BVY 23-023, License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 | 10 October 2023 | License Amendment Request Addition of License Condition 3.K, License Termination Plan; Proposed Change No. 317 | Time of Discovery Offsite Dose Calculation Manual Coatings Met Tower Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report License Renewal Exemption Request Earthquake Chernobyl Environmental Justice Scaffolding Fatality Power Uprate |
3F1120-02, and Crystal River Nuclear Plant - Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization | 19 November 2020 | and Crystal River Nuclear Plant - Application for Order Approving Indirect Transfers of Control of Licenses in Connection with Internal Corporate Reorganization | |
BVY 17-004, Technical Specifications Proposed Change No. 313: Revision to License and Permanently Defueled Technical Specifications to Reflect Permanent Removal of Spent Fuel from the Spent Fuel Pool | 20 July 2017 | Technical Specifications Proposed Change No. 313: Revision to License and Permanently Defueled Technical Specifications to Reflect Permanent Removal of Spent Fuel from the Spent Fuel Pool | Safe Shutdown Time of Discovery High Radiation Area Offsite Dose Calculation Manual Probabilistic Risk Assessment Cyber Security Aging Management Annual Radiological Environmental Operating Report Process Control Program B.5.b Mitigating Strategies Fire Protection Program |
BVY 17-022, License Amendment Request - Cyber Security Plan License Condition Removal Proposed Change No. 316 | 13 July 2017 | License Amendment Request - Cyber Security Plan License Condition Removal Proposed Change No. 316 | Cyber Security Fuel cladding Recently irradiated fuel |
BVY 17-005, Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving Conforming License Amendment and Notification of Amendment to Decommissioning Trust Agreement | 9 February 2017 | Application for Order Consenting to Direct and Indirect Transfers of Control of Licenses and Approving Conforming License Amendment and Notification of Amendment to Decommissioning Trust Agreement | Offsite Dose Calculation Manual Cyber Security |
BVY 15-040, License Amendment Request - Revised Cyber Security Plan Implementation Schedule - Proposed Change No. 311 | 24 June 2015 | License Amendment Request - Revised Cyber Security Plan Implementation Schedule - Proposed Change No. 311 | Safe Shutdown Cyber Security Fire Protection Program |
BVY 14-083, Technical Specifications Proposed Change No. 307, Revision to Technical Specification Administrative Controls for Permanently Defueled Condition - Supplement 3 | 5 December 2014 | Technical Specifications Proposed Change No. 307, Revision to Technical Specification Administrative Controls for Permanently Defueled Condition - Supplement 3 | High Radiation Area Offsite Dose Calculation Manual Annual Radiological Environmental Operating Report Process Control Program Fire Protection Program |
BVY 14-062, Proposed Change No. 310 - Deletion of Renewed Facility Operating License Conditions Related to Decommissioning Trust Provisions | 4 September 2014 | Proposed Change No. 310 - Deletion of Renewed Facility Operating License Conditions Related to Decommissioning Trust Provisions | Safety Limit Minimum Critical Power Ratio |
BVY 13-109, Cyber Security Plan Implementation Schedule, Proposed Change No. 308 | 19 December 2013 | Cyber Security Plan Implementation Schedule, Proposed Change No. 308 | Safe Shutdown Cyber Security Fire Protection Program |
BVY 13-097, Proposed Change 306, Areva Document No. 32-9145461-001, Vynpp - Re-analysis of Ast/Fha Radiological Consequences with Open Containment | 14 November 2013 | Proposed Change 306, Areva Document No. 32-9145461-001, Vynpp - Re-analysis of Ast/Fha Radiological Consequences with Open Containment | |
ML13323A518 | 14 November 2013 | Technical Specifications Proposed Change No. 306 Eliminate Certain ESF Requirements During Movement of Irradiated Fuel | Safe Shutdown Reactor Vessel Water Level Non-Destructive Examination Stroke time Control of Heavy Loads Fuel cladding Recently irradiated fuel |
BVY 12-084, License Amendment Request; Changes to 10CFR50.63 Licensing Basis | 21 December 2012 | License Amendment Request; Changes to 10CFR50.63 Licensing Basis | Safe Shutdown License Renewal Maintenance Rule Program Power Uprate |
BVY 12-085, Technical Specifications Proposed Change No. 302 Inoperable Control Rods | 17 December 2012 | Technical Specifications Proposed Change No. 302 Inoperable Control Rods | Anticipated operational occurrence Channel-control blade interference |
BVY 12-018, Technical Specifications Proposed Change No. 299 Recirculation System Discharge Bypass Valve Change | 17 April 2012 | Technical Specifications Proposed Change No. 299 Recirculation System Discharge Bypass Valve Change | Reactor Vessel Water Level |
