ML23004A152
| ML23004A152 | |
| Person / Time | |
|---|---|
| Site: | Palisades, Big Rock Point File:Consumers Energy icon.png |
| Issue date: | 12/16/2022 |
| From: | King J, Moody M, Nessel D State of MI, Dept of Attorney General |
| To: | Atomic Safety and Licensing Board Panel |
| SECY RAS | |
| References | |
| License Transfer, RAS 56588, 50-255-LT-2, 50-155-LT-2, 72-007-LT, 72-043-LT-2, ASLBP 22-974-01-LT-BD01 | |
| Download: ML23004A152 (0) | |
Text
UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of ENTERGY NUCLEAR OPERATIONS, INC., ENTERGY NUCLEAR PALISADES, LLC, HOLTEC INTERNATIONAL, and HOLTEC DECOMMISSIONING INTERNATIONAL, LLC (Palisades Nuclear Plant and Big Rock Point Site)
)
Docket Nos.
)
)
)
)
)
ASLBP No.
)
)
)
)
50-255-LT-2 50-155-LT-2 72-007-LT 72-043-LT-2 22-974-01-LT-BD01 MICHIGAN ATTORNEY GENERALS WRITTEN RESPONSES AND REBUTTAL TESTIMONY WITH SUPPORTING AFFIDAVIT Dana Nessel Attorney General State of Michigan Michael E. Moody Joel B. King Assistant Attorneys General Special Litigation Division P.O. Box 30755 Lansing, Michigan 48909 MoodyM2@michigan.gov KingJ38@michigan.gov (517) 335-7627 Dated: December 16, 2022
i TABLE OF CONTENTS Page Index of Authorities....................................................................................................... ii List of Abbreviations and Acronyms........................................................................... iiii Introduction................................................................................................................... 1 Attorney Generals Written Responses......................................................................... 6 A.
Projected length of time for transfer of all spent nuclear fuel off of the Palisades site.................................................................................. 6 B.
Reasonableness of the site-specific decommissioning cost estimate falling below the minimum formula amount......................... 11 C.
Contingency Funding............................................................................. 15 D.
Additional Financial Assurances........................................................... 24 Conclusion.................................................................................................................... 36
ii INDEX OF AUTHORITIES Page Cases In re Smith, 79 N.R.C. 131; 2014 NRC LEXIS 16......................................................................... 4 Regulations 10 C.F.R. § 2.325............................................................................................................ 4 10 C.F.R. § 50.75(b).......................................................................................... 11, 12, 14
iii LIST OF ABBREVIATIONS AND ACRONYMS Applicants Entergy Nuclear Operations, Inc.; Entergy Nuclear Palisades, LLC; Holtec International; and Holtec Decommissioning International, LLC ASLB Atomic Safety and Licensing Board BWR Boiling water reactor CDI Comprehensive Decommissioning International, LLC DCE Decommissioning Cost Estimate DOE United States Department of Energy Enbridge Enbridge, Inc.
ENOI Entergy Nuclear Operations, Inc.
Entergy Entergy Nuclear Operations, Inc.; and Entergy Nuclear Palisades FERC Federal Energy Regulatory Commission GAO Government Accounting Office GTCC Greater-than-class-C waste HDI Holtec Decommissioning International, LLC Holtec Holtec Intl; CDI; HDI; or Holtec Palisades Holtec Intl Holtec International Holtec Palisades Holtec Palisades, LLC ISFSI Independent spent fuel storage installation LTA License transfer application MPSC Michigan Public Service Commission NAMCo Nuclear Asset Management Company, LLC NRC United States Nuclear Regulatory Commission Oyster Creek Oyster Creek Nuclear Generating Station (New Jersey)
iv PFAS Per-and polyfluorinated alkyl substances PHMSA Pipeline and Hazardous Materials Safety Administration Pilgrim Pilgrim Nuclear Power Station (Massachusetts)
PNNL Pacific Northwest National Laboratory PSDAR Post-shutdown decommissioning activities report PWR Pressurized water reactor State State of Michigan TVA Tennessee Valley Authority
1 INTRODUCTION The Nuclear Regulatory Commission (NRC) is considering whether to grant an application by Entergy Nuclear Operations, Inc. (ENOI); Entergy Nuclear Palisades, LLC (ENP) (together Entergy); Holtec International (Holtec); and Holtec Decommissioning International, LLC (HDI) (collectively Applicants) requesting approval to transfer the operating licenses for the Palisades Nuclear Plant, Big Rock Point Plant, and associated independent spent fuel storage installations (ISFSI) from Entergy to Holtec and HDI.1 The license transfer application notes that Entergy plans to transfer all of the assets and liabilities of ENP to a new entity that will become Holtec Palisades, LLC (Holtec Palisades).2 The LTA also notes that Nuclear Asset Management Company, LLC (NAMCo), a wholly-owned subsidiary of Holtec, will acquire the equity interests in either the new Holtec Palisades or the parent company owner of Holtec Palisades; either way, emerging as the direct parent company of Holtec Palisades.3 Holtec plans to engage another Holtec subsidiary, Comprehensive Decommissioning International, LLC (CDI), to decommission the single unit at Palisades, restore the site, and manage on-1 License Transfer Application (LTA) at 12 (Dec. 23, 2020.)
2 LTA at 2 (Dec. 23, 2020.)
3 LTA at 2 (Dec. 23, 2020.)
2 site spent nuclear fuel.4 Holtec5 represents that it will release the site for unrestricted use by approximately 2041.6 On February 24, 2021, the Michigan Attorney General (Attorney General, MIAG, or AG) filed with the NRC a petition for leave to intervene and request for a hearing.7 In December 2021, the NRC Staff issued an order approving both the transfer of the licenses and draft conforming license amendments as well as approving a related regulatory exemption requested by HDI in support of the license transfer application.8 Although the Staff issued this order, the NRC explained that the staffs order approving the license transfer... remains subject to our authority to rescind, modify, or condition the approved transfer based on the outcome of this adjudicatory proceeding.9 On July 15, 2022, the NRC issued its Memorandum and Order granting the Attorney Generals petition to intervene and request for a hearing.10 In the order, the NRC explained that an application for a license transfer must contain sufficient information to demonstrate that the applicant has the financial qualifications to carry out the activities for which the license is sought, and the 4 LTA at 2-3 (Dec. 23, 2020). As noted in the NRCs Memorandum and Order in this case, HDI later informed the NRC that HDI no longer plans to contract with CDI to serve as the decommissioning general contractor for Palisades and that HDI is absorbing CDIs resources and will directly employ site personnel to perform the scope of work previously planned to be executed by CDI. Entergy Nuclear Operations, Inc. (Palisades Nuclear Plant and Big Rock Point Site), Memorandum and Order, CLI-22-08, __ NRC __, slip op. (July 15, 2022), p 5.
