June 21, 2006
REGULATORY ISSUE SUMMARY 2006-09NRC'S PROCEDURES FOR REVIEW OF DECOMMISSIONINGFUNDING ASSURANCE REPORTS
ADDRESSEES
All holders of operating licenses for nuclear power reactors, except those who havepermanently ceased operations and certified that fuel has been permanently removed from the reactor vessel.
INTENT
The U.S. Nuclear Regulatory Commission (NRC) is issuing this regulatory issue summary(RIS) to inform all licensees that the staff developed NRR Office Instruction LIC-205(Agencywide Documents Access and Management System (ADAMS) Accession No.
ML060940529), ?Procedures for NRC's Independent Analysis of Decommissioning FundingAssurance for Operating Nuclear Power Reactors." LIC-205 defines and documents how the staff conducts its timely independent analysis of thereports required to be submitted every 2 years (biennial) pursuant to Title 10 of the Code ofFederal Regulations (10 CFR) Section 50.75(f)(1) on the status of decommissioning fundingassurance for each nuclear power reactor or part of a reactor owned by a license These biennial reports (which were initially submitted by March 31, 1999, and are to be submitted at least once every 2 years thereafter by March 31) reflect funding data as of the end of the preceding calendar yea The NRC staff performs an independent analysis of each of thesereports to determine whether licensees have provided reasonable assurance that sufficient funding for radiological decommissioning of the reactor will be available at the time permanenttermination of operations is expecte This RIS requires no action or written response on the part of the addressee.
BACKGROUND INFORMATION
Pursuant to 10 CFR 50.75(f)(1), each power reactor licensee is required to report on the status of its decommissioning funding assurance to the NRC every 2 years, with the first reportsbeing submitted by March 31, 1999. Based on the staff's lessons learned exercise conducted following the analysis of the initialbiennial reports submitted by March 31, 1999, and subsequent biennial reports submitted by the end of March 2001, March 2003, and March 2005, the staff developed LIC-20 LIC-205defines and documents how the staff performs its independent analysis of each biennial report ML061100154 RIS 2006-09
|
---|
|
list | | | Topic |
---|
RIS 2006-02, Good Practices for Licensee Performance During the Emergency Preparedness Component of Force-On-Force Exercises | 23 February 2006 | Backfit | RIS 2006-02, Good Practices For Licensee Performance During The Emergency Preparedness Component of Force-On-Force Exercises | 23 February 2006 | Backfit | RIS 2006-04, Draft RAI on Meteorology for Full-Scope AST Application | 11 July 2006 | | RIS 2006-07, Proposed Changes to the Safety System Unavailability Performance Indicators | 12 June 2006 | Enforcement Discretion Significance Determination Process Backfit | RIS 2006-08, Publicly Available Cover Letters for Security-Related Inspection Reports | 12 June 2006 | Significance Determination Process Backfit | RIS 2006-08, Publicly Available Cover Letters For Security-Related Inspection Reports | 12 June 2006 | | RIS 2006-09, Nrc'S Procedures for Review of Decommissioning Funding Assurance Reports | 21 June 2006 | Backfit | RIS 2006-09, Nrc'S Procedures For Review of Decommissioning Funding Assurance Reports | 21 June 2006 | | RIS 2006-10, NRC Regulatory Issue Summary NRC Regulatory Issue Summary 2006-010 - Regulatory Expectations with Appendix R Paragraph III.G.2 Operator Manual Actions | 30 June 2006 | Hot Short Safe Shutdown Fire Barrier Enforcement Discretion Operator Manual Action Exemption Request Fire Protection Program Backfit Manual Operator Action | RIS 2006-10, NRC Regulatory Issue Summary NRC Regulatory Issue Summary 2006-010 - Regulatory Expectations with Appendix R Paragraph Iii.G.2 Operator Manual Actions | 30 June 2006 | Hot Short Safe Shutdown Fire Barrier Enforcement Discretion Operator Manual Action Exemption Request Fire Protection Program | RIS 2006-12, Us Nuclear Regulatory Commission. NRC Regulatory Issue Summary 2006-12; Endorsement of Nuclear Energy Institute Guidance Enhancements to