ML17136A3613 May 2017Technical Specification Bases, Revision 149
ML15175A44724 June 2015Application to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process. Part 5 of 6
ML15175A44524 June 2015Application to Revise Technical Specifications to Adopt TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process. Part 4 of 6
ML15175A43924 June 2015Duke Energy Carolinas, LLC, Application to Revise Technical Specifications to Adopt TSTF-523, Rev. 2, Generic Letter 2008-01, Managing Gas Accumulation, Using the Consolidated Line Item Improvement Process. Part 1 of 6
IR 05000369/201300523 January 2014IR 05000369-13-005, 05000370-13-005, 05000369-13-502 & 05000370-13-502; on 10/01/2013 - 12/31/2013; McGuire Nuclear Station; Routine Integrated Inspection Report
IR 05000369/20110026 May 2011IR 05000369-11-002, 05000370-11-002, on 1/1/2011 - 3/31/2011, McGuire Nuclear Station, Licensed Operator Requalification Program, Follow-up of Events and Notices of Enforcement Discretion
ML0806704197 March 2008CDBI Findings
IR 05000369/20070099 October 2007IR 05000369-07-009 and 05000370-07-009, on 09/11/07-09/18/07; McGuire Nuclear Station, Units 1 and 2; Special Inspection
IR 05000369/199900413 July 1999Insp Repts 50-369/99-04 & 50-370/99-04 on 990509-0619.Four Violations of NRC Requirements Occurred & Being Treated as Ncvs.Major Areas Inspected:Aspects of Licensee Operations, Maint,Engineering & Plant Support
IR 05000369/199801018 December 1998Insp Repts 50-369/98-10 & 50-370/98-10 on 981004-1121.No Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support
ML20196F29023 November 1998Advises of Planned Insp Effort Resulting from Insp Planning Meeting Held on 981102.Details of Insp Plan for Next Four Months & Historical Listing of Plant Issues Called PIM Encl
IR 05000369/199800821 September 1998Insp Repts 50-369/98-08 & 50-370/98-08 on 980712-0822.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Maint,Engineering & Plant Support
ML20216H6176 April 1998Insp Repts 50-369/98-02 & 50-370/98-02 on 980125-0307. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support
IR 05000369/199702023 February 1998Insp Repts 50-369/97-20 & 50-370/97-20 on 971214-980124. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support,Including Review of Radiological Protection Practices & Plant Physical Security
ML20149G68816 June 1997Insp Repts 50-369/97-08 & 50-370/97-08 on 970406-0517. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering,Maint & Plant Support
IR 05000369/19970045 May 1997Insp Repts 50-369/97-04 & 50-370/97-04 on 970223-0405. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support
ML20135F1779 December 1996Forward Copy of Resolution of Comments on Preliminary Accident Sequence Precursor Analysis of Operational Event at McGuire Nuclear Station,Units 1 & 2
IR 05000369/199600815 November 1996Insp Repts 50-369/96-08 & 50-370/96-08 on 960908-1019. Violations Noted.Major Areas Inspected:Operations,Maint, Engineering & Plant Support
ML20128H6952 October 1996Insp Repts 50-369/96-07 & 50-370/96-07 on 960728-0907. Violations Noted.Major Areas Inspected:Licensee Operations, Engineering Maint & Plant Support
ML20117M59015 August 1996Loss of Electrical Power
ML20079B76115 December 1994Provides Supplemental Response to NOV Issued 940506 for Insp Repts 50-369/94-08 & 50-370/94-08.Corrective Actions:Rev to Design Basis Document to Address RCS Leakage Calculation Will Be Completed by 950501
ML20072J37717 August 1994Responds to NRC Request for Supplemental Info Re Nc Leakage Detection Systems.Info Encl
ML20072C0165 August 1994Responds to NRC Re Violations Noted in Insp Repts 50-369/94-12 & 50-370/94-12.Corrective Actions:Control Room Personnel Access Doors Immediately Opened & Fans Placed to Ventilate Vapors
ML20069G6811 June 1994Responds to NRC Re Violation Noted in Insp Repts 50-369/94-08 & 50-370/94-08.Corrective Actions: PIP 0-M93-1253 Initiated & Present & Past Operability Evaluations W/Regard to Compliance W/Ts 3.4.6.2 Initiated
ML20059C39025 October 1993Proposed Tech Specs for Reduction of Required Min Measured RCS Flow from 385,000 Gpm to 382,000 Gpm
ML20126F28224 December 1992Forwards Description of Valves Affected by Stroke Testing & Effect of Valves Being Opened or Closed During Testing,W/ Respect to Encl LER 369/90-022-1 Re RHR Sys Being Inoperable
ML20106D7409 October 1992RO 92-19:on 920804,discovered That Drive Shaft on Pump 1MNVPU0046 Was Rotating in Opposite Direction than Specified on Pump Casing.Caused by Mgt Deficiency.Motor Leads of Subj Pump Reconfigured to Provide Correct Pump Shaft Rotation
IR 05000369/19890189 August 1989Insp Repts 50-369/89-18 & 50-370/89-18 on 890629-0728.No Violations or Deviations Noted.Major Areas Inspected: Operations Safety Verification,Surveillance Testing,Maint Activities,Followup of LER & Followup on Previous Findings
ML20245F90814 June 1989Advises That Violation Re Design Control Has Been Categorized as Severity Level Iv,Per 890428 Enforcement Conference & Insp Rept, .Since NRC Wants to Encourage Licensee Initiative,Notice Will Not Be Issued
IR 05000369/198900515 May 1989Forwards Summary of Enforcement Conference on 890428 Re Insp Repts 50-369/89-05 & 50-370/89-05.Issues Discussed Re Instrument Air Sys Interface W/Diesel Generator Starting Air Sys.List of Attendees & Handout Also Encl
ML20247D24115 May 1989Forwards Summary of Enforcement Conference on 890428 Re Insp Repts 50-369/89-05 & 50-370/89-05.Issues Discussed Re Instrument Air Sys Interface W/Diesel Generator Starting Air Sys.List of Attendees & Handout Also Encl
IR 05000369/198900129 March 1989Insp Repts 50-369/89-01 & 50-370/89-01 on 890120-0227. Violations Noted.Major Areas Inspected:Operations Safety Verification,Surveillance Testing,Maint Activities & Review of Plant Procedures
ML20244A88329 March 1989Insp Repts 50-369/89-01 & 50-370/89-01 on 890120-0227. Violations Noted.Major Areas Inspected:Operations Safety Verification,Surveillance Testing,Maint Activities & Review of Plant Procedures
IR 05000369/198802923 September 1988Insp Repts 50-369/88-29 & 50-370/88-29 on 880829-0909. Violations Noted.Major Areas Inspected:Inoperability of Safety Sys Due to Inadequate post-mod Testing
ML20148D97614 January 1988Forwards Response to IE Bulletin 85-003, Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings. Summary of Schedule for Responding to Bulletin for McGuire & Catawba Stated
ML20206L8308 August 1986Responds to Apparent Violations Noted in Insp Repts 50-369/85-38 & 50-370/85-39 Re Nuclear Svc Water Sys Operability.Encl Corrective Actions Should Be Considered Prior to Any NRC Enforcement Actions
ML20202B9412 June 1986Insp Repts 50-369/85-38 & 50-370/85-39 on 851015-17 & 860127-31.Violations Noted:Failure to Adequately Perform Preoperational Test on Control Room Chiller & Implement & Maintain Procedures.Related Info Encl