March 18, 2025 MEMORANDUM TO:
Josh M. Borromeo, Chief Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation FROM:
Mallecia A. Sutton, Senior Project Manager /RA/
Advanced Reactor Licensing Branch 1 Division of Advanced Reactors and Non-Power Production and Utilization Facilities Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF AUGUST 22, 2024, PARTIALLY CLOSED MEETING WITH TERRAPOWER, LLC TO DISCUSS COMPREHENSIVE VIBRATION ASSESSMENT PROGRAM FOR THE NATRIUM DESIGN (EPID NO. L-2024-CPS-0000)
Meeting Information:
Applicant: TerraPower, LLC (TerraPower)
Docket No.: 05000613 Meeting Type: Partially Closed Public Meeting Notice Agencywide Documents Access and Management System (ADAMS)
Accession No.: ML24205A153 Applicant Presentation Slides ADAMS Accession No.: ML24221A341
Contact:
Mallecia A. Sutton, NRR/DANU (301) 415-0673
J. Borromeo 2
Meeting Summary:
On August 22, 2024, the U.S. Nuclear Regulatory Commission (NRC) staff held an observation meeting with TerraPower to provide the NRC staff with an overview of the Comprehensive Vibration Assessment Program (CVAP) strategy proposed for the Natrium design. Participants included representatives from TerraPower. The NRC staff conducted the meeting in accordance with NRC Management Directive 3.5, Attendance at NRC Staff-Sponsored Meetings (ML21180A271).
The meeting began with TerraPower providing an overview of the operating experience of sodium fast reactors. TerraPower next gave an overview of the Natrium CVAP strategy, including relevant regulatory guidance such as Regulatory Guide 1.20, Comprehensive Vibration Assessment Program for Reactor Internals During Preoperational and Initial Startup Testing, the goal of the Natrium CVAP, and goal of the meeting. TerraPower then presented on vibration mechanisms, including mechanical induced vibration, acoustic induced vibration, acoustic resonance, and flow-included vibration. TerraPower provided an overview of the vibration operating experience incorporated for the CVAP strategy for the Natrium design and named historical CVAPs that had been developed for other facilities.
At the end of the meeting, the TerraPower representatives and the NRC staff discussed the next steps for future interactions regarding the Natrium design.
No regulatory decisions were made as a result of this meeting. No public comments were received in the meeting.
Enclosure:
List of Attendees cc: TerraPower Natrium via GovDelivery
ML25045A096 NRR-001 OFFICE NRR/DANU/UAL1:PM NRR/DANU/UAL1:PM NRR/DANU/UAL1:LA NAME KWagner MSutton DGreene DATE 02/27/2025 03/05/2025 03/11/2025 OFFICE NRR/DANU/UAL1:BC NAME JBorromeo DATE 03/18/2025
Enclosure List of Attendees Summary of Meeting with Terrapower, LLC to Discuss Comprehensive Vibration Assessment Program for the Natrium Design August 22, 2024 Name Organization Reed Anzalone U.S. Nuclear Regulatory Commission (NRC)
Deion Atkinson NRC Josh Borromeo NRC Candace De Messieres NRC Stephanie Devlin-Gill NRC Matt Hiser NRC Bruce Lin NRC Andy Patz NRC Thomas Scarbrough NRC Clair Song NRC Mallecia Sutton NRC Katie Wagner NRC Yuken Wong NRC Aaron Eyler TerraPower, LLC (TerraPower)
Ian Gifford TerraPower Jamie Getchius TerraPower Nick Kellenberger TerraPower Tamas Liszkai TerraPower Ching-Ching Yu TerraPower Andy Crompton Public Citizen Lauren Drakopulos Public Citizen Ashkan Eslaminejad Public Citizen