5 Throughout this petition, use of the term Holtec refers to any or all of Holtec Intl, CDI, HDI, or Holtec Palisades unless otherwise specified.
6 LTA at 3 (Dec. 23, 2020.)
7 Petition of the Michigan Attorney General for Leave to Intervene and for a Hearing, February 24, 2021.
8 Mem. and Order, CLI-22-08, slip op. at 1.
9 Mem. and Order, CLI-22-08, slip op. at 2.
10 Mem. and Order, CLI-22-08, slip op.
3 application also must provide reasonable assurance that funds will be available to decommission the facility including any ISFSI.11 The NRC further explained that its license transfer regulations do not require an applicant to demonstrate financial qualifications to cover site restoration costs, but that in this case [s]ite restoration costs nonetheless are relevant to this proceeding because Holtec intends to pay for those costs with the Palisades decommissioning trust, on which Holtec relies for its showing of financial qualifications.12 Although the Attorney General raised two contentions, the NRC admitted only four issues raised in the first contention. Those issues are as follows: (1) the Applicants estimated 11-year timeframe for the removal by DOE of all of the spent fuel at Palisades; (2) the reasonableness of the site-specific decommissioning cost estimates falling well below the minimum formula amount; (3) the 12% contingency allowance allocated to the radiological decommissioning, spent fuel management, and site restoration cost estimate; and (4) the Applicants description of their planned means to adjust funding if necessary to complete decommissioning and terminate the license.13 The parties filed Initial Statements, Exhibits, and Affidavits on November 18, 2022. What follows here are written responses to Applicants Initial Statements and Expert Testimony, filed pursuant to the schedule ordered the Judge in this case. As a reminder, this proceeding deals with Holtecs request for license transfer 11 Mem. and Order, CLI-22-08, slip op. at 7.
12 Mem. and Order, CLI-22-08, slip op. at 10.
13 Mem. and Order, CLI-22-08, slip op. at 18.
4 approval.14 Much of Holtecs argument in its initial statements strays into what happens when the plant is actually being decommissioned, but that is not at issue at this point, because the license transfer approval is not yet considered final.
Moreover, as provided in 10 C.F.R. § 2.325, Holtec bears the burden of proof in this case and must support its application by a preponderance of evidence. In re Smith, 79 N.R.C. 131, 149; 2014 NRC LEXIS 16.
As stated in her Petition, the Attorney General supports prompt, thorough, and safe decommissioning and site restoration at Palisades and Big Rock, but she does not believe Holtec possesses the financial qualifications or assurances necessary to complete such a risk-intensive project. At the outset of this filing, the Attorney General comments that she hopes common sense will prevail in this proceeding and that appropriate safeguards will be put in place to make sure that future generations of Michiganders are not stuck covering costs that should be the responsibility of the party decommissioning Big Rock and Palisades. Simply put, those safeguards do not exist if HDIs proposal goes forward as laid out in its application. There is too much uncertainty surrounding where monies for any shortfall would come from and nothing in this proceeding has addressed those concerns. HDIs vague, unpersuasive initial statements only add to the lack of clarity and fail to answer, as laid out below, the questions posed by the NRC in its opinion. Accordingly, the Attorney General appreciates that the NRC granted her 14 Mem. and Order, CLI-22-08, slip op. at 2.
5 petition and that it is seeking further answers from the applicants to the arguments raised in the Attorney Generals petition.
6 ATTORNEY GENERALS WRITTEN RESPONSES A.
Projected length of time for transfer of all spent nuclear fuel off of the Palisades site In its July 15, 2022 order, the Commission granted the Michigan Attorney Generals petition for hearing and intervention and noted that the hearing would be limited to four of the Attorney Generals challenges to the application. The first challenge noted by the Commission is the length of time to transfer spent fuel off of the Palisades site:
(a) The projected length of the time for transfer of all spent fuel off of the Palisades site:
The applicants should address how they determined that the estimated 11-year spent fuel transfer period constitutes a plausible timeframe for removal of all Palisades spent fuel. In their description, the applicants should clarify the assumptions on which they relied, including what fuel acceptance priority and fuel allocation or transfer rate they assumed for their schedule.
In assessing financial qualifications for a license transfer we accept plausible forecasts. The parties arguments therefore should address whether the estimated 11-year period reflects a plausible timeframe to complete the fuel transfer.15 So, the Commissions directive to HDI was to address whether the estimated 11-year period reflects a plausible timeframe to complete the fuel transfer.
The Attorney General addressed this in her initial statements and continues to argue that the 11-year period is not a plausible timeframe in which to complete the fuel transfer.16 15 Mem. and Order, CLI-22-08, slip op. at 134.
16 Michigan Attorney General Initial Statement, pp 6-8.
7 In its first statement of position on the Attorney Generals admitted contentions, HDI argues that it is plausible that, once it begins performance, DOE will accept all of the SNF at Palisades within the eleven-year window assumed in the DCE.17 The Attorney General disagrees with HDIs argument and provides a reply here.
At base, in its initial statements HDI fails to address the NRCs question and instead adds more uncertainty into its request. On page 12 of its statements, HDI notes that, [t]he Commission did order HDI to address how [it] determined that the estimated 11-year spent fuel transfer period constitutes a plausible timeframe for removal of all Palisades spent fuel.18 However, HDI immediately twists that directive, stating that, [t]hus, the only question regarding HDIs assumed SNF transfer timeline that is at issue in this proceeding is whether an eleven-year transfer window is plausible.19 This is not what the NRC asked. The NRC asked how HDI determined, as discussed in its license transfer application (LTA), that an 11-year transfer period is plausible. HDIs statements, however, avoid the NRCs question and instead raise new scenarios and hypotheticals that were not included in its LTA nor reviewed by NRC staff or other interested parties.
Specifically, HDIs statements discuss fifty-plus years of the Nuclear Waste Policy Act (NWPA)20 and then assert that, no matter what was said in its actual LTA, there are multiple paradigms that would allow HDI to transfer all Palisades 17 Applicants Initial Statement p 11.
18 Applicants Initial Statement p 12, internal citation omitted.
19 Applicants Initial Statement p 12.
20 Applicants Initial Statement pp 13-18.
8 SNF offsite within 11 years.
There are several problems with each of these newly raised paradigms. First, none of this was included in HDIs application. To include completely new arguments and vague, unsupported ideas at this point in the process is untimely and therefore improper.
