ND-19-1257, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.5.01.03b (Index Number 512)

From kanterella
Jump to navigation Jump to search
Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.5.01.03b (Index Number 512)
ML19290H287
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 10/17/2019
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 2.5.0103b, ND-19-1257
Download: ML19290H287 (6)


Text

Michael J. Yox 7825 River Road

^Southern Nuclear Regulatory Affairs Director Vogtle 3 & 4 Waynesboro, GA 30830 706-848-6459 tel OCT 1 7 2019 Docket Nos.: 52-026 ND-19-1257 10 CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 Notice of Uncompleted ITAAC 225-clavs Prior to Initial Fuel Load Item 2.5.01.03b [Index Number 5121 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of October 11, 2019, Vogtle Electric Generating Plant(VEGP) Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.5.01.03b [Index Number 512] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed.

All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted, Michael J. Yox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 4 Completion Plan for Uncompleted ITAAC 2.5.01.03b [Index Number 512]

MJY/SBB/sfr

U.S. Nuclear Regulatory Commission ND-19-1257 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power ComDanv Mr. Peter P. Sena III (w/o enclosures)

Mr. D. L. McKinney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. D. H. Jones(w/o enclosures)

Mr. G. Chick Mr. M. Page Mr. M. J. Vox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. L. Hughes Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Requlatorv Commission Mr. W.Jones(w/o enclosures)

Mr. F. D. Brown Mr. C. P. Patel Mr. G. J. Khouri Ms. S. E. Temple Mr. N. D. Karlovich Mr. A. Lerch Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert M C. Welch M J. Gaslevic M V. Hall M G. Armstrong Ms. T. Lamb M M. Webb M T. Fredette M C. Weber M S. Smith Qqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen

U.S. Nuclear Regulatory Commission ND-19-1257 Page 3 of 3 Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Orlani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-19-1257 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-19-1257 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 4 Completion Plan for Uncompleted ITAAC 2.5.01.03b [Index Number 512]

U.S. Nuclear Regulatory Commission ND-19-1257 Enclosure Page 2 of 3 ITAAC Statement Design Commitment 3.b) The display hardware of the DAS uses a different display device than that used in the RMS.

Inspections/Tests/Analvses Inspection of the as-built DAS and RMS display hardware will be performed.

Acceptance Criteria The DAS display hardware is different than the display hardware used in the RMS. The difference may be a different design, use of different component types, or different manufacturers.

ITAAC Completion Description Inspection of the as-built Diverse Actuation System (DAS)and Protection and Safety Monitoring System (RMS)display hardware is performed to demonstrate that display hardware used in the DAS is different than that used in the RMS. The display hardware for the DAS and RMS is inspected and compared with respect to whether there is a different hardware design, use of different component types, or different manufacturers.

The results of the inspections are documented in the Principal Closure Document XXX (Reference 1) supporting the ITAAC 2.5.01.03b Completion Package (Reference 2). The results of the inspection show that the DAS display hardware is different than the RMS display hardware in either design, use of different component types, or different manufacturers.

Principal Closure Document XXX is available for NRC inspection as part of the ITAAC 2.5.01.03b Completion Package.

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-19-1257 Enclosure Page 3 of 3 References(available for NRG inspection^

1. Principal Closure Document XXX
2. ITAAC 2.5.01.03b Completion Package
3. NEI 08-01,"Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"