Text

Kevin M.Ellis ef,DUKE General Manager

~;ENERGY Nuclear Regula/off Affairs, Policy &

Emergency Preparedness Duke Energy 13225 Hagers Ferry Rd., MG011E Huntersville, NC 28078 843-951-1329 Kevin.Ellis@duke-energy.com Serial: RA-22-0013 October 31, 2022 10 CFR 52, Appendix D, X.B U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 SHEARON HARRIS NUCLEAR POWER PLANT, UNITS 2 AND 3 DOCKET NOS.52-022 AND 52-023

SUBJECT:

AP1000 Combined License Application Departure Report Update

REFERENCE:

1. Letter from J. Scarola (Duke Energy) to U.S. Nuclear Regulatory Commission (NRC), dated February 18, 2008, "Application for Combined License for Shearon Harris Nuclear Power Plant Units 2 and 3,"

(ADAMS Accession No. ML080580078).

2. Letter from C. Nolan (Duke Energy) to NRC, dated April 27, 2022, "AP1000 Combined License Application (COLA) Departure Report Update and 10 CFR 50.46 Annual Update," (ADAMS Accession No. ML22117A084).

Duke Energy Progress, Inc. (DEP) submitted an application, dated February 18, 2008, for a combined license (COL) for two AP1000 advanced pressurized water reactors to be located at the Shearon Harris Nuclear Power Plant Site (Reference 1). Part 7 of the application is entitled "Departures and Exemption Requests." This letter provides an update to the report describing plant-specific departures from the AP1000 Design Control Document (i.e. Departures Report) as required by 10 CFR 52, Appendix D, paragraphs X.B.1 and X.B.3.b.

There have been no new departures or changes to the departures described in the Shearon Harris Nuclear Power Plant, Units 2 and 3, COLA Part 7, "Departures and Exemption Requests" for the period of April 27, 2022 to October 31, 2022 (Reference 2).

This submittal contains no new regulatory commitments.

Please address any comments or questions regarding this matter to Ryan Treadway, Director-Fleet Licensing at (980) 373-5873.

Sincerely, Kevin Ellis General Manager, Nuclear Regulatory Affairs, Policy & Emergency Preparedness

U.S. Nuclear Regulatory Commission RA-22-0013 Page 2 cc: L. Dudes, U.S. NRC Region II Administrator D. Murray, U.S. NRC Project Manager