MONTHYEARRS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report RS-24-019, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF2024-03-19019 March 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF RS-24-020, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS2024-03-15015 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS RS-24-015, Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval2024-02-29029 February 2024 Submittal of RP-01 Relief Request Associated with the Sixth Inservice Testing Interval RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request – Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request – Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-08-28028 August 2023 Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling RS-22-067, 10 CFR 50.46 Annual Report2023-05-0404 May 2023 10 CFR 50.46 Annual Report RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell2023-04-28028 April 2023 Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell RS-23-058, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges2023-04-24024 April 2023 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-11 Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell Flanges RS-23-049, Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations2023-03-23023 March 2023 Constellation Energy Generation, LLC, Report on Status of Decommissioning Funding for Reactors and Independent Spent Fuel Storage Installations RS-23-007, Application to Adopt TSTF-564, Safety Limit MCPR2023-03-0303 March 2023 Application to Adopt TSTF-564, Safety Limit MCPR RS-23-045, Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.2032023-02-28028 February 2023 Constellation Energy Generation, LLC Submittal of Fitness for Duty Performance Data Reports for 2022 Per 10 CFR 26.717(c) & 10 CFR 26.203 RS-23-032, Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location2023-02-0303 February 2023 Application to Move SR 3.5.1.2 Note to LCO 3.5.1 in Accordance with TSTF-416, LPCI Valve Alignment Verification Note Location RS-23-034, Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program2023-02-0202 February 2023 Notification of Extension to the Fifth Ten-Year Interval of the Inservice Testing Program RS-23-003, Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-102023-01-31031 January 2023 Constellation Energy Generation, LLC, Summary of Changes to Quality Assurance Topical Report, NO-AA-10, and Decommissioning Quality Assurance Program, NO-DC-10 RS-23-033, Request for Exemption from 10 CFR 2.109(b)2023-01-27027 January 2023 Request for Exemption from 10 CFR 2.109(b) RS-23-005, Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves2023-01-17017 January 2023 Response to Request for Additional Information for Quad Cities Relief Request RV-04, Inservice Testing of High Pressure Coolant Injection Drain Pot Solenoid Valves RS-22-127, Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair2022-12-14014 December 2022 Submittal of Sixth Inservice Inspection Interval Relief Request I6R-10 Reactor Pressure Vessel Penetration N-11B Repair RS-22-126, Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI2022-11-30030 November 2022 Constellation Energy Generation, LLC - Request to Use Provisions of a Later Edition of the ASME Boiler and Pressure Vessel Code, Section XI RS-22-119, Withdrawal of Relief Request RV-11 Associated with the Sixth Inservice Testing Interval2022-10-31031 October 2022 Withdrawal of Relief Request RV-11 Associated with the Sixth Inservice Testing Interval RS-22-109, Response to Request for Additional Information License Amendments Related to Fuel Storage2022-10-12012 October 2022 Response to Request for Additional Information License Amendments Related to Fuel Storage RS-22-112, Submittal of RV-04 Relief Request Associated with the Sixth Inservice Testing Interval2022-10-0707 October 2022 Submittal of RV-04 Relief Request Associated with the Sixth Inservice Testing Interval RS-22-108, Response to Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage2022-10-0505 October 2022 Response to Request for Additional Information LaSalle County Station, Units 1 and 2 and Quad Cities Nuclear Power Station, Units 1 and 2 License Amendments Related to Fuel Storage RS-22-092, Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration2022-10-0303 October 2022 Nine and Quad Cities - Application to Revise Primary Containment Isolation Instrumentation Technical Specifications in Accordance with TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration RS-22-102, Supplement to Request to Revise Technical Specification 3.1.4, Control Rod Scam Times2022-08-18018 August 2022 Supplement to Request to Revise Technical Specification 3.1.4, Control Rod Scam Times RS-22-093, Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans2022-08-18018 August 2022 Advisement of Leadership Changes for Constellation Energy Generation, LLC and Submittal of Updated Standard Practice Procedures Plans RS-22-095, Response to Request for Additional Information Regarding Request to Expand Applicability of GNF Thermal Mechanical Analysis Methods to Framatome Fuel2022-08-10010 August 2022 Response to Request for Additional Information Regarding Request to Expand Applicability of GNF Thermal Mechanical Analysis Methods to Framatome Fuel RS-22-096, Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval2022-08-10010 August 2022 Response to Request for Additional Information Related to Relief Request I6R-01 Associated with the Sixth Inservice Inspection Interval RS-22-098, Response to Request for Additional Information for Quad Cities Relief Request RV-11, Code Case OMN-282022-08-0101 August 2022 Response to Request for Additional Information for Quad Cities Relief Request RV-11, Code Case OMN-28 2024-08-20
[Table view] |
Text
Exelon Generation W~W.~Xelo~COT~.Co~
4300 Winfieid Road Warrenville, IL 60555 10 CFR 50.46 RS-05-056 May 5,2005 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265
Subject:
Transmittal of I 0 CFR 50.46, "Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors," Annual Report for Quad Cities Nuclear Power Station, Units 1 and 2
Reference:
Letter from Patrick R. Simpson (Exelon Generation Company, LLC) to U. S. NRC, "Transmittal of 10 CFR 50.46, 'Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors,'
Annual Report for Quad Cities Nuclear Power Station, Units 1 and 2,"
RS-04-066, dated May 5, 2004 The purpose of this letter is to provide the annual report required by 10 CFR 50.46, "Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors," for Quad Cities Nuclear Power Station, Units 1 and 2. The attachments describe the changes in accumulated Peak Cladding Temperature (PCT) since the previous annual submittal (Reference).
