Issue date | Title | |
---|---|---|
RA-23-0218, Review Request for the Aging Management Program and Inspection Plan for the Shearon Harris Nuclear Power Plant, Unit 1, Reactor Vessel Internals | 21 September 2023 | Review Request for the Aging Management Program and Inspection Plan for the Shearon Harris Nuclear Power Plant, Unit 1, Reactor Vessel Internals |
RA-21-0191, License Amendment Request to Revise Technical Specifications Related to Reactor Protection System Instrumentation | 6 August 2021 | License Amendment Request to Revise Technical Specifications Related to Reactor Protection System Instrumentation |
ML21033B007 | 22 March 2021 | Issuance of Amendment No, 183 to Correct Non-Conservative Technical Specification Related to Reactor Coolant System Pressure/Temperature Limits |
ML20147A022 | 15 May 2020 | Amendment 63 to Final Safety Analysis Report, Chapter 5, Reactor Coolant System and Connected Systems |
ML20147A032 | 15 May 2020 | Amendment 63 to Update Final Safety Analysis Report, Chapter 15, Accident Analysis |
ML20147A028 | 15 May 2020 | Amendment 63 to Final Safety Analysis Report, Chapter 11, Radioactive Waste Management |
RA-18-0072, License Amendment Request to Modify Reactor Trip System and Engineered Safety Features Actuation System Instrumentation Trip Setpoints | 30 July 2018 | License Amendment Request to Modify Reactor Trip System and Engineered Safety Features Actuation System Instrumentation Trip Setpoints |
HNP-17-033, License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3, Footnote 11 | 22 May 2017 | License Amendment Request Proposing a New Set of Fission Gas Gap Release Fractions for High Burnup Fuel Rods That Exceed the Linear Heat Generation Rate Limit Detailed in Regulatory Guide 1.183, Table 3, Footnote 11 |
ML18337A329 | 10 May 2017 | UFSAR Rev 61, Chapter 11, Radioactive Waste Management |
HNP-15-038, License Amendment Request for Main Steam Safety Valve Lift Setting Tolerance Change | 17 December 2015 | License Amendment Request for Main Steam Safety Valve Lift Setting Tolerance Change |
RA-15-0005, Duke Energy - Response to Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for All Power Reactor Licensees | 5 February 2015 | Duke Energy - Response to Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for All Power Reactor Licensees |
HNP-14-108, Response to Request for Additional Information Re License Amendment Request to Revise Technical Specification Table 3.3-4 Loss of Offsite Power 6.9 Kv Emergency Undervoltage Primary Setpoints | 23 October 2014 | Response to Request for Additional Information Re License Amendment Request to Revise Technical Specification Table 3.3-4 Loss of Offsite Power 6.9 Kv Emergency Undervoltage Primary Setpoints |
HNP-14-051, Relief Request I3R-14, Deferral of Reactor Vessel Inspections Inservice Inspection Program - Third Ten-Year Interval | 25 April 2014 | Relief Request I3R-14, Deferral of Reactor Vessel Inspections Inservice Inspection Program - Third Ten-Year Interval |
HNP-12-116, License Amendment Request to Revise Technical Specification Table 3.3-4 Re Degraded Voltage Time Delay Values | 29 November 2012 | License Amendment Request to Revise Technical Specification Table 3.3-4 Re Degraded Voltage Time Delay Values |
HNP-12-094, Cycle 18 Startup Test Report | 5 September 2012 | Cycle 18 Startup Test Report |
ML12157A281 | 11 June 2012 | Correction to Issuance of Amendment No. 139 Measurement Uncertainty Recapture Power Uprate |
HNP-12-069, Request for License Amendment Measurement Uncertainty Recapture Power Uprate Comments Re Amendment 139 | 5 June 2012 | Request for License Amendment Measurement Uncertainty Recapture Power Uprate Comments Re Amendment 139 |
ML12076A103 | 30 May 2012 | Issuance of Amendment Regarding the Revision to Technical Specification Core Operating Limits Report References for Realistic Large Break Loss-of-Coolant Accident Analysis |
HNP-12-044, Response to Request for Additional Information on License Amendment Request - Measurement Uncertainty Recapture Power Uprate | 26 March 2012 | Response to Request for Additional Information on License Amendment Request - Measurement Uncertainty Recapture Power Uprate |
ML12067A180 | 29 February 2012 | ANP-3011Q1(NP), Revision 000, Harris Nuclear Plant Unit 1 Realistic Large Break LOCA Analysis. Enclosure 4 Response to Request for Additional Information (Non-Proprietary) |
HNP-12-002, Request for License Amendment Measurement Uncertainty Recapture Power Uprate Supplemental Information | 9 February 2012 | Request for License Amendment Measurement Uncertainty Recapture Power Uprate Supplemental Information |
