 Issue dateTitleFromTo
CP-201100828, 30-Day Response to NRC Bulletin 2011-01, Mitigation Strategies8 June 201130-Day Response to NRC Bulletin 2011-01, Mitigation StrategiesLuminant
Flores R
Office of Nuclear Reactor Regulation
Document Control Desk
CP-201100899, 60-Day Response to NRC Bulletin 2011-01, Mitigating Strategies.11 July 201160-Day Response to NRC Bulletin 2011-01, Mitigating Strategies.Luminant
Flores R
Madden F
Office of Nuclear Reactor Regulation
Document Control Desk
IR 05000445/201101121 October 2011NRC Inspection Report 50-445/2011-11, 50-446/2011-11, and 72-74/2011-01NRC/RGN-IV/DNMS/RSFSB
Spitzberg D
Luminant
Flores R
ML1208705769 April 2012Safety Evaluation Related to Licensee'S Responses to NRC Bulletin 2011-01, Mitigating StrategiesBalwant Singal
Plant Licensing Branch IV
Luminant
Flores R
ML18207A2728 August 2018Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai-ichi AccidentRobert Bernardo
Beyond-Design-Basis Management Branch
Vistra Operations Company
Peters K