Letter Sequence Other |
---|
|
Initiation
- Request, Request, Request
- Acceptance, Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
Results
Other: ML15327A213, ML16133A459, ML16133A499, ML17101A697, ML17207A165, ML17256A286, ML18212A032, ML18212A185, NL-16-138, Amendment 18 to License Renewal Application, NL-17-005, Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components., NL-17-019, Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms, NL-17-157, Amendment 19 to License Renewal Application (LRA)
|
MONTHYEARML15344A4362015-12-10010 December 2015 Lr Hearing - (External_Sender) Draft Audit Plan Edits Project stage: Request ML15327A2132015-12-21021 December 2015 Plan for the Regulatory Audit of the Service Water Integrity and Fire Water System Aging Management Programs Pertaining to the Indian Point Nuclear Generating Unit Nos. 2 and 3 LRA Project stage: Other ML15351A2032015-12-30030 December 2015 Summary of Conference Call Held on December 9, 2015, Between the NRC and Entergy Nuclear Operations, Inc. Concerning the Draft Audit Plan for the Service Water Integrity and Fire Water System Aging Management Programs Project stage: Draft Other ML16133A4592016-06-15015 June 2016 Service Water and Fire Water Systems Aging Management Programs Audit Report for the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application Project stage: Other ML16133A4992016-06-21021 June 2016 Summary of Telephone Conference Call Held Between NRC and Entergy Concerning the Indian Point LRA Safety Review Project stage: Other ML16138A1942016-07-25025 July 2016 Request for Additional Information for the Review of License Renewal Application, Set 2016-01 Project stage: RAI ML16208A2772016-07-26026 July 2016 Lr Hearing - RAI Set 2016-01 Project stage: Request NL-16-122, Reply to Request for Additional Information for the Review of License Renewal Application, Set 2016-01 (CAC Nos. MD5407 and MD5408)2016-12-0202 December 2016 Reply to Request for Additional Information for the Review of License Renewal Application, Set 2016-01 (CAC Nos. MD5407 and MD5408) Project stage: Response to RAI NL-16-138, Amendment 18 to License Renewal Application2016-12-15015 December 2016 Amendment 18 to License Renewal Application Project stage: Other NL-17-005, Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components.2017-01-17017 January 2017 Actions Concerning License Renewal Commitments 41 and 42 in Response to LR-ISG-2016-01, Changes to Aging Management Guidance for Various Steam Generator Components. Project stage: Other NL-17-019, Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms2017-02-0808 February 2017 Amendment to License Renewal Application - Reflecting Shortened License Renewal Terms Project stage: Other ML17046A2312017-03-0808 March 2017 Request for Additional Information for the Review of the Indian Point License Renewal - Set 2017-01 Project stage: RAI ML17082A3112017-04-11011 April 2017 Summary of Clarification Call with Entergy Regarding Follow-Up RAIs on ISG-2012-02 Project stage: RAI ML17088A3272017-04-19019 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 (CAC Nos. MD5407 and MD5408) Project stage: RAI ML17088A4052017-04-20020 April 2017 Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-3 (CAC Nos. MD5407 and MD5408) Project stage: RAI ML17101A6972017-04-25025 April 2017 License Renewal Clarification Call on Baffle Bolt Rai'S Project stage: Other NL-17-052, Reply to Request for Additional Information for the Review of the License Renewal Application, Set 2017-012017-05-0808 May 2017 Reply to Request for Additional Information for the Review of the License Renewal Application, Set 2017-01 Project stage: Response to RAI NL-17-053, Reply to Request for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-03 (CAC Nos. MD5407 and MD5408)2017-05-18018 May 2017 Reply to Request for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-03 (CAC Nos. MD5407 and MD5408) Project stage: Response to RAI NL-17-060, Reply to Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 (CAC Nos. MD5407 and MD5408)2017-05-19019 May 2017 Reply to Requests for Additional Information for the Review of the Indian Point License Renewal Application RAI Set 2017-02 (CAC Nos. MD5407 and MD5408) Project stage: Response to RAI ML17128A3352017-05-23023 May 2017 Summary of Telephone Conference Call Between the NRC and Entergy Concerning RAIs Pertaining to IP2 and IP3 Project stage: RAI NL-17-061, Reply to Requests for Additional Information for the Review of the License Renewal Application RAI Set 2017-042017-05-24024 May 2017 Reply to Requests for Additional Information for the Review of the License Renewal Application RAI Set 2017-04 Project stage: Response to RAI NL-17-069, Reply to Requests for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application RAI Set 2017-05 (CAC Nos. MD5407 and MD5408)2017-06-0808 June 2017 Reply to Requests for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application RAI Set 2017-05 (CAC Nos. MD5407 and MD5408) Project stage: Response to RAI NL-17-074, Supplemental Information Regarding Reply to Request for Additional Information Set 2017-01 for the Review of the License Renewal Application (LRA)2017-06-27027 June 2017 Supplemental Information Regarding Reply to Request for Additional Information Set 2017-01 for the Review of the License Renewal Application (LRA) Project stage: Response to RAI ML17170A2862017-06-27027 June 2017 RAI Set 2017-06 Project stage: RAI ML17160A1652017-06-27027 June 2017 Summary of Telephone Conference Call Held on May 31,2017, Between the NRC and Entergy Nuclear Operations Inc. Concerning Requests for Additional Information Pertaining to the Indian Point, License Renewal Application (TAC Nos. MD5407/MD5408 Project stage: RAI NL-17-084, Reply to