ML23094A022

From kanterella
Jump to navigation Jump to search
Michigan Attorney General'S Post Hearing Statement of Position (Redacted)
ML23094A022
Person / Time
Site: Palisades, Big Rock Point  File:Consumers Energy icon.png
Issue date: 03/20/2023
From: King J, Moody M
State of MI, Office of Attorney General
To:
Atomic Safety and Licensing Board Panel
SECY RAS
References
License Transfer, RAS 56691, 50-255-LT-2, 50-155-LT-2, 72-007-LT, 72-043-LT-2, ASLBP 22-974-01-LT-BD01
Download: ML23094A022 (0)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of ) Docket Nos. 50-255-LT-2 ENTERGY NUCLEAR OPERATIONS, ) 50-155-LT-2 INC., ENTERGY NUCLEAR ) 72-007-LT PALISADES, LLC, HOLTEC ) 72-043-LT-2 INTERNATIONAL, and HOLTEC )

DECOMMISSIONING

) ASLBP No. 22-974-01-LT-BD01 INTERNATIONAL, LLC

)

)

(Palisades Nuclear Plant and Big

)

Rock Point Site)

)

MICHIGAN ATTORNEY GENERALS POST HEARING STATEMENT OF POSITION Dana Nessel Attorney General State of Michigan Michael E. Moody Joel B. King Assistant Attorneys General Special Litigation Division P.O. Box 30755 Lansing, Michigan 48909 MoodyM2@michigan.gov KingJ38@michigan.gov (517) 335-7627 Dated: March 20, 2023

TABLE OF CONTENTS Page List of Abbreviations and Acronyms ............................................................................. ii Introduction ................................................................................................................... 1 A. Projected length of time for transfer of all spent nuclear fuel off of the Palisades site .................................................................................. 5 B. Reasonableness of the site-specific decommissioning cost estimate falling below the minimum formula amount ......................... 12 C. Applicants failed to fully explain how they derived the 12%

contingency amount and, based on relevant industry norms, practices, and standards, failed to demonstrate that the 12%

contingency amount is a plausible amount of funding for covering the contingency costs reasonably expected to be incurred at Palisades. ............................................................................ 19 D. Applicants failed to adequately describe how they will ensure that sufficient additional funding will be available as a means to adjust funding if needed, and therefore should be required to provide license conditions or other forms of assurances as discussed below. ..................................................................................... 28 Conclusion .................................................................................................................... 44 i

LIST OF ABBREVIATIONS AND ACRONYMS Applicants Entergy Nuclear Operations, Inc.; Entergy Nuclear Palisades, LLC; Holtec International; and Holtec Decommissioning International, LLC ASLB Atomic Safety and Licensing Board BWR Boiling water reactor CDI Comprehensive Decommissioning International, LLC DCE Decommissioning Cost Estimate DOE United States Department of Energy Enbridge Enbridge, Inc.

ENOI Entergy Nuclear Operations, Inc.

Entergy Entergy Nuclear Operations, Inc.; and Entergy Nuclear Palisades FERC Federal Energy Regulatory Commission GAO Government Accounting Office GTCC Greater-than-class-C waste HDI Holtec Decommissioning International, LLC Holtec Holtec Intl; CDI; HDI; or Holtec Palisades Holtec Intl Holtec International Holtec Palisades Holtec Palisades, LLC ISFSI Independent spent fuel storage installation LTA License transfer application MPSC Michigan Public Service Commission NAMCo Nuclear Asset Management Company, LLC NRC United States Nuclear Regulatory Commission Oyster Creek Oyster Creek Nuclear Generating Station (New Jersey) ii

PFAS Per- and polyfluorinated alkyl substances PHMSA Pipeline and Hazardous Materials Safety Administration Pilgrim Pilgrim Nuclear Power Station (Massachusetts)

PNNL Pacific Northwest National Laboratory PSDAR Post-shutdown decommissioning activities report PWR Pressurized water reactor State State of Michigan TVA Tennessee Valley Authority iii

INTRODUCTION The Nuclear Regulatory Commission (NRC) is considering whether to grant an application by Entergy Nuclear Operations, Inc. (ENOI); Entergy Nuclear Palisades, LLC (ENP) (together Entergy); Holtec International (Holtec); and Holtec Decommissioning International, LLC (HDI) (collectively Applicants) requesting approval to transfer the operating licenses for the Palisades Nuclear Plant, Big Rock Point Plant, and associated independent spent fuel storage installations (ISFSIs) from Entergy to Holtec and HDI.1 The license transfer application notes that Entergy plans to transfer all of the assets and liabilities of ENP to a new entity that will become Holtec Palisades, LLC (Holtec Palisades).2 The LTA also notes that Nuclear Asset Management Company, LLC (NAMCo), a wholly-owned subsidiary of Holtec, will acquire the equity interests in either the new Holtec Palisades or the parent company owner of Holtec Palisades; either way, emerging as the direct parent company of Holtec Palisades.3 Holtec plans to engage another Holtec subsidiary, Comprehensive Decommissioning International, LLC (CDI), to decommission the single unit at Palisades, restore the site, and manage on-site spent nuclear fuel.4 1 License Transfer Application (LTA) at 12 (Dec. 23, 2020).

2 LTA at 2 (Dec. 23, 2020).

3 LTA at 2 (Dec. 23, 2020).

4 LTA at 2-3 (Dec. 23, 2020). As noted in the NRCs Memorandum and Order in this case, HDI later informed the NRC that HDI no longer plans to contract with CDI to serve as the decommissioning general contractor for Palisades and that HDI is absorbing CDIs resources and will directly employ site personnel to perform the scope of work previously planned to be executed by CDI. Entergy Nuclear Operations, Inc. (Palisades Nuclear Plant and Big Rock Point Site), Memorandum and Order, CLI-22-08, __ NRC __, slip op. (July 15, 2022), p 5.

1

Holtec5 represents that it will release the site for unrestricted use by approximately 2041.6 On February 24, 2021, the Michigan Attorney General (Attorney General, MIAG, or AG) filed with the NRC a petition for leave to intervene and request for a hearing.7 In December 2021, the NRC Staff issued an order approving both the transfer of the licenses and draft conforming license amendments as well as approving a related regulatory exemption requested by HDI in support of the license transfer application.8 Although the Staff issued this order, the NRC explained that the staffs order approving the license transfer . . . remains subject to our authority to rescind, modify, or condition the approved transfer based on the outcome of this adjudicatory proceeding.9 On July 15, 2022, the NRC issued its Memorandum and Order granting the Attorney Generals petition to intervene and request for a hearing.10 In the order, the NRC explained that an application for a license transfer must contain sufficient information to demonstrate that the applicant has the financial qualifications to carry out the activities for which the license is sought, and the application also must provide reasonable assurance that funds will be available to decommission the facility including any ISFSI.11 The NRC further explained that its license transfer 5 Throughout this petition, use of the term Holtec refers to any or all of Holtec Intl, CDI, HDI, or Holtec Palisades unless otherwise specified.

6 LTA at 3 (Dec. 23, 2020).

7 Petition of the Michigan Attorney General for Leave to Intervene and for a Hearing, February 24, 2021.

8 Mem. and Order, CLI-22-08, slip op. at 1.

9 Mem. and Order, CLI-22-08, slip op. at 2.

10 Mem. and Order, CLI-22-08, slip op.

11 Mem. and Order, CLI-22-08, slip op. at 7.

2

regulations do not require an applicant to demonstrate financial qualifications to cover site restoration costs, but that in this case [s]ite restoration costs nonetheless are relevant to this proceeding because Holtec intends to pay for those costs with the Palisades decommissioning trust, on which Holtec relies for its showing of financial qualifications.12 The NRC admitted four contentions raised by the Attorney General. Those contentions are as follows: (1) the Applicants estimated 11-year timeframe for the removal by DOE of all of the spent fuel at Palisades; (2) the reasonableness of the site-specific decommissioning cost estimates falling well below the minimum formula amount; (3) the 12% contingency allowance allocated to the radiological decommissioning, spent fuel management, and site restoration cost estimate; and (4) the Applicants description of their planned means to adjust funding if necessary to complete decommissioning and terminate the license.13 The parties filed Initial Statements, Testimony, Exhibits, and Affidavits on November 18, 2022, and Written Responses Rebuttal, Rebuttal Testimony, Exhibits, and Affidavits on December 16, 2022, Written Concluding Statements of Position on January 23, 2023, and the NRC held hearings before Judge Michael Gibson on February 8 and 9, 2023. As a reminder, this proceeding deals with Holtecs request for license transfer approval.14 Moreover, as provided in 10 C.F.R. § 2.325, Holtec 12 Mem. and Order, CLI-22-08, slip op. at 10.

