MONTHYEARML23047A5022022-07-31031 July 2022 Document No. NFK-MPCF-2210002, Explanation of Quality Control Methods, Etc. (Limited to Those Relating to Design) Relating to the Packaging, Model No. GP-01 Package Project stage: Other ML23026A1402023-01-24024 January 2023 Transmittal Letter E-62007 from Orano - Request for Revalidation of the Model No. GP-01 Project stage: Request ML23026A1412023-01-25025 January 2023 Transmittal Letter from R. Boyle (U.S. Department of Transportation) to Director of Fuel Management - Request for NRCs Review and Revalidation Recommendation for the Model No. GP-01 Project stage: Request ML23026A1372023-01-25025 January 2023 Transmittal Letter E-62007, Enclosure 4, Document No. NFK-MPCF-2209003-01, Summary of the New SAR Changes Project stage: Request ML23044A0982023-02-10010 February 2023 Safety Analysis Report for the Japanese Certificate of Competent Authority No. J/2009/AF, Model No. GP-01 with Tracked Changes Project stage: Other ML23046A0602023-02-15015 February 2023 Email Dated February 15, 2023, from R. Boyle (DOT) to N. Garcia Santos (NRC) Supplemental Information Needed - Missing Quality Assurance Chapter in the Application for the Revalidation Request of the Japanese Package Model No. GP-01 Project stage: Other ML23047A5032023-02-16016 February 2023 Email Dated February 16, 2023, from R. Boyle (DOT) to N. Garcia Santos (NRC) Response: GP-01, Supplemental Information Needed - Missing Quality Assurance Chapter from Application Project stage: Supplement ML23062A5042023-03-0101 March 2023 Email from Norma Garcia Santos (NRC) to Richard W. Boyle (Dot), Subject: GP-01-Need Translated Figure 12 (of the Application) Project stage: Other ML23066A2612023-03-0606 March 2023 Translated Figure 13 of Chapter II A1-A4, Page II-A-38, of the Safety Analysis Report for the Model No. GP-01 Project stage: Other ML23066A2602023-03-0606 March 2023 Email Dated March 6, 2023 from Rick Boyle (DOT) to Norma Garcia Santos (NRC) Response to Request of Translation of Figure 13 on Page II-A-38, Safety Analysis Report for the Model No. GP-01 Project stage: Other ML23062A7312023-03-14014 March 2023 Application for the Japanese Certificate of Competent Authority No. J/2009/AF, Revision 2, Model No. GP-01 - Accepted for Review - CAC No. A33010/EPID No. L-2023-DOT-0002 Project stage: Other ML23131A0992023-05-0505 May 2023 Email Dated May 5, 2023, from Ngarcia Santos (NRC) to Rboyle (Dot), GP-01 Staggered RAIs No. 2 - Materials Evaluation Project stage: RAI ML23131A1002023-05-0505 May 2023 Attachment to Email Dated May 5, 2023, from Ngarcia Santos (NRC) to Rboyle (Dot), Subject: GP-01 Staggered RAIs No. 2 - Materials Evaluation Project stage: RAI ML23118A0082023-05-24024 May 2023 Request for Additional Information for Review of the Certificate of Compliance No. 3098, Model No.GP-01 Project stage: RAI ML24134A1092023-07-0707 July 2023 U.S. DOT Transmittal Letter - Response to Requests for Additional Information for the Revalidation Review of the Model No. GP-01, Revision 2, Japanese Package Project stage: Response to RAI ML24134A0722023-07-25025 July 2023 E-62515 Oranos Transmittal Letter and Enclosure 2, Affidavit - Response to Requests for Additional Information for the Revalidation Review of the Model No. GP-01, Revision 2, Japanese Package Project stage: Response to RAI ML24053A2462023-09-28028 September 2023 9/28/23, Orano Tn Request to the U.S. DOT for a Short-Term Approval of a Shipment Using the Model No. GP-01 Japanese Package Taking Place in April 2024 Project stage: Request ML23300A0742023-10-27027 October 2023 NRC Form 699-8/30/23, Conference Summary Call, NRC, DOT, Orano-TN, and Orano-NPS, Discussion of Materials and Structural Unacceptable Responses to Requests for Additional Information, Revalidation Request of the Model No. GP-01 Package (Dkt Project stage: RAI ML23319A2732023-10-31031 October 2023, 11 March 2024, 14 March 2024 Supplemental Responses to Unacceptable Requests for Additional Information, Revalidation of the Japanese Package Model No. GP-01 Package Project stage: Request ML23319A2772023-10-31031 October 2023 Letter E-62897 Dated 10/31/23 from D. Shaw (Orano) to