AECM-84-0107, Requests Addl Delay in Submittal of Inservice Insp Program Until 840801.Justification Provided | 16 March 1984 | Dale L MISSISSIPPI POWER & LIGHT CO. | Requests Addl Delay in Submittal of Inservice Insp Program Until 840801.Justification Provided | Other |
AECM-84-0257, Forwards Sample Plan for Selection of Pipe Supports to Be Subj to 10-yr Inservice Insp Plan,Per ASME Boiler & Pressure Vessel Code,Section Xi.Plan Does Not Encompass Snubbers. Review by 840601 Requested | 11 May 1984 | Dale L MISSISSIPPI POWER & LIGHT CO. | Forwards Sample Plan for Selection of Pipe Supports to Be Subj to 10-yr Inservice Insp Plan,Per ASME Boiler & Pressure Vessel Code,Section Xi.Plan Does Not Encompass Snubbers. Review by 840601 Requested | Other |
AECM-84-0335, Forwards Requests for Relief from ASME Section XI Code Requirements for Inservice Insp of 11 Items.Requests Submitted in Accordance W/Requirements of 10CFR50.55a(g)(5)(IV) | 29 June 1984 | Dale L MISSISSIPPI POWER & LIGHT CO. | Forwards Requests for Relief from ASME Section XI Code Requirements for Inservice Insp of 11 Items.Requests Submitted in Accordance W/Requirements of 10CFR50.55a(g)(5)(IV) | Other |
AECM-84-0371, Forwards 10-yr Inservice Insp Plan for Piping,Welds & Supports,Vols I-III | 25 July 1984 | Dale L MISSISSIPPI POWER & LIGHT CO. | Forwards 10-yr Inservice Insp Plan for Piping,Welds & Supports,Vols I-III | Other |
AECM-84-0470, Forwards Request for Relief from ASME Section XI Code Requirements for Inservice & Preservice Insp of Pressure Retaining Piping Weld.Expeditious Review Requested | 20 September 1984 | Dale L MISSISSIPPI POWER & LIGHT CO. | Forwards Request for Relief from ASME Section XI Code Requirements for Inservice & Preservice Insp of Pressure Retaining Piping Weld.Expeditious Review Requested | Request |
ML20134K491 | 22 August 1985 | Adensam E Office of Nuclear Reactor Regulation | Forwards Request for Addl Info Re Proposed Inservice Insp Program & Requests for Relief from Requirements in Section XI of ASME Code Submitted on 840920.Info Needed by 850930 | RAI |
AECM-85-0349, Forwards Response to 850822 Request for Addl Info Re 840725 10-yr Inservice Insp Program & 840920 Request for Exemption from Certain ASME Code Section XI Requirements.Program Approval Requested by 860302 | 31 October 1985 | Dale L MISSISSIPPI POWER & LIGHT CO. | Forwards Response to 850822 Request for Addl Info Re 840725 10-yr Inservice Insp Program & 840920 Request for Exemption from Certain ASME Code Section XI Requirements.Program Approval Requested by 860302 | Request |
ML20202J455 | 28 March 1986 | SCIENCE APPLICATIONS INTERNATIONAL CORP. (FORMERLY | First Interval Inservice Insp Program,Grand Gulf Nuclear Station, Technical Evaluation Rept | Other |
AECM-86-0186, Requests Response to Encl Rev to Justification for Relief Request I-00008 Re ASME Section XI Code Requirements for Inservice Insp of CRD & in-core Housing Welds & Flange Bolting,Per ,By 860801 | 14 July 1986 | Kingsley O MISSISSIPPI POWER & LIGHT CO. | Requests Response to Encl Rev to Justification for Relief Request I-00008 Re ASME Section XI Code Requirements for Inservice Insp of CRD & in-core Housing Welds & Flange Bolting,Per ,By 860801 | Request |
ML20203G425 | 22 July 1986 | Butler W Office of Nuclear Reactor Regulation | Forwards Safety Evaluation Re Inservice Insp Program & Requests for Relief from Certain Inservice Insp Requirements & SAIC-86/1626, First Interval Inservice Insp Program, Technical Evaluation Rept.Plan & Requests Acceptable | Approval |
ML20203G436 | 22 July 1986 | Office of Nuclear Reactor Regulation | Safety Evaluation Re Inservice Insp Program & Requests for Relief from Certain Inservice Insp Requirements.Inservice Insp Plan Acceptable for Implementation | Approval |
AECM-86-0224, Requests NRC Approval of Proposed Change to Inservice Insp Program to Allow Use of Figure Iwb 2500-7(b) from 1983 Edition,Summer 1983 Addenda of ASME Code,Section XI Re Exam Category B-D Weldments.Fee Paid | 23 July 1986 | Kingsley O MISSISSIPPI POWER & LIGHT CO. | Requests NRC Approval of Proposed Change to Inservice Insp Program to Allow Use of Figure Iwb 2500-7(b) from 1983 Edition,Summer 1983 Addenda of ASME Code,Section XI Re Exam Category B-D Weldments.Fee Paid | Request |
ML20203J811 | 30 July 1986 | Office of Nuclear Reactor Regulation Kintner L | Notifies That 860723 Request to Use Portion of 1983 ASME Boiler & Pressure Vessel Code,Section XI in Plant Inservice Insp Program Should Be Resubmitted,As Request for Relief from 1977 Edition of Code,By 860816 | Other |
AECM-86-0248, Forwards Relief Request I-00013 Seeking NRC Approval for Use of Summer 1983 Addenda of ASME Section Xi,Based on Interpretation of 10CFR50.55(a)(g)(4)(iv), Re Inservice Insp Requirements for Reactor Pressure Vessel Nozzles | 15 August 1986 | Kingsley O MISSISSIPPI POWER & LIGHT CO. | Forwards Relief Request I-00013 Seeking NRC Approval for Use of Summer 1983 Addenda of ASME Section Xi,Based on Interpretation of 10CFR50.55(a)(g)(4)(iv), Re Inservice Insp Requirements for Reactor Pressure Vessel Nozzles | Request |
AECM-86-0252, Forwards Fee for 860714 Application Revising Relief Request I-00008,per NRC 860804 Request | 20 August 1986 | Kingsley O MISSISSIPPI POWER & LIGHT CO. | Forwards Fee for 860714 Application Revising Relief Request I-00008,per NRC 860804 Request | Request |
ML20215E763 | 6 October 1986 | Butler W Office of Nuclear Reactor Regulation | Forwards Safety Evaluation Supporting Inservice Insp Relief Requests I-00008 & I-00013 Which Request Relief from ASME Code Section XI Requirements for Inservice Control Rod Drive Insp & Approval of 1983 ASME Code Re Inservice Insp Program | Approval |
ML20215E777 | 6 October 1986 | Office of Nuclear Reactor Regulation | Safety Evaluation Re Inservice Insp Program & Requests for Relief from Certain Inservice Insp Requirements | Approval |
AECM-87-0068, Documents Conversations Re Postulated Complete through-wall Circumferential Fracture of CRD Housing & Normal Makeup Capacity Available at or Near Cold Shutdown.Crd Pump Can Supply Normal Makeup Inventory Due to Failure.Fee Paid | 23 July 1987 | Kingsley O INC. SYSTEM ENERGY RESOURCES | Documents Conversations Re Postulated Complete through-wall Circumferential Fracture of CRD Housing & Normal Makeup Capacity Available at or Near Cold Shutdown.Crd Pump Can Supply Normal Makeup Inventory Due to Failure.Fee Paid | Other |