13 Mem. and Order, CLI-22-08, slip op. at 18.

14 Mem. and Order, CLI-22-08, slip op. at 2.

3

bears the burden of proof in this case and must support its application by a preponderance of evidence. In re Smith, 79 N.R.C. 131, 149; 2014 NRC LEXIS 16.

On February 28, 2023, Judge Gibson issued an amended order closing the evidentiary record in this proceeding and setting March 20, 2023, as the deadline for the parties written post-hearing statements of position. Accordingly, Michigan Attorney General Dana Nessel files the following written post-hearing statements of position that mirrors her written responses and rebuttal testimony but incorporates citations to testimony from the two-day hearing in this proceeding.

As stated in her Petition, the Attorney General supports prompt, thorough, and safe decommissioning and site restoration at Palisades and Big Rock, but she does not believe Holtec possesses the financial qualifications or assurances necessary to complete such a risk-intensive project. At the outset of this filing, the Attorney General comments that she hopes common sense will prevail in this proceeding and that appropriate safeguards will be put in place to make sure that future generations of Michiganders are not stuck covering costs that should be the responsibility of the party decommissioning Big Rock and Palisades. Simply put, those safeguards do not exist if HDIs proposal goes forward as laid out in its application. There is too much uncertainty surrounding where monies for any shortfall would come from and nothing in this proceeding has addressed those concerns. HDIs vague, unpersuasive discussion during the proceeding has only added to the lack of clarity and HDI has failed to answer, as laid out below, the questions posed by the NRC in its opinion.

Accordingly, the Attorney General appreciates that the NRC granted her petition and 4

that it is seeking further answers from the applicants to the arguments raised in the Attorney Generals petition.

ATTORNEY GENERALS CONCLUDING STATEMENTS OF POSITION A. Projected length of time for transfer of all spent nuclear fuel off of the Palisades site In its order, the NRC noted that the hearing will cover four challenges to the application, the first of which is the projected length of time for transfer of all spent fuel off of the Palisades site.

(a) The projected length of time for transfer of all spent fuel off of the Palisades site:

The applicants should address how they determined that the estimated 11-year spent fuel transfer period constitutes a plausible timeframe for removal of all Palisades spent fuel. In their description, the applicants should clarify the assumptions on which they relied, including what fuel acceptance priority and fuel allocation or transfer rate they assumed for their schedule.

In assessing financial qualifications for a license transfer we accept plausible forecasts. The parties arguments therefore should address whether the estimated 11-year period reflects a plausible timeframe to complete the fuel transfer.15 In its order, the NRC explained that, the applicants general references to [the] two Standard Contract provisions do not by themselves answer the Attorney Generals challenge to the plausibility of the specific 11-year schedule on which the applicants rely. The applicants have not described how they applied their assumptions to reach their 11-year schedule.16 The NRC found that the Attorney General raised a supported, genuine dispute with the application on a material issue, and that neither the Palisades site-15 Mem. and Order, CLI-22-08, slip op. at 31. Internal citation omitted.

16 Mem. and Order, CLI-22-08, slip op. at 31.

5

specific decommissioning cost estimate nor the applicants answer clearly explains how HDI determined that 11 years constitutes a plausible schedule for removal of all of the Palisades spent fuel.17 The NRC explained that it expects that.

Holtec should clarify how it determined that 11 years constitutes a plausible transfer schedule. If HDIs schedule departs from the commonly applied maximum transfer rate of 3,000 metric tons of uranium/year, then Holtec should describe the spent fuel transfer rate that it used, and why it determined that a faster rate is plausible. If Holtec bases its schedule on the commonly applied spent fuel transfer rate, then it should nonetheless explain how it reached the 11-year transfer accelerated schedule.18 The NRC also agreed with the Attorney General that, with regard to Holtecs spent fuel cost analysis, there is a genuine issue regarding whether the impact on overall cost estimates would be minimal, and also that there is no commitment by Holtec to use any costs recovered from DOE.19 The NRC stated, Based on the application, the NRC must be able to find adequate financial qualifications and reasonable assurance of decommissioning funding. If cost estimates on which the application relies for necessary findings are implausible, or if further inquiry is necessary to assess their adequacy, that is a matter warranting resolution in this license transfer proceeding.20 So, as noted in the Attorney Generals written responses, the Commissions directive to HDI was to address whether the estimated 11-year period reflects a plausible timeframe to complete the fuel transfer.

The Attorney General addressed this in her initial statements and written responses and continues to argue that the 11-year period is not a plausible timeframe in which to complete the fuel transfer.21 17 Mem. and Order, CLI-22-08, slip op. at 31-32.

18 Mem. and Order, CLI-22-08, slip op. at 32-33.

19 Mem. and Order, CLI-22-08, slip op. at 33. (Internal citation omitted).

20 Mem. and Order, CLI-22-08, slip op. at 33.

21 Michigan Attorney General Initial Statement, pp. 6-8.

6

In its first statement of position on the Attorney Generals admitted contentions, HDI argued that it is plausible that, once it begins performance, DOE will accept all of the SNF at Palisades within the eleven-year window assumed in the DCE.22 The Attorney General disagrees and argues that HDI has failed to address the NRCs question and, during the pendency of this case, has only added more uncertainty into its request. On page 12 of its statements, HDI notes that, [t]he Commission did order HDI to address how [it] determined that the estimated 11-year spent fuel transfer period constitutes a plausible timeframe for removal of all Palisades spent fuel.23 However, HDI immediately twisted that directive, stating that, [t]hus, the only question regarding HDIs assumed SNF transfer timeline that is at issue in this proceeding is whether an eleven-year transfer window is plausible.24 This is not what the NRC asked. The NRC asked how HDI determined, as discussed in its license transfer application (LTA), that an 11-year transfer period is plausible. HDIs statements avoided the NRCs question and instead raised new scenarios and hypotheticals that were not included in its LTA nor reviewed by NRC staff or other interested parties.

At the February 8, 2023, hearing, Judge Michael Gibson questioned the parties witnesses regarding this first issue dealing with the 11-year spent fuel transfer period:

22 Applicants Initial Statement p. 11.

23 Applicants Initial Statement p. 12. Internal citation omitted.

24 Applicants Initial Statement p. 12.

7

As the above colloquy demonstrates, Holtec never presented a witness that could support or even discuss the 11-year spent fuel transfer period on which Holtecs DCE and LTA is based. In fact, at the end of the entire hearing, Judge Gibson noted it seems clear that our witnesses were not able to talk about some of these issues, but Im sure that you all made notes of them and Im sure youll be addressing those in your final written concluding papers, pleadings, this case. So, theres not anything 8

more we can say about that.26 Holtec spent the majority of the two days of hearing avoiding answering the NRCs question or supporting its DCE/LTA, but rather presenting lengthy testimony detailing questionable new ways that Holtec could alter the 11-year schedule Instead of addressing the NRCs question on this 11-year time frame that is one of the bases for the DCE/LTA, HDIs statements discussed fifty-plus years of the Nuclear Waste Policy Act (NWPA)31 and then asserted that, no matter what was said in its actual LTA, there are multiple paradigms that would allow HDI to transfer all Palisades SNF offsite within 11 years.

