Letter Sequence Approval |
|---|
EPID:L-2023-TOP-0036, Final Request for Additional Information - Mitsubishi Electric Power Products, Inc. (Meppi) JEXU-1041-1008, Safety System Digital Platform - Meltac (Approved, Closed) |
Results
Other: ML23179A176, ML23179A182, ML23179A184, ML24075A314, ML24117A209, ML24117A210, ML24117A212, ML24157A382, ML24236A706, ML24236A707, ML24236A708, ML24236A710, ML24236A712, ML24296B178, ML24317A161, ML24317A162, ML25069A451, ML25069A452, ML25069A454, ML25069A456, ML25069A458, ML25069A460
|
MONTHYEARML23179A1822023-08-11011 August 2023 NRC Form 897, Topical Report Withholding Determination, for Safety System Digital Platform - Meltac Project stage: Other ML23179A1842023-08-15015 August 2023 NRC Form 898, Topical Report Completeness Determination, for Safety System Digital Platform - Meltac Project stage: Other ML23179A1762023-08-16016 August 2023 E-mail - U. S. Nuclear Regulatory Commission Completion Determination Form 898 and Withholding Determination from 897 for JEXU-1041-1008, Safety System Digital Platform - Meltac (Mitsubishi Electric Total Advanced Controller) Topical Report Project stage: Other ML23249A2302023-09-13013 September 2023 Mitsubishi Electric Company (Melco) Regulatory Audit in Support of Review of the Revision to the Meltac Platform Topical Report Project stage: Approval ML24010A0182024-01-19019 January 2024 Final Request for Additional Information - Mitsubishi Electric Power Products, Inc. (Meppi) JEXU-1041-1008, Safety System Digital Platform - Meltac Project stage: Request ML24019A0292024-01-19019 January 2024 Enclosure 3 - Request for Additional Information Deleted - Mitsubishi Electric Power Products, Inc. (Meppi) JEXU-1041-1008, Safety System Digital Platform - Meltac Project stage: RAI ML24019A0282024-01-19019 January 2024 Enclosure 2 - Final Request for Additional Information - Mitsubishi Electric Power Products, Inc., (Meppi) JEXU-1041-1008, Safety System Digital Platform - Meltac Project stage: RAI ML24010A0222024-01-19019 January 2024 Final Request for Additional Information - Mitsubishi Electric Power Products, Inc., (Meppi) JEXU-1041-1008, Safety System Digital Platform - Meltac Project stage: RAI ML24037A0972024-02-0606 February 2024 Status of NRC Staff Review of JEXU-1041-1008, Safety System Digital Platform - Meltac Project stage: Approval ML24078A4352024-03-13013 March 2024 Mitsubishi Electric Corp Response to Request for Additional Information for Meltac Topical Report - RAI 4 for L-2023-TOP-0036 Project stage: Response to RAI ML24078A4432024-03-13013 March 2024 Mitsubishi Electric Corp Response to Request for Additional Information for Meltac Topical Report - RAI 9 for L-2023-TOP-0036 Project stage: Response to RAI ML24078A4412024-03-13013 March 2024 Mitsubishi Electric Corp Response to Request for Additional Information for Meltac Topical Report - RAI 7 for L-2023-TOP-0036 Project stage: Response to RAI ML24078A4392024-03-13013 March 2024 Mitsubishi Electric Corp Response to Request for Additional Information for Meltac Topical Report - RAI 6 for L-2023-TOP-0036 Project stage: Response to RAI ML24078A4372024-03-13013 March 2024 Mitsubishi Electric Corp Response to Request for Additional Information for Meltac Topical Report - RAI 5 for L-2023-TOP-0036 Project stage: Response to RAI ML24078A4422024-03-13013 March 2024 Mitsubishi Electric Corp Response to Request for Additional Information for Meltac Topical Report - RAI 8 for L-2023-TOP-0036 Project stage: Response to RAI ML24078A4342024-03-13013 March 2024 Mitsubishi Electric Corp Response to Request for Additional Information for Meltac Topical Report - RAI 3 for L-2023-TOP-0036 Project stage: Response to RAI ML24078A4332024-03-13013 March 2024 Mitsubishi Electric Corp Response to Request for Additional Information for Meltac Topical Report - RAI 2 for L-2023-TOP-0036 Project stage: Response to RAI ML24078A4322024-03-13013 March 2024 Mitsubishi Electric Corp., Response to Request for Additional Information for Meltac Topical Report - RAI 1 for L-2023-TOP-0036 Project stage: Response to RAI ML24075A3142024-03-15015 March 2024 Mitsubishi Electric Corporation (Melco) Submittal of Support Documents for Meltac Topical Report Project stage: Other ML24088A0412024-03-28028 March 2024 NRC 897 for Meltac RAI 1 Response Withholding Review - NRC 897 Project stage: RAI ML24117A2122024-04-24024 April 2024 Enclosure 2: Summary of Compliance to the Regulatory Guide 1.152 Revision 4 Project stage: Other ML24117A2092024-04-25025 April 2024 Mitsubishi Electric Corporation (Melco), Submittal of Support Documents for Meltac Topical Report Project stage: Other ML24117A2102024-04-25025 April 2024 Enclosure 1: Affidavit for Topical Report Support Document 20240425 Project stage: Other PMNS20240676, Melco Meltac Request for Additional Information Response and Supplement Discussion2024-05-13013 May 2024 Melco Meltac Request for Additional Information Response and Supplement Discussion Project stage: RAI ML24137A1512024-05-16016 