R. Boyle (Dot), GP-01 Supplement to Requests for Additional Information, Application for Revalidation Project stage: Supplement ML23319A2782023-10-31031 October 2023 Email Dated 10-31-23 from P. Vescovi (Orano) to R. Boyle DOT (GP-01), Supplement to Requests for Additional Information Application for Revalidation, Model No. GP-01 - Redacted Project stage: Supplement ML24081A3042024-03-11011 March 2024 Letter E-63336 Dated 3/11/24 from D. Shaw (Orano) to R. Boyle (Dot), Supplement to Requests for Additional Information, Application for the Revalidation of the Model No. GP-01 Package, Japanese Certificate of Competent Authority No. J/2009/ Project stage: Supplement ML24081A3052024-03-14014 March 2024 Letter Dated 3/14/24 from R. Boyle (DOT) to Director, Division of Fuel Management, Supplement to Requests for Additional Information, Application for the Revalidation of the Model No. GP-01 Package, Japanese Certificate of Competent Authori Project stage: Supplement ML24135A2112024-06-0404 June 2024 Enclosure 1: Safety Evaluation Report Revalidation Recommendation Japanese Certificate of Approval J/2009/AF, Model No. GP-01; Project stage: Approval ML24135A2102024-06-0404 June 2024 Cover Letter: Revalidation Recommendation for the Japanese Competent Authority Certificate of Approval J/2009/AF, Model No. GP-01 Package Project stage: Other 2023-03-14
[Table View] |
Text
1 Nuclear Fuel Industries, Ltd.
2022.11.8 NFK-MPCF-2209003-01 Prepared by Reviewed by Approved by Summary of describe the modification of the new SAR
- 1. Chapters added to the SAR due to the amendment of Japanese regulation.
(5) Chapter II-F Aging Considerations for Nuclear Fuel Packages (Create New)
Evaluation of aging was added to the SAR due to amendment of the NRA Ordinance on off-Site Transportation of Nuclear Fuel Materials, etc. Issuance: Order of the Prime Minister's Office No. 57 of December 28, 1978 and the Notification on Technical Details for Off-Site Transportation of Nuclear Fuel Materials, etc. Issuance: The Public Notice of the Science and Technology Agency No. 5, an extra of November 28, 1990. Four aging factors (heat, radiation, chemical, fatigue) of packaging and contents were evaluated in chapter II-F (Aging of Consideration s for Nuclear Fuel Packages).
(1) Chapter II-A A.4.4.10 Evaluation of Repetitive Stress due to Lifting (Create New)
(2) Chapter II-A A.4.6.3 Evaluation of Repetitive Stress due to Internal Pressure (Create New)
These chapters were added to SAR with addition of chapter II-F. One of aging factors (fatigue) was evaluated in chapter II-F, and this detailed evaluation was conducted in chapter II-A (A.4.4.10 and A.4.6.3). Fatigue by repetitive stress due to lifting was evaluated in chapter A.4.4.10, and fatigue by repetitive stress due to internal pressure.
- 2. The modified chapters due to NRA (Japanese authority) requests (unrelated to the amendment of Japanese regulation)
(3) Chapter II-A A.4.7 Vibrations (Significant changes)
This chapters was modified significantly because NRA requested more quantitative evaluation of vibration. To meet the requirement of the NRA, the natural frequency of package was compared with the frequency by excitation force received from vehicle during transport, and it was confirmed that there is no risk of damages and cracking of
2 packaging due to the displacement amplitude multiplication by the two frequencies.
(4) Appendix 3 to Chapter II-A Supplementary Explanatory Material for Derivation of Natural Frequency (Create New, relating to A.4.7).
This chapter was added to the SAR due to derivation of natural frequency of package(related to A.4.7).
(6) Chapter II-G Evaluation of Conformity to Regulations and Stipulations in the Public Notice (Significant changes)
This chapter was modified significantly because NRA requested that the evaluation of each chapter be specific in its description.
(7) Chapter II-E Criticality Analysis (Change of descriptions wording and error correction)
This chapter was modified in the wording throughout. Table II-E-1 was corrected for errors. These changes dont affect any evaluation of criticality analysis, and there is no additional evaluation.