Press Release-II-03-042: NRC Sends Inspection Team to Review Shutdown at Sequoyah Nuclear Plant
ML032410406
Person / Time
Site: Sequoyah Tennessee Valley Authority icon.png
Issue date: 08/29/2003
From:
Office of Public Affairs Region II
To:
Category:Press Release
References
Press Release-II-03-042
Download: ML032410406 (1)


Text

NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION OFFICE OF PUBLIC AFFAIRS, REGION II 61 Forsyth Street SW, Atlanta, GA 30303 Web Site: http://www.nrc.gov No. II-03-042 August 29, 2003 CONTACT: Ken Clark (404)562-4416 E-mail: OPA2@nrc.gov Roger Hannah (404)562-4417 NRC SENDS INSPECTION TEAM TO REVIEW SHUTDOWN AT SEQUOYAH NUCLEAR PLANT U.S. Nuclear Regulatory Commission officials have dispatched an Augmented Inspection Team (AIT) to review the circumstances surrounding an August 28 shutdown and alert declaration at Unit 1 of the Tennessee Valley Authoritys Sequoyah nuclear plant northeast of Chattanooga. The AIT will assess equipment performance as well as plant operator actions, and preliminary results of that inspection will be presented at a public exit meeting late next week at a time to be announced later.

Sequoyah Unit 1 experienced a turbine trip during routine testing, and when control room operators saw that the reactor did not automatically trip as expected, they manually shut it down.

TVA declared an alert, the second of four emergency classification levels for commercial nuclear power plants, and all plant functions during the shutdown were normal. The plant exited the alert status after a little more than four hours when plant operators determined the plant was stable and systems were performing as designed.

The NRC resident inspector was at the plant and responded to the control room as the events began.

After being notified, the NRC Region II staff in Atlanta manned their emergency response center to monitor the situation.

The NRCs AIT members began their inspection early Friday, August 29, and the team is comprised of the Sequoyah plants senior NRC resident inspector, a regional NRC manager to serve as team leader and three Atlanta-based inspectors with expertise in plant operations and systems.

In addition to the public exit meeting where inspectors will discuss their preliminary findings, the NRC team will issue a written report which will be available to the public several weeks later.