Independent Spent Fuel Storage Installation (Isfsi), Submittal of Cask Registration for Spent Fuel Storage
ML23005A171
Person / Time
Site: Millstone, 07201004  Dominion icon.png
Issue date: 01/04/2023
From: O'Connor M
Dominion Energy Nuclear Connecticut
To:
Office of Nuclear Material Safety and Safeguards, Office of Nuclear Reactor Regulation, Document Control Desk
References
22-383
Download: ML23005A171 (1)


Text

Dominion En ergy Nuclear Connecticut, Inc.

Millstone Power Station ~=-~ Dominion 314 Rope Ferry Road, Waterford , CT 06385 Dominion Energy.com JAN O;~ 2023  :=;iiiii" Energy Attention: Document Control Desk Serial No.22-383 Director, Division of Fuel Management NSSL/TFO Office of Nuclear Material Safety and Safeguards Docket Nos. 72-47 U.S. Nuclear Regulatory Commission 50-423 Washington, DC 20555-0001 License No. NPF-49 DOMINION ENERGY NUCLEAR CONNECTICUT, INC.

MILLSTONE POWER STATION UNIT 3 INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI)

SUBMITTAL OF CASK REGISTRATION FOR SPENT FUEL STORAGE Pursuant to 10 CFR 72.212, "Conditions of general license issued under §72.21 O,"

paragraph (b )(2), Dominion Energy Nuclear Connecticut, Inc. (DENG) hereby provides the Nuclear Regulatory Commi_ ssion (NRG) notification regarding the registration of spent fuel storage casks approved under NRG Certificate of Compliance No. 1004. The required registration information is submitted within 30 days of loading. The information required per 10 CFR 72.212(b)(2) is provided as follows:

Licensee Name: Dominion Energy Nuclear Connecticut, Inc.

Licensee Address: 314 Rope Ferry Road Waterford, CT 06385 Reactor License No.: NPF-49 Reactor Docket No.: 50-423 Cask Certificate No.: 1004 Cask Model No.: NUHOMS-32PT DSC Canister Cask Identification Nos.:

MPS32PT-L 125-A232-HZ048 Initial Use: December 12, 2022 MPS32PT-L 125-A232-HZ049 Initial Use: December 19, 2022 The casks were placed in service under Amendment 15 of Certificate of Compliance No. 1004.

Should there be any questions regarding this submittal, or additional information required regarding spent fuel storage under the general license requirements of 10 CFR 72 Subpart K, please contact Mr. Dean Rowe, Manager Station Licensing, at (860) 444-5292.

~incerely, ,,--..t*

'l\\ JLL~ J.

Michae1 O'Connor

/b----

Site Vice President - Millstone Commitments made in this letter: None

Serial No.22-383 Docket Nos. 72-4 7 /50-423 Page 2 of 2 cc: Regional Administrator U.S. Nuclear Regulatory Commission Region I 475 Allendale Road, Suite 102 King of Prussia, PA 19406-141"5 K. J. Sturzebecher Decommissioning Project Manager Millstone Unit 1 U.S. Nuclear Regulatory Commission Two White Flint North, Mail Stop A60M 11545 Rockville Pike RockvilleJ MD 20852-2738 R. V. Guzman NRG Senior Project Manager Millstone Units 2 and 3 U.S. Nuclear Regulatory Commission One White Flint North, Mail Stop 08 C-2 11555 Rockville Pike Rockville, MD 20852-2738 NRC Senior Resident Inspector Millstone Power Station