MONTHYEARML23321A0362023-11-16016 November 2023 Submittal of Terrapower Plume Exposure Pathway Emergency Planning Zone Methodology Topical Report, Revision 1 Project stage: Request ML24187A1172024-07-15015 July 2024 Us Sfr Owner, LLC - Audit Plan for a General Audit of the Kemmerer Unit 1 Construction Permit Application Project stage: Other ML24213A2682024-07-31031 July 2024 Us Sfr Owner, Llc–Kemmerer Unit 1 Environmental Report Audit Plan - CAC No. 001912; EPID No. L-2024-LNE-0002 Project stage: Other ML24221A3412024-08-0707 August 2024 Comprehensive Vibration Assessment Program (Cvap) Strategy Presentation Materials Project stage: Request ML24304A9772024-11-25025 November 2024 Us Sfr Owner, LLC – Kemmerer Power Station Unit 1 Construction Permit Application Revised Resource Estimate (Epids: L-2024-CPS-0000 and L-2024-LNE-0002) Project stage: Other ML25055A0192025-02-26026 February 2025 Terrapower, LLC, Kemmerer Power Station, Unit 1, Construction Permit Application Review Status (Epids: L-2024-CPS-0000 and L-2024-LNE-0002) Project stage: Other ML25045A0962025-03-18018 March 2025 Summary of the August 22, 2024, Partially Closed Meeting with Terrapower, LLC to Discuss Comprehensive Vibration Assessment Program for the Natrium Design Project stage: Meeting ML25115A0482025-06-16016 June 2025 Terrapower Deis FRN - OGC and LRC Comments Project stage: Request ML25115A0072025-06-18018 June 2025 Notice of Availability of the Environmental Impact Statement for the Construction Permit for Terrapower Natrium Kemmerer Unit 1 Project, Draft Report for Comment Project stage: Draft Other ML25181A7642025-07-0101 July 2025 Uso Kemmerer 1 Schedule Status Letter Project stage: Other ML24285A0442025-08-0505 August 2025 Email Dated 8-5-2024 to Uso Terrapower Providing Batch No.1 Information Needs Document Project stage: Other ML25232A0412025-08-21021 August 2025 Summary of the July 22, 2025 Public Meeting to Receive Comments on the Deis for the Construction Permit Application for Kemmerer Power Station One Project stage: Meeting ML25274A1302025-10-0101 October 2025 Terrapower, LLC, Submittal of Supplemental Information to Support Kemmerer Unit 1 Construction Permit Application Review Project stage: Supplement ML25282A0032025-10-22022 October 2025 Notice of Availability of the Environmental Impact Statement for the Construction Permit for Terrapower Natrium Kemmerer Unit 1 Project, Final Report Project stage: Other NUREG-2268, Environmental Impact Statement for the Construction Permit Application for Kemmerer Power Station Unit 1 Final Report2025-10-31031 October 2025 NUREG-2268, Environmental Impact Statement for the Construction Permit Application for Kemmerer Power Station Unit 1 Final Report Project stage: Other ML25302A4502025-11-21021 November 2025 Enclosure 3 - Us Sfr Owner, LLC - Summary Report for the General Regulatory Audit of the Kemmerer Power Station Unit 1 Construction Permit Application Project stage: Other ML25302A4482025-11-21021 November 2025 Enclosure 2 - Us Sfr Owner, LLC - Summary Report for the General Regulatory Audit of the Kemmerer Power Station Unit 1 Construction Permit Application Project stage: Other ML25302A4522025-11-21021 November 2025 Enclosure 4 - Us Sfr Owner, LLC - Summary Report for the General Regulatory Audit of the Kemmerer Power Station Unit 1 Construction Permit Application Project stage: Other ML25302A4452025-11-21021 November 2025 Letter - Us Sfr Owner, LLC - Summary Report for the General Regulatory Audit of the Kemmerer Power Station Unit 1 Construction Permit Application Project stage: Other ML25302A4462025-11-21021 November 2025 Enclosure 1 - Us Sfr Owner, LLC - Summary Report for the General Regulatory Audit of the Kemmerer Power Station Unit 1 Construction Permit Application Project stage: Other ML25329A3672025-11-28028 November 2025 Safety Evaluation for the U.S. Sfr Owner, Llc., Construction Permit Application for the Kemmerer Power Station, Unit 1 Project stage: Approval ML25329A2522025-11-30030 November 2025 Safety Evaluation Related to the U.S. Sfr Owner, LLC Construction Permit Application for the Kemmerer Power Station, Unit 1, Project stage: Approval 2025-11-21
[Table View] |
Text
July 1, 2025 Mr. George Wilson Senior Vice President, Regulatory Affairs TerraPower, LLC 15800 Northup Way Bellevue, WA 98008
SUBJECT:
US SFR OWNER, LLC - KEMMERER POWER STATION UNIT 1 CONSTRUCTION PERMIT APPLICATION REVIEW STATUS (EPIDS: L-2024-CPS-0000 AND L-2024-LNE-0002)
Dear George Wilson The purpose of this letter is to inform US SFR Owner, LLC (USO), a wholly owned subsidiary of TerraPower, LLC (TerraPower), of a schedule change for the U.S. Nuclear Regulatory Commission (NRC) staffs review of the construction permit (CP) application for the Kemmerer Power Station Unit 1 (Kemmerer 1). By letter dated February 26, 2025 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25055A019), the NRC staff communicated that it planned to complete the review of the CP application by June 2026, which was ahead of the original August 2026 date. Additionally, the draft environmental impact statement (EIS) was recently issued in June 2025 (ML25154A651), one month ahead of schedule. As a result of frequent and productive engagements with USO and considering Executive Order 14300, the NRC staff plans to issue the final safety evaluation and the final EIS by December 31, 2025, ahead of the updated schedule communicated in the February 26, 2025, letter.
This schedule shift is being accommodated primarily through streamlined reviews by management and the Advisory Committee on Reactor Safeguards; however, there remain technical topics for the staff to make its regulatory findings. These include materials qualification, appropriate identification of special treatments for design and construction of safety-significant structures, systems and components; treatment of preventative controls under the licensing modernization project (LMP) approach; documentation supporting the probabilistic risk assessment used in the LMP and other licensing programs; design and safety classification of the pool immersion cell and associated systems; and the safety basis for non-safety-related with special treatment seismic/structural design approaches. For the environmental review, the unresolved items include completing the Section 106 consultation under the National Historic Preservation Act and resolving any substantive comments on the draft EIS. The NRC staff remains engaged with USO in regulatory audits and other activities supporting the NRC staffs review of the CP application and resolution of these topics. The accelerated timeline depends on a continued commitment from USOs staff to resolve these issues and provide necessary information in a timely manner. Likewise, the NRC staff remains committed to working with USO
to expeditiously drive the remaining technical topics to resolution to achieve the new schedule timeline.
If you have any questions regarding this matter, please contact me at (301) 415-0673 or via email at Mallecia.Sutton@nrc.gov.
Sincerely,
/RA/
Mallecia Sutton, Senior Project Manager Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation Docket No.: 50-0613 cc: TerraPower Natrium via Gov Delivery