There are several problems with each of these newly raised paradigms. First, none of this was included in HDIs application. To include completely new arguments and vague, unsupported ideas in initial statements is untimely and therefore improper.

26 Applicants Initial Statement pp. 13-18.

31 Applicants Initial Statement pp. 13-18.

32 Applicants Initial Statement pp. 22-23.

9

Similarly, regarding the idea of DOE removing SNF at a faster pace than was initially envisioned 35 years ago, that is pure speculation. HDI has no control over DOE and cannot purport to speak for DOE. Decades of delays and nuclear waste stalemate make all timelines discussed in this case highly suspect and unlikely to come to fruition. That aside, even if DOE were to get a program up and running, it is certain that the early years of the rollout would go slowly and that DOE would ease into a ramp-up, as the organization figured out how to safely, cost-effectively, and efficiently transport SNF.

Regardless of HDIs failure to address the Commissions question, transfer of all of Palisades SNF offsite within an 11-year window is simply not plausible, as it is neither reasonable nor probable to believe such a transfer will occur.35 Attorney General expert Nick Capik provided specific discussion on this in his rebuttal testimony. He noted numerous reasons that HDIs fuel removal date 35 The Oxford Languages Dictionary defines plausible as seeming reasonable or probable.

Additionally, in In re La. Energy Servs., L.P., 45 N.R.C. 99; 1997 NRC LEXIS 19, the NRC noted that Although in its hearing notice the Commission listed a number of possible generic tails disposal strategies such as storage of tails at the plant site as a possible future resource or conversion of tails to uranium oxide for disposal, the Commission did not specifically define what constitutes a plausible strategy. The plain meaning of these terms, however, provides the answer. The dictionary defines "plausible" as "reasonable" or "credible," Webster's Third New International Dictionary 1736 (1971) . [emphasis added] Board Decision, p. 5 (Lexis pagination). See also In re La. Energy Servs., L.P., 63 N.R.C. 591; 2006 NRC LEXIS 212, Board Decision, p. 637.

10

discussion is implausible under even the most optimistic of scenarios. These include that:

a.

b. HDIs experts model is not consistent with the DCE process. Delivery Commitment Schedules per the Standard Contract are not issued for all fuel at the beginning of performance. DOE expects them to be issued 63 months before delivery (see Article V.B.1).
c. HDIs experts model assumes all DOE capacity will be suitable for canistered fuel. DOE has considered using multiple, parallel systems to process incoming fuel. One option considered (and likely the primary one at the time) would have used a small part of that parallel processing for fuel from ISFSIs.

The remaining systems would have been used for fuel from operating plants (directly from fuel pools). Again, HDI and its expert are engaging in speculation about what may happen in the future with no basis or knowledge of the physical design.

d. Fuel out dates for Pilgrim (2062), and Indian Point (2061 for IP3) make HDIs projections here all the more implausible.
e. Using the original Holtec assumption of OFF at 3,000 MTU per year results in a 2064 fuel out date.37 If the rate in the 2013 NRC study is accepted, the final acceptance would result in a 2078 fuel out date.

The point here is that, regardless of the assumptions used, a mechanism for providing additional funding is needed.

As HDI has failed to answer the Commissions question of why it determined, in its LTA, that an 11-year timeframe to transfer all of Palisades SNF offsite is plausible, and as under any even remotely plausible scenario Palisades SNF transfer will take much longer than 11 years, HDI has failed to adequately address either this challenge or the Attorney Generals concerns.

36 Applicants Initial Statement, p. 26. See 1987 DOE Mission Plan Amendment, p. 55 (p. 61 of the pdf).

37 Exhibit MICH001, pp. 4-5.

11

B. Reasonableness of the site-specific decommissioning cost estimate falling below the minimum formula amount The second challenge the Commission admitted was as to the [r]easonableness of the site-specific decommissioning cost estimate falling below the minimum formula amount.

(b) Reasonableness of the site-specific decommissioning cost estimate falling below the minimum formula amount:

The applicants should provide a detailed explanation of the primary reasons that the cost estimate falls significantly below the minimum formula amount.

We also direct the parties and invite the staff to address whether the minimum formula regulation in section 50.75(b) applies to this application.39 The NRC instructed that the minimum formula has relevance beyond merely establishing a decommissioning funding floor early in reactor life.40 It found that the cost estimate falling below the minimum formula amount is a material consideration given that the applicants are relying on this decommissioning cost estimate for their related exemption request to use the trust fund amounts in excess of the estimate to fund spent fuel management costs and non-radiological site restoration costs.41 Further, the NRC found that, current NRC guidance on site-specific decommissioning cost estimates calls for a comparison of the estimate to the minimum formula, and this guidance expressly applies to the site-specific cost estimates submitted under the decommissioning regulations in section 50.82 (e.g., with a PSDAR under section 50.82(a)(4)(i), or within two years of cessation of operations under section 50.82(a)(8)(iii)).42 39 Mem. and Order, CLI-22-08, slip op. at 134.

40 Mem. and Order, CLI-22-08, slip op. at 38.

41 Mem. and Order, CLI-22-08, slip op. at 39.

42 Mem. and Order, CLI-22-08, slip op. at 39.

12

The NRC also opined that the minimum formula amount remains a benchmark to assess the acceptability of a site-specific decommissioning cost estimate that is submitted with a PSDAR or within two years of permanent cessation of operations, and that cost estimates falling below the formula amount warrant explanation.43 So, in its Order the Commissions directive to HDI was twofold: 1) to explain why the companys site-specific decommissioning cost estimate (DCE) falls significantly below the minimum formula amount and 2) to address whether the minimum formula regulation in section 50.75(b) applies to this application.

The Attorney General addressed this in her initial statements and written responses and continues to argue that 1) it is not reasonable for the site-specific DCE to fall significantly below the minimum formula amount and 2) that the minimum formula regulation in section 50.75(b) applies to this application.44 In its first statement of position on the Attorney Generals admitted contentions, HDI argued that the HDI cost estimate reasonably falls below the NRC formula amount due to differences between the formulas vintage and generic purpose and the HDI estimates basis on contemporaneous project-specific inputs.45 The Attorney General disagrees.

In its initial statement, HDI provided more than 30 pages of discussion that raised a host of different arguments. First, applicants addressed the legal question of whether 10 CFR § 50.75(b) applies to this application and second provided its 43 Mem. and Order, CLI-22-08, slip op. at 39-40.

44 Michigan Attorney General Initial Statement, pp. 8-11.

45 Applicants Initial Statement p. 11.

13

rationale for why the DCE falls significantly below the minimum formula amount.

10 CFR § 50.75(b)

Applicants argued that the purpose of the minimum formula in § 50.75 is to ensure during operations that licensees have a viable plan to accumulate funds . . .

by the projected time of permanent cessation of operations.46 They went on to state that the text of § 50.75(b) itself is clearly limited to the certification that the licensee is collecting adequate funds based on the formula, and that the certification is not required during decommissioning, and there is no requirement in § 50.75 or elsewhere that a § 50.82 SSCE be more, but not less, than the formula amount.47 The clear problem with this is that this proceeding solely covers HDIs license transfer application.48 It does not, as HDIs statement explicitly contemplates, cover the decommissioning stage. Thus, HDIs entire argument attempted to move the discussion past the point of this proceeding and deal with requirements at the decommissioning stage, which has not yet been reached.

The AG argues that it is clear that 10 CFR § 50.75(b) and the minimum formula amount apply at this stage of the proceeding. The unambiguous language requires that each applicant for an operating license under part 50, which HDI is, must submit a decommissioning report that must contain a certification that financial assurance for decommissioning will be (for a license applicant), or has been 46 Applicants Initial Statement p. 28.

