L-2023-180, Submittal of Changes to the Technical Specification Bases | 13 December 2023 | Submittal of Changes to the Technical Specification Bases | Surveillance Frequency Control Program |
SBK-L-21135, Submittal of Changes to the Seabrook Station Technical Specification Bases | 29 December 2021 | Submittal of Changes to the Seabrook Station Technical Specification Bases | Surveillance Frequency Control Program |
SBK-L-21098, Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements | 22 September 2021 | Supplement to License Amendment Request 21-01, Revise 120-Volt AC Vital Instrument Panel Requirements | Safe Shutdown Internal Flooding Probabilistic Risk Assessment FLEX Surveillance Frequency Control Program Large early release frequency Flooding Focused Evaluation Earthquake |
SBK-L-20154, Submittal of Changes to the Seabrook Station Technical Specification Bases | 22 December 2020 | Submittal of Changes to the Seabrook Station Technical Specification Bases | Shutdown Margin Surveillance Frequency Control Program |
SBK-L-19129, Submittal of Changes to the Seabrook Station Technical Specification Bases | 31 December 2019 | Submittal of Changes to the Seabrook Station Technical Specification Bases | Safe Shutdown Ultimate heat sink Stroke time Surveillance Frequency Control Program Pressure Boundary Leakage Offsite Circuit |
SBK-L-18195, Submittal of Changes to the Seabrook Station Technical Specification Bases | 18 December 2018 | Submittal of Changes to the Seabrook Station Technical Specification Bases | Safe Shutdown Ultimate heat sink Anticipated operational occurrence |
SBK-L-17208, Submittal of Changes to the Seabrook Station Technical Specification Bases | 14 December 2017 | Submittal of Changes to the Seabrook Station Technical Specification Bases | Time to boil Hydrostatic Incorporated by reference Surveillance Frequency Control Program |
L-2017-041, Application to Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month,' Using the Consolidated Line Item Improvement Process | 30 March 2017 | Application to Revise Technical Specifications to Adopt TSTF-522, Revise Ventilation System Surveillance Requirements to Operate for 10 Hours Per Month,' Using the Consolidated Line Item Improvement Process | Surveillance Frequency Control Program Recently irradiated fuel |
SBK-L-16206, Submittal of Changes to Technical Specification Bases Dated 12/21/2016 | 21 December 2016 | Submittal of Changes to Technical Specification Bases Dated 12/21/2016 | Shutdown Margin Surveillance Frequency Control Program |
SBK-L-15228, Submittal of Changes to the Technical Specification Bases | 5 January 2016 | Submittal of Changes to the Technical Specification Bases | Shutdown Margin Ultimate heat sink Stroke time Time to boil Surveillance Frequency Control Program |
SBK-L-14231, Submittal of Changes to Technical Specification Bases | 18 December 2014 | Submittal of Changes to Technical Specification Bases | Safe Shutdown Shutdown Margin Ultimate heat sink Stroke time Surveillance Frequency Control Program Pressure Boundary Leakage Offsite Circuit Power change |
SBK-L-13224, Request for Review and Approval of License Amendment Request (LAR) 11-04, Changes to Technical Specifications for New and Spent Fuel Storage, in Two Parts | 20 December 2013 | Request for Review and Approval of License Amendment Request (LAR) 11-04, Changes to Technical Specifications for New and Spent Fuel Storage, in Two Parts | |
SBK-L-12265, Submittal of Changes to the Technical Specification Bases | 19 December 2012 | Submittal of Changes to the Technical Specification Bases | Grab sample Stroke time Nondestructive Examination Pressure Boundary Leakage |
SBK-L-12052, Submittal of Changes to Technical Specification Bases | 16 February 2012 | Submittal of Changes to Technical Specification Bases | Reactor Vessel Water Level Ultimate heat sink |
SBK-L-11066, License Amendment Request 11-01, Application to Revise the Technical Specifications for Reactor Coolant System Leakage Detection Instrumentation | 21 April 2011 | License Amendment Request 11-01, Application to Revise the Technical Specifications for Reactor Coolant System Leakage Detection Instrumentation | Safe Shutdown Grab sample Cyber Security Fuel cladding Pressure Boundary Leakage |
SBK-L-10236, Submittal of Changes to the Technical Specification Bases | 30 December 2010 | Submittal of Changes to the Technical Specification Bases | Safe Shutdown Anticipated operational occurrence Offsite Circuit |
SBK-L-09269, Submittal of Changes to Technical Specification Bases | 30 December 2009 | Submittal of Changes to Technical Specification Bases | Safe Shutdown Reactor Vessel Water Level High Radiation Area Stroke time Power-Operated Valves Offsite Circuit |
SBK-L-08216, Submittal of Changes to Technical Specification Bases | 16 December 2008 | Submittal of Changes to Technical Specification Bases | Stroke time Anticipated operational occurrence Time to boil Tornado Generated Missile Power-Operated Valves Fuel cladding Pressure Boundary Leakage |
SBK-L-06244, Submittal of Changes to Seabrook Station Technical Specification Bases | 3 January 2007 | Submittal of Changes to Seabrook Station Technical Specification Bases | Pressure Boundary Leakage |
SBK-L-06214, Clarification of Response to RAI Regarding LAR 06-02, Application for Technical Specification Improvement Regarding Steam Generator Integrity Using Consolidated Line Item Improvement Process. | 28 November 2006 | Clarification of Response to RAI Regarding LAR 06-02, Application for Technical Specification Improvement Regarding Steam Generator Integrity Using Consolidated Line Item Improvement Process. | Nondestructive Examination Pressure Boundary Leakage |
SBK-L-06171, Response to Request for Additional Information Regarding License Amendment Request 05-11, Changes to Technical Specification 3.8.3.1 Onsite Power Distribution, for Vital Inverter Allowed Outage Time. | 1 October 2006 | Response to Request for Additional Information Regarding License Amendment Request 05-11, Changes to Technical Specification 3.8.3.1 Onsite Power Distribution, for Vital Inverter Allowed Outage Time. | Enforcement Discretion Probabilistic Risk Assessment Large early release frequency Power change |
SBK-L-04050, Submittal of Changes to the Plant Technical Specification Bases | 2 September 2004 | Submittal of Changes to the Plant Technical Specification Bases | Shutdown Margin Reactor Vessel Water Level High Radiation Area Ultimate heat sink Stroke time Anticipated operational occurrence Tornado Generated Missile Power change Unidentified leakage Unidentified leak |
ML040710678 | 3 March 2004 | Submittal of Changes to the Technical Specification Bases | Safe Shutdown Time to boil |
ML040440432 | 4 February 2004 | License Amendment Request 03-03, Miscellaneous Changes to the Technical Specifications. | Shutdown Margin High Radiation Area Offsite Dose Calculation Manual Annual Radioactive Effluent Release Report Annual Radiological Environmental Operating Report Process Control Program Fire Protection Program |