ND-17-2031, Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.2.00.01d (Index Number 743)

From kanterella
Jump to navigation Jump to search
Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 3.2.00.01d (Index Number 743)
ML17362A079
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 12/21/2017
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ND-17-2031
Download: ML17362A079 (7)


Text

Michael J. Yox 7825 River Road Regulatory Affairs Director Waynesixrro, GA 30830 Southern Nuclear Vogtie 3 & 4 706-848-6459 tei 410-474-8587 ceii myox@southernco.com DEC 2 12017 Docket Nos.: 52-025 52-026 ND-17-2031 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtie Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 3.2.00.01 d [Index Number 7431 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of November 28, 2017, Vogtie Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.2.00.01 d

[Index Number 743] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, oranalyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

JilVlQftcla Michael J. Yox Regulatory Affairs Director Vogtie 3 &4

U.S. Nuclear Regulatory Commission ND-17-2031 Page 2 of 4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 3.2.00.01 d [Index Number 743]

MJY/LBP/amw

U.S. Nuclear Regulatory Commission ND-17-2031 Page 3 of 4 To:

Southern Nuclear Operating Company I Georgia Power Companv Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Rauckhorst (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKinney Mr. M. J. Vox Mr. D. L. Fulton Mr. J. D. Williams Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. 0. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. C. Chamberlain Mr. D. R. Culver Mr. R. L. Belike Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reaulatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. T. C. Brimfield Mr. A. J. Lerch Mr. C. J. Even Ms. V. L. Ordaz Mr. B. J. Kemker Ms. A. E. Rivera-Varona Oalethorpe Power Corporation Mr. K. T. Haynes Mr. R. B. Brinkman Municipal Electric Authorltv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson

U.S. Nuclear Regulatory Commission ND-17-2031 Page 4 of 4 Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. 8. DiTommaso Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hosier, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch Bingham

U.S. Nuclear Regulatory Commission ND-17-2031 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-17-2031 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 3.2.00.01 d [Index Number 743]

U.S. Nuclear Regulatory Commission ND-17-2031 Enclosure Page 2 of 3 ITAAC Statement Desion Commitment

1. The HFE verification and validation program is performed in accordance with the HFE verification and validation implementation plan and includes the following activities:

d) Issue resolution verification Insoections/Tests/Analvses d) An evaluation of the implementation of the HFE design issue resolution verification will be performed.

Acceotance Criteria d) A report exists and concludes that: HFEdesign issue resolution verification was conducted in conformance with the implementation plan and includes verification that human factors issues documented in the design issues tracking system have been addressed in the final design.

ITAAC Completion Description Multiple ITAAC are performed to confirm that the Human Factors Engineering (HFE) Verification and Validation (V&V) program is performed in accordance with the HFE V&V implementation plan.

The subject ITAAC performs an evaluation of the implementation of the HFE design issue resolution verification.

Human Engineering Discrepancies (HEDs) are departures ofthe API000 design from HFE design guidance and/orhuman performance criteria as identified during the execution of HFE V&V activities. The objective of the HFE issue resolution verification is to ensure that HEDs are documented, tracked, and adequately addressed in the final API000 design. The HFE issue resolution verification is conducted in accordance with "API 000 Human Factors Engineering Discrepancy Resolution Process", APP-OCS-GEH-420 (Reference 1).

The HED plan for the API000 plantwas developed based on the information and guidance described in NUREG-0711, "Human Factors Engineering Program Review Model". The overall objective ofthe HFE design issue resolution verification is to ensure that the API000 design attains a high standard of human factors adequacy and thereby contributes to the safety, operability and maintainability of the plant. The HEDs identified during previous HFE V&V activities and ITAAC completion are prioritized and placed into the Human Factors Tracking System and assigned to a specialist or relevant group for resolution.

For HED design resolutions associated with the HFE Design Verification, the HFE Task Support Verification, or the HFE Integrated System Validation, independent verifiers will evaluate the Human-System Interface (HSI) design changes using the same standards, guidance and methodology as described in the corresponding verification plan. The purpose ofthe evaluation is to provide reasonable assurance that the HSI resources and Operations and Controls Centers Systems (OCS) designs satisfy the applicable criteria.

The results of the HFE issue resolution process are documented in the Principal Closure Document APP-OCS-GER-420 (Reference2) and conclude that the HFE design issue resolution verification is

U.S. Nuclear Regulatory Commission ND-17-2031 Enclosure Page 3 of 3 conducted In conformance with the Implementation plan and Includes verification that human factors Issues documented In the design Issues tracking system are addressed In the final design.

References 1 and 2 are available for NRG Inspection as part of the Unit 3 and Unit 4 ITAAC 3.2.00.01 d Completion Packages (References 3 and 4).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

References (available for NRG inspection)

1. APP-OCS-GEH-420, "API000 Human Factors Engineering Discrepancy Resolution Process"
2. APP-OCS-GER-420, "API 000 Human Factors Engineering Issue Resolution Verification Report"
3. XXX, "Completion Package for U3 ITAAC 3.2.00.01 d [Index Number 743]"
4. YYY, "Completion Package for U4 ITAAC 3.2.00.01 d [Index Number 743]"
5. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"