MONTHYEARML24032A0252024-02-0505 February 2024 NRC Initial Test Program and Operational Programs Integrated Inspection Report 05200026-2023009 ML24010A0712024-01-31031 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports and Recordkeeping and Suspicious Activity Reporting) ML24031A6102024-01-31031 January 2024 Cyber Security Inspection Report 05200026/2024401 - Public ML24029A0592024-01-30030 January 2024 Request for Withholding Information from Public Disclosure Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report Enclosure 2, GAE-NRCD-RF-LR-000002 P-Attachment, Rev. 0 ML24016A1132024-01-30030 January 2024 Correction of Unit 1 Amendment Nos. 96 and 190 and Unit 2 Amendment Nos. 74 and 173 Adoption of Standard Technical Specifications Westinghouse Plants NL-24-0031, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R232024-01-29029 January 2024 Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 2R23 IR 05000424/20244032024-01-26026 January 2024 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000424/2024403; 05000425/2024403 NL-24-0020, Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report2024-01-22022 January 2024 Plan, Unit 1 Responses to NRC Request for Additional Information for Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23347A2092024-01-17017 January 2024 Voluntary Requests for Data, Information, And/Or Observation ML23279A0042024-01-17017 January 2024 Amendment No. 194 to Remove Combined License Appendix C NL-23-0926, Correction of Technical Specification Typographical Error2024-01-12012 January 2024 Correction of Technical Specification Typographical Error ML23341A2042024-01-12012 January 2024 Request for Additional Information Exemption Requests for Physical Barriers (EPID L-2023-LLE-0018 & L-2023-LLE-0021) ML23345A1312024-01-0303 January 2024 Withholding Letter - SNC Fleet - Physical Barriers Exemption (L-2023-LLE-0018 and L-2023-LLE-0021) ML23317A2072023-12-22022 December 2023 Issuance of Amendments 223 and 206 Regarding Revision to Technical Specifications to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the COLR Consistent with WCAP-1448 ML23335A1222023-12-19019 December 2023 Safety Evaluation Regarding Implementation of Mitigating Strategies Related to Order EA-12-049 (EPID L-2023-LRQ-0002) - Letter ML23353A1702023-12-19019 December 2023 LAR-22-002, TS 3.8.3 Inverters Operating Completion Time Extension Letter ML23310A2922023-12-0707 December 2023 Issuance of Amendment for Exception to Regulatory Guide 1.163, LAR 23 007 ML23339A1812023-12-0707 December 2023 Correction Letter Regarding License Amendment Request: More Restrictive Action for Technical Specification 3.1.9 ML23338A2182023-12-0606 December 2023 Project Manager Reassignment NL-23-0878, Request for Exemption from Security Event Notification Implementation2023-11-29029 November 2023 Request for Exemption from Security Event Notification Implementation ML23289A1632023-11-28028 November 2023 Letter and Amendment 195 and 192 LAR-23-006R1 TS 3.1.9 More Restrictive Action NL-23-0827, Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.142023-11-17017 November 2023 Response to Requests for Additional Information for a License Amendment Request and a Proposed Alternative Related to TS 3.4.14 ML23318A4582023-11-14014 November 2023 Integrated Inspection Report 05200025/2023003 ML23312A3502023-11-14014 November 2023 Integrated Inspection Report 05200026/2023003 ML23306A3552023-11-0808 November 2023 NRC Initial Test Program and Operational Programs Integrated Inspection Report 052000/262023008 ML23268A0572023-11-0707 November 2023 Issuance of Amendments 194 & 191 Request for License Amendment Relocation of Technical Specification 3.7.9, Spent Fuel Pool Makeup Water Sources (LAR-23-003) IR 05000424/20234022023-11-0606 November 2023 Security Baseline Inspection Report 05000424/2023402 and 05000425/2023402 IR 05000424/20230032023-10-27027 October 2023 Integrated Inspection Report 05000424/2023003 and 05000425/2023003 ML23291A1512023-10-18018 October 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 0520026/2024401 ML23263A9852023-10-12012 October 2023 Issuance of Amendments Nos. 221 and 204, Regarding Technical Specification 5.5.11.C, Acceptance Criteria for Charcoal Filter Testing ML23283A0472023-10-0808 October 2023 Neop Letter Dated October 8, 2023 - Vogtle 3 & 4 - TS 3.7.6 License Amendment Request NL-23-0750, Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr2023-10-0404 October 2023 Response to Second