Letter Sequence Meeting |
|---|
|
Administration
- Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting, Meeting
|
MONTHYEARML24313A0792024-11-0808 November 2024 Request a Change of Name for Orano USA, LLC License Application, (Docket 07007038, EPID L-2024-NEW-0007) Project stage: Other ML24313A2182024-11-0808 November 2024 Request a Meeting for Orano Enrichment USA, LLC, License Application Project stage: Meeting ML25029A2522025-01-29029 January 2025 Orano Enrichment USA, LLC, Ike Enrichment Facility - Letter of Intent – License Application Project stage: Other ML25036A3412025-02-0505 February 2025 Environmental Report Exemption Request for Orano Enrichment USA LLC, Ike Enrichment Facility Project stage: Request ML25037A2432025-02-0606 February 2025 Request a Meeting for Orano Enrichment USA, LLC, License Application, Environmental Report Project stage: Meeting ML25038A0072025-02-27027 February 2025 Orano Enrichment: Pre-Application Meeting - Environmental Report Project stage: Meeting ML25094A0032025-04-0303 April 2025 Orano Enrichment USA, LLC, Ike Enrichment Facility, Request for a Pre-Application Meeting for Electrical Distribution and Instrumentation & Controls Project stage: Meeting ML25084A2162025-04-0808 April 2025 Summary of February 27, 2025, Partially Closed Meeting with Orano Enrichment USA, LLC Project stage: Meeting ML25142A0022025-05-22022 May 2025 Orano Enrichment USA LLC - Discussion of Physical Protection and Classified Information Project stage: Other ML25142A0012025-05-22022 May 2025 Orano Enrichment USA, LLC - Request for a Pre-Application Meeting for Physical Protection and Classified Information Project stage: Meeting ML25154A4432025-06-0303 June 2025 Orano Enrichment USA, LLC - Affidavit Project stage: Other ML25174A1312025-06-20020 June 2025 Request for a Pre-Application Meeting for ISA; Management System, and MC&A Project stage: Meeting ML25184A1572025-07-0808 July 2025 Summary of Orano-NRC April 24, 2025 Pre-Application Meeting Project stage: Meeting ML25238A2072025-08-0707 August 2025 Orano Enrichment USA, LLC, Enrichment Facility Pre-application Meeting Structural Codes and Standards Project stage: Meeting ML25238A2062025-08-0707 August 2025 Orano Enrichment USA, LLC, Request for a Pre-Application Meeting Structural Codes and Standards Project stage: Meeting ML25258A0932025-09-0909 September 2025 Orano USA, LLC - Legal Succession of Areva by Orano for the Purpose of the Treaty of Paris Project stage: Other ML25337A0012025-12-0202 December 2025 Orano Enrichment USA, LLC - Request for a Pre-Application Meeting Safety Program - Integrated Safety Analysis & Management Measures Project stage: Meeting ML25338A2902025-12-11011 December 2025 Meeting Briefing Package/Handouts for Orano Enrichment USA, Ike Enrichment Facility, Pre-application Meeting - Safety Program Integrated Safety Analysis, December 11, 2025, NRC Headquarters - Rockville, MD Project stage: Meeting 2025-04-03
[Table View] |
Text
May 22, 2025 Cor. #: OE-25-0006 Attention: Document Control Desk Director, Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Orano Enrichment USA LLC 4747 Bethesda Avenue Suite 1001 Bethesda, MD 20814
Subject:
Request for a Pre-Application Meeting for Physical Protection and Classified Information (Docket #: 07007038, EPID #: L-2024-NEW-0007)
Orano Enrichment USA LLC requests a closed meeting to discuss Physical Protection and Classified Information for the IKE Enrichment Facility to be in Oak Ridge, Tennessee. An agenda for the meeting with a list of items to be discussed is enclosed.
Enclosed you will find the meeting presentation provided containing proprietary information to be withheld from public access. An affidavit is enclosed as required by 10 CFR 2.390 of the Commissions regulations for withholding this information.
Should the NRC staff require additional information, please do not hesitate to contact me at 336-420-8325, or by email at peter.vescovi@orano.group.
Sincerely, Peter Vescovi Licensing Manager www.orano.group 1
OPI 0 UNRESTRICTED when separated from OPI 1 RESTRICTED or ORANO PROPRIETARY enclosures.
CC:
Osiris Siurano-Perez, USNRC/NMSS/DFM/FFLB Lionel Antognelli, VP Engineering and Projects, Orano Enrichment USA Enc:
- 1) Meeting Agenda, IKE Enrichment Facility Pre-application meeting-Physical Protection and Classified Information
- 2) IKE Enrichment Facility Pre-application meeting, Physical Protection and Classified Information (PROPRIETARY)
- 3) Affidavit Pursuant to 10 CFR 2.390 www.orano.group 2