Email Dated 1/21/26 from Ngarcia Santos (NRC) to Mrose (Inc), Follow Up Question to RAI-M-1,Materials Evaluation, SAR Drawing IR100ST-D, Model No. IR-100 ST, CoC No. 9385
ML26021A162
Person / Time
Site: 07109385
Issue date: 01/21/2026
From: Garcia-Santos N, Christopher Sydnor
Division of Fuel Management
To: Maret Rose
Industrial Nuclear Co
Shared Package
ML26021A160 List:
References
001029, L-2024-NEW-0008
Download: ML26021A162 (0)


Text

From:

Norma Garcia Santos To:

Mike Rose; rlm52 Cc:

Yoira Diaz Sanabria; Lisa Regner; Christopher Sydnor

Subject:

Follow Up Question, Model No. IR-100 ST, Materials Evaluation, CoC No. 9385 Date:

Wednesday, January 21, 2026 12:32:00 PM Good afternoon,

The staff has a follow up request related to the materials evaluation of the application for Model No. IR-100 ST package. The staff is asking to revise the SAR Drawing No. IR100ST-D, Revision 1, because the last paragraph of your response to RAI M-1 (top of page 13 of the October 01, 2025, RAI response document, ML25274A104) stated the following:

The specific LiFePO4 power cells identified in Section 1.2.1 of the SAR have been added to Section A-A and the parts list on SAR Drawing IR100ST-D, Rev. 1. Note that these power cells are the only lithium power cells that are authorized in the PM Tag Assembly for the IR-100ST package.

Nevertheless, the response provided to the staff did not include the revised drawing with the battery specification as committed in the RAI response, as stated above. This drawing will be referenced in the CoC and will be part of the certification basis for the package.

Therefore, the staff needs to review the drawings to ensure that these are accurate and complete.

Please feel free to reach out to me if you have any questions about this request.

Thanks in advance, Norma Garcia Santos Project Manager U.S. NRC Email: Norma.GarciaSantos@nrc.gov Phone No. 301-415-6999