47 Applicants Initial Statement p. 30.

48 Mem. and Order, CLI-22-08, slip op. at 2 (The staffs order approving the license transfer explicitly remains subject to [the NRCs] authority to rescind, modify, or condition the approved transfer based on the outcome of this adjudicatory proceeding.).

14

(for a license holder), provided in an amount which may be more, but not less, than

[the formula] in the table in [50.75(c)].49 Much of HDIs argument and discussion during this matter conflated what is actually at issue in this proceeding, with what is required during the decommissioning process.

At the February 9, 2023, hearing, Judge Gibson questioned Mr. Capik on this point as follows:

JUDGE GIBSON: Okay, great. And they further criticize you in this regard because they say that HDI is an applicant -- pardon me. Let me rephrase it. And they further criticize you for asserting that because HDI is an applicant for an operating license under Part 50, you assert it must provide a decommissioning report that contains a certification that financial assurance for decommissioning will be provided in an amount which may be more but not less than the formula in the table in 50.75(c). You're familiar with that assertion?

MR. CAPIK: Your Honor, these are statements by the Attorney General that are not part of my report, I believe.

JUDGE GIBSON: It's okay. These are pleadings. These are not part of your report.

MR. CAPIK: Understood.

JUDGE GIBSON: What I'm saying is they're criticizing you for -- oh, I see what you're saying now. Okay. So you're saying that the Michigan Attorney General has taken some positions. And you're not -- you weren't involved with those, and those were essentially legal arguments that were being made.

Okay. Now I'm following you. Okay. All right. Got it. Do you have an opinion about whether or not HDI needed to do that?

MR. CAPIK: I think it is certainly the NRC's precedent. The last proceeding to look at is the Pilgrim proceeding where Holtec also submitted an estimate that was less than the NRC formula.

And the NRC made them re-analyze their cash flow based on the NRC formula.

49 10 CFR § 50.75(b).

15

JUDGE GIBSON: Okay. In light of the fact that it has been shut down, do you see any reason why they should be held to the standard of an operating reactor?

MR. CAPIK: The basis of a formula was to provide assurance for the bulk of the funds. And there is an exemption process to use an estimate less than the formula. And that's been used in a number of cases, for example, Big Rock Point.

JUDGE GIBSON: Okay. Fair enough. So if I understand you, you're saying that in order to -- even though the reactor has been decommissioned, I guess it hadn't been dismantled. And so in your estimation for them not to have to meet those financial standards for an operating reactor, they would need to apply for an exemption. And short of that, they would then need to meet the standards for an exemption. Is that -- I mean, met the standards for the operating reactor. Is that your testimony, sir?

MR. CAPIK: At a point in time. Clearly, when you shut down, that number still applies.50 As explained above by Mr. Capik, there is NRC precedent applying the minimum formula to a situation similar to Holtecs DCE in this case. The NRC rejected Holtecs estimate that was less than the minimum formula in the Pilgrim proceeding and made Holtec re-analyze their cash flow based on the NRC formula. Moreover, Mr.

Capik explained that the reason why Holtec should be held to this standard is because the basis for the formula was to provide assurance for the bulk of the funds and there is an exemption process to use an estimate less than the formula, but Holtec never availed itself of this this exemption. Mr. Capik further noted that the minimum formula is generic and captures what the NRC intends to be the bulk of the cost and 50 February 9, 2023, Hearing Transcript, pp 322:6-323:12, 324:14-22, 325:7-19 (emphasis added.)

16

thats why the formula check is still there because its not letting you use some overly optimistic value. That may or may not be realized over time.51 DCE and Minimum Formula Amount In the remainder of part two of its initial statement, HDI argued that there are numerous reasons its DCE falls significantly below the minimum formula amount and that ultimately its in-house cost estimate is reasonable. As laid out in the AGs filings, this is incorrect. Accordingly, even if the NRC finds that HDIs financial assurance did not need to be equal to or greater than the minimum formula, HDI has failed to provide a detailed explanation for, and support the reasonableness for, why its cost estimate falls significantly below the minimum formula amount.

Attorney General expert Nick Capik provided further discussion on this in his rebuttal testimony. He noted numerous reasons that the analyses performed by HDIs witnesses are wrong and therefore render its arguments incorrect. These include that HDIs projected waste volume substantially overstates waste density compared to current and past projects,55 and e) that unreasonable 51 February 9, 2023, Hearing Transcript, p 339.

55 Exhibit MICH019, pp. 10-11. February 9, 2023, Hearing Transcript, p 334 (Mr. Capik reconfirmed 17

waste density results in understated waste disposal costs.56 at the hearing that the density of the spent nuclear fuel matters in determining cost.)

56 Exhibit MICH019, pp. 10-11.

18

Accordingly, the Attorney General continues to argue that the requirements of 10 CFR § 50.75(b) and the minimum formula regulation do apply to this application.

HDIs DCE is objectively below the minimum amount and therefore its application is deficient on its face.

C. Applicants failed to fully explain how they derived the 12%

contingency amount and, based on relevant industry norms, practices, and standards, failed to demonstrate that the 12% contingency amount is a plausible amount of funding for covering the contingency costs reasonably expected to be incurred at Palisades.

In its order, the NRC explained that site-specific decommissioning cost estimates include an amount added under the title of contingency to cover unknown costs.60 Thus, the identified contingency value, expressed as a percentage, reflects the percentage of the overall final cost estimate that was added as a margin to cover unknown costs.61 The NRC noted that a contingency factor is a nearly universal 60 Mem. and Order, CLI-22-08, slip op. at 43.

61 Mem. and Order, CLI-22-08, slip op. at 43.

19

element in large-scale construction and demolition projects and explained that it expects that

[A] plausible decommissioning cost estimate will include an adequate contingency allowance. The contingency allowance is intended to cover unforeseeable events that are almost certain to occur in decommissioning, based on industry experience. Funds allocated for contingency typically have been expected to be fully expended. These funds are to cover costs considered inevitable in a large project (e.g.

weather delays, equipment breakage). Contingency funds are therefore an integral part of the total cost to complete the decommissioning process.62 The NRC also addressed two additional important points about contingency funds:

(1) They have not been intended as surplus funds for possible but speculative events but instead funding necessary to cover expected costs; and (2) The annual funding review process . . . is not intended as a substitute for providing reasonable estimates of expected projected costs in the site-specific decommissioning cost estimate.63 Turning to the instant case, the NRC noted that on estimated project costs of

$644 million, the current projected funding remaining in 2041 is less than $20 million; therefore, even a small increase in the percentage of contingency expenditures could exceed the available funding.64 Although the NRC has rejected other challenges to contingency levels where petitioners had not identified a material supported dispute and the levels on their face did not appear disproportionately low, the NRC explained that [h]ere, the Attorney General claims that the challenged level is both unsupported and inconsistent with industry norms for such analyses. . . .65 62 Mem. and Order, CLI-22-08, slip op. at 49 (citations omitted).

63 Mem. and Order, CLI-22-08, slip op. at 49-50, n 175 (citation omitted).

64 Mem. and Order, CLI-22-08, slip op. at 50-51.

65 Mem. And Order, CLI-22-08, slip op. at 46 (citation omitted).

20

Accordingly, the NRC ruled, in its July 15th order granting the hearing, that Holtec should explain not just how they calculated and derived the 12% level applied for contingency, but also how they concluded that this amount for contingency is reasonably adequate for Palisades.66 In addition, the NRC explained that the parties should not just address relevant industry norms, practices and standards for the contingency amount added to reactor decommissioning cost estimates as a similar project stage, but also address whether the 12% funding added reflects a plausible amount of funding for covering the contingency costs reasonably expected to be incurred at Palisades.67 As to Holtecs argument that the Commission has rejected previous challenges to HDIs contingency amount on other projects, including arguments that HDIs summary-level explanation was insufficient.68 This attack, however, works against Holtec in this case. Not only were the contingencies in these other projects higher than the contingency in this case, but also the fact that the NRC staff has accepted HDIs contingency methodology in four DCEs69 simply shows that the NRC staff didnt know Holtecs (HDIs) contingency methodology was flawed since it only had a summary-level explanation from Holtec. It was only when the NRC examined Holtecs extremely low contingency in this case, coupled with the lack of explanation as to how it was developed, and the inconsistency with industry norms, that the NRC granted the petition and asked Holtec to explain how it calculated the contingency 66 Mem. and Order, CLI-22-08, slip op. at 134.

