Updated Inspection Plan for South Teexas Project Electric Generating Station, Units 1 and 2 (Report 05000498/2025005 and 05000499/2025005)
ML25227A050
Person / Time
Site: South Texas, 07201041  STP Nuclear Operating Company icon.png
Issue date: 08/18/2025
From: Geoffrey Miller
NRC/RGN-IV/DORS/PBA
To: Kharrl C
South Texas
References
IR 2025005
Download: ML25227A050 (1)


Text

August 18, 2025

SUBJECT:

UPDATED INSPECTION PLAN FOR SOUTH TEXAS PROJECT ELECTRIC GENERATING STATION, UNITS 1 AND 2 (REPORT 05000498/2025005 AND 05000499/2025005)

Dear Charles Kharrl:

The enclosed inspection plan lists the inspections scheduled through June 30, 2027, for the South Texas Project Electric Generating Station, Units 1 and 2. The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. As discussed in SECY-25-0045, Recommendations for Revising the Reactor Oversight Process, dated June 5, 2025, (ML25042A278), the NRC determined that a broad, comprehensive review of the Reactor Oversight Process (ROP) is necessary to reflect improvements in industry performance and advancements in technology. The outcome of the comprehensive review and recommendations to revise the ROP baseline inspection program, when approved by the NRC Commission, will require a revision to this inspection plan. The NRC will contact you as soon as possible to discuss any revisions after the new baseline inspection program is implemented. The Regional Administrator has approved the staffs plan to conduct Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal, for each unit at your facility as indicated in the enclosed inspection plan.

As we communicated to you in our Annual Assessment Letter, dated March 11, 2025 (ML25062A164), the NRC plans to conduct a supplemental inspection in accordance with IP 95001, Supplemental Response to Action Matrix Column 2 (Regulatory Response) Inputs.

This inspection will be scheduled when you notify the NRC of your readiness.

During the last assessment cycle, the NRC had identified a cross-cutting theme in the Human Performance area in accordance with Inspection Manual Chapter 0305 because the inspectors had identified six findings with the Avoid Complacency cross-cutting aspect in this area. In the current assessment cycle this cross-cutting theme no longer exists.

This letter and its enclosure will be made available for public inspection and copying at ADAMS Public Documents l NRC.gov and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding. Please contact Patricia Vossmar of my staff at (817) 200-1144 with any questions you have regarding this letter.

Sincerely, Geoffrey B. Miller, Director Division of Operating Reactor Safety Docket Nos. 05000498; 05000499; 07201041 License Nos. NPF-76 and NPF-80 Enclosure:

Inspection Plan Distribution:

cc w/ encl: Distribution via LISTSERV Signed by Miller, Geoffrey on 08/18/25

ML25227A050

SUNSI Review By: RLB

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available OFFICE SPE:DORS/PBA BC:DORS/PBA D:DORS NAME RBywater PVossmar GMiller SIGNATURE

/RA/

/RA/

/RA/

DATE 08/15/25 08/18/25 08/18/25

Site Inspection Activity Plan South Texas Project 07/01/2025 - 06/30/2027 Unit Start End Activity CAC Title Staff Count Comprehensive Engineering Team Inspection - South Texas

1,2 7/14/2025 7/18/2025 IP 71111.21M 000713 Comprehensive Engineering Team Inspection 1,2 7/28/2025 8/1/2025 IP 71111.21M 000713 Comprehensive Engineering Team Inspection STP 2025 BRQ

1,2 8/3/2025 8/9/2025 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance Security Access Control (71130.02), Security Plan Changes (71130.09), Security PIV (71151)

1,2 9/8/2025 9/12/2025 IP 71130.02 000734 Access Control 1,2 9/8/2025 9/12/2025 IP 71130.09 001656 Security Plan Changes 1,2 9/8/2025 9/12/2025 IP 71151 001338 Performance Indicator Verification STP 2025 INITIAL EXAM