Requests for Additional Information for the Review of the License Renewal Application. Re RAI Set 2017-062017-07-27027 July 2017 Reply to Requests for Additional Information for the Review of the License Renewal Application. Re RAI Set 2017-06 Project stage: Response to RAI NL-17-092, Amended Response to Request for Additional Information Question RAI 3.3.2-17-IP3-1 Re License Renewal Application RAI Set 2017-052017-07-27027 July 2017 Amended Response to Request for Additional Information Question RAI 3.3.2-17-IP3-1 Re License Renewal Application RAI Set 2017-05 Project stage: Response to RAI ML17207A1652017-09-0101 September 2017 License Renewal Audit Plan Regarding the Service Water Integrity Program Project stage: Other ML17250A2442017-09-20020 September 2017 Audit Report for IP Swi - Aug 2017 Project stage: Acceptance Review ML17191A4562017-09-20020 September 2017 06/08/2017 Telecon Summary Related to Indian Point License Renewal RAIs Associated with ISG-2016-01 Project stage: RAI ML17180A5032017-09-21021 September 2017 04/19/2017 Summary of Teleconference with Entergy Nuclear Operations, Inc., Concerning Request for Additional Information Pertaining to the Indian Point Unit Nos. 2 and 3 License Renewal Application Project stage: RAI ML17256A2862017-09-25025 September 2017 Summary of Telephone Call on 09/06/17, Between NRC and Entergy Concerning Next Steps from the Site Audit on 08/1-3/17 Project stage: Other NL-17-127, Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA) (CAC Nos. MD5407 and MD5408)2017-11-0808 November 2017 Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA) (CAC Nos. MD5407 and MD5408) Project stage: Supplement NL-17-155, Re-Submittal of Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA)2017-12-14014 December 2017 Re-Submittal of Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3 License Renewal Application (LRA) Project stage: Supplement NL-17-157, Amendment 19 to License Renewal Application (LRA)2017-12-14014 December 2017 Amendment 19 to License Renewal Application (LRA) Project stage: Other NL-17-161, Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Units 2 and 3 License Renewal Application (LRA) (CAC Nos. MD5407 and MD5408)2017-12-21021 December 2017 Supplemental Information Regarding the Service Water Integrity Aging Management Program for the Review of the Indian Point Nuclear Generating Units 2 and 3 License Renewal Application (LRA) (CAC Nos. MD5407 and MD5408) Project stage: Supplement NL-18-010, Supplemental Information Regarding the Review of the License Renewal Application2018-02-26026 February 2018 Supplemental Information Regarding the Review of the License Renewal Application Project stage: Supplement ML18107A7592018-04-30030 April 2018 NUREG-1437, Suppl. 38, Vol. 5, Generic Environmental Impact Statement for License Renewal of Nuclear Plants Supplement 38 Regarding Indian Port Nuclear Generating Unit Nos. 2 and 3 Final. Project stage: Acceptance Review NL-18-030, Supplemental Information Associated with Amendment 19 to the License Renewal Application (LRA)2018-05-0808 May 2018 Supplemental Information Associated with Amendment 19 to the License Renewal Application (LRA) Project stage: Supplement NL-18-044, Supplemental Information Regarding the Review of the License Renewal Application2018-06-25025 June 2018 Supplemental Information Regarding the Review of the License Renewal Application Project stage: Supplement ML18200A3332018-08-0101 August 2018 NUREG-1930, Supp 3, Safety Evaluation Report Related to the License Renewal of Indian Point Nuclear Generating Plant, Units 2 and 3. Project stage: Approval ML18211A4842018-08-0707 August 2018 to NUREG-1930, Safety Evaluation Report Related to the License Renewal of Indian Point Nuclear Generating Plant, Units 2 and 3. Project stage: Approval ML18211A5842018-09-17017 September 2018 Issuance of Renewed Facility Operating License Nos. DPR 26 and DPR-64 for Indian Point Nuclear Generating Unit Nos. 2 and 3 (CAC Nos. MD5407 and MD5408) Project stage: Request ML18212A1882018-09-17017 September 2018 Renewed License Appendix C Project stage: Acceptance Review ML18212A1852018-09-17017 September 2018 Renewed Facility Operating License DPR-26, Technical Specifications, Appendix B Project stage: Other ML18212A1812018-09-17017 September 2018 Renewed Facility Operating License DPR-26, Technical Specifications, Appendix a Project stage: Acceptance Review ML18212A0322018-09-17017 September 2018 Records of Decision for the Indian Point Renewed Licenses Project stage: Other ML18211A5962018-09-17017 September 2018 Transmittal Letter - Issuance of Renewed Facility Operating License Nos. DPR-26 and DPR-64 for Indian Point Nuclear Generating Unit Nos. 2 and 3 (CAC Nos. MD5407 and MD5408) Project stage: Approval ML18211A5782018-09-17017 September 2018 Federal Register Notice - Announcing the Issuance of the Indian Point Renewed Licenses Project stage: Approval ML18213A1142018-09-17017 September 2018 Renewed Facility Operating License Project stage: Other 2017-04-25
[Table View] |
|
---|
Category:Letter type:NL