67 Mem. and Order, CLI-22-08, slip op. at 134-135.

68 Applicants Initial Statement, pp 65-66.

69 Applicants Initial Statement, p 68.

21

and how it decided the 12 percent contingency amount was reasonably adequate for Palisades. In fact, the NRC explained that it had rejected other challenges to contingency levels but noted that on their face [they] did not appear disproportionately low.70 The record in this case demonstrates that the contingency amount is not reasonably adequate for Palisades.

As explained above by the NRC, the contingency funds have not been intended as surplus funds for possible speculative events but instead funding necessary to cover expected costs.71 Thus, properly developing the contingency is critical to cover unforeseeable events that are almost certain to occur based on industry experience.

It is the lack of conservatism and the lack of committed other sources of funding (i.e.,

DOE recovered funds) that makes the contingency funding so important in this case.

Moreover, the NRC noted that the margin for error on the contingency in this case is extremely narrow because even a small increase in the percentage of contingency expenditures could exceed the available funding.72 As Attorney General expert Nicholas Capik explained in his Initial and Rebuttal testimony, Holtec failed to provide the necessary detail to support its modeling, failed to conduct the modeling properly, and there are numerous risks . . .

that would argue for substantially greater contingency, including the uncertainty with fuel out date, annual ISFSI maintenance costs, and waste disposal costs.73 In 70 Mem. and Order, CLI-22-08, slip op. at 46 (citation omitted).

71 Mem. and Order, CLI-22-08, slip op. at 49-50.

72 Mem. and Order, CLI-22-08, slip op. at 50-51.

73 Exhibit MICH019, p 11.

22

demonstrating why the contingency is important and why simply an annual report is insufficient to cure a deficient contingency, Mr. Capik explained:

MR. CAPIK: The NRC requires annual reports. And they require an identification if there is a projected shortfall. Whats in the other plans weve discussed, theres substantially larger decommissioning trust funds.

So theres the ability to accommodate more changes. Theyre also closer in time. The issue here is that the plants is owned by a limited liability company with no other assets.

So if these things change over the next 15 years, it's not clear where the funds come from to accommodate those changes. So right now, the NRC requires annual reporting. So eventually, the identification of the problem would be made but without a realistic way to address the problem.

Hence, without a reasonably adequate contingency for Palisades at the beginning, DCE/LTA, there is a significant chance that there are insufficient funds to appropriately handle the decommissioning.74 In his Initial Testimony, Mr. Capik explained that the 12 percent contingency used by Holtec for Palisades is inconsistent with industry norms, practices, and standards.75 For example, the Association for the Advancement of Cost Engineering (AACE) in AACE International Recommended Practice No. 18R-97, provides guidelines for identifying proper contingency for various phases of project estimation.76 Mr. Capik opined that Holtecs contingency would be classified as a Class 2 estimate under the AACE guidelines, which means that there is a 20 percent 74 February 9, 2023, Hearing Transcript, p 421:8-22.

75 Exhibit MICH001, p 9.

76 Exhibit MICH001, p 9.

23

probability that costs will ultimately be better than 15 percent below the estimate or worse than 20 percent above the estimate.77 In addition, Holtecs 12 percent contingency is significantly less than the NRC 25 percent contingency guidance for ISFSI decommissioning in NUREG-1757.78 Moreover, Holtecs 12 percent contingency is unexplainably lower than the 19 percent contingency Holtec itself used for the Indian Point project, which is the same reactor type as Palisades.79 It is also lower than Holtecs Oyster Creek (15 percent) and Pilgrim (17 percent) projects.80 Not only is Holtecs contingency for Palisades lower than its other decommissioning projects, but also the majority of work for Palisades will not be performed until over 15 years after the estimate was created, thus creating more estimating uncertainty for Palisades compared to other Holtec projects.81 As Holtec states in its initial statement it is expected that site-specific estimates prepared closer to decommissioning will have a higher degree of certainty and, thus lower contingency.82 Thus, Holtec itself agrees that the contingency for Palisades should be higher than other projects that do not have the 15-year gap.

Mr. Capik further noted that Holtecs Palisades DCE could not have benefitted from lessons learned from these other Holtec projects because at the time Holtec submitted the Palisades DCE, sufficient progress had not yet been made at these other projects to allow for any more accurate estimation for Palisades.83 This refutes 77 Exhibit MICH001, p 10.

78 Exhibit MICH001, p 10.

79 Exhibit MICH001, p 11.

80 Exhibit MICH001, p 11.

81 Exhibit MICH001, p 11.

82 Applicants Initial Statement, p 67.

83 Exhibit MICH001, p 12.

24

Holtecs claim in its Initial Statement that previous experience and actual work progress at the other projects were used by Mr. Goulette in developing the contingency for Palisades.84 At hearing, Mr. Capik explained that looking at the time frame in 2020, the sale of Pilgrim and Oyster Creek closed in 2019 and they were waiting for fuel to cool to offload the fuel at a fuel pool and the reactor vessel segmentation was in early planning states [so] there isnt a lot of experience in either of those plants that could be applied here.85 Mr. Capik agreed with Judge Gibsons summary that it [would] be fair to say that they may have had some more experience with planning for what they were going to do but they didnt have any hands-on experience with actually doing the work.86 As to the risk modeling provided by Holtec in its initial statement and testimony that was used to create the 12 percent contingency, Mr. Capik explained 84 Applicants Initial Statement, p 71.

85 February 9, 2023, Hearing Transcript, p 415:1-17.

86 February 9, 2023, Hearing Transcript, p 415:1-17.

25

that Holtec actually provides two types of contingency, which together form the 12 percent value they use.89 The first type of contingency included by Holtec is uncertainty, which is not the same type of contingency that the industry and the NRC discuss - that which is expected to be fully consumed during decommissioning.90 The second type of contingency included by Holtec is due to discrete events.91 The problem with this analysis is that [t]he probability distributions for each risk event were not provided, nor were the cost ranges for risk mitigation included. Mr. Capik further noted that the costs included were not adequate and the probability distributions not wide enough to capture the range of possibilities.93 As a result of these deficiencies, Mr. Capik opined that the analysis resulted in a narrow range of total risk and a low contingency.94 He concluded that [a]pplying what I believe to be proper mitigation costs and risk probabilities would result in identification of increased risk contingency.95 Mr. Capik explained:

89 Exhibit MICH019, p 11.

90 Exhibit MICH019, pp 11-12.

91 Exhibit MICH019, p 12.

92 Exhibit MICH019, p 12.

93 Exhibit MICH019, p 12.

94 Exhibit MICH019, p 12.

95 Exhibit MICH019, p 12.

26

Mr. Capiks analysis fits with the argument that Holtec had a goal in mind and tailored the modeling to meet the goala low contingency that would fit the amount of money in the trust fund.

In summary, Mr. Capik explained that the risk of underfunding associated with Holtecs 12 percent combined contingency (lower than any other Holtec project) is exacerbated by the lowest estimated license termination of any of Holtecs projects.98 Thus, the absolute amount of contingency included by Holtec for Palisades is substantially less than any other Holtec project.99 Mr. Capik further noted that the 12 percent contingency for Palisades results in about $53 million of contingency for license termination activities (including dormancy).100 In comparison, the average of Holtecs other projects is $94 million per unit, a 77 percent increase over that provided for Palisades.101 The 12 percent contingency is not a plausible amount for covering costs that are reasonably expected to be incurred, because there are numerous risks as noted in this [Mr. Capiks] testimony that would 98 Exhibit MICH019, p 12.

