Meeting Briefing Package/Handouts for Orano Enrichment USA, Ike Enrichment Facility, Pre-application Meeting - Safety Program Integrated Safety Analysis, December 11, 2025, NRC Headquarters - Rockville, MD
ML25338A290
Person / Time
Site: 07007038
Issue date: 12/11/2025
From:
Orano Enrichment USA
To:
Office of Nuclear Material Safety and Safeguards
References
COR-IKE-2025-10001, EPID L-2024-NEW-0007
Download: ML25338A290 (0)


Text

Orano Enrichment USA IKE Enrichment Facility Pre-application Meeting - Safety Program Integrated Safety Analysis December 11, 2025 NRC Headquarters - Rockville, MD OPI 0 UNRESTRICTED

INTRODUCTION GENERAL INFORMATION PROCESS SPECIFIC INFORMATION IFROFS CONCLUSION

Introduction 00

IKE Enrichment Facility - Pre-application Meeting - Safety Program Integrated Safety Analysis 4

Orano Enrichment USA 00 Headquartered in Bethesda, MD, Orano USA is a leading supplier of advanced reactor services, nuclear fuel materials, used fuel management, decommissioning, decontamination, and radwaste treatment solutions to U.S. commercial and federal customers.

  • Letter of Intent
  • Docket 70-7035
  • Kickoff meeting
  • Pre-application activities
  • Environmental Review
  • Safety and Safeguards Review
  • Issue Materials License Application Review 2026-2027
  • Site preparation
  • Facility construction
  • Pre-operation readiness review Build and Startup 2026-2031 Orano Enrichment USA, LLC, created to build, commission and operate the Chemistry and Enrichment Facilities in the US.

IKE Enrichment Facility - Pre-application Meeting - Safety Program Integrated Safety Analysis 5

IKE Program Facility planned for Idaho Falls, ID License Application accepted Materials License SNM-2015 Issued Project terminated due to low demand due to cancelled reactor projects Eagle Rock Enrichment Facility 00 Orano has initiated exclusive discussions to establish a future uranium enrichment facility at a Department of Energy-owned site in Oak Ridge, Tennessee.

Pre-application activities started IKE Enrichment Facility 2004 2008 2011 2014 2024 2025 IKE is comparable to EREF, and GB2 is the reference plant in operation in France since 2011 EREF GB2

IKE Enrichment Facility - Pre-application Meeting - Safety Program Integrated Safety Analysis 6

Meeting Objectives Integrated Safety Analysis Provide an overview of conduct the integrated safety analysis and ISA Summary.

Management Measures Provide an overview of management measures to ensure compliance with the performance requirements of § 70.61 for an enrichment facility.

Review quality control graded approach for IROFS.

00 Focus on ISA and Management Measures

IKE Enrichment Facility - Pre-application Meeting - Safety Program Integrated Safety Analysis 7

Project Team 00 Orano Enrichment USA is a large multi-discipline project team working on design and licensing of IKE Enrichment Facility.

ISA and Management Measures

Lionel Antognelli, VP Engineering and Projects

Peter Vescovi, Licensing Manager / QA Manager

Matt Lang, Safety System Engineer

Tevor Turner, Senior Quality Assurance Engineer