BVY 12-016, License Amendment Request to Revise License Renewal Commitments | 12 March 2012 | License Amendment Request to Revise License Renewal Commitments | Aging Management |
BVY 12-006, Technical Specifications Proposed Change No. 298, Rod Worth Minimizer Bypass Allowance | 1 February 2012 | Technical Specifications Proposed Change No. 298, Rod Worth Minimizer Bypass Allowance | |
BVY 12-005, Technical Specifications Proposed Change No. 297, Suppression Chamber-Drywell Leak Rate Test Surveillance Frequency Change | 1 February 2012 | Technical Specifications Proposed Change No. 297, Suppression Chamber-Drywell Leak Rate Test Surveillance Frequency Change | |
BVY 11-085, Proposed Change No. 296, Steam Dryer License Condition Change | 22 December 2011 | Proposed Change No. 296, Steam Dryer License Condition Change | |
BVY 11-069, Technical Specifications Proposed Change No. 295 Proposed Emergency License Amendment for Single Loop Operation | 29 September 2011 | Technical Specifications Proposed Change No. 295 Proposed Emergency License Amendment for Single Loop Operation | |
BVY 10-059, Technical Specifications Proposed Change No. 294, Elimination of Provisions Allowing HPCI and RCIC Suctions to Be Aligned to the Suppression Pool | 8 November 2010 | Technical Specifications Proposed Change No. 294, Elimination of Provisions Allowing HPCI and RCIC Suctions to Be Aligned to the Suppression Pool | Reactor Vessel Water Level |
BVY 10-045, Technical Specifications Proposed Change No. 289 Suppression Chamber-Drywell Vacuum Breakers and Differential Pressure | 19 August 2010 | Technical Specifications Proposed Change No. 289 Suppression Chamber-Drywell Vacuum Breakers and Differential Pressure | Stroke time |
BVY 10-036, Technical Specifications Proposed Change No. 292, License Amendment Withdrawal and Request - Cyber Security Plan | 16 July 2010 | Technical Specifications Proposed Change No. 292, License Amendment Withdrawal and Request - Cyber Security Plan | Safe Shutdown Cyber Security Incorporated by reference Fire Protection Program |
BVY 09-068, Technical Specifications Proposed Change No. 288 Scram Discharge Volume Vent and Drain Valves | 3 December 2009 | Technical Specifications Proposed Change No. 288 Scram Discharge Volume Vent and Drain Valves | Abnormal operational transient Scram Discharge Volume Fuel cladding |
BVY 09-063, Technical Specification Proposed Change No. 287 Safety Limit Minimum Critical Power Ratio Change | 27 October 2009 | Technical Specification Proposed Change No. 287 Safety Limit Minimum Critical Power Ratio Change | Safety Limit Minimum Critical Power Ratio Abnormal operational transient Fuel cladding |
BVY 09-052, Technical Specifications Proposed Change No. 284 Change to Requirements for Inoperable Containment Isolation Valves | 16 September 2009 | Technical Specifications Proposed Change No. 284 Change to Requirements for Inoperable Containment Isolation Valves | |
BVY 09-051, Technical Specifications Proposed Change No. 285 Revision of High Radiation Area Controls | 26 August 2009 | Technical Specifications Proposed Change No. 285 Revision of High Radiation Area Controls | High Radiation Area Locked High Radiation Area Process Control Program Fire Protection Program |
ML091200162 | 31 May 2009 | Safety Evaluation Report Related to the License Renewal of Vermont Yankee Nuclear Power Station Supplement 1 | Finite Element Analysis Aging Management |
BVY 09-029, Technical Specifications Proposed Change No. 283 Change to Requirements for Performing 10 CFR 50, Appendix J, Type a Test | 5 May 2009 | Technical Specifications Proposed Change No. 283 Change to Requirements for Performing 10 CFR 50, Appendix J, Type a Test | Probabilistic Risk Assessment |
BVY 09-012, Submittal of Proposed License Amendment for Technical Specifications No. 282, Revision of Drywell Vacuum Breaker Surveillance Requirements | 24 February 2009 | Submittal of Proposed License Amendment for Technical Specifications No. 282, Revision of Drywell Vacuum Breaker Surveillance Requirements | |
BVY 08-079, Technical Specifications Proposed Change No. 280, Supplement 1 Relocation of Reactor Building Crane Technical Specifications | 31 October 2008 | Technical Specifications Proposed Change No. 280, Supplement 1 Relocation of Reactor Building Crane Technical Specifications | Non-Destructive Examination Control of Heavy Loads |
BVY 08-055, Technical Specifications Proposed Change No. 277, License Amendment Request Application for Licensee Name Changes | 30 September 2008 | Technical Specifications Proposed Change No. 277, License Amendment Request Application for Licensee Name Changes | Safe Shutdown Safety Limit Minimum Critical Power Ratio Offsite Dose Calculation Manual Fire Protection Program |