99 Exhibit MICH019, p 12.

100 Exhibit MICH019, p 12.

101 Exhibit MICH019, p 12.

27

argue for substantially greater contingency, including uncertainty with fuel out date, annual ISFSI maintenance costs, and waste disposal costs.102 As shown above, Holtec failed to fully explain how they derived the 12%

contingency by providing incomplete analysis; failed to demonstrate that its flawed analysis supports the 12% contingency; failed to demonstrate that industry norms, practices, and standards support the 12% contingency; and ultimately failed to demonstrate that the 12% contingency amount is a plausible amount of funding for covering the contingency costs reasonably expected to be incurred at Palisades.

D. Applicants failed to adequately describe how they will ensure that sufficient additional funding will be available as a means to adjust funding if needed, and therefore should be required to provide license conditions or other forms of assurances as discussed below.

In its order, the NRC stated that Holtec projects major decommissioning activities to begin in December 2035, following the dormancy period, with final license termination to occur in 2041.103 Under NRC regulations, for decommissioning activities that delay completion of decommissioning by including a period of storage or surveillance, the licensee must provide a means of adjusting cost estimates and of adjusting the associated funding levels over the storage or surveillance period.104 NRC guidance instructs the staff to determine whether the means described by the licensee provides adequate assurance that funds will be available for decommissioning activities at the time they are needed.105 Thus, the NRC explained 102 Exhibit MICH019, p 11.

103 Mem. and Order, CLI-22-08, slip op. at 74.

104 Mem. and Order, CLI-22-08, slip op. at 74-75.

105 Mem. and Order, CLI-22-08, slip op. at 79-80.

28

that for this hearing, the applicants should describe how they will ensure that sufficient additional funding will be available to use at the time of decommissioning if additional funding proves necessary to complete decommissioning.106 The NRC further noted that while the applicants emphasize that they must file annual reports on decommissioning funding, these status reports will not address the recoveries and they will not indicate how much funding Holtec Palisades may have recovered nor whether some, all, or none of the funds remain available to adjust funding.107 The NRC continued by noting that [i]f there are unanticipated decommissioning costs that will not be known until decommissioning is underway, status reports submitted in the years prior to the start of the major decommissioning activities may not capture such costs either.108 The NRCs conclusion section of its order states that the applicants should describe how they will ensure that sufficient additional funding will be available as a means to adjust funding, if needed and that [a]s part of their description, the applicants should address the issues described at the end of Section III.C.1.h.109 In addition, [t]he parties additionally should address whether license conditions or other forms of assurances are warranted.110 At the end of Section III.C.1.h, the NRC reaffirms that the applicants should outline how they will ensure sufficient DOE-related recoveries or other funding (if 106 Mem. and Order, CLI-22-08, slip op. at 81.

107 Mem. and Order, CLI-22-08, slip op. at 79.

108 Mem. and Order, CLI-22-08, slip op. at 79.

109 Mem. and Order, CLI-22-08, slip op. at 135.

110 Mem. and Order, CLI-22-08, slip op. at 135.

29

applicable) will be available as a means to augment funding if necessary to complete decommissioning.111 Moreover, the NRC expressly requires the applicants, who rely on DOE-related recoveries as a source of funding112, to describe (1) whether any applicable DOE-related settlement in in place; (2) the timetable on which the applicants would expect to file its DOE-related claims (including the respective estimated amounts in damages reasonable expected to be obtained); and (3) approximately when and in what estimated amounts the DOE recoveries can reasonably be expected to be paid.113 Instead of explaining how they will ensure sufficient DOE-related recoveries or other funding (if applicable) will be available as a means to augment funding if necessary to complete decommissioning,114 Holtec focuses only on the 10-year dormancy period.115 Holtecs argument completely ignores the NRCs order addressing this question. Under NRC regulations, for decommissioning activities that delay completion of decommissioning by included a period of storage or surveillance, the licensee must provide a means of adjusting cost estimates and of adjusting the associated funding levels over the storage or surveillance period.116 And, NRC guidance instructs the staff to determine whether the means described by the licensee provides adequate assurance that funds will be available for decommissioning activities at the time they are needed.117 In addition to the 111 Mem. and Order, CLI-22-08, slip op. at 81.

112 Applicants Initial Statement, pp 91-94.

113 Mem. and Order, CLI-22-08, slip op. at 81.

114 Mem. and Order, CLI-22-08, slip op. at 81.

115 Applicants Initial Statement, p 85.

116 Mem. and Order, CLI-22-08, slip op. at 74-75.

117 Mem. and Order, CLI-22-08, slip op. at 79-80 (emphasis in the original.)

30

narrowing of the question presented by the NRC in this case, Holtec makes several other misstatements that the NRC already addressed in its order granting this hearing. Holtec argues, citing the order, that the NRC has no requirement that prevents an application from relying on a single funding source.118 Although that is an accurate statement, the NRC explained that this argument by Holtec mischaracterizes the application in this case.119 Addressing this argument made by Holtec in its earlier briefs, the NRC notes that the applicants highlight that the Palisades application explicitly states that DOE reimbursements of spent fuel management expenses would provide a substantial source of additional funds in case an adjustment were needed.120 Thus, reliance on just the single funding source, is not Holtec what chose to do in its application.

Similarly, in response to arguments about a lack of adequate assurance to adjust funding levels as necessary, Holtec argues that it also [has] the ability to enlarge that cushion by adjusting its decommissioning schedule since NRC regulations allow a license 60 years from shutdown to complete decommissioning activities.121 Not only does this not provide a cushion as explained by Attorney General expert witness Nicholas Capik, but also the NRC explained in its order that

[t]his is a separate issue, however, than whether reimbursements from DOE would 118 Applicants Initial Statement, p 87.

119 Mem. and Order, CLI-22-08, slip op. at 77.

120 Mem. And Order, CLI-22-08, clip op. at 77 (citation omitted.)

121 Applicants Initial Statement, p 89.

31

provide the means to adjust decommissioning funding, and neither the application nor the cost estimate discuss or rely on extending the dormancy period.122 Again, in response to arguments about the lack of adequate financial assurances, Holtec argues that NRC regulations provide more than an adequate means to address funding issues and that Holtec must continue, until the license is terminated to demonstrate annually that funding for both decommissioning and spent fuel management remains adequate. In response to that exact argument in prior briefs in this case, the NRC explained that while the applicants emphasize that they must file annual reports on decommissioning funding, these status reports will not address the recoveries and they will not indicate how much funding Holtec Palisades may have recovered nor whether some, all, or none of the funds remain available to adjust funding.123 Problems with Applicants ability to provide additional financial assurance as a means to adjust funding and the need for license conditions or other forms of assurances in this case.

Attorney General expert Nicholas Capik testified that there are numerous reasons that Holtecs DCE could understate actual costs, including an increase in scope due to unforeseen conditions, any delay in performance of activities, inflation beyond what is assumed with two percent real growth of the NDT, or higher than anticipated actual costs 14 years from now when decommissioning activities commence.124 He explained that delaying decommissioning activities (beyond 122 Mem. and Order, CLI-22-08, slip op. at 76, fn 258.

