RNP-RA/04-0053, Steam Generator Tube Plugging Report for Refueling Outage 22

From kanterella
Jump to navigation Jump to search
Steam Generator Tube Plugging Report for Refueling Outage 22
ML041460268
Person / Time
Site: Robinson Duke Energy icon.png
Issue date: 05/18/2004
From: Baucom C
Progress Energy Carolinas
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RNP-RA/04-0053
Download: ML041460268 (2)


Text

TS 5.6.8 a C Progress Energy Serial: RNP-RA/04-0053 MAY 1 8 2004 United States Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-26 11LICENSE NO. DPR-23 STEAM GENERATOR TUBE PLUGGING REPORT FOR REFUELING OUTAGE 22 Ladies and Gentlemen:

In accordance with the H. B. Robinson Steam Electric Plant, Unit No. 2, Technical Specifications 5.6.8, "Steam Generator Tube Inspection Report," Paragraph a, Progress Energy Carolinas, Inc., also known as Carolina Power and Light Company, submits the attached steam generator tube plugging report for Refueling Outage 22.

The steam generator tube plugging was completed on May 7, 2004.

If you have any questions concerning this matter, please contact me.

Sincerely, C. T. Baucom Supervisor - Licensing/Regulatory Programs JMG/jmg Attachment C: NRC Resident Inspector, HBRSEP L. A. Reyes, NRC, Region II C. P. Patel, NRC, NRR 1q Progress Energy Carolinas. Inc.

Robinson Nuclear Plant 3581 West Entrance Road Hartsville, SC 29550

United States Nuclear Regulatory Commission Attachment to Serial: RNP-RA/04-0053 Page 1 of 1 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 STEAM GENERATOR TUBE PLUGGING REPORT FOR REFUELING OUTAGE 22 Steam Number of Generator Tubes Plugged During RO 22 A 0 B 5 C 2