MONTHYEARRA-23-0314, AP1000 Combined License Application Departure Report Update2023-11-17017 November 2023 AP1000 Combined License Application Departure Report Update RA-23-0106, AP1000 Combined License Application (Cola) Departure Report Update and 10 CFR 50.46 Annual Update2023-05-0303 May 2023 AP1000 Combined License Application (Cola) Departure Report Update and 10 CFR 50.46 Annual Update RA-22-0013, AP1000 Combined License Application Departure Report Update2022-10-31031 October 2022 AP1000 Combined License Application Departure Report Update RA-22-0012, AP1000 Combined License Application (Cola) Departure Report Update and 10 CFR 50.46 Annual Update2022-04-27027 April 2022 AP1000 Combined License Application (Cola) Departure Report Update and 10 CFR 50.46 Annual Update RA-21-0045, Units 2 and 3 - AP1000 Combined License Application Departure Report Update2021-10-26026 October 2021 Units 2 and 3 - AP1000 Combined License Application Departure Report Update RA-21-0044, AP1000 Combined License Application Departure Report Update and 10 CFR 50.46 Annual Update2021-04-21021 April 2021 AP1000 Combined License Application Departure Report Update and 10 CFR 50.46 Annual Update RA-20-0304, AP1000 Combined License Application Departure Report Update2020-09-24024 September 2020 AP1000 Combined License Application Departure Report Update RA-20-0061, AP1000 Combined License Application Departure Report Update and 10 CFR 50.46 Annual Update2020-04-14014 April 2020 AP1000 Combined License Application Departure Report Update and 10 CFR 50.46 Annual Update RA-19-0363, AP1000 Combined License Application Departure Report Update2019-10-0101 October 2019 AP1000 Combined License Application Departure Report Update RA-19-0195, Submittal of AP1000 Combined License Application Departure Report Update and 10 CFR 50.46 Annual Update2019-04-10010 April 2019 Submittal of AP1000 Combined License Application Departure Report Update and 10 CFR 50.46 Annual Update RA-13-020, Duke Energy - 10 CFR 71.95 Report on the 8-120B Cask2013-10-0808 October 2013 Duke Energy - 10 CFR 71.95 Report on the 8-120B Cask 2023-05-03
[Table view] Category:License-Combined License (COL) (New/Renewal/Amendments) DKT 52
[Table view] |
Text
~ ~ DUKE
~ ENERGY M. Christopher Nolan 526 South Church Street Charlotte, NC 28202 Mailing Address:
Mail Code EC07H /P.O. Box 1006 Charlotte, NC 28201-1006 704-382-7426 Serial: RA-19-0363 October 1, 2019 10 CFR 52, Appendix D, X.B U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 SHEARON HARRIS NUCLEAR POWER PLANT, UNITS 2 AND 3 DOCKE T NOS.52-022 AND 52-023
SUBJECT:
AP1000 Combined License Application Departure Report Update Duke Energy Progress, Inc. (DEP) submitted an application, dated February 18, 2008, for a combined license for two AP1000 advanced pressurized water reactors to be located at the Shearon Harris Nuclear Power Plant Site. Part 7 of the application is entitled "Depart ures and Exemption Requests." This letter provides an update to the report describing plant-sp ecific departures from the AP1000 Design Control Docume nt (i.e. Departures Report) as required by 10 CFR 52, Appendix D, paragraphs X.B.1 and X.B.3.b.
There have been no new departures or changes to the departures described in the Shearon Harris Nuclear Power Plant (HAR), Units 2 and 3, COLA Part 7, "Departures and Exemption Requests" for the period of April 1, 2019 to Septem ber 30, 2019.
This submittal contains no regulatory commitments.
Please address any comments or questions regarding this matter to Art Zaremb a, Manage r -
Fleet Licensing at (980) 373-2062.
tt ~
Sincerely, M. Christopher Nolan Vice President, Nuclear Regulatory Affairs cc: L. Dudes, U.S. NRC Region II Administrator M. Comar, U.S. NRC Project Manager