MONTHYEARNL-21-034, Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals2021-05-26026 May 2021 Notification of Expected Date of Transfer of Ownership of Nuclear Units to Holtec Indian Point 2, LLC and Holtec Indian Point 3, LLC; and Notification of Receipt of All Required Regulatory Approvals NL-21-039, Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary2021-05-20020 May 2021 Response to Request for Additional Information - License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary NL-21-033, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2021-05-11011 May 2021 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-21-032, Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center2021-05-11011 May 2021 Termination of Emergency Response Data System Feed to the U.S. Nuclear Regulatory Commission at Indian Point Energy Center NL-21-005, Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions2021-05-11011 May 2021 Cancellation of Commitments Related to Beyond-Design-Basis External Events Seismic and Flooding Actions NL-21-030, Submittal of 2020 Annual Radiological Environmental Operating Report2021-05-0606 May 2021 Submittal of 2020 Annual Radiological Environmental Operating Report NL-21-027, Registration of Spent Fuel Cask Use2021-04-20020 April 2021 Registration of Spent Fuel Cask Use NL-21-021, Registration of Spent Fuel Cask Use2021-04-19019 April 2021 Registration of Spent Fuel Cask Use NL-21-017, Pre-Notice of Disbursement from Decommissioning Trusts2021-04-0808 April 2021 Pre-Notice of Disbursement from Decommissioning Trusts NL-21-010, Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2021-02-17017 February 2021 Submittal of 2020 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-21-006, Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement2021-02-10010 February 2021 Relief Request IP3-ISI-RR-16, Proposed Alternative to American Society of Mechanical Engineers Code Case N-513-4 Inspection Requirement NL-21-014, Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2021-01-26026 January 2021 Response to 2nd Round Request for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-082, Notice of Planned Transfer of Decommissioning Funds2020-12-14014 December 2020 Notice of Planned Transfer of Decommissioning Funds NL-20-081, Pre-Notice of Disbursement from Decommissioning Trusts2020-12-0909 December 2020 Pre-Notice of Disbursement from Decommissioning Trusts NL-20-080, Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-93212020-11-19019 November 2020 Report in Accordance with 10 CFR 71.95(a) for Failure to Comply with Certificate of Compliance No. 71-9321 NL-20-079, (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-12012 November 2020 (IP2 and IP3) - Request for a One-Time Exemption from 10 CFR 73, Appendix B, Section VI, Subsection C.3.(I)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic NL-20-077, Submittal of Quality Assurance Program Manual Revision 22020-11-0909 November 2020 Submittal of Quality Assurance Program Manual Revision 2 NL-20-078, Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-11-0909 November 2020 Response to Requests for Additional Information - License Amendment Request to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-076, Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal2020-11-0202 November 2020 Revision of Commitment Related to Nuclear Reactor Safeguards Interim Compensatory Measure - Section B.5.b Issue Regarding Spent Fuel Dispersal NL-20-069, One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency2020-10-0808 October 2020 One-time Scheduler Exemption Request from 10 CFR 50, Appendix E Biennial Emergency Preparedness Exercise Requirements Due to COVID-19 Public Health Emergency NL-20-070, Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-10-0202 October 2020 Response to Requests for Additional Information, License Amendment Request to Revise the Indian Point Nuclear Generating Unit No. 3 Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-067, Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-09-16016 September 2020 Redacted Version of Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-064, 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments2020-09-0101 September 2020 10 CFR 50.59(d)(2) Summary Report of Changes, Tests and Experiments NL-20-060, Status of Remaining Actions for Generic Letter 2004-022020-08-11011 August 2020 Status of Remaining Actions for Generic Letter 2004-02 NL-20-057, Cancellation of Commitment Related to Large Break LOCA Reanalysis2020-07-30030 July 2020 Cancellation of Commitment Related to Large Break LOCA Reanalysis NL-20-0851, 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material2020-07-22022 July 2020 30-Day 10 CFR 21 Notification - Continuously Energized Eaton D26 Relays Could Fail to Deenergize Because of an Organic C3 Insulating Material NL-20-051, Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center2020-07-0707 July 2020 Submittal of Quality Assurance Program Manual, Revision 1 for the Indian Point Energy Center NL-20-052, Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results2020-07-0707 July 2020 Unsatisfactory 10 CFR 26 Fitness-For-Duty Blind Performance Testing Results NL-20-012, Application to Revise Provisional Operating License and Technical Specifications2020-06-30030 June 2020 Application to Revise Provisional Operating License and Technical Specifications NL-20-050, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-06-24024 June 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-041, Registration of Unit 3 Spent Fuel Cask Use2020-05-13013 May 2020 Registration of Unit 3 Spent Fuel Cask Use NL-20-042, Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel2020-05-12012 May 2020 Certifications of Permanent Cessation of Power Operations and Permanent Removal of Fuel from the Reactor Vessel NL-20-033, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2020-04-28028 April 2020 Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-20-038, Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline2020-04-23023 April 2020 Response to U.S. Nuclear Regulatory Commission Region I Letter Regarding Algonquin Incremental Market Project Pipeline NL-20-035, Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-16016 April 2020 Response to Request for Additional Information - Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-034, Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic2020-04-13013 April 2020 Temporary Exemption