Semantic search

Jump to navigation Jump to search
 Issue dateTitleFromTo
ML11165A0088 June 2011Response to NRC Bulletin 2011-01, Mitigating StrategiesDuke Energy
Morris J R
Office of Nuclear Reactor Regulation
Document Control Desk
ML11195A06911 July 201160 Day Response to NRC Bulletin 2011-01, Mitigating Strategies.Duke Energy
Morris J R
Office of Nuclear Reactor Regulation
Document Control Desk
IR 05000413/20110061 September 2011Mid-Cycle Performance Review and Inspection Plan for Catawba, Unit 1 & 2 Inspection Report 05000413-11-006 and 05000414-11-006NRC/RGN-II/DRP/RPB1
Hutto G
Duke Energy
Morris J
ML11335A05421 December 2011Request for Additional Information Regarding 60-Day Response to Bulletin 2011-01, Mitigating StrategiesJacqueline Thompson
Plant Licensing Branch II
Duke Energy
Morris J
ML12023A07519 January 2012Response to NRC Request for Additional Information Dated December 21, 2011 Regarding NRC Bulletin 2011-01, Mitigating Strategies.Duke Energy
Morris J
Office of Nuclear Reactor Regulation
Document Control Desk
ML12193A49917 July 2012Closeout of Bulletin 2011-01, Mitigating Strategies.Jacqueline Thompson
Plant Licensing Branch II
Duke Energy
Morris J
ML20093B6325 May 2020Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai-Ichi AccidentRobert Bernardo
NRC/NRR/DORL/LPMB
Duke Energy
Simril R