MONTHYEARML21035A0742021-01-29029 January 2021 Framatome, Inc. Request for Review and Approval of ANP-10353P, Revision 0, Increased Enrichment for PWRs Project stage: Request ML21061A2132021-03-0202 March 2021 Acceptance for Framatome Topical Report ANP-10353P - Increased Enrichment for PWRs Project stage: Acceptance Review ML21217A1012021-08-10010 August 2021 September 13, 2021, Regulatory Audit Plan for Framatome Inc. Topical Report, ANP-10353, Revision 0, Increased Enrichment for PWRs Project stage: Other ML21258A3402021-09-21021 September 2021 Letter-Request for Additional Information Regarding Framatome Topical Report, ANP-10353P, Revision 0, Increased Enrichment for PWRs (Pressurized Water Reactors) Project stage: RAI ML21305A0322021-11-0303 November 2021 Report for September 13, 2021, Regulatory Audit Regarding Framatome Inc. Topical Report, ANP-10353P, Revision 0, Increased Enrichment for PWRs Project stage: Other PMNS20220371, Closed Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Framatome Inc. to Discuss Topical Report ANP-10353P, Revision 0 - Increased Enrichment for Pressurized Water Reactors (Pwrs)2022-04-0808 April 2022 Closed Meeting Between the U.S. Nuclear Regulatory Commission (NRC) and Framatome Inc. to Discuss Topical Report ANP-10353P, Revision 0 - Increased Enrichment for Pressurized Water Reactors (Pwrs) Project stage: Request ML22129A0032022-05-31031 May 2022 Letter - August 17, 2022, Regulatory Audit Plan for Framatome Inc. Topical Report, ANP-10353P, Revision 0, Increased Enrichment for PWRs Project stage: Other ML22137A2712022-06-0101 June 2022 June 13-17, 2022, Audit Plan for Framatome Inc. TR, ANP-10311P-A, Rev. 1, Supplement 1P, Rev. 0, Cobra-FLX: ORFEO-HMP Critical Heat Flux Correlation and EMF-2310, Rev. 1, Supplement 2P, Rev. 0 (Epids L-2021-TOP-0004 & L-2022-TOP-0008) Project stage: Other ML22158A1472022-06-14014 June 2022 NRCs Revised Schedule for the Review of Framatomes Topical Reports, ANP-10353P, Rev. 0, Increased Enrichment for Pwrs and ANP-10340P, Rev. 0, Suppl. 1, Rev. 0, Incorporation of Chromia-Doped Fuel Properties in Framatome PWR Methods Project stage: Approval ML22252A2522022-09-15015 September 2022 Report Regarding August 17, 2022, Regulatory Audit for Framatome Inc. Topical Report, ANP-10353P, Revision 0, Increased Enrichment for PWRs - Letter - Project stage: Other ML22353A6042022-12-22022 December 2022 Audit Report Regarding Framatome TR, ANP-10311P-A, Rev. 1, Supplement 1P, Rev. 0, COBRA-FLX: ORFEO-HMP CHF Correlation & EMF-2310, Rev. 1, Supplement 2P, Rev. 0, SRP Chpt. 15 Non-LOCA Methodology for PWR (EPIDs L-2021-TOP-0004 & L-2022-TOP- Project stage: Other ML23023A2662023-01-26026 January 2023 Withholding Determination Regarding Request for Comment on Draft Safety Evaluation for ANP-10353P, Revision 0, Increased Enrichment for PWRs (EPID L-2021-TOP-0004) - Transmittal Project stage: Draft Approval ML23023A2732023-01-26026 January 2023 Withholding Determination Regarding Response to Request for Comment on Draft Safety Evaluation for Framatome Topical Report, ANP-10353P, Revision 0, Increased Enrichment for PWRs (EPID L-2021-TOP-0004) - Form 897 Project stage: Draft Approval ML23053A0532023-03-22022 March 2023 Final Safety Evaluation for Framatome Topical Report ANP-10353P, Revision 0, Increased Enrichment for PWRs (Letter) Project stage: Approval ML23165A1902023-06-16016 June 2023 Withholding Determination for Publication of Approved Framatome Topical Report, ANP-10353P-A, Revision 0, Increased Enrichment for PWRs (Form 897) Project stage: Other ML23165A1882023-06-16016 June 2023 Withholding Determination for Publication of Approved Framatome Topical Report, ANP-10353P-A, Revision 0, Increased Enrichment for PWRs (EPID L-2021-TOP-0004) (Transmittal) Project stage: Other ML23167A0022023-06-28028 June 2023 Verification for Publication of Approved Framatome Topical Report, ANP-10353P-A, Revision 0, Increased Enrichment for PWRs Project stage: Other ML23167A0032023-06-28028 June 2023 Verification for Publication of Approved Framatome Topical Report, ANP-10353P-A, Revision 0, Increased Enrichment for PWRs EPID L-2021-TOP-0004 Project stage: Other 2022-05-31
[Table View] |
Text
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION NOTICE: The enclosure to this transmittal letter has proprietary information, once this letter is separated from the enclosure it is decontrolled.
May 31, 2022 Mr. Gary Peters, Director Licensing and Regulatory Affairs Framatome Inc.
3315 Old Forest Road Lynchburg, VA 24501
SUBJECT:
AUGUST 17, 2022, REGULATORY AUDIT PLAN FOR FRAMATOME INC.
TOPICAL REPORT, ANP-10353P, REVISION 0, INCREASED ENRICHMENT FOR PWRs (EPID L-2021-TOP-0004)
Dear Mr. Peters:
By letter dated January 29, 2021 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML21035A074), Framatome, Inc. (Framatome) submitted Topical Report (TR) ANP-10353P, Revision 0, Increased Enrichment for [Pressurized Water Reactors]
PWRs (ADAMS Package No. ML21035A073), to the U.S. Nuclear Regulatory Commission (NRC) for review and approval for licensing applications. Framatome states in part that ANP-10353P, Revision 0, addresses the codes and methods used to perform neutronics analyses, thermal hydraulic analyses, non-loss-of-coolant accident (non-LOCA) analyses, loss-of-coolant accident (LOCA) analyses, and thermal-mechanical fuel evaluations with respect to applicability to fuel with enrichment greater than 5 weight-percent Uranium-235.
The NRC staff technical review of this TR is ongoing. The NRC staff will perform a virtual regulatory audit on August 17, 2022, via Microsoft Teams. This audit was re-scheduled from May 25, 2022, per Framatomes request. The NRC staff determined that this regulatory audit is needed to facilitate the review. A previous audit was held on September 13, 2021 (ADAMS Accession No. ML21305A032). Enclosed for your information is a copy of the proprietary audit plan that the NRC staff will follow.
OFFICIAL USE ONLY - PROPRIETARY INFORMATION OFFICIAL USE ONLY - PROPRIETARY INFORMATION Please contact Ngola Otto at 301-415-6695 or via e-mail at Ngola.Otto@nrc.gov with any questions you may have regarding this letter.
Sincerely,
/RA/
Richard Chang, Chief Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 99902041
Enclosure:
Audit Plan (Proprietary)
ML22129A003 (Letter); ML22129A002 (Audit Plan)
OFFICE NRR/DORL/LLPB NRR/DORL/LLPB NRR/DSS/SFNB NRR/DORL/LLPB NRR/DORL/LLPB NAME NOtto DHarrison RLukes RChang NOtto DATE 05/9/2022 05/25/2022 05/16/2022 05/26/2022 05/31/2022