HDI cannot re-work its application at this stage of the proceeding by tossing out untested hypotheticals that rely on self-serving speculation.
HDI has no control over DOE and cannot purport to speak for DOE. Decades of delays and nuclear waste stalemate make all timelines discussed in this case highly suspect and unlikely to come to fruition, but that aside, even if DOE were to get a program up and running, it is certain that the early years of the rollout would go slowly and
9 that DOE would ease into a ramp-up, as the organization figured out how to safely, cost-effectively, and efficiently transport SNF. HDIs speculation to the contrary should be rejected by the Commission.
Regardless of HDIs failure to address the Commissions question, transfer of all of Palisades SNF offsite within an 11-year window is simply not plausible, as it is neither reasonable nor probable to believe such a transfer will occur.24 Attorney General expert Nick Capik provides specific discussion on this in his rebuttal testimony. He notes numerous reasons that HDIs fuel removal date discussion is implausible under even the most optimistic of scenarios. These include that:
- a. Holtecs 2030 date was predicated on a 2013 projection, with DOE starting a pilot program by 2021 and starting to actually accept significant amounts of SNF by 2025. Since that 2013 projection, little to no progress has been made, resulting in Holtec assuming an additional five-year delay in accepting significant amounts of SNF, to the 2030 date. However, since that 2020 assumption an additional two years have passed, with no new progress. Thus, all other assumptions being the same, the final acceptance should be no earlier than 2042. Additionally, HDIs spent fuel management plan was never updated per 10 CFR 50.54(bb) for this substantial change.25
- b.
24 The Oxford Languages Dictionary defines plausible as seeming reasonable or probable.
Additionally, in In re La. Energy Servs., L.P., 45 N.R.C. 99; 1997 NRC LEXIS 19, the NRC noted that Although in its hearing notice the Commission listed a number of possible generic tails disposal strategies such as storage of tails at the plant site as a possible future resource or conversion of tails to uranium oxide for disposal, the Commission did not specifically define what constitutes a plausible strategy. The plain meaning of these terms, however, provides the answer. The dictionary defines plausible as reasonable or credible, Websters Third New International Dictionary 1736 (1971). [emphasis added] Board Decision, p 5 (Lexis pagination).
See also In re La. Energy Servs., L.P., 63 N.R.C. 591; 2006 NRC LEXIS 212, Board Decision, p 637.
25 Exhibit MICH019, pp 8-9.
10 Along with those observations, the Attorney General also notes that,
- a.
This is another example of the lack of plausibility in HDIs analyses.
- b.
The 2013 DOE study notes that the NWPA must be changed.29 Again, HDI is engaging in hopeful speculation that this is a possibility and does not have any control over whether it happens.
- c.
Delivery Commitment Schedules per the Standard Contract are not issued for all fuel at the beginning of performance. DOE expects them to be issued 63 months before delivery (see Article V.B.1).
- d.
DOE has considered using multiple, parallel systems to process incoming fuel. One option considered (and likely the primary one at the time) would have used a small part of that parallel processing for fuel from ISFSIs. The remaining systems would have been used for fuel from operating plants (directly from fuel pools). Again, HDI and its expert are engaging in speculation about what may happen in the future with no basis or knowledge of the physical design.
- e. Fuel out dates for Pilgrim (2062), and Indian Point (2061 for IP3) make HDIs projections here all the more implausible. The AG also notes that Oyster Creek had a projected 2025 start date for removing fuel, and 2035 for fuel off site, and that has not been revised as is required by regulation.
29 Exhibit MICH031.
11
- f. Using the original Holtec assumption of OFF at 3,000 MTU per year results in a 2064 fuel out date.30 If the rate in the 2013 NRC study is accepted, the final acceptance would result in a 2078 fuel out date.
The point here is that, regardless of the assumptions used, a mechanism for providing additional funding is needed.
As HDI has failed to answer the Commissions question of why it determined, in its LTA, that an 11-year timeframe to transfer all of Palisades SNF offsite is plausible, and as under any even remotely plausible scenario Palisades SNF transfer will take much longer than 11 years, HDI has failed to adequately address either this challenge or the Attorney Generals concerns.
B.
Reasonableness of the site-specific decommissioning cost estimate falling below the minimum formula amount The second challenge the Commission admitted was as to the reasonableness of the site-specific decommissioning cost estimate falling below the minimum formula amount:
(b) Reasonableness of the site-specific decommissioning cost estimate falling below the minimum formula amount:
The applicants should provide a detailed explanation of the primary reasons that the cost estimate falls significantly below the minimum formula amount. We also direct the parties and invite the staff to address whether the minimum formula regulation in section 50.75(b) applies to this application.32 So, the Commissions directive to HDI was twofold: (1) to explain why its site-specific decommissioning cost estimate (DCE) falls significantly below the minimum 30 Exhibit MICH001, pp 4-5.
32 Mem. and Order, CLI-22-08, slip op. at 134.
12 formula amount, and (2) to address whether the minimum formula regulation in section 50.75(b) applies to this application.
The Attorney General addressed this in her initial statements and continues to argue that (1) it is not reasonable for the site-specific DTE to fall significantly below the minimum formula amount, and (2) that the minimum formula regulation in section 50.75(b) applies to this application.33 In its first statement of position on the Attorney Generals admitted contentions, HDI argues that the HDI cost estimate reasonably falls below the NRC formula amount due to differences between the formulas vintage and generic purpose and the HDI estimates basis on contemporaneous project-specific inputs.34 The Attorney General disagrees with HDIs argument and provides a reply here.
In its initial statement, HDI provides more than 30 pages of discussion that raise a host of different arguments. First, applicants address the legal question of whether 10 C.F.R. § 50.75(b) applies to this application and second provide its rationale for why the DCE falls significantly below the minimum formula amount.
10 C.F.R. § 50.75(b)
Applicants argue that the purpose of the minimum formula in § 50.75 is to ensure during operations that licensees have a viable plan to accumulate funds...
by the projected time of permanent cessation of operations.35 They then go on to state that the text of § 50.75(b) itself is clearly limited to the certification that the 33 Michigan Attorney General Initial Statement, pp 8-11.
34 Applicants Initial Statement p 11.
35 Applicants Initial Statement p 28.
13 licensee is collecting adequate funds based on the formula, and that the certification is not required during decommissioning, and there is no requirement in § 50.75 or elsewhere that a § 50.82 SSCE be more, but not less, than the formula amount.36 The clear problem with this is that this proceeding solely covers HDIs license transfer application.37 It does not, as HDIs statement explicitly contemplates, cover the decommissioning stage. Thus, HDIs entire argument attempts to move the discussion past the point of this proceeding and deal with requirements at the decommissioning stage, which has not yet been reached.