May 2024 Mitsubishi Electric Corporation (Melco) Submittal of Support Documents for MEL TAC Topical Report Project stage: Request ML24157A3852024-05-29029 May 2024 Mitsubishi Electric Corporation (Melco), Responses for Discussion Topics on RAI Responses and Supplements Project stage: Request ML24157A3822024-06-0404 June 2024 Mitsubishi Electric Corporation (Melco), Submittal of Presentation Material for MEL TAC Topical Report Project stage: Other ML24179A2902024-06-27027 June 2024 NRC 897 for Meltac RAI 5 Response, Document No. JEXU-1041-1018 Revision 1 Project stage: RAI ML24179A2912024-06-27027 June 2024 NRC 897 for Meltac RAI 6 Response, Document No. JEXU-1041-1018 Revision 1 Project stage: RAI ML24179A2922024-06-27027 June 2024 NRC 897 for Meltac RAI 7 Response, Document No. JEXU-1041-1018 Revision 1 Project stage: RAI ML24320A0912024-06-27027 June 2024 NRC 897 for Meltac RAI 10 Response, Document No. JEXU-1041-1008 Project stage: RAI ML24092A0822024-07-0101 July 2024 E-mail - Proprietary Review Form 897 for Meltac RAI Response, Document No. JEXU-1041-1018 Revision 1 Project stage: RAI ML24206A0782024-07-31031 July 2024 U.S. NRC Summary of Observation Public Meeting to Discuss Melcos Responses to the Rais and Supplement Response Project stage: RAI 2024-03-28
[Table View] |
Text
December 23, 2024 Chad Modro, Department Manager Nuclear Systems Department Mitsubishi Electric Power Products Inc.
1-1-2 Wadasaki, Hyogo Kobe, Japan 652-8555
SUBJECT:
THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVISED SCHEDULE FOR THE REVIEW OF MITSUBISHI ELECTRICAL CORPORATIONS TOPICAL REPORT, JEXU-1041-1008, REVISION 3, SAFETY SYSTEM DIGITAL PLATFORM - MELTAC (EPID L-2023-TOP-0036)
Dear Chad Modro:
By letters dated March 15, April 25, May 16, and August 23, 2024 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML24075A314, Accession No. ML24117A209, Accession No. ML24137A151, and Accession No. ML24236A706, respectively), Mitsubishi Electrical Corporation (MELCO) submitted supplemental information to Topical Report (TR) JEXU-1041-1008, Revision 3, Safety System Digital Platform - MELTAC, for U.S. Nuclear Regulatory Commission (NRC) staffs review. The NRC staff had agreed to consider the supplement information as part of the ongoing review of JEXU-1041-1008, Revision 3, in discussions with MELCO representatives.
The NRC staff has found that the supplemental information is sufficient to begin its detailed technical safety review of the new information in combination with the initial June 16, 2023, JEXU-1041-1008, Revision 3, submittal (ADAMS Package Accession No. ML23167C167).
Below are discussions and the NRC staffs rationale for planned schedule revisions and level of effort increases to accommodate review of the supplemental information and the overall TR.
Based on the information provided in your submittal, the NRC staff plans to review the responses to the Requests for Additional Information (RAIs) by December 20, 2024, issue the draft safety evaluation (SE) by June 13, 2025, and final SE by September 12, 2025, as annotated in the enclosed schedule. The draft SE completion date assumes 60 days for RAI responses, but will be adjusted, if necessary, to accommodate any delays in the responses. The enclosed schedule provides dates for the initial planned, actual, and revised milestones for the overall review.
Additionally, the NRC staff estimates that it will require an increase of approximately 250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> to the current 880 hours0.0102 days <br />0.244 hours <br />0.00146 weeks <br />3.3484e-4 months <br /> that was planned for the initial August 16, 2023, submittal, for a total of 1130 hours0.0131 days <br />0.314 hours <br />0.00187 weeks <br />4.29965e-4 months <br /> to complete the safety review. The Advisory Committee on Reactor Safeguards (ACRS) does not plan to review this TR, and as such, no subcommittee nor full committee meetings are expected to be scheduled.
Section 170.21 of Title 10 of the Code of Federal Regulations requires that TRs are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff-hours will be billed accordingly.
If you have any questions regarding the TR review, please contact me at 301-415-4116 or via email at Jeffery.Smith@nrc.gov.
Sincerely,
/RA/
Jeffery Smith, Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902039
Enclosure:
Initial Planned, Actual, and Revised Schedule
Enclosure Initial Planned, Actual, and Revised Schedule Milestone Initial Planned Actual Revised Initial Submittal Aug. 18, 2023 Aug. 16, 2023 Acceptance Aug. 18, 2023 Aug. 16, 2023 Audit-1 Sep. 25, 2023 Sep. 25, 2023 Issued Requests for Additional Information (RAI) - Set #1 Dec. 19, 2022 Jan. 19, 2024 Response to RAIs - Set #1 Mar. 15, 2024 Aug. 23, 2024 Supplemental Information Dec. 2023 Feb. 21, 2024 Issue RAIs - Set #2 Oct. 18, 2024 Oct. 23, 2024 Response to RAIs - Set #3 Nov. 22, 2024 Nov. 12, 2024 Issue Draft SE Nov. 22, 2024 Jun. 13, 2025 Issue Final SE Mar. 11, 2025 Sep. 12, 2025