MONTHYEARML23045A2582023-02-24024 February 2023 U. S. Nuclear Regulatory Commission Withholding Determination Form 897 for the Slides for Technical Exchange Closed Meeting with Electric Power Research Institute on the Update to BWRVIP-100, Updated Assessment of the Fracture Toughness of Project stage: Request ML23045A2642023-02-24024 February 2023 E-Mail - NRC Withholding Determination Form 897 for the Slides for Closed Meeting with Electric Power Research Institute on BWRVIP-100, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Core Shroud Project stage: Meeting ML23045A2652023-02-24024 February 2023 NRC Withholding Determination Form 897 for the Slides for Closed Meeting with Electric Power Research Institute on BWRVIP-100, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Core Shroud (EPID Project stage: Meeting ML23198A3332023-05-31031 May 2023, 11 July 2023 Submittal of BWRVIP-100, Rev. 2, BWR Vessel and Internals Project, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internal Components Project stage: Request ML23214A0722023-09-14014 September 2023 BWRVIP-100, Rev 2, Fracture Toughness of Irradiated Stainless Steel for BWR Core Shrouds - NRC 897, Topical Report Withholding Determination Project stage: Other ML23214A0692023-09-14014 September 2023 BWRVIP-100, Rev 2, Fracture Toughness of Irradiated Stainless Steel for BWR Core Shrouds - NRC 898,Topical Report Completeness Determination Project stage: Other ML23214A0532023-09-14014 September 2023 E-mail - NRC Completion Determination Form 898 and Proprietary Determination Form 898 for BWRVIP-100, Revision 2, BWR Vessel and Internals Project, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel Project stage: Other ML23011A3422023-10-30030 October 2023 February 27, 2023, Meeting Summary: Pre-application Meeting for Submittal of a Revision to BWRVIP-100, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Core Shrouds (EPID L-2023-TOP-0018) - Memo Project stage: Meeting ML23060A0972023-10-30030 October 2023 February 27, 2023, Meeting Summary: Pre-application Meeting for Submittal of a Revision to BWRVIP-100, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Core Shrouds (EPID L-2023-TOP-0018) - Enclosure 3 - at Project stage: Meeting ML24036A0072024-02-12012 February 2024 Redacted - Enclosure 2 - Final Request for Additional Information - BWRVIP-100, Revision 2, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for Boiling Water Reactor (BWR) Internal Components (EPID L-2023-NTR-0005 Project stage: RAI ML24036A0052024-02-12012 February 2024 E-Mail - Final Request for Additional Information - BWRVIP-100, Revision 2, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for Boiling Water Reactor (BWR) Internal Components Project stage: RAI ML24219A0532024-09-12012 September 2024 Summary of August 2024 Meetings Responses to RAIs for Technical Report BWRVIP 100, Rev 2: Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internals Components Project stage: RAI ML24219A0802024-09-12012 September 2024 Attendees List for August 2024 Meetings Responses to RAIs for Technical Report BWRVIP 100, Rev 2: Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internals Components Project stage: RAI ML24219A0762024-09-12012 September 2024 August 2024 Summary of Meetings Responses to RAIs for Technical Report BWRVIP 100, Rev 2: Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internals Components Project stage: RAI ML24255A0022024-09-23023 September 2024 Change in Estimated Review Schedule for BWRVIP-100, Revision 2, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internal Components Project stage: Other ML25023A0922025-03-21021 March 2025 E-mail - Draft Safety Evaluation Associated with EPRI Technical Report BWRVIP-100, BWR Vessel and Internals Project, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internal Components, Revision 2 Project stage: Draft Approval ML25202A1192025-12-12012 December 2025 E-mail - Transmittal: NRC Forms 896, -A Topical Report Verification, for BWRVIP-100, Rev 2, Updated Assessment of the Fracture Toughness of Irradiated SS for BWR Internal Comps Project stage: Other ML25202A1222025-12-12012 December 2025 BWRVIP-100, Revision 2 - NRC Form 896, - a Topical Report Verification Project stage: Other 2024-02-12
[Table View] |
Text
1 Lois James From:
Lois James Sent:
Monday, September 23, 2024 8:50 AM To:
npalm@epri.com; martin.bonifanti@constellation.com Cc:
RidsNrrOd Resource; RidsNrrDnrl Resource; RidsNrrLADHarrison Resource; RidsNrrDorl Resource; RidsNrrDorlLlpb Resource; RidsACRS_MailCTR Resource; Lois James; Gerond George; Angie Buford; Scott Krepel; David Rudland; Michael Benson; John Tsao; Steven Levitus; Joseph Messina; Christopher Brown; wmcgruder@epri.com
Subject:
Change in Estimated Review Schedule for BWRVIP-100, Revision 2, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internal Components (EPID L-2023-NTR-0005)
Martin Bonifanti, Constellation, BWRVIP Chairman Nathan Palm, EPRI, BWRVIP Program Manager Electric Power Research Institute 1300 West W.T. Harris Blvd Charlotte, NC 28262-8550
Dear Martin Bonifanti and Nathan Palm:
By letter dated July 11, 2023 (Agencywide Documents Access and Management System (ADAMS)
Accession No. ML23198A333), Electric Power Research Institute (EPRI) submitted BWRVIP-100, BWR Vessel and Internals Project, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internal Components, Revision 2, to the U.S. Nuclear Regulatory Commission (NRC) for review and approval. Revision 2 of BWRVIP-100 incorporations newly acquired test data from harvested reactor internals materials which may indicated a potential non-conservatism in BWRVIP-100, Revision 1-A and reassess the relationship between fracture toughness and fluence. The NRC staff reviewed and accepted the technical report on September 14, 2023 (ADAMS Accession No. ML23214A047).
On September 14, 2023 (ADAMS Accession No. ML23214A047), the NRC staff notified you that your request had been accepted for review, and the NRC staff estimated it would issue the draft safety evaluation by complete the review by September 9, 2024. Through a proprietary meeting on August 7, 2024, and a nonproprietary meeting on August 21, 2024 (ADAMS Accession No. ML24219A034),
the NRC staff and EPRI representatives discussed EPRIs request for additional information (ADAMS Accession No. ML24131A043). During these meetings, the NRC staff and EPRI representatives agreed that additional information was needed and EPRI would voluntarily supplement the information. During routine status calls, the EPRI representatives informed the NRC staff that the supplemental information would be submitted by October 31, 2024. Therefore, the NRC staff needs to update the schedule for the NRC staffs review of BWRVIP-100, Revision 2.
The purpose of this email is to officially inform you of the revised schedule. The revised issuance date for the draft safety evaluation for BWRVIP-100, Revision 2, is May 16, 2025.
If you have any questions, please contact me at lois.james@nrc.gov.
Sincerely,
ML24255A002 ^via eConcurrence *via email NRR-106 OFFICE NRR/DORL/LLPB/PM NRR/DORL/LLPB/LA NRR/DNRL/NVIB/BC NRR/DSS/SFNB/BC NAME LJames^
DHarrison^
ABuford^
SKrepel^
DATE 09/12/2024 09/17/2024 09/18/2024 09/23/2024 OFFICE DORL/LLPB/BC DORL/LLPB/PM NAME GGeorge^
LJames^
DATE 09/23/2024 09/23/2024