Request from 10 CFR Appendix R, Section Iii.H Due to COVID-19 Pandemic NL-20-021, Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device2020-03-24024 March 2020 Proposed License Amendment to Revise the Licensing Basis to Incorporate the Installation and Use of a New Auxiliary Lifting Device NL-20-020, Submittal of 2019 Annual Fitness for Duty Performance Data Report Update2020-02-26026 February 2020 Submittal of 2019 Annual Fitness for Duty Performance Data Report Update NL-20-015, Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report2020-02-10010 February 2020 Submittal of 2019 Annual Fitness for Duty Program Performance Data Report and Fatigue Management Program Data Report NL-20-008, Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane2020-01-0606 January 2020 Transmittal of Presentation Slides for Partially Closed Pre-Submittal Meeting to Discuss a Planned License Amendment Request to Replace the Fuel Handling Building Crane NL-19-094, 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report2019-12-16016 December 2019 2018 Annual 10 CFR 50.46 Emergency Core Cooling System Evaluation Changes Report NL-19-084, Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments2019-11-21021 November 2019 Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-093, Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.12019-11-21021 November 2019 Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.1 NL-19-092, Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-11-20020 November 2019 Request for Rescission of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-043, Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.122019-10-22022 October 2019 Request for Partial Exemption from Record Retention Requirements in 10 CFR 50.12 NL-19-073, Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049)2019-10-22022 October 2019 Request for Relaxation of Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events (Order Number EA-12-049) NL-19-078, Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2019-10-22022 October 2019 Supplement to Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-19-091, Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use2019-10-17017 October 2019 Independent Spent Fuel Storage Installation (Isfsi), Registration of Spent Fuel Cask Use NL-19-090, Registration of Unit 2 Spent Fuel Cask Use2019-10-0909 October 2019 Registration of Unit 2 Spent Fuel Cask Use NL-19-079, 50.59(d)(2) Summary Report of Changes, Tests and Experiments2019-09-26026 September 2019 50.59(d)(2) Summary Report of Changes, Tests and Experiments 2021-05-06
[Table view] Category:License-Application for Facility Operating License (Amend/Renewal) DKT 50
MONTHYEARML23024A0462023-01-17017 January 2023 License Amendment Request for the Independent Spent Fuel Storage Installation-Only Security, Training and Qualification, Safeguards Contingency Plan ML22332A0482022-11-22022 November 2022 New York State Alyse Peterson Comments on Completion of Emergency Planning Nd License Amendment Request Prior to Spent Fuel Transfer from Spent Fuel Pools to Casts (Dockets 50-003, 50-247, 50-286) ML22321A1482022-11-17017 November 2022 License Amendment Request to Approve the Independent Spent Fuel Storage Installation-Only Emergency Plan ML22306A1262022-11-0202 November 2022 License Amendment Request to Revise Indian Point Nuclear Generating Unit Nos. 2 and 3 Renewed Facility Licenses and Permanently Defueled Technical Specifications and IP3 Appendix C Technical Specifications to Reflect Permanent Removal of Sp ML22214A1282022-08-0202 August 2022 License Amendment Request to Revise Indian Point Nuclear Generating Unit No. 2 Permanently Defueled Technical Specifications to Modify Staffing Requirements Following Transfer of Spent Fuel to Dry Storage ML22140A1262022-05-20020 May 2022 License Amendment Request - Revise License Condition to Eliminate Cyber Security Plan Requirements ML22035A1212022-02-0404 February 2022 Revision to Holtec Decommissioning International, LLC, License Amendment Request to Revise the Emergency Plan and Emergency Action Level Scheme to Address the Permanently Defueled Condition ML21356B7042021-12-22022 December 2021 License Amendment Request to Revise the Emergency Plan and Emergency Action Level Scheme to Address the Permanently Defueled Condition NL-20-012, Application to Revise Provisional Operating License and Technical Specifications2020-06-30030 June 2020 Application to Revise Provisional Operating License and Technical Specifications ML20078L1402020-04-15015 April 2020 Issuance of Amendment Nos. 62, 293, and 268 Changes to Emergency Plan for Post-Shutdown and Permanently Defueled Condition ML20017A2902020-01-17017 January 2020 Supplement to Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-093, Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.12019-11-21021 November 2019 Proposed Technical Specifications (TS) Changes - Indian Point Nuclear Generating Unit 3 TS SR 3.7.7.2 and TS 3.7.6, Required Action A.1 NL-19-084, Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments2019-11-21021 November 2019 Application for Order Consenting to Transfers of Control of Licenses and Approving Conforming License Amendments NL-19-053, Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051)2019-06-0606 June 2019 Request for Rescission of Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order EA-12-051) NL-19-013, Proposed Technical Specifications Change - Administrative Controls for Permanently Defueled Condition2019-04-15015 April 2019 Proposed Technical Specifications Change - Administrative Controls for Permanently Defueled Condition NL-19-026, Technical Specifications Proposed Change - Permanently Defueled Technical Specifications2019-04-15015 April 2019 Technical Specifications