HNP-11-097, Request for License Amendment - Measurement Uncertainty Recapture Power Uprate Supplemental Information | 20 December 2011 | Request for License Amendment - Measurement Uncertainty Recapture Power Uprate Supplemental Information |
HNP-11-107, Supplement to Request for License Amendment Measurement Uncertainty Recapture Power Update | 28 November 2011 | Supplement to Request for License Amendment Measurement Uncertainty Recapture Power Update |
HNP-11-096, Request for License Amendment Measurement Uncertainty Recapture Power Uprate Response to Request for Additional Information (RAI 10) | 28 October 2011 | Request for License Amendment Measurement Uncertainty Recapture Power Uprate Response to Request for Additional Information (RAI # 10) |
HNP-11-095, Request for License Amendment Measurement Uncertainty Recapture Power Uprate Response to Request for Additional Information (RAI 9) | 21 October 2011 | Request for License Amendment Measurement Uncertainty Recapture Power Uprate Response to Request for Additional Information (RAI #9) |
HNP-11-094, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate (RAI 8) | 20 October 2011 | Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate (RAI #8) |
ML11276A107 | 18 October 2011 | Request for Additional Information Regarding Measurement Uncertainty Recapture |
ML11278A170 | 14 October 2011 | Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate |
ML11276A102 | 14 October 2011 | Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate |
ML11276A105 | 14 October 2011 | Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate |
ML112730082 | 30 September 2011 | Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate |
ML11272A065 | 28 September 2011 | NRR E-mail Capture - Additional Mur RAI (Emcb Part 2)(ME6169) |
HNP-11-082, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request | 7 September 2011 | Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request |
ML11256A026 | 6 September 2011 | Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request |
ML11238A078 | 31 August 2011 | ANP-3011(NP), Rev. 1, Harris Nuclear Plant Unit 1 Realistic Large Break LOCA Analysis. |
HNP-11-079, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment | 31 August 2011 | Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment |
HNP-11-077, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture License Amendment Request | 30 August 2011 | Response to Request for Additional Information Regarding Measurement Uncertainty Recapture License Amendment Request |
HNP-11-075, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture License Amendment Request | 25 August 2011 | Response to Request for Additional Information Regarding Measurement Uncertainty Recapture License Amendment Request |
HNP-11-067, License Amendment Request for Revision to Technical Specification Core Operating Limits Report References for Realistic Large Break LOCA Analysis | 22 August 2011 | License Amendment Request for Revision to Technical Specification Core Operating Limits Report References for Realistic Large Break LOCA Analysis |
HNP-11-076, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request | 15 August 2011 | Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request |
ML11214A079 | 5 August 2011 | Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate |
ML11214A174 | 5 August 2011 | Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate |
ML11213A179 | 5 August 2011 | Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate |
ML11217A004 | 4 August 2011 | NRR E-mail Capture - Measurement Uncertainty Recapture Power Uprate - Mur RAI (Eeb)( ME6169).docx |
HNP-11-073, Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request | 3 August 2011 | Response to Request for Additional Information Regarding Measurement Uncertainty Recapture Power Uprate License Amendment Request |
ML11213A000 | 29 July 2011 | NRR E-mail Capture - Measurement Uncertainty Recapture Power Uprate - Mur RAI (HP-HPB)(ME6169) |
ML11181A016 | 1 July 2011 | Acceptance for Review of Measurement Uncertainty Recapture Power Uprate License Amendment Request |
ML11206A496 | 29 June 2011 | NRR E-mail Capture - Draft RAI Questions to Support Harris Mur Review (ME6169) |
HNP-11-065, Supplement Information in Regard to Measurement Uncertainty Recapture Power Uprate License Amendment Request | 23 June 2011 | Supplement Information in Regard to Measurement Uncertainty Recapture Power Uprate License Amendment Request |
ML11165A186 | 10 June 2011 | NRR E-mail Capture - FW: Acceptance Review for Harris 1 Measurment Uncertainity Recapture (Mur) TAC ME6169 |