Should you have any questions concerning this letter, please contact Mr. Dave Gullott at (630) 657-2819.
Respectfully, Manager - Licensing Attachments: Attachment A: Quad Cities Nuclear Power Station Unit 1, 10 CFR 50.46 Report Attachment B: Quad Cities Nuclear Power Station Unit 2, 10 CFR 50.46 Report Attachment C: Quad Cities Nuclear Power Station Units 1 and 2, 10 CFR 50.46 Report Assessment Notes cc: Regional Administrator - NRC Region Ill NRC S Cit ea Illinois - of
Attachment A Quad Cities Nuclear Power Station Unit 1 I 0 CFR 50.46 Report PLANT NAME: Quad Cities Unit 1 ECCS EVALUATION MODEL: SAFEWGESTR-LOCA REPORT REVISION DATE: 05/05/05 CURRENT OPERATING CYCLE: 19 ANALYSIS OF RECORD Evaluation Model:
The GESTR-LOCA and SAFER Models for the Evaluation of the Loss-of-Coolant Accident, Volume Ill, SAFEWGESTR Application Methodology, NEDE-23785-1-PA, General Electric Company, Revision 1, October 1984.
Calculations:
"SAFEWGESTR-LOCA Loss-of-Coolant Accident Analysis for Dresden Nuclear Station 2 and 3 and Quad Cities Nuclear Station Units 1 and 2," NEDC-32990P, Revision 2, GE Nuclear Energy, September 2003.
Fuel Analyzed in Calculation: GE9/10, ATRIUM-9B and GE14 Limiting Fuel Type: GE14 Limiting Single Failure: Diesel Generator Limiting Break Size and Location: 1.O Double-Ended Guillotine in a Recirculation Suction Pipe Reference Peak Cladding Temperature (PCT) PCT = 21 10°F MARGlN ALLOCATION A. PRIOR LOCA MODEL ASSESSMENTS B. CURRENT LOCA MODEL ASSESSMENTS GE LOCA Model Change due to New Heat Source (See Note 6) APCT = 0°F GE14 Fuel Reload (See Note 7) APCT = 0°F Total PCT change from current assessments CAPCT = 0°F Cumulative PCT change from current assessments C IAPCT = 0°F 2110 "F Net PCT
Attachment B Quad Cities Nuclear Power Station Unit 2 10 CFR 50.46 Report PLANT NAME: Quad Cities Unit 2 ECCS EVALUATION MODEL: SAFEWGESTR-LOCA REPORT REVISION DATE: 05105/05 CURRENT OPERATING CYCLE: -
18 ANALYSIS OF RECORD Evaluation Model:
The GESTR-LOCA and SAFER Models for the Evaluation of the Loss-of-Coolant Accident, Volume Ill, SAFERIGESTR Application Methodology, NEDE-23785-1-PA, General Electric Company, Revision 1, October 1984.
Calculations:
"SAFEWGESTR-LOCA Loss-of-Coolant Accident Analysis for Dresden Nuclear Station 2 and 3 and Quad Cities Nuclear Station Units 1 and 2," NEDC-32990P, Revision 2, GE Nuclear Energy, September 2003.
Fuel Analyzed in Calculation: GE9/10, ATRIUM-96 and GE14 Limiting Fuel Type: GE14 Limiting Single Failure: Diesel Generator Limiting Break Size and Location: 1.O Double-Ended Guillotine in a Recirculation Suction Pipe Reference Peak Cladding Temperature (PCT) PCT = 2110°F MARGl N ALLOCATION A. PRIOR LOCA MODEL ASSESSMENTS
. I 0 CFR 50.46 Report dated May 9,2002 (See Note 3) APCT = 0°F 10 CFR 50.46 Report dated May 8,2003 (See Note 4) APCT = 0°F 10 CFR 50.46 Report dated May 5,2004 (See Note 5) APCT = 0°F I Net PCT I 2110°F I B. CURRENT LOCA MODEL ASSESSMENTS GE LOCA Model Change due to New Heat Source (See Note 6) APCT = 0°F Total PCT change from current assessments CAPCT = 0°F Cumulative PCT change from current assessments c (APCT] = OOF
, Net PCT 21 10°F
Attachment C Quad Cities Nuclear Power Station Units 1 and 2 10 CFR 50.46 Report Assessment Notes
- 1. Prior LOCA Model Assessment The 50.46 letter dated March 28, 2002 reported a new LOCA analysis to support extended power uprate (EPU) and transition to GE14 fuel for Quad Cities Unit 2.