The AG argues that it is clear that 10 C.F.R. § 50.75(b) and the minimum formula amount apply at this stage of the proceeding. The unambiguous language requires that each applicant for an operating license under part 50, which HDI is, must submit a decommissioning report that must contain a certification that financial assurance for decommissioning will be (for a license applicant), or has been (for a license holder), provided in an amount which may be more, but not less, than [the formula] in the table in [50.75(c)]. 10 C.F.R. § 50.75(b). Much of the rest of HDIs argument and discussion conflates what is actually at issue in this proceeding, with what is required during the decommissioning process. HDIs argument and deflections to the contrary should be rejected.
36 Applicants Initial Statement p 30.
37 Mem. and Order, CLI-22-08, slip op. at 2 (The staffs order approving the license transfer explicitly remains subject to [the NRCs] authority to rescind, modify, or condition the approved transfer based on the outcome of this adjudicatory proceeding.)
14 DCE and Minimum Formula Amount In the remainder of part two of its initial statement, HDI argues that there are numerous reasons its DCE falls significantly below the minimum formula amount and that ultimately its in-house cost estimate is reasonable. As laid out in the AGs other filings, this is incorrect. Accordingly, even if the NRC finds that HDIs financial assurance did not need to be equal to or greater than the minimum formula, HDI failed to provide a detailed explanation for, and support the reasonableness for, why its cost estimate falls significantly below the minimum formula amount.
Attorney General expert Nick Capik provides further discussion on this in his rebuttal testimony. He notes numerous reasons that the analyses performed by HDIs witnesses are wrong and therefore render its arguments incorrect.
15 Accordingly, the Attorney General continues to argue that the requirements of 10 C.F.R. § 50.75(b) and the minimum formula regulation do apply to this application. HDIs DCE is objectively below the minimum amount and therefore its application is deficient on its face. This alone is sufficient grounds for the NRC to reject HDIs application.
C.
Contingency Funding Background and question presented in this case.
In its order, the NRC explained that site-specific decommissioning cost estimates include an amount added under the title of contingency to cover unknown costs.43 Thus, the identified contingency value, expressed as a percentage, reflects the percentage of the overall final cost estimate that was added as a margin to cover unknown costs.44 The NRC noted that a contingency factor is a nearly universal element in large-scale construction and demolition projects and explained that it expects that
[A] plausible decommissioning cost estimate will include an adequate contingency allowance. The contingency allowance is intended to cover unforeseeable events that are almost certain to occur in decommissioning, based on industry experience. Funds allocated for contingency typically have been expected to be fully expended. These funds are to cover costs considered inevitable in a large project (e.g.
weather delays, equipment breakage). Contingency funds are therefore an integral part of the total cost to complete the decommissioning process.45 43 Mem. and Order, CLI-22-08, slip op. at 43.
44 Mem. and Order, CLI-22-08, slip op. at 43.
45 Mem. and Order, CLI-22-08, slip op. at 49 (citations omitted.)
16 The NRC also addressed two additional important points about contingency funds:
(1) They have not been intended as surplus funds for possible but speculative events but instead funding necessary to cover expected costs; and (2) The annual funding review process... is not intended as a substitute for providing reasonable estimates of expected projected costs in the site-specific decommissioning cost estimate.46 Turning to the instant case, the NRC noted that on estimated project costs of
$644 million, the current projected funding remaining in 2041 is less than $20 million; therefore, even a small increase in the percentage of contingency expenditures could exceed the available funding.47 Although the NRC has rejected other challenges to contingency levels where petitioners had not identified a material supported dispute and the levels on their face did not appear disproportionately low, the NRC explained that [h]ere, the Attorney General claims that the challenged level is both unsupported and inconsistent with industry norms for such analyses....48 Accordingly, the NRC ruled, in its July 15th order granting the hearing, that Holtec should explain not just how they calculated and derived the 12% level applied for contingency, but also how they concluded that this amount for contingency is reasonably adequate for Palisades.49 In addition, the NRC explained that the parties should not just address relevant industry norms, 46 Mem. and Order, CLI-22-08, slip op. at 49-50, n 175 (citation omitted.)
47 Mem. and Order, CLI-22-08, slip op. at 50-51.
48 Mem. And Order, CLI-22-08, slip op. at 46 (citation omitted) 49 Mem. and Order, CLI-22-08, slip op. at 134.
17 practices and standards for the contingency amount added to reactor decommissioning cost estimates as a similar project stage, but also address whether the 12% funding added reflects a plausible amount of funding for covering the contingency costs reasonably expected to be incurred at Palisades.50 Holtecs response to the NRCs question presented Holtec begins its response by immediately confusing the purpose of the contingency in this case. Holtec notes that the contingency is not the only means to address unforeseen costs in the DCE because the DCE includes conservatisms and other sources of funding.51 As explained above by the NRC, the contingency funds have not been intended as surplus funds for possible speculative events but instead funding necessary to cover expected costs.52 Thus, properly developing the contingency is critical to cover unforeseeable events that are almost certain to occur based on industry experience, and therefore, it is not the same as conservatism and other sources of funding and they do not serve the same purpose. In any event, as explained in the Attorney Generals initial statement and in this response, it is the lack of conservatism and the lack of committed other sources of funding (i.e. DOE recovered funds) that makes the contingency funding so important in this case.
Moreover, the NRC noted that the margin for error on the contingency in this case is narrow because even a small increase in the percentage of contingency expenditures could exceed the available funding.53 50 Mem. and Order, CLI-22-08, slip op. at 134-135.
51 Applicants Initial Statement, p 65.
52 Mem. and Order, CLI-22-08, slip op. at 49-50.
53 Mem. and Order, CLI-22-08, slip op. at 50-51.
18 Holtec then provides a discussion that there are no NRC guidelines on the methodology to develop the contingency,54 but that was already discussed in the NRCs order in this case. The NRC explained that it does not provide any guidance on calculating or assessing the contingency allowance for reactor decommissioning cost estimates, but its guidance provides that that a contingency should be separately identified as an allowance for unexpected costs and that the cost estimate should describe how the contingency costs are calculated.55 Holtec next spends some time attacking the NRCs request that Holtec explain how it calculated and derived the 12 percent contingency.56 Holtec notes that the Commission has rejected previous challenges to HDIs contingency amount on other projects, including arguments that HDIs summary-level explanation was insufficient.57 This attack, however, works against Holtec in this case. Not only were the contingencies in these other projects higher than the contingency in this case, but also the fact that the NRC staff has accepted HDIs contingency methodology in four DCEs58 simply shows that the NRC staff didnt know Holtecs (HDIs) contingency methodology was flawed since it only had a summary-level explanation from Holtec. It was only when the NRC examined Holtecs extremely low contingency in this case, coupled with the lack of explanation as to how it was developed, and the inconsistency with industry norms, that the NRC granted the 54 Applicants Initial Statement, p 65.
