Byron, Units 1 and 2, Peach Bottom, Units 1, 2, and 3, Three Mile Island, Units 1 and 2 - Transmittal of Radiological Emergency Plan Annex and Addendum Revisions
ML17271A177
Person / Time
Site: Peach Bottom, Byron, Three Mile Island  Constellation icon.png
Issue date: 09/21/2017
From: David Helker
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation
References
RS-17-128, TMl-17-098
Download: ML17271A177 (3)


Text

Exelon Generation 200 Exelon Way Kennett Square, PA 19348 www.exeloncorp.com RS-17-128 TMl-17-098 10 CFR 50.54(q)(5) 10 CFR 50.4 10 CFR 72.44(f) September21, 2017 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

Subject:

Byron Station, Units 1 and 2 Renewed Facility Operating License Nos. NPF-37 and NPF-66 NRC Docket Nos. 50-454. 50-455. and 72-68 Peach Bottom Atomic Power Station, Units 1, 2, and 3 Facility Operating

[Possession Only] License No. DPR-12 Renewed Facility Operating License Nos. DPR-44 and DPR-56 NRC Docket Nos. 50-171, 50-277. 50-278, and 72-79 Three Mile Island Nuclear Station, Unit 1 Renewed Facility Operating License No. DPR-50 NRC Docket No. 50-289 Three Mile Island Nuclear Station, Unit 2 Facility Possession-Only License No. DPR-73 NRC Docket No. 50-320 Exelon Nuclear Radiological Emergency Plan Annex and Addendum Revisions In accordance with 10 CFR 50.4(b)(5), "Emergency plan and related submissions," Exelon Generation Company, LLC (Exelon) is submitting revisions to Emergency Plan Annex and Addendums as listed in the table below for Byron Station (Byron), Peach Bottom Atomic Power Station (PBAPS), and Three Mile Island Nuclear Station (TMI). I Document II Revision I Title EP-AA-1002, Addendum 3 2 Emergency Action Levels for Byron Station EP-AA-1007, Addendum 3 5 Emergency Action Levels for Peach Bottom Atomic Power Station EP-AA-1009 26 Exelon Nuclear Radiological Emergency Plan Annex for Three Mile Island (TM!) Station U.S. Nuclear Regulatory Commission Emergency Plan Annex and Addendum Revisions Docket Nos. 50-454, 50-455, 72-68, 50-171, 50-277, 50-278, 72-79, 50-289, and 50-320 September 21, 2017 Page2 The changes to the Emergency Plan Annex and Addendums listed above were evaluated under the requirements of 1 O CFR 50.54(q) and were determined not to result in a reduction in the effectiveness of the Emergency Plans for Byron, PBAPS, and TMI. This notification is being submitted within 30 days of implementation of the changes as required by 1 O CFR 50.54(q)(5).

The changes continue to meet the applicable planning standards established in 1 O CFR 50.47(b) and 10 CFR 50, Appendix E. In addition, as required by 1OCFR50.54(q)(5), this submittal includes a summary analysis of the changes to the Emergency Plan Annex and Addendums listed (Attachment 1 ). This submittal also satisfies the reporting requirements associated with 10 CFR 72.44(f), which stipulates that within six months after any change is made to the Emergency Plan, the licensee shall submit a report containing a description of the changes to the U.S. Nuclear Regulatory Commission (NRC) Director, Division of Spent Fuel Management.

A copy of the revised Emergency Plan Annex and Addendums and supporting change summary analysis are included in the attachments to this letter. There are no regulatory commitments in this submittal.

If you have any questions or require additional information, please contact Richard Gropp at (610) 765-5557.

Respectfully, Pf.

David P. Helker Manager, Licensing and Regulatory Affairs Exelon Generation Company, LLC Attachments:

1. 1 O CFR 50.54(q)(5)

Procedure Change Summary Analysis 2. EP-AA-1002, Addendum 3, Revision 2, "Emergency Action Levels for Byron Station" 3. EP-AA-1007, Addendum 3, Revision 5, "Emergency Action Levels for Peach Bottom Atomic Power Station" 4. EP-AA-1009, Revision 26, "Exelon Nuclear Radiological Emergency Plan Annex for Three Mile Island (TM/) Station" cc: w/ Attachment 1 only Regional Administrator

-NRC Region Ill Regional Administrator

-NRC Region I Director, NRC Division of Spent Fuel Management, ONMSS NRC Senior Resident Inspector

-Byron Station NRC Project Manager, NRR -Byron Station NRC Senior Resident Inspector

-Peach Bottom Atomic Power Station NRC Project Manager, NRR -Peach Bottom Atomic Power Station NRC Senior Resident Inspector

-Three Mile Island Nuclear Station U.S. Nuclear Regulatory Commission Emergency Plan Annex and Addendum Revisions Docket Nos. 50-454, 50-455, 72-68, 50-171, 50-277, 50-278, 72-79, 50-289, and 50-320 September 21, 2017 Page 3 cc: (continued)

NRG Project Manager, NRR -Three Mile Island Nuclear Station Illinois Emergency Management Agency -Division of Nuclear Safety Director, Bureau of Radiation Protection

-Pennsylvania Department of Environmental Resources R. R. Janati, Commonwealth of Pennsylvania Chairman, Board of County Commissioners of Dauphin County, PA Chairman, Board of Supervisors of Londonderry Township, PA