Semantic search

Jump to navigation Jump to search
 Issue dateTitleFromTo
ML11167A09810 June 20112 & 3; Sequoyah, Units 1 & 2 and Watts Bar, Units 1 & 2 - Response to NRC Bulletin 2011-01, Mitigating StrategiesTennessee Valley Authority
Krich R M
Office of Nuclear Reactor Regulation
Document Control Desk
ML11195A34014 July 2011NRC Staff Submittal of Supplement 18 to Hearing File for Watts Bar, Unit 2 OL ProceedingNRC/OGC
Roth D
Lawrence Mcdade
Gary Arnold
Abramson P
Atomic Safety and Licensing Board Panel
ML11201A30318 July 2011Response to NRC Bulletin 2011-01, Mitigation StrategiesTennessee Valley Authority
Stinson D
Office of Nuclear Reactor Regulation
Document Control Desk
ML11224A10019 July 2011OL - TVA Letter to Nrc_Response to NRC Bulletin 2011-01- No Known AffiliationDivision of Operating Reactor Licensing
ML11153039928 July 2011SECY-11-0102 - Fourth Report on Status of Reactivation of Constrcution and Licensing for the Watts Bar Nuclear Plant, Unit 2Leeds E
Office of Nuclear Reactor Regulation
Kristine Svinicki
NRC/OCM
NRC/Chairman
Ostendorff W
Jaczko G
Magwood W
Apostolakis G
ML11227A23415 August 2011NRC Staff Submittal of Supplement 18 to Hearing File for Watts Bar, Unit 2NRC/OGC
Roth D
Lawrence Mcdade
Gary Arnold
Abramson P
Atomic Safety and Licensing Board Panel
IR 05000390/20110061 September 2011Mid-Cycle Performance Review and Inspection Plan for Watts Bar Nuclear Plant, Unit 1 Inspection Report 05000390-2011-006Scott Shaeffer
Reactor Projects Region 2 Branch 6
Tennessee Valley Authority
Rod Krich
ML12102A21823 April 2012Closeout of NRC Bulletin 2011-01, Mitigating StrategiesLyon C
Watts Bar Special Projects Branch
Tennessee Valley Authority
James Shea
ML12152A04824 July 2012SECY-12-0103 - Sixth Report on the Status of Reactivation of Construction and Licensing for Watts Bar Nuclear Plant, Unit 2Leeds E
Office of Nuclear Reactor Regulation
NRC/OCM
Commissioners
ML13036A2397 January 2013OL - 2012-01-07 - WBN Project Plan - Unit 2.pdf- No Known AffiliationDivision of Operating Reactor Licensing
ML13036A24110 January 2013OL - 2012-01-10 - WBN Project Plan - Unit 2.pdf- No Known AffiliationDivision of Operating Reactor Licensing
ML13036A24921 January 2013OL - 2012-01-21 - WBN Project Plan - Unit 2.pdf- No Known AffiliationDivision of Operating Reactor Licensing
ML13036A25224 January 2013OL - 2012-01-24 - WBN Project Plan - Unit 2.pdf- No Known AffiliationDivision of Operating Reactor Licensing
ML13036A25728 January 2013OL - 2012-01-28 - WBN Project Plan - Unit 2.pdf- No Known AffiliationDivision of Operating Reactor Licensing
IR 05000391/20126104 February 2013IR 05000391-12-610, on 12/31/2012, Watts Bar Unit 2 Construction - NRC IntegratedEric Michel
NRC/RGN-II/DCP/CPB3
Tennessee Valley Authority
Skaggs M
ML13072A2204 February 2013OL - 2012-02-04 - WBN Project Plan - Unit 2.pdf- No Known AffiliationDivision of Operating Reactor Licensing
ML13072A2437 February 2013OL - 2012-02-07 - WBN Project Plan - Unit 2.pdf- No Known AffiliationDivision of Operating Reactor Licensing
ML13072A25111 February 2013OL - 2012-02-11 - WBN Project Plan - Unit 2.pdf- No Known AffiliationDivision of Operating Reactor Licensing
ML13051A04514 February 2013Updated Response to NRC Bulletin 2011-01, Mitigation StrategiesTennessee Valley Authority
Shea J W
Office of Nuclear Reactor Regulation
Document Control Desk
ML13074A71115 March 2013NRC March 2012 Hearing File Update 38NRC/OGC
Roth D
Gary Arnold
Paul Ryerson
Abramson P
Atomic Safety and Licensing Board Panel
ML13213A19425 July 2013Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 10 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 10Tennessee Valley Authority
Hruby R
Office of Nuclear Reactor Regulation
Document Control Desk
CNL-14-154, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 12 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 122 September 2014Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 12 (TAC No. MD6311), and Status of Generic Communications for Unit 2 - Revision 12Tennessee Valley Authority
James Shea
Office of Nuclear Reactor Regulation
Document Control Desk
L-11-011, Transmittal of Response to NRC Bulletin 2011-01, Mitigating Strategies.29 June 2015Transmittal of Response to NRC Bulletin 2011-01, Mitigating Strategies.Tennessee Valley Authority
James Shea
Office of Nuclear Reactor Regulation
Document Control Desk
CNL-15-137, Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 13 (TAC No. MD6311) and Status of Generic Communications for Unit 2 - Revision 1327 July 2015Status of Regulatory Framework for the Completion of Construction and Licensing for Unit 2 - Revision 13 (TAC No. MD6311) and Status of Generic Communications for Unit 2 - Revision 13Tennessee Valley Authority
James Shea
Office of Nuclear Reactor Regulation
Document Control Desk
L-11-001, Submittal of 30-Day Response to NRC Bulletin 2011-01, Mitigating Strategies.24 September 2015Submittal of 30-Day Response to NRC Bulletin 2011-01, Mitigating Strategies.Tennessee Valley Authority
James Shea
Office of Nuclear Reactor Regulation
Document Control Desk
CNL-15-207, Submittal of 30-Day Response to NRC Bulletin 2011-01, Mitigating Strategies.24 September 2015Submittal of 30-Day Response to NRC Bulletin 2011-01, Mitigating Strategies.Tennessee Valley Authority
Shea J W
Office of Nuclear Reactor Regulation
Document Control Desk
ML15280A08514 October 2015Closeout of NRC Bulletin 2011-01, Mitigating StrategiesJustin Poole
Watts Bar Special Projects Branch
Tennessee Valley Authority
James Shea
ML20322A16025 November 2020Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai-Ichi AccidentRobert Bernardo
NRC/NRR/DORL/LPMB
Tennessee Valley Authority
James Barstow