55 Mem. and Order, CLI-22-08, slip op. at 45.
56 Applicants Initial Statement, pp 65-70.
57 Applicants Initial Statement, pp 65-66.
58 Applicants Initial Statement, p 68.
19 petition and asked Holtec to explain how it calculated the contingency and how it decided the 12 percent contingency amount was reasonably adequate for Palisades.
In fact, the NRC explained that it had rejected other challenges to contingency levels but noted that on their face [they] did not appear disproportionately low.59 Here, Holtecs contingency is on its face disproportionately low as well as objectively too low as explained by Attorney General expert Nicholas Capik in his initial and rebuttal testimony. And, this objectively too low contingency has significant impact on available funding as noted by the NRC when it stated that even a small increase in the percentage of the contingency expenditures could exceed the available funding.60 It is almost like the 12 percent contingency in this case, borrowing a phrase Holtec uses in a later section, coincidentally works out61 to perfectly leave just a few million excess to remain within the parameters of the trust fund.
Holtec finally proceeds to provide an explanation of how it developed the contingency using Mr. Goulettes testimony.62 Holtec concludes that the 12 percent contingency is accurate and that conservatism and other sources of funds will address any funding shortfall.63 However, as Attorney General expert Nicholas Capik explains below as well as in his Initial and Rebuttal testimony, 59 Mem. and Order, CLI-22-08, slip op. at 46 (citation omitted).
60 Mem. and Order, CLI-22-08, slip op. at 51.
61 Applicants Initial Statement, p 93.
62 Applicants Initial Statement, pp 71-82.
63 Applicants Initial Statement, p 84.
20 Problems with Holtecs methodology and further explanation why the 12%
contingency is inadequate for Palisades.
In his Initial Testimony, Mr. Capik explains that the 12 percent contingency used by Holtec for Palisades is inconsistent with industry norms, practices, and standards.65 For example, the Association for the Advancement of Cost Engineering (AACE) in AACE International Recommended Practice No. 18R-97, provides guidelines for identifying proper contingency for various phases of project estimation.66 Mr. Capik opines that Holtecs contingency would be classified as a Class 2 estimate under the AACE guidelines which means that there is a 20 percent probability that costs will ultimately be better than 15 percent below the estimate or worse than 20 percent above the estimate.67 In addition, Holtecs 12 percent contingency is significantly less than the NRC 25 percent contingency guidance for ISFIS decommissioning in NUREG-1757.68 Moreover, Holtecs 12 percent contingency is unexplainably lower than the 19 percent contingency Holtec itself used for the Indian Point project which is the same reactor type as Palisades.69 It is also lower than Holtecs Oyster Creek (15 percent) 65 Exhibit MICH001, p 9.
66 Exhibit MICH001, p 9.
67 Exhibit MICH001, p 10.
68 Exhibit MICH001, p 10.
69 Exhibit MICH001, p 11.
21 and Pilgrim (17 percent) projects.70 Not only is Holtecs contingency for Palisades lower than its other decommissioning projects, but also the majority of work for Palisades will not be performed until over 15 years after the estimate was created, thus creating more estimating uncertainty for Palisades compared to other Holtec projects.71 As Holtec states in its initial statement it is expected that site-specific estimates prepared closer to decommissioning will have a higher degree of certainty and, thus lower contingency.72 Thus, Holtec itself agrees that the contingency for Palisades should be higher than other projects which dont have the 15-year gap.
Mr. Capik further notes that Holtecs Palisades DCE could not have benefitted from lessons learned from these other Holtec projects because at the time Holtec submitted the Palisades DCE, sufficient progress had not yet been made at these other projects to allow for any more accurate estimation for Palisades.73 This refutes Holtecs claim in its Initial Statement that previous experience and actual work progress at the other projects were used to Mr. Goulette in developing the contingency for Palisades.74 70 Exhibit MICH001, p 11.
71 Exhibit MICH001, p 11.
72 Applicants Initial Statement, p 67.
73 Exhibit MICH001, p 12.
74 Applicants Initial Statement, p 71.
75 Exhibit MICH001, p 12.
22 Accordingly, Mr. Capik concludes that a 12 percent contingency is not reasonable given the proposed timing of decommissioning activities and apparent state of contracting.76 After reviewing the details of the risk modeling provided by Holtec in its initial statement and testimony that was used to create the 12 percent contingency, Mr. Capik explains that Holtec actually provides two types of contingency, which together form the 12 percent value they use.77 The second type of contingency included by Holtec is due to discrete events.81 76 Exhibit MICH001, p 12.
77 Exhibit MICH019, p 11.
81 Exhibit MICH019, p 12.
82 Exhibit MICH019, p 12.
23 He concludes that [a]pplying what I believe to be proper mitigation costs and risk probabilities would result in identification of increased risk contingency.85 Mr. Capiks analysis fits with the argument that Holtec had a goal in mind and tailored the modeling to meet the goala low contingency that would fit the amount of money in the trust fund.
In summary, Mr. Capik explains that the risk of underfunding associated with Holtecs 12 percent combined contingency (lower than any other Holtec project) is exacerbated by the lowest estimated license termination of any of Holtecs projects.86 Thus, the absolute amount of contingency included by Holtec for Palisades is substantially less than any other Holtec project.87 Mr. Capik further notes that the 12 percent contingency for Palisades results in about $53 million of contingency for license termination activities (including dormancy).88 In comparison, the average of Holtecs other projects is $94 million per unit, a 77 percent increase over that provided for Palisades.89 The 12 percent contingency isnt a plausible amount for covering costs that are reasonably expected to be incurred, because there are numerous risks as noted in this [Mr. Capiks]
testimony that would argue for substantially greater contingency, including 85 Exhibit MICH019, p 12.
86 Exhibit MICH019, p 12.
87 Exhibit MICH019, p 12.
88 Exhibit MICH019, p 12.
89 Exhibit MICH019, p 12.
24 uncertainty with fuel out date, annual ISFSI maintenance costs, and waste disposal costs.90 As shown above, Holtec did explain how it calculated and derived the 12 percent level applied for contingency as requested by the NRC, but its explanation simply showed the deficiencies in the modeling and demonstrates that the 12 percent contingency was engineered to fit the goal in this case and was not designed to be reasonably adequate for Palisades.
D.