Request for Additional Information Regarding License Amendment Request: Technical Specification Revision to Adopt TSTF-339-A, Relocate Technical Specification Parameters to the Colr NL-23-0745, Refueling Outage 1R24 Steam Generator Tube Inspection Report2023-09-22022 September 2023 Refueling Outage 1R24 Steam Generator Tube Inspection Report ML23254A2032023-09-13013 September 2023 Initial Test Program and Operational Programs Inspection Report 05200025/2023013 ML23241B0212023-09-12012 September 2023 Review of Quality Assurance Topical Report ML23234A2352023-09-0808 September 2023 Request for Withholding Information from Public Disclosure Notification of Full Compliance of Required Action for NRC Order EA-12-049 Mitigation Strategies for Beyond-Design-Basis External Events IR 05000424/20230912023-09-0505 September 2023 Plan Units 1 and 2 - NRC Investigation Report 2-2022-006 and Notice of Violation - NRC Inspection Report 05000424/2023091 and 05000425/2023091 ML23234A3002023-09-0101 September 2023 NRC Integrated Inspection Report 05200026/2023003 ML23243A0092023-08-31031 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 3 & 4 (Report 05200025 2023005 & 05200026 2023005) NL-23-0695, Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2)2023-08-31031 August 2023 Response to Round 2 Request for Additional Information Regarding License Amendment Request for Technical Specification 3.8.3, Inverters Operating, Completion Time Extension (LAR-22-002S2) ML23243B0252023-08-30030 August 2023 Exam Corporate Notification Letter (210 Day) IR 05000424/20230052023-08-29029 August 2023 Updated Inspection Plan for Vogtle Electric Generating Plant, Units 1 & 2 - Report 05000424/2023005 and 05000425/2023005 NL-23-0666, License Amendment Request: Remove Combined License Appendix C (LAR 23-008)2023-08-28028 August 2023 License Amendment Request: Remove Combined License Appendix C (LAR 23-008) 2024-02-05
[Table view] |
Text
November 26, 2019 Mr. Brian H. Whitley, Director Regulatory Affairs Southern Nuclear Operating Company, Inc.
3535 Colonnade Parkway, Bin N-226-EC Birmingham, AL 35243
SUBJECT:
NOTICE OF NO OBJECTION FOR PRELIMINARY AMENDMENT REQUEST (PAR 19-014), TORNADO MISSILE PROTECTION FOR MAIN STEAM VENT STACKS AND WALL 11, FOR THE VOGTLE ELECTRIC GENERATING PLANT UNITS 3 AND 4
Dear Mr. Whitley:
By letter dated November 13, 2019, Southern Nuclear Operating Company (SNC) submitted Preliminary Amendment Request (PAR)19-014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML19317F386). SNC notified the U.S. Nuclear Regulatory Commission (NRC) that absent NRCs objection and pending the outcome of the NRCs detailed technical review of License Amendment Request (LAR)19-014 (ADAMS Accession No. ML19228A241), SNC will proceed with selected activities outlined in Block 7 of the enclosure to the PAR 19-014 consistent with requested changes in LAR 19-014.
As required by License Condition 2.D.(1), the NRC has received LAR 19-014, referenced in PAR 19-014. The staff has evaluated LAR 19-014 and has determined that there is sufficient information to accept the LAR for detailed technical review in a letter dated September 11, 2019 (ADAMS Accession No. ML19319A011).
The NRC staff has determined that PAR 19-014 contained sufficient information on the impact of the proposed plant change on associated Inspections, Tests, Analyses, and Acceptance Criteria. In addition, the NRC staff reviewed the scope of the PAR and found that it is consistent with the changes from the current licensing basis as requested in LAR 19-014. Therefore, the NRC has no objection to SNC proceeding with the construction of the proposed plant changes identified in Block 7 of the enclosure to PAR 19-014, pending the outcome of the NRCs detailed technical review of LAR 19-014. NRC staff expects that if LAR 19-014 is denied, SNC will return the plant to its current licensing basis as required by License Condition 2.D.(1)(b).
B. Whitley If you have any questions or comments concerning this matter, please contact the Project Manager, Billy Gleaves, at 301-415-5848 or via e-mail at Bill.Gleaves@nrc.gov.
Sincerely,
/RA/
Michael F. King, Director Vogtle Project Office Office of Nuclear Reactor Regulation Docket Nos.: 52-025 52-026 cc: See next page
ML19322C029 *via e-mail NRO-008 OFFICE NRR/VPO:PM NRR/VPO:LA NRR/VPO NRR/VPO:PM NAME WGleaves* RButler* TFredericks* CPatel*
DATE 11/19/19 11/19/19 11/18/19 11/19/19 OFFICE NRR/VPO:BC NRR/VPO:D NAME VHall* MKing*
DATE 11/19/19 11/26/19