Proposed Change - Permanently Defueled Technical Specifications NL-19-001, License Amendment Request to Revise the Indian Point Energy Center Site Emergency Plan to Address the Permanently Shut Down and Defueled Condition2019-04-15015 April 2019 License Amendment Request to Revise the Indian Point Energy Center Site Emergency Plan to Address the Permanently Shut Down and Defueled Condition CNRO-2019-00003, Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 42019-01-31031 January 2019 Application to Revise Technical Specifications to Adopt TSTF-529 11 Clarify Use and Application Rules, 11 Revision 4 NL-18-034, License Amendment Request- Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions2018-06-20020 June 2018 License Amendment Request- Deletion of Facility Operating License Conditions Related to Decommissioning Trust Provisions NL-17-157, Amendment 19 to License Renewal Application (LRA)2017-12-14014 December 2017 Amendment 19 to License Renewal Application (LRA) NL-17-070, Additional Information for the Review of the Plants License Renewal Application (LRA) Regarding the Containment Leak Rate Program2017-05-31031 May 2017 Additional Information for the Review of the Plants License Renewal Application (LRA) Regarding the Containment Leak Rate Program NL-17-049, Unit Nos., 1, 2, and 3, License Amendment Request - Cyber Security Plan Implementation Schedule2017-04-28028 April 2017 Unit Nos., 1, 2, and 3, License Amendment Request - Cyber Security Plan Implementation Schedule NL-17-035, Proposed License Amendment Regarding Connection of Non-Seismic Boric Acid Recovery System to the Refueling Water Storage Tank2017-04-0707 April 2017 Proposed License Amendment Regarding Connection of Non-Seismic Boric Acid Recovery System to the Refueling Water Storage Tank NL-17-018, Consistency Certification for Entergy Nuclear Indian Point 2 and Entergy Nuclear Indian Point 3 License Renewal Application2017-01-31031 January 2017 Consistency Certification for Entergy Nuclear Indian Point 2 and Entergy Nuclear Indian Point 3 License Renewal Application NL-16-138, Amendment 18 to License Renewal Application2016-12-15015 December 2016 Amendment 18 to License Renewal Application NL-16-118, Indian Point Nuclear Power Plant, Units 2 & 3, Proposed License Amendment Regarding the Inter-Unit Transfer of Spent Fuel2016-12-14014 December 2016 Indian Point Nuclear Power Plant, Units 2 & 3, Proposed License Amendment Regarding the Inter-Unit Transfer of Spent Fuel ML16355A0682016-12-14014 December 2016 Licensing Report on the Inter-Unit Transfer of Spent Nuclear Fuel NL-16-118, Proposed License Amendment Regarding the Inter-Unit Transfer of Spent Fuel2016-12-14014 December 2016 Proposed License Amendment Regarding the Inter-Unit Transfer of Spent Fuel CNRO-2016-00020, Application for Order to Transfer Master Decommissioning Trust from PASNY to ENO, Consenting to Amendments to Trust Agreement, and Approving Proposed License Amendments to Modify and Delete Decommissioning .2016-08-16016 August 2016 Application for Order to Transfer Master Decommissioning Trust from PASNY to ENO, Consenting to Amendments to Trust Agreement, and Approving Proposed License Amendments to Modify and Delete Decommissioning . NL-15-148, Amendment 17 to License Renewal Application (LRA)2015-12-14014 December 2015 Amendment 17 to License Renewal Application (LRA) NL-15-144, License Amendment Request - Conditional Exemption from End-of-Life (Eol) Moderator Temperature Coefficient (Mtc) Measurement2015-12-10010 December 2015 License Amendment Request - Conditional Exemption from End-of-Life (Eol) Moderator Temperature Coefficient (Mtc) Measurement NL-15-144, Indian Point, Units 2 and 3 - License Amendment Request - Conditional Exemption from End-of-Life (Eol) Moderator Temperature Coefficient (Mtc) Measurement2015-12-10010 December 2015 Indian Point, Units 2 and 3 - License Amendment Request - Conditional Exemption from End-of-Life (Eol) Moderator Temperature Coefficient (Mtc) Measurement NL-15-109, Reply to Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-022015-09-0101 September 2015 Reply to Request for Additional Information for the Review of the Indian Point Nuclear Generating Unit Nos. 2 and 3, License Renewal Application, Set 2015-02 NL-15-067, License Amendment Request - Cyber Security Plan Implementation Schedule2015-06-16016 June 2015 License Amendment Request - Cyber Security Plan Implementation Schedule NL-15-021, Proposed License Amendment Regarding a Change to Technical Specification 3.1.4 Reactivity Control Systems Indian Point Unit Number 22015-02-12012 February 2015 Proposed License Amendment Regarding a Change to Technical Specification 3.1.4 Reactivity Control Systems Indian Point Unit Number 2 NL-14-146, Amendment 16 to License Renewal Application (LRA)2014-12-15015 December 2014 Amendment 16 to License Renewal Application (LRA) NL-14-128, Proposed License Amendment Regarding Extending the Containment Type a Leak Rate Testing Frequency to 15 Years2014-12-0909 December 2014 Proposed License Amendment Regarding Extending the Containment Type a Leak Rate Testing Frequency to 15 Years ML14304A7002014-04-30030 April 2014 Annual Energy Outlook 2014 NL-13-145, Proposed License Amendment to Adopt TSTF-510, Revision 2, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection Indian Point Unit Nuclear Generating Unit Nos. 2 and 32014-04-0101 April 2014 Proposed License Amendment to Adopt TSTF-510, Revision 2, Revision to Steam Generator Program Inspection Frequencies and Tube Sample Selection Indian Point Unit Nuclear Generating Unit Nos. 2 and 3 NL-14-035, Proposed Changes to Technical Specifications Regarding Reactor Vessel Pressure/Temperature Limit Curves2014-04-0101 April 2014 Proposed Changes to Technical Specifications