E-mail - NRC Completion Determination Form 898 and Proprietary Determination Form 898 for BWRVIP-100, Revision 2, BWR Vessel and Internals Project, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel
ML23214A053
Person / Time
Site: 99902016
Issue date: 09/14/2023
From: James Smith
Licensing Processes Branch
To: Bonifanti M, Palm N
Electric Power Research Institute
References
BWRVIP-100, BWRVIP-100 Rev 2, BWRVIP-100 Revision 2, EPID L-2023-TOP-0018 (Pre-Application), L-2023-TOP-0042 (Pre Fee Exemption)
Download: ML23214A053 (1)


Text

From:

Lois James To:

martin.bonifanti@constellation.com; Palm, Nathan Cc:

Lois James; Gerond George; Angie Buford; Scott Krepel; David Rudland; John Wise; David Dijamco; Michael Benson; Benjamin Parks (He/Him/His); David Dijamco; James Medoff; Carol Moyer; Cory Parker (He/Him); John Tsao; wmcgruder@epri.com; npalm@epri.com; Carter, Bob; Dan Widrevitz

Subject:

NRC Completion Determination Form 898 and Proprietary Determination Form 898 for BWRVIP-100, Rev 2, BWRVIP, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internal Components Date:

Thursday, September 14, 2023 3:41:35 PM Attachments:

BWRVIP-100 Rev 2 Fracture Toughness of Irradiated Stainless Steel for BWR Core Shrouds - NRC 898 -signed.pdf BWRVIP-100 Rev 2 Fracture Toughness of Irradiated Stainless Steel for BWR Core Shrouds - NRC 897 - signed.pdf Martin Bonifanti, Constellation, BWRVIP Chairman Nathan Palm, EPRI, BWRVIP Program Manager Electric Power Research Institute 1300 West W.T. Harris Blvd Charlotte, NC 28262-8550

Mr. Bonifanti and Mr. Palm,

Attached is the U.S. Nuclear Regulatory Commission (NRC) staff completeness determination for the Electric Power Research Institutes (EPRIs) BWRVIP-100, Revision 2:

BWR Vessel and Internals Project, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internal Components. The NRC staff determined that it provides sufficient information for the NRC staff to conduct a detailed technical review.

Also, attached please find the completed form for the U.S. Nuclear Regulatory Commission staff proprietary information withholding determination for EPRIs proprietary version of BWRVIP100, Revision2, BWR Vessel and Internals Project, Updated Assessment of the Fracture Toughness of Irradiated Stainless Steel for BWR Internal Components.

As discussed, the NRC staff plans to issue its draft safety evaluation by September 9, 2024. If needed, the NRC staff will issue a request for additional information (RAI) by February 12, 2024, with a request for EPRI to provide a response within 90 days. The NRC staff estimates that 500 staff hours will be needed to complete the technical review and issue the safety evaluation. The schedule and level of effort could change due to several factors including, the need for additional RAIs, unanticipated changes to the scope of the review, and unsolicited supplements to the topical report. The NRC staff will communicate any changes to the review schedule or estimated staff hours by email, including the reason(s) for the changes.

If you have any questions, please feel free to contact me via email lois.james@nrc.gov.

Sincerely,

Lois M. James, Senior Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission

Docket No. 99902016 EPID: L-2023-NTR-0005

ADAMS Accession Nos.: ML23214A047 (pkg); ML23214A053 (email); ML23214A072

(Form897);

ML23214A069 (Form 898) *via email NRR-106 OFFICE NRR/DORL/LLPB/PM NRR/DNRL/NVIB/BC NRR/DORL/LLPB/BC NRR/DORL/LLPB/PM NAME LJames*

ABuford DWidrevitz for*

GGeorge LJames DATE 09/13/2023 09/14/2023 09/14/2023 09/14/2023 OFFICIAL RECORD COPY