David P. Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
SCHEDULE FOR THE SUPPLEMENTAL ENVIRONMENTAL REVIEW OF THE PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3, SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NUMBER: L-2024-SLE-0003)
(DOCKET NUMBERS: 50-0277 AND 50-0278)
Dear David P. Rhoades:
By letter dated June 5, 2024 (Agencywide Documents Access and Management System (ADAMS) ML24157A069) Constellation Energy Generation, LLC (CEG) submitted a letter to the U.S. Nuclear Regulatory Commission (NRC, staff) regarding the subsequent license renewal of Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom), in which CEG requested that the NRC staff provide a plan for completing the environmental review for Peach Bottom and for restoring the end dates for the subsequent renewed licenses. By letter dated September 6, 2024 (ML24221A258), the NRC staff provided a plan for completing the required regulatory activities to include an environmental audit. By letter dated November 13, 2024 (ML24313A101) the NRC staff provided a detailed environmental audit plan. The environmental audit has concluded, and the NRC staff provided a summary of the audit activities and requests for additional information and requests for confirmation of information in a letter dated December 13, 2024 (ML24344A110). The staff is now proceeding with the preparation of a draft supplement to NUREG-1437, "Generic Environmental Impact Statement for License Renewal of Nuclear Plants Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 and 3 (NUREG-1437, Supplement 10, Second Renewal) Final Report," which will be issued for public comment.
The purpose of this letter is to provide the NRC staffs projected review schedule to complete the supplemental environmental review for Peach Bottom (Enclosure 1). The NRC staff will follow established review procedures and the enclosed schedule to complete the reviews required by Title 10 of the Code of Federal Regulations (10 CFR) part 51, Environmental Protection Regulations for Renewal of Operating Licenses for Nuclear Power Functions, and part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants. The NRC staff has estimated that the supplemental environmental review will take approximately 2,650 hours0.00752 days <br />0.181 hours <br />0.00107 weeks <br />2.47325e-4 months <br /> to complete. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates will be communicated via separate correspondence. Milestones for hearing activities that may be needed are not included February 28, 2025
D. Rhoades 2
in the enclosed schedule or the estimated hours because these dates, if applicable, would be established by the Commission or the Atomic Safety and Licensing Board and new resource considerations would need to be developed. The projected review schedule to complete the supplemental environmental review for Peach Bottom was communicated to CEG staff on February 26, 2025.
If you have any questions on this matter, please contact Jessica Hammock, Project Manager, for the safety review of the Peach Bottom subsequent license renewal application at Jessica.Hammock@nrc.gov, or Kevin Folk, Project Manager, for the environmental review at Kevin.Folk@nrc.gov.
Sincerely, Michele Sampson, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-0277 and 50-0278
Enclosure:
As stated cc w/encls: Listserv Signed by Sampson, Michele on 02/28/25
D. Rhoades 3
SUBJECT:
SCHEDULE FOR THE SUPPLEMENTAL ENVIRONMENTAL REVIEW OF THE PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3, SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NUMBER: L-2024-SLE-0003) (DOCKET NUMBERS: 50-0277 AND 50-0278)
DATED: FEBRUARY 28, 2025 DISTRIBUTION:
PUBLIC RidsNrrDnrl Resource RidsACRS_MailCTR Resource RidsNrrDorlLpl1 Resource RidsNrrPMPeachBottom Resource RidsRgn1MailCenter Resource RidsNrrOd Resource RidsRgn1Dnms Resource RidsRgn1Drp Resource RidsRgn1Drs Resource RidsRgn1Ora Resource RidsRgn1Opa Resource JHammock, NRR/DNRL BRogers, NRR/DNRL SKoenick, NMSS/REFS KFolk, NMSS/REFS KLoomis, NMSS/REFS MSampson, NRR/DNRL SLee, NRR/DNRL AKlett, NRR/DORL HGonzalez, NRR/DORL DRoth, OGC APatz, OEDO/AO SBurnell, HQ/OPA CWolf, OCA MHoskins, OCA SRutenkroger, RI/DORS CDukehart, RI/DORS SElkhiamy, RI/DORS DTifft, RI, ORA EMAIL:
christopher.wilson2@constellation.com hannah.pell@constellation.com kristin.meek@constellation.com allison.stalker@constellation.com ADAMS Accession No.: ML25035A001 NRR-106 OFFICE NRR/DNRL/PM NRR/DNRL/LA NMSS/REFS/PM NAME JHammock KBratcher KFolk DATE 02/04/2025 02/12/2025 02/05/2025 OFFICE NMSS/REFS/BC NRR/DNRL/BC (A)
NRR/DNRL/D NAME SKoenick BRogers MSampson DATE 02/07/2025 02/12/2025 OFFICE RECORD COPY 2/28/25 PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 SUBSEQUENT LICENSE RENEWAL APPLICATION SUPPLEMENTAL ENVIRONMENTAL REVIEW SCHEDULE Milestone Scheduled Actual Publish Federal Register Notice (FRN) - Notice of intent to Prepare Supplement to Final Supplemental Environmental Impact Statement (SEIS) 1/2025 1/07/2025 Publish FRN - Notice of Availability of Draft Supplement to Final SEIS 6/2025 Public Meeting - Draft Supplement to Final SEIS 7/2025 End of Draft Supplement Comment Period 8/2025 Publish Final SEIS Supplement 12/2025 U.S. Environmental Protection Agency (EPA) FRN Published -
Availability of Final Supplement to FSEIS 1/2026 Decision - Director, Office of Nuclear Reactor Regulation 3/2026