Semantic search

Jump to navigation Jump to search
 Issue dateTitleFromTo
LR-N11-0178, Thirty Day Response to NRC Bulletin 2011-019 June 2011Thirty Day Response to NRC Bulletin 2011-01PSEG
Neely C
Office of Nuclear Reactor Regulation
Document Control Desk
LR-N11-0207, Sixty Day Response to NRC Bulletin 2011-01, Mitigating Strategies.11 July 2011Sixty Day Response to NRC Bulletin 2011-01, Mitigating Strategies.PSEG
Braun R
Office of Nuclear Reactor Regulation
Document Control Desk
ML1124113151 September 2011Mid-Cycle Performance Review and Inspection Plan 2011 - Hope Creek Generating StationArthur Burritt
Reactor Projects Region 1 Branch 3
PSEG
Joyce T
ML11311024814 November 2011and Salem Nuclear Generating Station, Units 1 and 2 - Request for Additional Information Regarding 60-Day Response to Bulletin 2011-01, Mitigating StrategiesRichard Ennis
Plant Licensing Branch I
PSEG
Joyce T
LR-N11-0363, Response to NRC Bulletin 2011-01, Mitigating Strategies Request for Additional Information12 December 2011Response to NRC Bulletin 2011-01, Mitigating Strategies Request for Additional InformationPSEG
Braun R
Office of Nuclear Reactor Regulation
Document Control Desk
ML12220A25010 August 2012Closeout of Bulletin 2011-01, Mitigating StrategiesJohn Hughey
Plant Licensing Branch I
PSEG
Joyce T
ML20217L64314 August 2020Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai Ichi AccidentRobert Bernardo
Plant Licensing Branch I
PSEG
Carr E