123 Mem. and Order, CLI-22-08, slip op. at 79.

124 Exhibit MICH001, p 13.

32

Holtecs 10-year dormancy period) will not address a situation with insufficient funds because two percent real growth on $325.5 million (the amount Holtec projects for the end of the dormancy period) will only grow by $6.3 million a year, which is barely enough to cover the $4.4 million a year to store and maintain the facility as estimated by Holtec.125 Thus, it would require many years of dormancy to address a shortfall in funding. Moreover, as noted by the NRC, neither Holtecs application nor the cost estimate discuss or rely on extending the dormancy period.126 As to the spent fuel management costs from DOE that Holtec relies upon, there are two significant problems. First, any recovery on a Holtec claim for ISFSI construction costs and cask loading (the largest portion of spent fuel management costs) would be paid many years before decommissioning activities, and thus not necessarily available unless recovered funds were segregated and could not be withdrawn for other purposes.127 Second, Mr. Capik noted that a sizeable portion of the projected spent fuel management costs (specifically related to transfer of spent fuel to DOE) may not be recovered from DOE or could be subject to an offset that significantly reduces recovery.128 An excellent colloquy between Judge Gibson and Holtec expert Mr. Goulette demonstrates the problem with Holtec Palisades having no resources other than the trust fund:

125 Exhibit MICH001, p 13.

126 Mem. and Order, CLI-22-08, slip op. at 76, fn 258.

127 Exhibit MICH001, p 13.

128 Exhibit MICH001, p 14.

33

34 Thus, Holtecs experts response to the lack of assurance is that there is an annual report and update. As noted earlier in the discussion about Holtecs contingency, the annual report just notifies the NRC that a problem has occurred but doesnt provide any way to remedy it especially when Holtec Palisades lacks any funds other than the trust fund and has no arrangement with the parent company, Holtec International, to provide additional funds if necessary or retain the DOE funds for such a purpose.

During the February Hearing, Mr. Capik reiterated this point as follows:

MR. CAPIK: The issue is that an LLC with no source of income, no assets, if there's a shortfall, has no ability on its own to ensure the shortfall is met. So, there is an obligation to file the reports every year and to explain how you are going to address a shortfall, but the LLC doesn't have the ability to do that.

There have been a number of nuclear power plants that have gone bankrupt. The most recent was last year. There have been applicants or licensees that have run out of money during decommissioning. The most recent of those is Zion. And in that case, Zion130 had a -- or EnergySolutions had a parental guarantee.

So, EnergySolutions is funding the continuing costs.

130 Information on Zion Nuclear Power Station and the parental guarantee can be found in NRC Docket Nos. 50-295 and 50-304 with a March 26, 2020, Report on Status of Decommissioning Funding for Shutdown Reactors ML20097C644.

35

As noted above, the lack of financial assurance could be solved by simply requiring a parental guarantee between Holtec International and its subsidiary Holtec Palisades.

In fact, the NRC adopted a similar financial assurance dealing with that Vermont Yankee proceeding132. In that case, the state negotiated substantial additional financial assurance of about $270 million and the NRC, then adopted that financial assurance in its approval of the license transfer.133 These assurances included a parental guarantee, including establishing escrow accounts, retaining funds, including DOE recoveries, and limits on the use of the trust fund for spend fuel management thus creating a layered approach to financial assurance.134 In fact, Judge Gibsons Exhibit PSO003 references a parental guarantee involving Dominion Energy Kewaunee and quotes the NRC Staff as follows During the phone calls with DEK representatives, the NRC Staff indicated that one acceptable method of adjusting funding levels would be through a commitment from DEKs parent to provide a parent company guarantee should additional funding assurance be necessary.135 Mr. Capik explained that for several other nuclear decommissionings, some of which Holtec is involved with, the company performing the decommissioning has provided financial assurances.136 For example, Mr. Capik explained that for the 132 Information on the Vermont Yankee proceeding can be found in Docket Nos. 50-271 and 72-59 ML18242A638.

133 February 9, 2023, Hearing Transcript, pp 501:14-502:3.

134 February 9, 2023, Hearing Transcript, pp 501:14-502:3.

135 Exhibit PSO003, p 6.

136 Exhibit MICH001, p 14.

36

Vermont Yankee, NorthStars financial assurance included a parental support agreement of $140 million, escrow accounts of at least $55 million, performance bonds of approximately $400 million, a $ 25 million letter of credit, retained DOE proceeds, and a commitment not to withdraw funds for any task exceeding the allocated cost in a schedule provided.137 For Indian Point, which has $2.4 billion in the NDT, Holtec agreed to minimum NDT balances of $400 million at 10 years and $360 million at Partial Site Release (PSR), when the operating license footprint is reduced to the ISFSI and return of 50 percent of the DOE recoveries to the NDT.138 For Pilgrim, Holtec agreed to minimum NDT balances ($193.3 million 2019 dollars at PSR adjusted as decommissioning proceeds, as well as a minimum balance until all fuel is removed from the site), use of DOE recoveries if needed to maintain the minimum balances, performance bonds, $30 million of insurance, and additional financial reporting requirements.139 These financial assurances were in addition to starting with a NDT balance of approximately $1 billion, which is significantly more than for Palisades.140 Mr. Capik further elaborated on why additional financial insurance is important for Palisades by examining the six plants (Oyster Creek, Pilgrim, Indian Point (3 plants on a single site), and Palisades) that Holtec purchased from Entergy 137 Exhibit MICH001, p 14.

138 Exhibit MICH001, p 14.

139 Exhibit MICH001, p 15.

140 Exhibit MICH001, p 15.

37

to decommission.141 He explained that each power plant had a different NDT fund as well as a different estimated license termination costs as follows:

a. Oyster Creek - $848 million NDT with $618 million estimated for license termination;
b. Pilgrim - $1,030 million NDT with $593 million estimated for license termination;
c. Indian Point Unit 1 - $534 million NDT with $485 million estimated for license termination;
d. Indian Point Unit 2 - $654 million NDT with $469 million estimated for license termination;
e. Indian Point Unit 3 - $916 million NDT with $583 million estimated for license termination; and
f. Palisades - $552 million NDT with $443 million estimated for license termination, including approximately $45 million for a ten-year dormancy period (for a comparable license termination cost of $398 million).142 The importance of this comparison is that the estimated cost to remediate and dismantle Palisades is less than every other plant owned by Holtec and there is less funding available for this work at Palisades compared to every other Holtec plant.143 In calculating the funding available for license termination (separate from spent fuel management and site restoration), Mr. Capik used the projected NDT fund balance plus projected earnings and subtracted estimated fuel management and site restoration costs.144 He explained that although detailed activities will vary from plant to plant, the decommissioning projects have to comply with the same 141 Exhibit MICH019, p 1.

142 Exhibit MICH019, pp 1-2 (citations omitted).

143 Exhibit MICH019, p 2.

144 Exhibit MICH019, pp 2-3.

38

regulations and thus have similar organizational structures (and departments).145 The plants also have similar waste disposal volumes (1.13 million cubic feet for Palisades compared to 0.956 million cubic feet for Oyster Creek, 1.42 million cubic feet for Pilgrim, and 1.365 million cubic feet for Indian Point 2).146 Thus, Mr. Capik explained that he would expect similar costs for Palisades to these other Holtec units, but instead there are wide and unexplained differences.147 For example, to maintain the on-site ISFSI there is a wide difference on estimated costs, even though the activities at the various ISFSIs are the same and the regulations applying to those facilities are the same.148 As Mr. Capik stated, Holtec has provided no explanation for why the estimated costs to maintain the Palisades ISFSI are markedly less than its other ISFSIs, given that the same requirements apply.149 An even more significant but unexplained difference exists for funds remaining when all radioactive material is removed from the site (except for spent fuel) as follows:

a. Palisades - $20 million;
b. Oyster Creek - $127 million;
c. Pilgrim - $217 million; and
d. Indian Point - $450 million.150 145 Exhibit MICH019, p 3.

146 Exhibit MICH019, p 3.

147 Exhibit MICH019, p 3.

148 Exhibit MICH019, pp 3-4 (showing Palisades at $1.7 million, Indian Point at $4.8 million (during active decommissioning), Pilgrim at $6 million, and Oyster Creek at $8 million).