BVY 08-059, Technical Specifications Proposed Change No. 280 Relocation of Reactor Building Crane Technical Specifications | 22 September 2008 | Technical Specifications Proposed Change No. 280 Relocation of Reactor Building Crane Technical Specifications | Probabilistic Risk Assessment Spiral reload |
BVY 08-052, Technical Specifications Proposed Change No. 278, Changes to Main Steam Isolation Valve Surveillance Requirements | 22 September 2008 | Technical Specifications Proposed Change No. 278, Changes to Main Steam Isolation Valve Surveillance Requirements | |
BVY 08-053, Technical Specifications Proposed Change No. 279 Sale or Lease of Property within the Exclusion Boundary | 4 September 2008 | Technical Specifications Proposed Change No. 279 Sale or Lease of Property within the Exclusion Boundary | |
BVY 08-001, Technical Specifications Proposed Change No. 273 Instrumentation Technical Specifications | 12 February 2008 | Technical Specifications Proposed Change No. 273 Instrumentation Technical Specifications | Shutdown Margin Reactor Vessel Water Level Post Accident Monitoring Probabilistic Risk Assessment Abnormal operational transient Scram Discharge Volume MELLLA Fuel cladding Power change |
ML080660203 | 12 February 2008 | Vermont Yankee, Technical Specifications Proposed Change No. 273, Instrumentation Technical Specifications | Shutdown Margin Reactor Vessel Water Level Post Accident Monitoring Probabilistic Risk Assessment Abnormal operational transient Scram Discharge Volume MELLLA Fuel cladding Power change |
BVY 08-007, Technical Specification Proposed Change No. 276 Revision to TS Sections 3.3/4.3 for Control Rod System | 6 February 2008 | Technical Specification Proposed Change No. 276 Revision to TS Sections 3.3/4.3 for Control Rod System | Shutdown Margin Anticipated operational occurrence Hydrostatic Abnormal operational transient Scram Discharge Volume Overtravel |
ML080420220 | 5 February 2008 | Vermont Yankee - License Renewal Application, Amendment 35 | Nondestructive Examination Aging Management EVT-1 |
ML073650228 | 11 December 2007 | (PA-LR) VY Response to RAI 4.3.3-2 | Aging Management |
BVY 07-056, Technical Specification Proposed Change No. 274, Changes to Technical Specifications for Emergency Diesel Generator Fuel Oil and Reactor Building Crane Surveillance Requirements | 18 October 2007 | Technical Specification Proposed Change No. 274, Changes to Technical Specifications for Emergency Diesel Generator Fuel Oil and Reactor Building Crane Surveillance Requirements | Spiral reload |
BVY 07-063, Technical Specifications Proposed Change No. 275 Primary Containment Oxygen Concentration and Drywell-to-Suppression Chamber Differential Pressure Limits | 18 October 2007 | Technical Specifications Proposed Change No. 275 Primary Containment Oxygen Concentration and Drywell-to-Suppression Chamber Differential Pressure Limits | Hydrostatic |
BVY 07-018, License Renewal Application, Amendment 26 | 23 March 2007 | License Renewal Application, Amendment 26 | Nondestructive Examination Aging Management Moisture barrier EVT-1 |
ML070240204 | 10 January 2007 | Email: (PA-LR) Other Word File | Safe Shutdown Non-Destructive Examination Aging Management EVT-1 Fire Protection Program |
ML070110504 | 4 January 2007 | Vermont Yankee - License Renewal Application, Amendment 23 | Fire Barrier Hydrostatic Nondestructive Examination Aging Management Moisture barrier EVT-1 Fire Protection Program Dissimilar Metal Weld |
ML063420178 | 4 December 2006 | 2006/12/04-Vermont Yankee Nuclear Power Station, License Renewal Application, Amendment 22, Clarification of Aging Management Program and Environmental Report Items | Aging Management |
ML063400453 | 9 November 2006 | 2006/11/09-E-Mail: (NPA-PD-LR) VYNPS License Renewal Application Am. 20, Vermont Yankee | Finite Element Analysis |
BVY 06-097, 2006/10/31-Vermont Yankee License Renewal Application, Amendment 19 | 31 October 2006 | 2006/10/31-Vermont Yankee License Renewal Application, Amendment 19 | Safe Shutdown Non-Destructive Examination Aging Management EVT-1 Fire Protection Program |
ML062780122 | 12 October 2006 | Summary of a Telephone Conference Call Held on September 19, 2006, Between the U.S. Nuclear Regulatory Commission and Entergy Nuclear Operations, Inc | Aging Management |
ML062680034 | 19 September 2006 | 2006/09/19-Vermont Yankee License Renewal Application, Amendment 13 | Mission time Internal Flooding Maintenance Rule Program |
ML062550439 | 5 September 2006 | License Renewal Application, Amendment 12 | Safe Shutdown Hydrostatic Aging Management Maintenance Rule Program |