Regarding Reactor Vessel Pressure/Temperature Limit Curves NL-14-016, License Amendment Request - Cyber Security Plan Implementation Schedule2014-01-30030 January 2014 License Amendment Request - Cyber Security Plan Implementation Schedule NL-13-131, Amendment 14 to License Renewal Application (LRA)2013-09-26026 September 2013 Amendment 14 to License Renewal Application (LRA) NL-13-077, License Renewal Application-Update to Electrical Meb and Structures Monitoring Program Scope, Aging Management Programs2013-05-0606 May 2013 License Renewal Application-Update to Electrical Meb and Structures Monitoring Program Scope, Aging Management Programs NL-13-015, Proposed License Amendment Regarding Connection of Non Seismic Boric Acid Recovery System to the Refueling Water Storage Tank2013-04-15015 April 2013 Proposed License Amendment Regarding Connection of Non Seismic Boric Acid Recovery System to the Refueling Water Storage Tank ML13116A0082013-04-0909 April 2013 Engineering Evaluation of Postulated RWST Inventory Loss During the Reverse Osmosis Clean-up Skid Process in Accordance to 2-TAP-001-ROS Due to Seismic Event NL-13-046, Amendment 13 to License Renewal Application (LRA) Pertaining to One-Time Inspection and Selective Leaching Programs2013-03-18018 March 2013 Amendment 13 to License Renewal Application (LRA) Pertaining to One-Time Inspection and Selective Leaching Programs ML13046A1662013-02-22022 February 2013 Issuance of Amendment Connecting Non-Seismic Purification System Piping to the Refueling Water Storage Tank NL-12-190, Amendment 12 to License Renewal Application (LRA)2012-12-27027 December 2012 Amendment 12 to License Renewal Application (LRA) NL-12-090, Proposed License Amendment Regarding Connection of Non Seismic Purification Line to Refuel Water Storage Tank2012-08-14014 August 2012 Proposed License Amendment Regarding Connection of Non Seismic Purification Line to Refuel Water Storage Tank NL-12-107, Application to Renew Operating Licenses for Indian Point Nuclear Power Reactors Unit 2 and Unit 3, General Correspondence - NL-12-1072012-08-0808 August 2012 Application to Renew Operating Licenses for Indian Point Nuclear Power Reactors Unit 2 and Unit 3, General Correspondence - NL-12-107 2023-01-17
[Table view] |
Text
{{#Wiki_filter:* Entergx
*===*
Entergy Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel (914) 254-2055 Anthony J Vitale Site Vice President NL-16-138 December 15, 2016 U.S. Nuclear Regulatory Commission Document Control Desk 11545 Rockville Pike, TWFN-2 F1 Rockville, MD 20852-2738
SUBJECT:
Amendment 18 to License Renewal Application (LRA)
Indian Point Nuclear Generating Unit Nos. 2 and 3 Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64
REFERENCES:
- 1. Entergy Letter dated April 23, 2007, F. R. Dacimo to Document Control Desk, "License Renewal Application" (NL-07-039)
- 2. Entergy Letter dated April 23, 2007, F. R. Dacimo to Document Control Desk, "License Renewal Application Boundary Drawings" (NL-07-040)
- 3. Entergy Letter dated April 23, 2007, F. R. Dacimo to Document Control Desk, "License Renewal Application Environmental Report References" (NL-07-041)
- 4. Entergy Letter dated October 11, 2007, F. R. Dacimo to Document Control Desk, "License Renewal Application (LRA)" (NL-07-124)
- 5. Entergy Letter dated November 14, 2007, F. R. Dacimo to Document Control Desk, "Supplement to License Renewal Application (LRA)
Environmental Report References" (NL-07-133)
Dear Sir or Madam:
In accordance with 10 CFR 54.21 (b), each year following submittal of the license renewal application and at least 3 months before scheduled completion of the NRC review, an amendment to the renewal application must be submitted that identifies any change to the CLB of the facility that materially affects the contents of the license renewal application (LRA), including the FSAR supplement. In the referenced letters, Entergy Nuclear Operations, Inc. applied for renewal of the Indian Point Nuclear Generating Units 2 and 3 operating licenses. This letter provides Amendment 18 of the Indian Poiryt Units 2 and 3 license renewal application.
There are no new commitments being made in this submittal.
Should you have any questions concerning this report, please contact Mr. Robert W. Walpole, Licensing Manager, at (914) 254-6710.
NL-16-138 Dockets 50-247 and 50-286 Page 2 of 2
. ~ de;lare!under penalty of perjury that the foregoing is true and correct. Executed on
~ce---{2.-<W--1.5' '2016.
Sincerely, AJV/rl Attachment 1. Annual Update Amendment cc: Mr. Daniel H. Dorman, Regional Administrator, NRC Region I Mr. William Burton, NRC Senior Project Manager, Division of License Renewal Mr. Douglas Pickett, NRR Senior Project Manager Ms. Bridget Frymire, New York State Department of Public Service Mr. John B. Rhodes, President and CEO NYSERDA NRC Resident Inspector's Office
ATTACHMENT 1 TO NL-16-138 ANNUAL AMENDMENT ENTERGY NUCLEAR OPERATIONS, INC.
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 and 3 DOCKET NO. 50-247 and 50-286
NL-16-138 Page 1 of 11 Dockets 50-247 and 50-286 Attachment 1 INDIAN POINT NUCLEAR GENERATING UNIT Nos. 2 AND 3 LICENSE RENEWAL APPLICATION ANNUAL AMENDMENT In accordance with 10 CFR 54.21 (b), each year following submittal of the license renewal application and at least 3 months before scheduled completion of the NRC review, an amendment to the renewal application must be submitted that identifies any change to the CLB of the facility that materially affects the contents of the license renewal application (LRA), including the FSAR supplement. This attachment is the required annual amendment to the LRA.
Amendment 18 is based on a review of documents potentially affecting the CLB during the periods of September 1, 2015 through August 31, 2016.