149 Exhibit MICH019, p 4.

150 Exhibit MICH019, p 4.

39

Mr. Capik explained that this number is important because it is a measure of funds available for risk mitigation to address cost increases prior to license termination or when the licensed footprint is shrunk to the ISFSI. As shown in his testimony, Palisades has the smallest remaining balance and thus the least ability to mitigate any potential cost increases.151 After reviewing these comparisons and unexplained differences in estimated costs, Mr. Capik concluded that Palisades has the lowest estimated license termination cost, the lowest estimated annual spent fuel management cost for dry storage, the lowest available funding, and the lowest funds remaining following radioactive remediation (partial site release or license termination).152 Even though Holtec doesnt explain the differences, the answer is clear when looking at the big picture. Holtec knew the amount available in Palisades NDT at the time of the deal with Entergy on the six nuclear plants and Holtec had to alter its analysis on estimated costs for Palisades to fit within the NDT. This explains why Palisades has the lowest estimated license termination costs, the lowest estimated annual spent fuel management cost for dry storage, the lowest funds remaining following radioactive remediation, and finally the lowest available funding. This also underscores why additional financial assurances are necessary in this case.

Interestingly, in four of the other five plants being decommissioned by Holtec, the states have negotiated additional increased financial assurance due to risk of insufficient funds. Here, with Palisades, this concern is significantly heightened 151 Exhibit MICH019, p 4.

152 Exhibit MICH019, pp 4-5 (emphasis in the original).

40

since it has the least amount of funding. Yet, no additional financial assurance has been negotiated for Palisades.

Holtec attempts, in its initial statement, to explain the lower costs for Palisades as lessons learned from the other plants, but Mr. Capik laid out why that is unsupported and inaccurate.153 To begin with, Holtec has already incurred $572 million at Pilgrim and $573 million at Oyster Creek through September of 2022, both of which already exceeds the NDT for Palisades.154 Moreover, in both cases, Holtec has yet to complete reactor vessel segmentation and there appears to be minimal progress on other power block buildings.155 Holtec filed the Palisades DCE in December of 2020. From January 2019 through May 2022, only 110,977 cubic feet of waste was shipped from the Pilgrim site, out of an estimated 1,419,563 total cubic feet (7.8%).156 Similarly, for Oyster Creek, from January 2019 through December 2021, only 222,072 cubic feet of waste was shipped off site, out of an estimated 956,029 total cubic feet (23.6%).157 Mr. Capik explained [t]hus even looking to a period after the Palisades DCE was generated and submitted, Holtec has not gained sufficient experience to justify a substantial reduction in estimated costs.158 Mr. Capik explained that Holtec has not committed to any additional financial assurance in this case.159 Holtec claims that it has multiple avenues for ensuring there will be sufficient funds, but it never provides any new assurance or 153 Exhibit MICH019, p 5.

154 Exhibit MICH019, p 5.

155 Exhibit MICH019, p 5.

156 Exhibit MICH019, p 5.

157 Exhibit MICH019, p 5.

158 Exhibit MICH019, p 5.

159 Exhibit MICH019, pp 5-6.

41

commitment.160 In fact, Holtecs arguments regarding any additional assurance can be summarized with its statement regarding DOE recoveries when it says there is no reason to think that those funds would not remain available to cover the shortfall.161 Mr. Capik then summarized Holtec claims that it has multiple avenues for ensuring there will be sufficient funds and he explains why none of those claims are accurate:

a. First, Holtec points to a sufficient cushion in the NDT resulting from its predicted $19,788,000 remaining at license termination. As noted above, this cushion is only realized if the Palisades costs are significantly less than other Holtec projects (which includes its unreasonable assumptions regarding spent fuel management acceptance dates and annual costs).

b.

c. Third, Holtec suggests it can extend the dormancy period to allow the NDT time for further growth. As discussed in my initial testimony, it is not clear that such extended dormancy would result in substantial additional funding, Also, Holtec did not assess any costs that may be incurred to demobilize and place the facility in a storage condition and costs to remobilize for dismantlement should the shortfall be identified after dismantlement begins.
d. Finally, Holtec points to recovery of SNF management costs from DOE. There are two issues with this assertion. First and most 160 Exhibit MICH019, p 6.

161 Applicants Initial Statement, p 93.

42

important, Holtec makes no commitment to keep any recovery within Holtec Palisades (as opposed to funds being transferred to the parent entity). If Holtec Palisades does not have a commitment to retain these funds for decommissioning, it is not reasonable to rely on these funds being available. Any recovery for Holtecs initial claim (estimated to be over $90 million based on Holtecs projected cash flow) is likely to be received no later than 2032 (contrary to Holtecs assertion) based on the statute of limitations requiring a claim to be filed no later than 2028 if all funds from the purchase of Palisades in 2022 are to be recovered, and a typical time from the end of a period of incurred costs to recovery of costs is between three and four years, resulting in a recovery of costs incurred through 2028 by the end of 2032. Thus, the availability of funds recovered from DOE to address a shortfall that may not occur until later in the decommissioning process (2038 or later) is unlikely unless such funds are segregated and preserved.162 In summary, Holtecs claims of multiple avenues of ensuring sufficient funds remain unsupported and inaccurate; Holtec refuses to provide any commitment to additional financial assurance, relying instead on statements like there is no reason to think that those funds would not remain available in the face of multiple reasons explaining why; and Holtec claims no license conditions are warranted, irrespective of the actual facts in this case demonstrating the need for some license conditions or commitments. Accordingly, Holtec has failed to adequately describe how it will ensure that sufficient additional funding will be available as a means to adjust funding if needed, and thus some license conditions or other forms of assurances are necessary.

162 Exhibit MICH019, pp 6-7 (citations omitted).

43

CONCLUSION At base, the application is inadequate to demonstrate that Applicants have the financial qualifications to carry out the activities for which the license is sought. The NRC should hold Holtec and all related entities to a high standard that protects the interests of the state of Michigan, those who live near the Palisades plant, future generations of taxpayers, and all of those who live in the Great Lakes watershed.

Giving Holtec a pass here and not requiring that sufficient financial assurances be provided risks the money, health, and wellbeing of millions of Americans for generations to come.

Due to these concerns and on behalf of the People of the State of Michigan, Attorney General Dana Nessel requests that the Commission require the Applicants to provide additional forms of financial assurance as it has in other license transfer cases discussed in the Attorney Generals briefs and testimony including, but not limited to, limitations on withdrawals on a line item basis not to exceed the line item value on the DCE submitted as part of the license transfer, a clear commitment to retain DOE recoveries and to have them remain available throughout decommissioning, as well as a parental guarantee, escrow accounts, and/or a line of credit, the three of which combined provide an additional assurance of $200 million.

44

Respectfully submitted, Dana Nessel Attorney General State of Michigan Signed (electronically) by

/s/ Michael E. Moody Michael E. Moody Joel King Assistant Attorneys General Special Litigation Division P.O. Box 30755 Lansing, Michigan 48909 MoodyM2@michigan.gov (517) 335-7627 Dated: March 20, 2023 45

STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of ) Docket Nos. 50-255-LT-2 ENTERGY NUCLEAR OPERATIONS, ) 50-155-LT-2 INC., ENTERGY NUCLEAR ) 72-007-LT PALISADES, LLC, HOLTEC ) 72-043-LT-2 INTERNATIONAL, and HOLTEC )

DECOMMISSIONING

) ASLBP No. 22-974-01-LT-BD01 INTERNATIONAL, LLC

)

)

(Palisades Nuclear Plant and Big

)

Rock Point Site)

)

CERTIFICATION OF SERVICE Pursuant to 10 C.F.R. § 2.305, I certify that I served the Michigan Attorney Generals Post Hearing Statement of Position in the above-captioned proceeding via the NRCs Electronic Information Exchange on March 20, 2023.

Signed (electronically) by

/s/ Michael E. Moody Michael E. Moody Assistant Attorney General Special Litigation Division P.O. Box 30755 Lansing, Michigan 48909 MoodyM2@michigan.gov (517) 335-7627 Dated: March 20, 2023 46