Emergency Preparedness Programs for Hostile Action. | 19 July 2006 | Safe Shutdown Safeguards Contingency Plan Backfit | RIS 2006-12, Endorsing NEI White Paper, Enhancements to Emergency Preparedness Programs for Hostile Action | 19 July 2006 | Safeguards Contingency Plan Backfit | RIS 2006-13, NRC000046-NRC Regulatory Issue Summary 2006-13, Information on the Changes Made to the Reactor Oversight Process to More Fully Address Safety Culture. | 31 July 2006 | Fitness for Duty Temporary Modification Backfit | RIS 2006-13, 2006/07/31-Intervenor-Exhibit 10-Information On The Changes Made To The Reactor Oversight Process To More Fully Address Safety Culture, Regulatory Issue Summary 2006-13, U.S. NRC | 31 July 2006 | Fitness for Duty Backfit | RIS 2006-13, Information on the Changes Made to the Reactor Oversight Process to More Fully Address Safety Culture | 31 July 2006 | Fitness for Duty Backfit | RIS 2006-14, NRC Regulatory Issue Summary - Enforcement Requirements for Facility Changes Under 10 CFR 70.72 (c) (2) | 22 September 2006 | Enforcement Discretion Backfit | RIS 2006-14, NRC Regulatory Issue Summary - Enforcement Requirements for Facility Changes Under 10 CFR 70.72 (C) (2) | 22 September 2006 | Enforcement Discretion Backfit | RIS 2006-15, Withdrawn NRC Regulatory Issue Summary 2006-15 Preparation and Scheduling of Operator Licensing Examinations | 14 August 2006 | Generic Fundamentals Examination Backfit | RIS 2006-17, NRC Staff Position on the Requirements of 10 CFR 50.36, Technical Specification, with Respect to Limiting Safety System Settings (LSSS) During Periodic Testing and Calibration of Instrument Channels | 24 August 2006 | Functionality Assessment Backfit Operability Assessment | RIS 2006-18, Wits200500191/Wits200500192/Wits2005193 - NRC Regulatory Issue Summary 2006-18 Requesting Exemption From the Public Dose Limits for Certain Caregivers of Hospital Patients | 31 August 2006 | Exemption Request | RIS 2006-18, WITS200500191/WITS200500192/WITS2005193 - NRC Regulatory Issue Summary 2006-18 Requesting Exemption from the Public Dose Limits for Certain Caregivers of Hospital Patients | 31 August 2006 | Enforcement Discretion Exemption Request | RIS 2006-19, Availability of Guidance on Radioactive Seed Localization. | 14 September 2006 | Backfit | RIS 2006-20, Guidance for Receiving Enforcement Discretion When Concentrating Uranium at Community Water Systems | 14 December 2011 | Enforcement Discretion Pandemic Backfit | RIS 2006-20, Enclosure 2 - List of Recently Issued Generic Communication | 14 September 2006 | | RIS 2006-21, Improving Response Capabilities Through the Use of an Incident Response Electronic Library | 28 September 2006 | Reactor Vessel Water Level Severe Accident Management Guideline Backfit Siren | RIS 2006-22, Lessons Learned from Recent 10 CFR Part 72 Dry Cask Storage Campaign | 15 November 2006 | Safe Shutdown Exemption Request Control of Heavy Loads Fuel cladding Backfit | RIS 2006-23, Post-Tornado Operability of Ventilating and Air-Conditioning (VAC) Systems Housed in Emergency Diesel Generator (EDG) Rooms | 6 December 2006 | | RIS 2006-23, Post-Tornado Operability of Ventilating and Air-Conditioning (Vac) Systems Housed in Emergency Diesel Generator (EDG) Rooms | 6 December 2006 | Earthquake Backfit | RIS 2006-25, Requirements for the Distribution and Possession of Tritium Exit Signs and the Requirements in 10 CFR 31.5 Ad 32.51a | 7 December 2006 | Tritium Exit Sign | RIS 2006-25, Requirements For the Distribution and Possession of Tritium Exit Signs and the Requirements in 10 CFR 31.5 Ad 32.51A | 7 December 2006 | Tritium Exit Sign | RIS 2006-26, SECY-06-0248 Enclosure 2 - Regulatory Issue Summary 2006-26, Training and Experience and Grandfather Provisions for Authorized Medical Physicists Under 10 CFR Part 35 | 7 December 2006 | | RIS 2006-26, Training and Experience and Grandfather Provisions for Authorized Medical Physicists Under 10 CFR 35 | 7 December 2006 | Enforcement Discretion | RIS 2006-27, Availability of NRC 313A Series of Forms and Guidance for Their Completion | 27 June 2007 | Brachytherapy TheraSphere |
|
---|