[
Reference:
Letter from Timothy J. Tulon (Exelon) to US. NRC, 10 CFR 50.46, 30-Day Report for Quad Cities Unit 2, SVP-02-025, dated March 28, 2002.1
- 2. Prior LOCA Assessment A new LOCA analysis was performed to support EPU and transition to GE14 fuel for Quad Cities Unit 1. In the referenced letter, the impact of CS and LPCl leakage, GE LOCA error in the WEVOL code and change in DG start time requirement were reported. There is no assessment penalty.
[
Reference:
Letter from Timothy J. Tulon (Exelon) to US. NRC, 10 CFR 50.46, 30-Day Report for Quad Cities Nuclear Power Station, Unit 1, SVP-02-104, dated December 6,2002.1
- 3. Prior LOCA Assessment In the referenced letter, no LOCA model assessment was reported for Unit 2 PCT.
[
Reference:
Letter from Timothy J. Tulon (Exelon) to US. NRC, Transmittal of 10 CFR 50.46, Acceptance criteria for emergency core cooling systems for light water nuclear power reactors, Annual Report for Quad Cities Units 1 and 2, SVP-02-039, dated May 9, 2002.]
- 4. Prior LOCA Assessment The referenced letter provided the annual 50.46 report for Units 1 and 2. This letter reported no LOCA model assessment for Unit 1 whereas it reported the impact of GE LOCA error in the WEVOL code and change in DG start time requirement for Unit 2. The PCT impact for these errors was determined to be OF.
[
Reference:
Letter from Timothy J. Tulon (Exelon) to U.S. NRC, Transmittal of 10 CFR 50.46, Acceptance criteria for emergency core cooling systems for light water nuclear power reactors, Annual Report for Quad Cities Nuclear Power Station, Units 1 and 2, SVP-03-063, dated May 8, 2003.1
- 5. Prior LOCA Assessment The referenced letter provided the annual 50.46 report for Units 1 and 2. This letter reported GE LOCA errors related to SAFER levellvolume table and Steam
Attachment C Quad Cities Nuclear Power Station Units 1 and 2 10 CFR 50.46 Report Assessment Notes Separator pressure drop and mid-cycle reload of GE14 fuel for Unit 1 (Cycle 18A). For Unit 2, this letter reported the same GE LOCA errors and second reload of GE14 fuel in Cycle 18 core. The PCT impact for these errors and reloads of GE14 fuel was determined to be O°F.
[
Reference:
Letter from Patrick R. Simpson (Exelon) to US. NRC, Transmittal of 10 CFR 50.46, Acceptance criteria for emergency core cooling systems for light-water nuclear power reactors, Annual Report for Quad Cities Nuclear Power Station, Units 1 and 2, RS-04-066, dated May 5, 2004.1 Current LOCA Assessment GE has postulated a new heat source applicable to the LOCA event. This heat source is due to recombination of hydrogen and excess oxygen drawn into the vessel from containment during core heatup. The oxygen enters the vessel either as a dissolved gas in the ECCS water or through the break when the vessel fully depressurizes and draws the containment non-condensible gases back into the vessel. The current LOCA evaluation model does not account for the effect of this heat source, which has potential to raise the steam temperature while leading to an increase in PCT and local oxidation. GE has evaluated the effect of this additional heat source for the jet pump plants like Quad Cities and determined that the impact is insignificant. This is because of the fact that oxygen from containment enters the vessel after the core is reflooded for the jet pump plants. Therefore, the PCT impact for all fuel types is zero and the effect on local oxidation is negligible.
[
Reference:
General Electric 10 CFR 50.46 Notification Letter 2003-05, May 13, 2004.1 Current LOCA Assessment Quad Cities Unit 1 Cycle 19 is to start up in April 2005 with a new reload of GE14 fuel. The impact of this reload was evaluated by GE and reported to be negligible. GE determined that there is no PCT impact because of the change due to the new reload of GE14 fuel.
[
Reference:
Supplemental Reload Licensing Report for Quad Cities 1 Reload 18 Cvcle 19. 0000-0028-1626-SRLR, Revision 0, January 2005.1