The review concluded that certain sections of the LRA are affected by changes to CLB documents and other related LRA reviews. The table below summarizes the changes listing the affected system (if applicable), an explanation of the change (including effect on the LRA), and the affected LRA section.
Affected LRA Sections Change LRA Section Affected IP3 - EC 46625 Permanently repaired pipe (line #
Table 3.3.2-17-IP3 1033) with a pressure retaining clamp and using CSI Pipe Wrap-Ply material (carbon fiber) applied on the exterior circumference of the pipe and clamp.
IP2- EC 58208 Install metal flex hoses on IP2 Table 2.3.3-19-39-IP2 hydrogen cooler vent and drain lines Table 3.3.2-19-39-IP2 and upgraded threaded pipe nipple from SCH 40 to SCH 80 IP2- EC 58594 Table 3.3.2-19-44-IP2 Re-route chlorine piping for the north service water bay
NL-16-138 Page 2of11 Dockets 50-247 and 50-286 Attachment 1 Change LRA Section Affected I I I IP3 - EC 59472 & NL-15-014 & RA-15-115 LRA Section 4.2.3 states "Technical Specifications contain pressure/temperature limits valid through 34 EFPY ... ". This EC extends the PIT limits to a lifetime burnup of 37 EFPY.
LRA Section 4.2.3 is revised to eliminate "valid through 34 EFPY."
Section 4.2.3 The validity period for the PIT limits is stated in the Technical Specification section containing the limits. The period of validity can change during normal operations as governed by 10 CFR 50.61 requirements. There is no need to state in the LRA the EFPY for which the limits are applicable. It is sufficient to indicate that the limits, and the period for which the limits are valid, are found in the Technical Specifications.
IP3 - EC 60109 Evaluation to change the Unit 3 Section 3.5.2.2.1.3 FSAR hot penetration cooling criteria Section 3.5.2.2.2.3 using prior Unit 2 Safety Evaluation 94-238-EV and calculation GCC-00021 CR-I P2-2016-5826 Section 2.3.3.4 Correction of 2014 IPEC Annual Section 2.3.2.5 Update(IP-RPT-14-LRD01 Rev 0)
Table 3.2.2-5-IP2 related to EC 42090
NL-16-138 Page 3of11 Dockets 50-247 and 50-286 Attachment 1 Change LRA Section Affected Appendix A UFSAR Appendix B Aging Management Programs and Activities A.2.1.11 Typographical corrections (revise 8.1.12
'cumulative use factor' to 'cumulative usage factor' to agree with Supplement 2 of the Safety Evaluation Report, November 2014)
NL-16-138 Page 4of11 Dockets 50-247 and 50-286 Attachment 1 IPEC LRA changes are shown below.
(Changes are shown as strikethroughs for deletions and underlines for additions)
Table 3.3.2-17-IP3 City Water Summary of Aging Management Review Table 3.3.2-17-IP3: City Water Aging Effect Aging NU REG-Component Intended Table 1 Material Environment Requiring Management 1801 Vol. Notes Type Function Item Management Programs 2 Item Pressure --- --- E 5Qjng Fiberglass Soil (ext) None None bounda!Y 3.5.2.2.1.3 Reduction of Strength and Modulus of Concrete Structures due to Elevated Temperature For Unit 3 containment during normal operation, areas are maintained below a bulk average temperature of 130°F. Piping penetrations through the containment cylinder wall associated with pipes carrying hot fluid are cooled using air-to-air heat exchangers and the pipes are insulated to maintain the temperature in the adjoining concrete below 2GG250°F. NUREG-1801 allows for concrete temperatures higher than 200°F for local areas if tests or calculations are provided to evaluate the reduction in strength. Concrete associated with the Unit 3 hot piping penetrations has been evaluated and determined acceptable at temperatures up to 250°F.
NL-16-138 Page 5of11 Dockets 50-247 and 50-286 Attachment 1 3.5.2.2.2.3 Reduction of Strength and Modulus of Concrete Structures due to ElevatedTemperature For reduction of strength and modulus of concrete structures due to elevated temperatures for Groups 1-5, NUREG-1801 recommends a plant-specific AMP and further evaluation if the general temperature is greater than 150°F or if the local temperature is greater than 200°F. During normal operation, bulk average temperature of Groups 1-5 concrete elements is maintained below 150°F and local temperatures remain below 200250°F. NUREG-1801 allows for concrete temperatures higher than 200°F for local areas if tests or calculations are provided to evaluate the reduction in strength.
Concrete associated with the hot piping Unit 3 penetrations has been evaluated and determined acceptable at temperatures up to 250°F.
Table 2.3.3-19-39-IP2 Service Water System Nonsafety-related Components Potentially Affecting Safety Functions Subject to Aging Management Review Component Type Intended Function Flex joint Pressure boundary
NL-16-138 Page 6of11 Dockets 50-247 and 50-286 Attachment 1 Table 3.3.2-19-39-IP2 Service Water System Nonsafety-Related Components Potentially Affecting Safety Functions Summary of Aging Management Review Table 3.3.2-19-39-IP2: Service Water System Aging Effect Aging NU REG-Component Intended Table 1 Material Environment Requiring Management 1801 Vol. Notes Type Function Item Management Programs 2 Item Vll.F1-1 Pressure Stainless Condensation Loss of External Surfaces 3.3.1-27 Flex joint (A-09) £ boundar:y steel (ext) material Monitoring
NL-16-138 Page 7of11 Dockets 50-247 and 50-286 Attachment 1 Table 3.3.2-19-44-IP2 Chlorination System Nonsafety-Related Components Potentially Affecting Safety Functions Summary of Aging Management Review Table 3.3.2-19-44-IP2: Chlorination System Aging Effect Aging NU REG-Component Intended Table 1 Material Environment Requiring Management 1801 Vol. Notes Type Function Item Management Programs 2 Item Pressure Air-indoor Piping Plastic None None ---
boundary (ext) --- ---
Pressure Treated water Piping Plastic boundary (int) None None --- --- ---
Pressure Air-indoor Valve body Plastic boundary (ext) None None --- --- ---
Pressure Treated water Valve body Plastic boundary (int) None None --- --- ---
4.2.3 Pressure-Temperature Limits Technical Specifications contain pressure/temperature limits valid through 34EFPY including the effects of the stretch power uprate.
