tornado Missile Risk Evaluator: SNC Response to NRC Request for Additional Information | 26 July 2018 | Tornado Missile Risk Evaluator: SNC Response to NRC Request for Additional Information |
ML18138A419 | 18 June 2018 | Regulatory Audit Report - Phase 1 Audit Conducted 4/4 to 4/6/18; Phase 2 Audit Conducted 5/15/18 License Amendment Request to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis |
ML18136A497 | 1 June 2018 | Request for Additional Information, License Amendment Request to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis |
ML18127B723 | 14 May 2018 | Biweekly Federal Register Notice - Applications and Amendments to Facility Operating Licenses and Combined Licenses Involving No Significant Hazards Considerations - Publication Date: May 22, 2018 |
ML18117A351 | 11 May 2018 | Summary of Public Meeting with Southern Nuclear Operating Company to Discuss Issues Associated with the Safety Review of Licensing Actions for Vogtle Electric Generating Plant Units 3 and 4 |
ML18114A230 | 3 May 2018 | Updated Audit Questions License Amendment Request for Approval to Utilize the Tornado Missile Risk Evaluator to Analyze Tornado Missile Protection Non-Conformances |
ML18074A003 | 1 May 2018 | Denial of Fee Exemption Request for Review of NEI 17-02, Tornado Missile Risk Evaluator (TMRE) Industry Guidance Document. |
ML18054A042 | 16 March 2018 | Audit Plan (Start Date No Later than 4/15/18) Related to License Amendment Request to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis |
NL-18-0102, Incorporate Seismic Probabilistic Risk Assessment Into the 10 CFR 50.69 Categorization Process, Response to Request for Additional Information (RAIs 1,2,3, & 12) | 6 February 2018 | Incorporate Seismic Probabilistic Risk Assessment Into the 10 CFR 50.69 Categorization Process, Response to Request for Additional Information (RAIs 1,2,3, & 12) |
ML17354A782 | 5 January 2018 | Request for Additional Information Incorporate Seismic Probabilistic Risk Assessment Into the 10 CFR 50.69 Categorization Process (CAC Nos. MF9861 and MF9862; EPID L-2017-LLA-0248) |
ML17319A325 | 4 December 2017 | Audit Plan Regarding Incorporate Seismic Probabilistic Risk Assessment Into the 10 CFR 50.69 Categorization Process (CAC Nos. MF9861 and MF9862; EPID L-2017-LLA-0248) |
ML17319A847 | 21 November 2017 | Acceptance Review Letter, License Amendment Request to Revise Updated Final Safety Analysis Report to Incorporate Tornado Missile Risk Evaluator Methodology Into Licensing Basis |
ML17244A074 | 28 September 2017 | 8/17/2017 Summary of Public Meeting with Nuclear Energy Institute and Licensees to Discuss the Tornado Missile Risk Evaluation Tool for Grand Gulf, Shearon Harris, and Vogtle, Units 1 and 2 |
ML17250B240 | 30 August 2017 | TMRE LAR Pre-Submittal Meeting with NRC |
ML17235B148 | 23 August 2017 | U.S. Nuclear Regulatory Commission - Tornado Missile Risk Evaluator (TMRE) Methodology Topics and Methodology Feedback |
ML17125A106 | 3 July 2017 | Request for Fee Waiver Regarding Pilot Review of Tornado Missile Risk Evaluator License Amendment Request |
IR 05000424/2016007 | 23 December 2016 | U.S. Nuclear Regulatory Commission Component Design Bases Inspection - Inspection Report 05000424/2016007 and 05000425/2016007, and Exercise of Enforcement Discretion |
ML16330A429 | 2 November 2016 | Vogtle Electric Generating Plant, Units 1 & 2, Updated Final Safety Analysis Report, Figure 8.3.1-1 (Sheet 25 of 34) Through Figure 10.2.2-2b |
NL-13-1920, Response to NRC Request for Additional Information for License Amendment Request to Revise Technical Specification 3.7.9 Ultimate Heat Sink (UHS) | 30 August 2013 | Response to NRC Request for Additional Information for License Amendment Request to Revise Technical Specification 3.7.9 Ultimate Heat Sink (UHS) |
NL-13-1727, Response to NRC Request for Additional Information for License Amendment Request to Revise Technical Specification 3.7.9 Ultimate Heat Sink (UHS) | 7 August 2013 | Response to NRC Request for Additional Information for License Amendment Request to Revise Technical Specification 3.7.9 Ultimate Heat Sink (UHS) |
ML13198A101 | 24 July 2013 | Request for Additional Information |
ML20198S228 | 29 October 1997 | Forwards Info to Supplement Presentation to Southeast Nuclear Plant Managers Meeting Held on 970821.Info Listed |
Information Notice 1996-64, Modifications to Containment Blowout Panels Without Appropriate Design Controls | 10 December 1996 | Modifications to Containment Blowout Panels Without Appropriate Design Controls |
ML20127L710 | 3 April 1985 | Forwards Response to Request for Addl Info,Including Draft SER Open Item 51, Toxic Gas Evaluation of Chemicals. Info Will Appear in Amend 16 to FSAR |
ML20112C309 | 15 March 1985 | Forwards Revised Responses to Questions 430.9,430.11 & 430.35,in Response to 850305 Request for Supplemental Info. Info Will Be Included in Next FSAR Amend Scheduled for 850410 |
ML20107F027 | 31 October 1984 | Nuclear Svc Cooling Water Tower & Valve House Design Dept |
ML20148R413 | 16 November 1978 | Lists Staff Review Categories 2,3 & 4 for Consideration in Preparation of FSAR & Lic Review.W/Encl Descriptions of Categories 2,3 & 4 |