Additional Financial Assurances Background and question presented in this case.
In its order, the NRC stated that Holtec projects major decommissioning activities to begin in December 2035, following the dormancy period, with final license termination to occur in 2041.91 Under NRC regulations, for decommissioning activities that delay completion of decommissioning by included a period of storage or surveillance, the licensee must provide a means of adjusting cost estimates and of adjusting the associated funding levels over the storage or surveillance period.92 And, NRC guidance instructs the staff to determine whether the means described by the licensee provides adequate assurance that funds will be available for decommissioning activities at the time they are needed.93 Thus, the NRC explained that for this hearing, the applicants should describe how 90 Exhibit MICH019, p 11.
91 Mem. and Order, CLI-22-08, slip op. at 74.
92 Mem. and Order, CLI-22-08, slip op. at 74-75.
93 Mem. and Order, CLI-22-08, slip op. at 79-80.
25 they will ensure that sufficient additional funding will be available to use at the time of decommissioning if additional funding proves necessary to complete decommissioning.94 The NRC further noted that while the applicants emphasize that they must file annual reports on decommissioning funding, these status reports will not address the recoveries and they will not indicate how much funding Holtec Palisades may have recovered nor whether some, all, or none of the funds remain available to adjust funding.95 The NRC continued by noting that If there are unanticipated decommissioning costs that will not be known until decommissioning is underway, status reports submitted in the years prior to the start of the major decommissioning activities may not capture such costs either.96 The NRCs conclusion section of its order states that the applicants should describe how they will ensure that sufficient additional funding will be available as a means to adjust funding, if needed and that [a]s part of their description, the applicants should address the issues described at the end of Section III.C.1.h.97 In addition, [t]he parties additionally should address whether license conditions or other forms of assurances are warranted.98 At the end of Section III.C.1.h, the NRC reaffirms that the applicants should outline how they will ensure sufficient DOE-related recoveries or other funding (if applicable) will be available as a means to augment funding if necessary to complete decommissioning.99 In fact, in the 94 Mem. and Order, CLI-22-08, slip op. at 81.
95 Mem. and Order, CLI-22-08, slip op. at 79.
96 Mem. and Order, CLI-22-08, slip op. at 79.
97 Mem. and Order, CLI-22-08, slip op. at 135.
98 Mem. and Order, CLI-22-08, slip op. at 135.
99 Mem. and Order, CLI-22-08, slip op. at 81.
26 second sentence before this conclusion, the NRC again states that applicants should describe how they will ensure sufficient additional funding will be available at the time of decommissioning if such additional funding proves necessary to complete decommissioning.100 Holtecs Initial Statement Response.
Holtec begins its response by narrowing the question presented by the NRC in its order granting the hearing. Instead of explaining how they will ensure sufficient DOE-related recoveries or other funding (if applicable) will be available as a means to augment funding if necessary to complete decommissioning,101 Holtec focuses only on the 10-year dormancy period.102 Holtecs argument completely ignores the NRCs order addressing this question. Under NRC regulations, for decommissioning activities that delay completion of decommissioning by included a period of storage or surveillance, the licensee must provide a means of adjusting cost estimates and of adjusting the associated funding levels over the storage or surveillance period.103 And, NRC guidance instructs the staff to determine whether the means described by the licensee provides adequate assurance that funds will be available for decommissioning activities at the time they are needed.104 In addition to the narrowing of the question presented by the NRC in this case, Holtec makes several other misstatements that the NRC already 100 Mem. and Order, CLI-22-08, slip op. at 81.
101 Mem. and Order, CLI-22-08, slip op. at 81.
102 Applicants Initial Statement, p 85.
103 Mem. and Order, CLI-22-08, slip op. at 74-75.
104 Mem. and Order, CLI-22-08, slip op. at 79-80 (emphasis in the original.)
27 addressed in its order granting this hearing. Holtec argues, citing the order, that the NRC has no requirement that prevents an application from relying on a single funding source.105 Although that is an accurate statement, the NRC explained that this argument by Holtec mischaracterizes the application in this case.106 Addressing this argument made by Holtec in its earlier briefs, the NRC notes that the applicants highlight that the Palisades application explicitly states that DOE reimbursements of spent fuel management expenses would provide a substantial source of additional funds in case an adjustment were needed.107 Thus, reliance on just the single funding source, is not Holtec what chose to do in its application.
Similarly, in response to arguments about a lack of adequate assurance to adjust funding levels as necessary, Holtec argues that it also [has] the ability to enlarge that cushion by adjusting its decommissioning schedule since NRC regulations allow a license 60 years from shutdown to complete decommissioning activities.108 Not only does this not provide a cushion as explained by Attorney General expert witness Nicholas Capik, but also the NRC explained in its order that
[t]his is a separate issue, however, than whether reimbursements from DOE would provide the means to adjust decommissioning funding, and neither the application nor the cost estimate discuss or rely on extending the dormancy period.109 105 Applicants Initial Statement, p 87.
106 Mem. and Order, CLI-22-08, slip op. at 77.
107 Mem. And Order, CLI-22-08, clip op. at 77 (citation omitted.)
108 Applicants Initial Statement, p 89.
109 Mem. and Order, CLI-22-08, slip op. at 76, fn 258.
28 Again, in response to arguments about the lack of adequate financial assurances, Holtec argues that NRC regulations provide more than an adequate means to address funding issues and that Holtec must continue, until the license is terminated to demonstrate annually that funding for both decommissioning and spent fuel management remains adequate. In response to that exact argument in prior briefs in this case, the NRC explained that while the applicants emphasize that they must file annual reports on decommissioning funding, these status reports will not address the recoveries and they will not indicate how much funding Holtec Palisades may have recovered nor whether some, all, or none of the funds remain available to adjust funding.110 Problems with Holtecs ability to provide additional financial assurance as a means to adjust funding and the need for license conditions or other forms of assurances are warranted in this case.
In the Initial Statement, Attorney General expert Nicholas Capik testifies that there are numerous reasons that Holtecs DCE could understate actual costs, including increase in scope due to unforeseen conditions, any delay in performance of activities, inflation beyond whats assumed with two percent real growth of the NDT, or higher than anticipated actual costs 14 years from now when decommissioning activities commence.111 He explains that delaying decommissioning activities (beyond Holtecs 10-year dormancy period) will not address a situation with insufficient funds because two percent real growth on
$325.5 million (the amount Holtec projects for the end of the dormancy period) will 110 Mem. and Order, CLI-22-08, slip op. at 79.
111 Exhibit MICH001, p 13.
29 only grow by $6.3 million a year which is barely enough to cover the $4.4 million a year to store and maintain the facility as estimated by Holtec.112 Thus, it would require many years of dormancy to address a shortfall in funding.
