Semantic search

Jump to navigation Jump to search
 Issue dateTitleFromTo
SBK-L-11116, 30-Day Response to NRC Bulletin 11-01, Mitigating Strategies10 June 201130-Day Response to NRC Bulletin 11-01, Mitigating StrategiesNextEra Energy Seabrook
Freeman P
Office of Nuclear Reactor Regulation
Document Control Desk
ML1124113401 September 2011Mid-Cycle Performance Review and Inspection Plan 2011 - Seabrook Station, Unit 1Arthur Burritt
Reactor Projects Region 1 Branch 3
NextEra Energy Seabrook
Freeman P
ML1133300858 December 2011Request for Additional Information Regarding 60-Day Response to Bulletin 2011-01, Mitigating StrategiesGeoffrey Miller
Plant Licensing Branch I
NextEra Energy Seabrook
O'Keefe M
Freeman P
SBK-L-11248, Response to Request for Additional Information Regarding 60-Day Response to NRC Bulletin 2011-01, Mitigating Strategies5 January 2012Response to Request for Additional Information Regarding 60-Day Response to NRC Bulletin 2011-01, Mitigating StrategiesNextEra Energy Seabrook
Freeman P
Office of Nuclear Reactor Regulation
Document Control Desk
ML12171A43127 June 2012Closeout of Bulletin 2011-01, Mitigating StrategiesJohn Lamb
Plant Licensing Branch I
NextEra Energy Seabrook
Walsh K
ML18302A2105 December 2019Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai-Ichi AccidentRobert Bernardo
Beyond-Design-Basis Management Branch
NextEra Energy Seabrook
Nazar M