At present, plate 82803-3 with an initial RTNDT of 74 °F restricts operation (P-T) in the 150-250°F range. Resolution to the P-T operating window is a current operating term issue and will be resolved three years prior to reaching the RTPTS screening criterion per 10 CFR 50.61 requirements.
NL-16-138 Page 8of11 Dockets 50-247 and 50-286 Attachment 1 The P-T limit curves will continue to be updated, as required by Appendix G of 10 CFR Part 50 or as operational needs dictate. This
. updating will assure that the operational limits remain valid through the period of extended operation. Additional P-T limit analysis is not required at this time. Maintaining the P-T limit curves in accordance with Appendix G of 10 CFR 50 assures that the effects of aging on the intended function(s) will be adequately managed for the period of extended operation consistent with 10 CFR 54.21 (c)(1 )(iii).
2.3.2.5 Containment Penetrations System Descrjption Containment penetrations have the following intended function for 10CFR54.4( a)( 1).
- Prevent release of radioactivity to outside environment.
Containment penetrations have no intended functions for 10CFR54.4(a)(2). or (a)(3).
Containment penetrations have the following intended funstion for 10CFR54.4(a)(3).
- Provide optional eapabilitv. located in the CCR to bypass the existing manual containment isolation valves allO'vving the instrument air flow to reaeh the Fan Mouse Safe Shut Down Panel in ease of fire inside containment to support the Alternate Safe Shutdmun System U\SSS).
NL-16-138 Page 9of11 Dockets 50-247 and 50-286 Attachment 1 Table 3.2.2-5-IP2 Containment Penetrations Summary of Aging Management Review Table 3.2.2-5-IP2: Containment Penetrations Aging Effect Aging Componen Intended NUREG-1801 Material Environment Requiring Management Table 1 Item Notes tType Function Vol. 2 Item Management Programs
+1:18iR~ PFess1:1Fe Stai Riess ,c,*<IF tFeateEI Nooe Nooe - - G ee1:1RElapt steel fffi!t Val>.ie eeEl>r PFess1:1Fe A" Stai Riess r<IF tFeateEI Nooe Nooe - - G ee1:1RElaPr steel fiffi1
NL-16-138 Page 10of11 Dockets 50-247 and 50-286 Attachment 1 2.3.3.4 Compressed Air
System Description
The compressed air systems include the instrument air (IA) and station air (SA) subsystems.
Instrument Air The IA system has the following intended functions for 10 CFR 54.4(a)(3).
- Provide a source of compressed gas for pneumatically operated components for the Appendix R event (10 CFR 50.48).
*Enable charging pump 21 to be run at high speed without the need for operator actions outside the CCR in response to a fire for the Appendix R event (1 O CFR 50.48).
- Provide optional capability. located in the CCR. to bypass the existing manual containment isolation valves allowing the instrument air flow to reach the Fan House Safe Shut Down Panel in case of fire inside containment to support the Alternate Safe Shutdown System (ASSS).
*Support safe shutdown in the event of a fire in the auxiliary feed pump room (10 CFR 50.48) (see Section 2.3.4.5).
A.2.1.11 Fatigue Monitoring Program The Fatigue Monitoring Program is an existing program that tracks the number of critical thermal and pressure transients for selected reactor coolant system components. The program ensures the validity of analyses that explicitly analyzed a specified number of fatigue transients by assuring that the actual effective number of transients does not exceed the analyzed number of transients. The program provides for update of the fatigue usage calculations to maintain a cumulative use usage factor fCUFl of< 1.0 for the period of extended operation. For the locations identified in Section A.2.2.2.46, updated calculations will account for the effects of the reactor water environment.
NL-16-138 Page 11 of 11 Dockets 50-247 and 50-286 Attachment 1 8.1.12 Fatigue Monitoring Program Description The Fatigue Monitoring Program is an existing program that tracks the number of critical thermal and pressure transients for selected reactor coolant system components. The program ensures the validity of analyses that explicitly analyzed a specified number of fatigue transients by assuring that the actual effective number of transients does not exceed the analyzed number of transients.
The program provides for update of the fatigue usage calculations to maintain a cumulative usage factor {CU Fl of < 1.0 for the period of extended operation. For the locations identified in LRA Table 4.3-13 (IP2) and LRA Table 4.3-14 (IP3}, updated calculations will account for the effects of the reactor water environment. These calculation updates are governed by Entergy's 10 CFR 50 Appendix B Quality Assurance (QA) program and include design input verification and independent reviews ensuring that valid assumptions, transients, cycles, external loadings, analysis methods, and environmental fatigue life correction factors will be used in the fatigue analyses.}}