E-mail to Uiuc - Acceptance Review Determination for Applicability of NRC Regulations Topical Report
ML23020A094
Person / Time
Site: 99902094
Issue date: 02/09/2023
From: Adrian Muniz
NRC/NRR/DANU/UAL2
To: Brooks C
University of Illinois
References
EPID L-2022-NFN-0008
Download: ML23020A094 (1)


Text

From:

Adrian Muniz To:

Csbrooks Cc:

Townsend, Clive; Foyto, Les

Subject:

Completeness Determination for UIUC"s Applicability of NRC Regulations Topical Report Date:

Thursday, February 9, 2023 9:22:00 AM Attachments:

NRC Form 898 Applicability of NRC Regulations Topical Report Completeness Determination.pdf

Caleb,

Attached is the U.S. Nuclear Regulatory Commission (NRC) staff completeness determination for the University of Illinois at Urbana-Champaign (UIUC) topical report titled University of Illinois at Urbana-Champaign High-Temperature Gas-cooled Research Reactor: Applicability of Nuclear Regulatory Commission Regulations. Based on a preliminary review of the report, the NRC staff determined that it provides sufficient information for the NRC staff to begin a detailed technical review.

As discussed, the NRC staff plans to issue its draft safety evaluation by December 8, 2023. If needed, the NRC staff will issue a request for additional information (RAI) by July 3, 2023, with a request for UIUC to provide a response within 30 days. The NRC staff estimates that 415 staff hours will be needed to complete the technical review and issue the safety evaluation. The schedule and level of effort could change due to several factors including, the need for additional RAIs, unanticipated changes to the scope of the review, and unsolicited supplements to the topical report. The NRC staff will communicate any changes to the review schedule or estimated staff hours by email, including the reason(s) for the changes.

If you have any questions, please feel free to contact me at 301-415-4093 or by email at Adrian.Muniz@nrc.gov.

Docket No.: 99902094 EPID: L-2022-NFN-0008

Thank you,

Adrian Muniz, Senior Project Manager Advanced Reactor Licensing Branch 2 Division of Advanced Reactors and Non-Power Production and Utilization Facilities (DANU)

U.S. Nuclear Regulatory Commission