1,2 8/24/2025 8/30/2025 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 9/28/2025 10/11/2025 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Inservice Inspection-STP (U2)

2 10/13/2025 10/24/2025 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 1,4,PI - STP

1,2 10/13/2025 10/17/2025 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 10/13/2025 10/17/2025 IP 71124.04 000728 Occupational Dose Assessment 1,2 10/13/2025 10/17/2025 IP 71151 000746 Performance Indicator Verification License Renewal Inspection 71003 - STP Unit 2 (Phase 1)

2 10/19/2025 10/25/2025 IP 71003 000687 Post-Approval Site Inspection for License Renewal Inservice Inspection - STP (U1)

1 3/30/2026 4/10/2026 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 1,3,PI - STP

1,2 3/30/2026 4/3/2026 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls 1,2 3/30/2026 4/3/2026 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation 1,2 3/30/2026 4/3/2026 IP 71151 000746 Performance Indicator Verification MC&A - STP

1,2 6/22/2026 6/26/2026 IP 71130.11 000742 Material Control and Accounting (MC&A)

South Texas Project 2026 PI&R

1,2 8/17/2026 8/21/2026 IP 71152B 000747 Problem Identification and Resolution 1,2 8/24/2026 9/4/2026 IP 71152B 000747 Problem Identification and Resolution STP 2026 INITIAL EXAM

Prepared on 8/13/2025 1:33:43 PM 1 of 2

Site Inspection Activity Plan 1,2 8/9/2026 8/15/2026 OV 000956 FB-OR-Onsite Validation Of Initial License Examination (OV)

1,2 9/13/2026 9/26/2026 EXAD 000500 FB-OR-Initial License Exam Administration (EXAD)

Age-Related Degradation Inspection - South Texas Project

1,2 9/14/2026 9/18/2026 IP 71111.21N.04 001832 Age-Related Degradation 1,2 9/28/2026 10/2/2026 IP 71111.21N.04 001832 Age-Related Degradation Security 71130.02/.07/.08

1,2 9/14/2026 9/17/2026 IP 71130.02 000734 Access Control 1,2 9/14/2026 9/17/2026 IP 71130.07 000739 Security Training 1,2 9/14/2026 9/17/2026 IP 71130.08 000740 Fitness-For-Duty Program 1,2 9/14/2026 9/17/2026 IP 71130.09 001656 Security Plan Changes 1,2 9/14/2026 9/17/2026 IP 71151 001338 Performance Indicator Verification EP Exercise & PI Inspection (2026) - STP

1,2 10/19/2026 10/23/2026 IP 71114.01 000716 Exercise Evaluation 1,2 10/19/2026 10/23/2026 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1,2 10/19/2026 10/23/2026 IP 71151 001397 Performance Indicator Verification Cybersecurity - STP

1,2 10/19/2026 10/23/2026 IP 71130.10 000741 Cybersecurity RP 5,8

1,2 11/16/2026 11/20/2026 IP 71124.05 000729 Radiation Monitoring Instrumentation 1,2 11/16/2026 11/20/2026 IP 71124.08 000732 Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, & Transportation FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - STP

1,2 1/4/2027 1/8/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1,2 2/1/2027 2/5/2027 IP 71130.03 000735 Contingency Response - Force-On-Force Testing License Renewal 71003-STP (Phase 2)

1,2 1/25/2027 2/12/2027 IP 71003 000687 Post-Approval Site Inspection for License Renewal Inservice Inspection-STP (U2)

2 3/29/2027 4/10/2027 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

RP 6,7 - STP

1,2 5/3/2027 5/7/2027 IP 71124.06 000730 Radioactive Gaseous and Liquid Effluent Treatment 1,2 5/3/2027 5/7/2027 IP 71124.07 000731 Radiological Environmental Monitoring Program Prepared on 8/13/2025 1:33:43 PM 2 of 2