As to the spent fuel management costs from DOE that Holtec relies upon, there are two significant problems. First, any recovery on a Holtec claim for ISFSI construction costs and cask loading (the largest portion of spent fuel management costs) would be paid many years before decommissioning activities, and thus not necessarily available unless recovered funds were segregated and could not be withdrawn for other purposes.113 Second, Mr. Capik notes that a sizeable portion of the projected spent fuel management costs (specifically related to transfer of spent fuel to DOE) may not be recovered from DOE or could be subject to an offset that significantly reduces recovery.114 Mr. Capik explained that for several other nuclear decommissionings, some of which Holtec is involved with, the company performing the decommissioning has provided financial assurances.115 For example, Mr. Capik explained that for the Vermont Yankee, NorthStars financial assurance included a parental support agreement of $140 million, escrow accounts of at least $55 million, performance bonds of approximately $400 million, a $25 million letter of credit, retained DOE proceeds, and a commitment not to withdraw funds for any task exceeding the 112 Exhibit MICH001, p 13.
113 Exhibit MICH001, p 13.
114 Exhibit MICH001, p 14.
115 Exhibit MICH001, p 14.
30 allocated cost in a schedule provided.116 For Indian Point, which has $2.4 billion in the NDT) Holtec agreed to minimum NDT balances of $400 million at 10 years and
$360 million at Partial Site Release (PSR), when the operating license footprint is reduced to the ISFSI, and return of 50 percent of the DOE recoveries to the NDT.117 For Pilgrim, Holtec agreed to minimum NDT balances ($193.3 million 2019 dollars at PSR adjusted as decommissioning proceeds, as well as a minimum balance until all fuel is removed from the site), use of DOE recoveries if needed to maintain the minimum balances, performance bonds, $30 million of insurance, and additional financial reporting requirements.118 These financial assurances were in addition to starting with a NDT balance of approximately $1 billion which is significantly more than for Palisades.119 After reviewing Holtecs Initial Statement and Testimony, Mr. Capik further elaborated on why additional financial insurance is important for Palisades by examining the six plants (Oyster Creek, Pilgrim, Indian Point (3 plants on a single site), and Palisades) that Holtec purchased from Entergy to decommission.120 He explained that each power plant had a different NDT fund as well as a different estimated license termination costs as follows:
- a. Oyster Creek - $848 million NDT with $618 million estimated for license termination;
- b. Pilgrim - $1,030 million NDT with $593 million estimated for license termination; 116 Exhibit MICH001, p 14.
117 Exhibit MICH001, p 14.
118 Exhibit MICH001, p 15.
119 Exhibit MICH001, p 15.
120 Exhibit MICH019, p 1.
31
- c. Indian Point Unit 1 - $534 million NDT with $485 million estimated for license termination;
- d. Indian Point Unit 2 - $654 million NDT with $469 million estimated for license termination;
- e. Indian Point Unit 3 - $916 million NDT with $583 million estimated for license termination; and
- f. Palisades - $552 million NDT with $443 million estimated for license termination, including approximately $45 million for a ten-year dormancy period (for a comparable license termination cost of $398 million).121 The importance of this comparison is that the estimated cost to remediate and dismantle Palisades is less than every other plant owned by Holtec and there is less funding available for this work at Palisades compared to every other Holtec plant.122 In calculating the funding available for license termination (separate from spent fuel management and site restoration), Mr. Capik used the projected NDT fund balance plus projected earnings and subtracted estimated fuel management and site restoration costs.123 He explained that although detailed activities will vary from plant to plant, the decommissioning projects have to comply with the same regulations and thus have similar organizational structures (and departments).124 The plants also have similar waste disposal volumes (1.13 million cubic feet for Palisades compared to 0.956 million cubic feet for Oyster Creek, 1.42 million cubic feet for Pilgrim, and 1.365 million cubic feet for Indian Point 2).125 121 Exhibit MICH019, pp 1-2 (citations omitted.)
122 Exhibit MICH019, p 2.
123 Exhibit MICH019, pp 2-3.
124 Exhibit MICH019, p 3.
125 Exhibit MICH019, p 3.
32 Thus, Mr. Capik explains that he would expect similar costs for Palisades to these other Holtec units, but instead there are wide and unexplained differences.126 For example, on estimated costs to maintain the on-site ISFSI, there is a wide difference on estimated costs even though the activities at the various ISFSIs are the same and the regulations applying to those facilities are the same127 As Mr. Capik states Holtec has provided no explanation for why the estimated costs to maintain the Palisades ISFSI are markedly less than its other ISFSIs given the same requirements apply.128 An even more significant but unexplained difference exists for funds remaining when all radioactive material is removed from the site (except for spent fuel) as follows:
- a. Palisades - $20 million;
- b. Oyster Creek - $127 million;
- c. Pilgrim - $217 million; and
- d. Indian Point - $450 million129 Mr. Capik explains that this number is important because it is a measure of funds available for risk mitigation to address cost increases prior to license termination or when the licensed footprint is shrunk to the ISFSI. As shown in his testimony, Palisades has the smallest remaining balance and thus least ability to mitigate any potential cost increases.130 126 Exhibit MICH019, p 3.
127 Exhibit MICH019, pp 3-4 (showing Palisades at $1.7 million, Indian Point at $4.8 million (during active decommissioning), Pilgrim at $6 million, and Oyster Creek at $8 million.)
128 Exhibit MICH019, p 4.
129 Exhibit MICH019, p 4.
130 Exhibit MICH019, p 4.
33 After reviewing these comparisons and unexplained differences in estimated costs, Mr. Capik concludes that Palisades has the lowest estimated license termination cost, the lowest estimated annual spent fuel management cost for dry storage, the lowest available funding, and the lowest funds remaining following radioactive remediation (partial site release or license termination).131 Even though Holtec doesnt explain the differences, the answer is clear when looking at the big picture. Holtec knew the amount available in Palisades NDT at the time of the deal with Entergy on the six nuclear plants and Holtec had to alter its analysis on estimated costs for Palisades to fit within the NDT. This explains why Palisades has the lowest estimated license termination costs, the lowest estimated annual spent fuel management cost for dry storage, the lowest funds remaining following radioactive remediation, and finally the lowest available funding. This also underscores why additional financial assurances are necessary in this case.
Interestingly, in four of the other five plants being decommissioned by Holtec, the states have negotiated additional increased financial assurance due to risk of insufficient funds. Here, with Palisades, this concern is significantly heightened since it has the least amount of funding. Yet, no additional financial assurance has been negotiated for Palisades.
