NRC-22-0046, Submittal of Biennial Review of the Fermi 1 Safety Analysis Report
ML22319A151 | |
Person / Time | |
---|---|
Site: | Fermi |
Issue date: | 11/14/2022 |
From: | Olson E DTE Electric Company |
To: | Office of Nuclear Material Safety and Safeguards, Document Control Desk |
References | |
NRC-22-0046 | |
Download: ML22319A151 (1) | |
Similar Documents at Fermi | |
---|---|
Category:Letter type:NRC
MONTHYEARNRC-24-0057, Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report2024-09-0303 September 2024
[Table view]Update to NRC 24-0041: Technical Specification (TS) 5.6.7 – Post Accident Monitoring Report NRC-24-0053, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 20242024-08-30030 August 2024 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30, 2024 NRC-24-0050, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2024-08-12012 August 2024 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-24-0048, Submittal of Inservice Inspection Summary Report2024-08-0606 August 2024 Submittal of Inservice Inspection Summary Report NRC-24-0046, Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance2024-07-25025 July 2024 Fenni 2 Power Plant - Approval of the National Pollutant Discharge Elimination System Permit Application for Reissuance NRC-24-0020, Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan2024-07-24024 July 2024 Submittal of Revision 51 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-24-0044, Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License)2024-07-10010 July 2024 Enrico Fermi 1 License Expiration - 10 CFR 50.51 (Continuation of License) NRC-24-0041, Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report2024-06-21021 June 2024 Technical Specification (TS) 5.6.7 - Post Accident Monitoring Report NRC-24-0042, Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data2024-06-18018 June 2024 Regulat01y Issues Summaty (RIS) 24-01 Preparation and Scheduling of Operator Licensing Examinations to Submit Fonn 536, Operator Licensing Examination Data NRC-24-0040, Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-00332024-06-0606 June 2024 Verification of No Significant Hazards Considerations for License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance Supplement Provided in NRC-24-0033 NRC-24-0033, DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-05-30030 May 2024 DTE Electric Company - Final Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0035, Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications2024-05-16016 May 2024 Primary Containment Isolation Valve Declared Inoperable for a Period Prohibited by Technical Specifications NRC-24-0025, Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-222024-05-15015 May 2024 Automatic RPS Scram on High RPV Pressure While Attempting to Lower Generator Output During RF-22 NRC-24-0017, 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report2024-04-29029 April 2024 2023 Annual Radioactive Effluent Release Report and 2023 Radiological Environmental Operating Report NRC-24-0032, Transmittal of the Core Operating Limits Report for Cycle 232024-04-25025 April 2024 Transmittal of the Core Operating Limits Report for Cycle 23 NRC-24-0027, Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance2024-04-24024 April 2024 Partial Response to Request for Additional Information for License Amendment Request Regarding Risk Informed Approach to Performance ECCS Strainer Performance NRC-24-0031, Retake Exam Outline Submittal Letter2024-04-22022 April 2024 Retake Exam Outline Submittal Letter NRC-24-0018, 2023 Annual Non-Radiological Environmental Operating Report2024-04-0909 April 2024 2023 Annual Non-Radiological Environmental Operating Report NRC-24-0015, Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report2024-03-31031 March 2024 Enrico Fermi Atomic Power Plant, Unit 1, Decommissioning Funding Status Report NRC-24-0001, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion2024-03-21021 March 2024 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Rev. 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, TSTF-439, Rev. 2, Eliminate Second Completion NRC-24-0019, Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report2024-03-14014 March 2024 Submittal of 2023 Safety Relief Valve Challenge Report, Main Steam Bypass Lines Report, and ECCS Cooling Performance Evaluation Model Changes or Errors Report NRC-24-0023, NRC-24-0023, Post Exam Package Submittal Letter to NRC2024-03-0707 March 2024 NRC-24-0023, Post Exam Package Submittal Letter to NRC NRC-24-0008, Levels and Sources of Property Insurance Coverage2024-02-15015 February 2024 Levels and Sources of Property Insurance Coverage NRC-24-0009, Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 22024-02-0606 February 2024 Request for NRC to Suspend Regulatory Audit of License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance for Fermi Unit 2 NRC-24-0002, Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122024-01-12012 January 2024 Clarification for Request for Additional Information Responses for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-24-0007, Report of Changes to Quality Assurance Program for Radioactive Material Packages2024-01-12012 January 2024 Report of Changes to Quality Assurance Program for Radioactive Material Packages NRC-23-0079, Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 222023-12-14014 December 2023 Transmittal of Revision 1 of the Core Operating Limits Report for Cycle 