NL-13-114, Implementation of License Renewal Regulatory Commitments

From kanterella
(Redirected from NL-13-114)
Jump to navigation Jump to search
Implementation of License Renewal Regulatory Commitments
ML13247A175
Person / Time
Site: Indian Point Entergy icon.png
Issue date: 08/28/2013
From: Dacimo F
Entergy Nuclear Northeast
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-13-114
Download: ML13247A175 (2)


Text

Entergy Nuclear Northeast Indian Point Energy Center

---Entergy 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel (914) 254-2055 Fred Dacimo Vice President Operations License Renewal NL-13-114 August 28, 2013 U.S. Nuclear Regulatory Commission Document Control Desk 11545 Rockville Pike, TWFN-2 F1 Rockville, MD 20852-2738

SUBJECT:

Implementation of License Renewal Regulatory Commitments Indian Point Nuclear Generating Unit No. 2 Docket No. 50-247 License No. DPR-26

REFERENCES:

1. NRC letter, "Indian Point Nuclear Generating Unit No. 2 - Actions to be Completed Prior to Entering the Period of Timely Renewal", dated August 19, 2013
2. Entergy letter, NL-1 3-052, "Reply to Request for Additional Information Regarding the License Renewal Application - Indian Point Nuclear Generating Unit Nos. 2 & 3", dated May 7, 2013

Dear Sir or Madam:

In accordance with Reference 1, Entergy Nuclear Operations, Inc. confirms that the Unit 2 license renewal commitments of Reference 2, required to be implemented prior to entry into the period of extended operation, are complete.

There are no new regulatory commitments in this submittal.

If you have any questions, or require additional information, please contact Mr. Robert Walpole at 914-254-6710.

I detlare under penalty of perjury that the foregoing is true and correct. Executed on 2013.

Sir cc: next page PF/2~6

Docket No. 50-247 NL-13-114 Page 2 of 2 cc: Mr. William Dean, Regional Administrator, NRC Region I Mr. Sherwin E. Turk, NRC Office of General Counsel, Special Counsel Mr. Dave Wrona, NRC Branch Chief, Engineering Review Branch I Ms. Kimberly Green, NRC Sr. Project Manager, Division of License Renewal Mr. Douglas Pickett, NRR Senior Project Manager Ms. Bridget Frymire, New York State Department of Public Service NRC Resident Inspector's Office Mr. Francis J. Murray, Jr., President and CEO NYSERDA