Holtec attempts, in its initial statement, to explain the lower costs for Palisades as lessons learned from the other plants, but Mr. Capik opines why that is unsupported and inaccurate.132 To begin with, Holtec has already incurred $572 131 Exhibit MICH019, pp 4-5 (emphasis in the original.)
132 Exhibit MICH019, p 5.
34 million at Pilgrim and $573 million at Oyster Creek through September of 2022, both of which already exceeds the NDT for Palisades.133 Moreover, in both cases, Holtec has yet to complete reactor vessel segmentation and there appears to be minimal progress on other power block buildings.134 Holtec filed the Palisades DCE in December of 2020. From January 2019 through May 2022, only 110,977 cubic feet of waste was shipped from the Pilgrim site, out of an estimated 1,419,563 total cubic feet (7.8%).135 Similarly, for Oyster Creek, from January 2019 through December 2021, only 222,072 cubic feet of waste was shipped off site, out of an estimated 956,029 total cubic feet (23.6%).136 Mr. Capik explains [t]hus even looking to a period after the Palisades DEC was generated and submitted, Holtec has not gained sufficient experience to justify a substantial reduction in estimated costs.137 Mr. Capik explains that Holtec has not committed to any additional financial assurance in this case.138 Holtec claims that it has multiple avenues for ensuring there will be sufficient funds, but it never provides any new assurance or commitment.139 In fact, Holtecs arguments regarding any additional assurance can be summarized with its statement regarding DOE recoveries when it says there is no reason to think that those funds would not remain available to cover the 133 Exhibit MICH019, p 5.
134 Exhibit MICH019, p 5.
135 Exhibit MICH019, p 5.
136 Exhibit MICH019, p 5.
137 Exhibit MICH019, p 5.
138 Exhibit MICH019, pp 5-6.
139 Exhibit MICH019, p 6.
35 shortfall.140 Mr. Capik then summarizes Holtec claims that it has multiple avenues for ensuring there will be sufficient funds and he explains why none of those claims are accurate:
- a. First, Holtec points to a sufficient cushion in the NDT resulting from its predicted $19,788,000 remaining at license termination.
As noted above, this cushion is only realized if the Palisades costs are significantly less than other Holtec projects (which includes its unreasonable assumptions regarding spent fuel management acceptance dates and annual costs).
- b.
- c. Third, Holtec suggests it can extend the dormancy period to allow the NDT time for further growth. As discussed in my initial testimony, it is not clear that such extended dormancy would result in substantial additional funding, Also, Holtec did not assess any costs that may be incurred to demobilize and place the facility in a storage condition and costs to remobilize for dismantlement should the shortfall be identified after dismantlement begins.
- d. Finally, Holtec points to recovery of SNF management costs from DOE. There are two issues with this assertion. First and most important, Holtec makes no commitment to keep any recovery within Holtec Palisades (as opposed to funds being transferred to the parent entity). If Holtec Palisades does not have a commitment to retain these funds for decommissioning, it is not reasonable to rely on these funds being available. Any recovery for Holtecs initial claim (estimated to be over $90 million based on Holtecs 140 Applicants Initial Statement, p 93.
36 projected cash flow) is likely to be received no later than 2032 (contrary to Holtecs assertion) based on the statute of limitations requiring a claim to be filed no later than 2028 if all funds from the purchase of Palisades in 2022 are to be recovered, and a typical time from the end of a period of incurred costs to recovery of costs is between three and four years, resulting in a recovery of costs incurred through 2028 by the end of 2032. Thus, the availability of funds recovered from DOE to address a shortfall that may not occur until later in the decommissioning process (2038 or later) is unlikely unless such funds are segregated and preserved.141 In summary, Holtecs claims of multiple avenues of ensuring sufficient funds remain unsupported and inaccurate; Holtec refuses to provide any commitment to additional financial assurance, relying instead on statements like there is no reason to think that those funds would not remain available in the face of multiple reasons explaining why; and Holtec claims no license conditions are warranted, irrespective of the actual facts in this case demonstrating the need for some license conditions or commitments.
CONCLUSION At base, the application is inadequate to demonstrate that Applicants have the financial qualifications to carry out the activities for which the license is sought.
The NRC should hold Holtec and all related entities to a high standard that protects the interests of the state of Michigan, those who live near the Palisades plant, future generations of taxpayers, and all of those who live in the Great Lakes watershed. Giving Holtec a pass here and not requiring that sufficient financial 141 Exhibit MICH019, pp 6-7 (citations omitted.)
37 assurances be provided risks the money, health, and wellbeing of millions of Americans for generations to come.
Due to these concerns and on behalf of the People of the State of Michigan, Attorney General Dana Nessel requests that the Commission require the Applicants to provide additional forms of financial assurance as it has in other license transfer cases discussed in the Attorney Generals briefs and testimony including, but not limited to, limitations on withdrawals on a line item basis not to exceed the line item value on the DCE submitted as part of the license transfer, a clear commitment to retain DOE recoveries and to have them remain available throughout decommissioning, as well as a parental guarantee, escrow accounts, and/or a line of credit, the three of which combined provide an additional assurance of $200 million.
Respectfully submitted, Dana Nessel Attorney General State of Michigan Signed (electronically) by
/s/ Michael E. Moody Michael E. Moody Joel King Assistant Attorneys General Special Litigation Division P.O. Box 30755 Lansing, Michigan 48909 MoodyM2@michigan.gov (517) 335-7627 Dated: December 16, 2022
38 STATES OF AMERICA NUCLEAR REGULATORY COMMISSION Before the Atomic Safety and Licensing Board In the Matter of ENTERGY NUCLEAR OPERATIONS, INC., ENTERGY NUCLEAR PALISADES, LLC, HOLTEC INTERNATIONAL, and HOLTEC DECOMMISSIONING INTERNATIONAL, LLC (Palisades Nuclear Plant and Big Rock Point Site)
)
Docket Nos.
)
)
)
)
)
ASLBP No.
)
)
)
)
50-255-LT-2 50-155-LT-2 72-007-LT 72-043-LT-2 22-974-01-LT-BD01 CERTIFICATION OF SERVICE Pursuant to 10 C.F.R. § 2.305, I certify that I served the Michigan Attorney Generals written responses and rebuttal testimony with supporting affidavit in the above-captioned proceeding via the NRCs Electronic Information Exchange on December 16, 2022.
Signed (electronically) by
/s/ Michael E. Moody Michael E. Moody Assistant Attorney General Special Litigation Division P.O. Box 30755 Lansing, Michigan 48909 MoodyM2@michigan.gov (517) 335-7627 Dated: December 16, 2022