Cover Letter - NRCs Approval of Centrus/Acos Phase II Extension Request Amendment 27
ML24345A252
Person / Time
Site: 07007004
Issue date: 12/31/2024
From: James Downs
NRC/NMSS/DFM/FFLB
To: Karen Fitch
American Centrifuge Operating
Shared Package
ML24345A251 List:
References
EPID L-2024-LRM-0078
Download: ML24345A252 (1)


Text

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION OFFICIAL USE ONLY - SECURITY RELATED INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 December 31, 2024 Kelly L. Fitch, Regulatory Manager American Centrifuge Operating, LLC P.O. Box 628 Mail Stop 7560 3930 U.S. 23 South Piketon, OH 45661

SUBJECT:

APPROVAL OF AMERICAN CENTRIFUGE OPERATINGS REQUEST TO EXTEND PHASE II OF ITS HIGH-ASSAY LOW-ENRICHED URANIUM OPERATIONS AT THE AMERICAN CENTRIFUGE PLANT IN PIKETON, OHIO (ENTERPRISE PROJECT IDENTIFIER L-2024-LRM-0078)

Dear Kelly L. Fitch:

By letter dated September 12, 2024, (Agencywide Documents Access and Management System [ADAMS] Accession No. ML24262A084), American Centrifuge Operating, LLC (ACO), a wholly owned subsidiary of Centrus Energy Corp., requested review and approval of proposed changes to its license application and supporting documents for the American Centrifuge Plant (ACP) located in Piketon, Ohio. The U.S. Nuclear Regulatory Commission (NRC) accepted the application for detailed review on October 21, 2024 (ML24298A160).

ACO supplemented the September 12, 2024, application on November 7, 2024 (ML24324A321). On November 15 and 20, 2024, the NRC staff conducted two conference calls with ACO to discuss a new license condition (LC) that would require ACO to provide the NRC prior notification of changes to ACOs high-assay low-enriched uranium (HALEU) contract with the U.S. Department of Energy (DOE) that are material to the ACP License SNM-2011 (ML24331A050). By letter dated November 21, 2024 (ML24331A050), ACO supplemented its September 12, 2024, application by proposing the following new LC:

ACO shall provide at least a 30-day prior written notification to the NRC of anticipated or needed changes to its HALEU Demonstration contract that are material to ACOs license, including contract completion date extensions. Such written notifications shall include the anticipated or needed changes to the contract and the status of DOEs review with respect to a proposed change. If it is not possible for ACO to provide the 30-day prior notification, ACO shall provide the prior notification before the change is made, and as early as possible, with an explanation of why the required 30-day notification time period could not be met.

Enclosures 1 and 2 transmitted herewith contain sensitive security related information.

When separated from the sensitive conditions in Enclosures 1 and 2, this document and Enclosures 3 and 4 are decontrolled.

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION K. Fitch 2

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION The NRC staff has completed its review of the September 12, 2024 request and supplements, dated November 7, 2024, and November 21, 2024. The details associated with the review are documented in the enclosed safety evaluation report (SER). The enclosed Amendment 27 to License SNM-2011 will become effective on January 1, 2025. The Environmental Assessment (ML24345A197) associated with this license amendment was issued on December 26, 2024, and published in the Federal Register on December 31, 2024 (ML24358A175).

As part of this licensing action, the following amendments to License SNM-2011 are being made:

(1) LC 10.c has been modified to incorporate the changes made to the Environmental Report (LA-3605-0002) consistent with ACOs submittal dated September 12, 2024.

(2) LC 10.d has been modified to incorporate the changes made to the Fundamental Nuclear Material Control Plan (NR-3605-0005) consistent with ACOs submittal dated September 12, 2024.

(3) LC 10.e has been modified to incorporate the changes made to the Security Plan for the Protection of Classified Matter (SP-3605-0041) consistent with ACOs submittal dated September 12, 2024.

(4) LC 10.s been modified to incorporate the substantial changes made to the License Application (LA-3605-0001) consistent with ACOs submittal dated September 12, 2024, and its update submitted on November 21, 2024.

(5) LC 10.y has been modified to incorporate the changes made to the Security Plan for the Physical Protection of Special Nuclear Material at the American Centrifuge Plant in Piketon, Ohio (SP-3605-0042) consistent with ACOs submittal dated September 12, 2024.

(6) LC 15 has been modified by removing the termination date of the DOE-ACO HALEU contract.

(7) A new LC 31 was added to incorporate ACOs proposed LC.

It is noted that certain changes made to LA-3605-0002 and LA-3605-0001 and all changes made to NR-3605-0005, SP-3605-0041 and SP-3605-0042 were non-substantial and therefore did not require NRC review and approval.

In accordance with Title 10 of the Code of Federal Regulations Part 2, Agency Rules of Practice and Procedure, a copy of this letter and public enclosures will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The PDR is open by appointment.

To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION K. Fitch 3

OFFICIAL USE ONLY - SECURITY RELATED INFORMATION If you have any questions regarding this action, please contact Yawar Faraz by telephone at 301-415-7220, or via email at Yawar.Faraz@nrc.gov.

Sincerely, James Downs, Acting Chief Fuel Facility Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No. 07007004 License No. SNM-2011

Enclosures:

1. Complete SER (OUO-SRI)
2. Amendment 27 of the ACP License SNM-2011 (OUO-SRI)
3. Amendment 27 of the ACP License SNM-2011 (Public)
4. Complete SER (Public) cc:

M. Snider, General Manager, ACO M. Reim, DOE NE-HQ J. Hutson, NRC Contractor S. Rice, NRC Contractor centrus_acp@listmgr.nrc.gov Signed by Downs, James on 12/31/24

ML24345A251(pkg); ML24345A252(ltr);

ML24345A253 (encl 1, non-public); ML24345A254 (encl 2, non-public);

ML24345A255 (encl 3); ML24345A256 (encl 4).

OFFICE NMSS/DFM/FFLB NMSS/DFM/FFLB NMSS/REFS/FAB NAME YFaraz JGoodridge SMcCarthy DATE 12/10/2024 12/16/2024 12/12/2024 OFFICE NMSS/REFS/FAB OGC NMSS/DFM/FFLB NAME FMiller PJehle JDowns DATE 12/18/2024 12/30/2024 12/31/2024