22 NRC-23-0077, Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan2023-12-0404 December 2023 Submittal of Revision 50 to the Fermi 2 Radiological Emergency Response Preparedness Plan NRC-23-0075, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation2023-11-30030 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notification Implementation NRC-23-0073, Guarantee of Payment of Deferred Premiums2023-11-29029 November 2023 Guarantee of Payment of Deferred Premiums NRC-23-0071, Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-10-13013 October 2023 Response to Request for Additional Information (RAI) for Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0062, Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.122023-10-12012 October 2023 Response to Request for Additional Information for License Amendment Request to Revise Technical Specification 3.8.1, AC Sources - Operating, Surveillance Requirement SR 3.8.1.12 NRC-23-0068, Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating2023-09-28028 September 2023 Exigent License Amendment Request for Revision of Technical Specification (TS) 3.8.1 AC Sources - Operating NRC-23-0064, Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-09-11011 September 2023 Additional Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0057, Independent Spent Fuel Storage Installation Cask Registration2023-08-31031 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0054, Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 20232023-08-31031 August 2023 Enrico Fermi Atomic Power Plant, Unit 1, Annual Report for Period Ending June 30 2023 NRC-23-0056, Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval2023-08-31031 August 2023 Inservice Testing (IST) Program for the Fourth 10-Year Inspection Interval NRC-23-0061, Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water..2023-08-30030 August 2023 Clarification for NRC-23-0059, Response to Request for Additional Information for Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water.. NRC-23-0059, Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Response to Request for Additional Information Exigent License Amendment Request for Technical Specification 3.7.2,Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0060, Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-25025 August 2023 Supplemental Information to Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0053, Independent Spent Fuel Storage Installation Cask Registration2023-08-23023 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0050, Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-08-10010 August 2023 Exigent License Amendment Request for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0048, Independent Spent Fuel Storage Installation Cask Registration2023-08-0101 August 2023 Independent Spent Fuel Storage Installation Cask Registration NRC-23-0049, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-07-24024 July 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0043, Independent Spent Fuel Storage Installation, Cask Registration2023-06-27027 June 2023 Independent Spent Fuel Storage Installation, Cask Registration NRC-23-0020, License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance2023-06-13013 June 2023 License Amendment Request for a Risk Informed Approach to ECCS Strainer Performance NRC-23-0039, Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS)2023-06-0606 June 2023 Request for Enforcement Discretion for Technical Specification 3.7.2, Emergency Equipment Cooling Water (Eecw)/Emergency Equipment Service Water (Eesw) System and Ultimate Heat Sink (UHS) NRC-23-0030, Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval2023-06-0505 June 2023 Inservice Inspection-Nondestructive Examination (ISI-NDE) Program for the Fourth 10-Year Inspection Interval NRC-23-0029, Snubber Program for the Fourth 10-Year Testing Interval2023-06-0505 June 2023 Snubber Program for the Fourth 10-Year Testing Interval NRC-23-0037, 56542-EN 56542 - Fermi2023-05-26026 May 2023 56542-EN 56542 - Fermi 2024-09-03 |
Text
Eric Olson Site Vice President DTE Electric Company 6400 N. Dixie Highway, Newport, Ml 48166 Tel: 734.586.5025 Fax: 734.586.5295 Email: eric.olson@dteenergy.com DTE November 14, 2022 10 CFR 50.7l(e)
NRC-22-0046 10 CFR 50.4(b)(6) 10 CFR 50.54(a) 10 CFR 50.59(d)(2)
U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, DC 20555-0001 Enrico Fermi Atomic Power Plant, Unit No. 1 NRC Docket No. 50-16 NRC License No. DPR-9
Subject:
Submittal of Biennial Review of the Fermi 1 Safety Analysis Report Pursuant to 10 CFR 50.71(e) and 10 CFR 50.4(b)(6), DTE Electric Company (DTE) hereby submits the biennial review of the Fermi 1 Safety Analysis Report (Fl SAR) for the period of November 2020 through October 2022.
In accordance with 10 CFR 50.71(e), a review of the Fl SAR was completed and determined that no content changes were made since November 2020.
There were no changes to the Fermi 1 Quality Assurance (QA) Program during this period.
There were no activities during this period that required a 10 CFR 50.59 evaluation.
No new commitments are being made in this submittal.
Should you have any questions or require additional information, please contact Mr. John F.
Lacasse, Fermi 1 Custodian, at (734) 748-8052.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on November 14, 2022,
~Q£__
Eric Olson Site Vice President
Enclosure:
None cc: NRC Project Manager Regional Administrator, Region III