Text
Date: Wednesday, December 22, 2021 Time: 7:42:14 AM TEST REPORT Question file: MASTER ILT-14 NRC QUESTION BANK Copyright:
Test Date: 12/21/2021 Test Name: MASTER ILT-14 NRC Exam (SRO) (25 Qs)
Test Form: 0 Test Version: 0 Test Points: 25.00 Test File: MASTER ILT-14 NRC EXAM (SRO) (25 QS) AS OF 11102021 Test Path: O:\\ILT-14\\NRC EXAM\\WRITTEN\\MASTER ILT-14 NRC EXAM (SRO) (25 QS) AS OF 11102021.LXRTEST ML22010A277
Name: ________________________________ MASTER ILT-14 NRC Exam (SRO) (25 Qs)
Form: 0 Version: 0
Subsequently a trip of ALL Condensate Pumps resulting in the following:
o Scram resulting in an ATWS o An Emergency Depress is REQUIRED o 7 ADS valves are OPEN o RHR Loop A can ONLY achieve a flowrate of 7,000 gpm o RHR stabilizes RWL at -185 inches (HIGHEST achievable)
Based on the above conditions and IAW the EOPs, which ONE of the choices below completes the following statements?
The HIGHEST listed RPV pressure in which injection was first ALLOWED is __________.
IAW with EOP bases, injection with Core Spray __________ REQUIRED.
130 psig; is 130 psig; is NOT 180 psig; is 180 psig; is NOT A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 1
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 77. 211000A2.06 001 Unit 2 is operating at 100% RTP.
o 34SV-C41-002-2, Standby Liquid Control Pump Operability Test, is being performed for the 2A SBLC Pump o A SO is stationed locally to perform valve manipulations At 10:00, 2C41-F001, Storage Tank Isolation, is closed.
At 10:15, SBLC Test Tank level is raised to 20 inches.
At 10:16, the SO leaves the SBLC skid to investigate an alarm at the Intake Structure.
Based on the above conditions, which ONE of the choices below completes the following statement?
At 10:17, SBLC is __________.
OPERABLE INOPERABLE ONLY because a manual valve is out of position INOPERABLE ONLY because SBLC Test Tank level is too high INOPERABLE because a manual valve is out of position AND SBLC Test Tank level is too high A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 2
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 78. 215003A2.05 001 Unit 2 Reactor startup is in progress.
The following IRM readings have been observed while switching up from range 6 to range 7:
IRM Channel Range 6 Range 7 A
75 8.0 B
60 0.0 C
75 8.0 D
70 6.0 E
70 8.5 F
50 5.0 G
65 9.0 H
70 8.5 Based on the above conditions and IAW 34GO-OPS-001-2, Plant Startup, which ONE of the choices below completes the following statements?
Acceptable overlap is confirmed on _________ IRMs.
The LOWEST level of authority required to continue the reactor startup is the _________.
six (6);
Shift Supervisor six (6);
Shift Manager seven (7);
Shift Supervisor seven (7);
Shift Manager A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 3
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 79. 216000G2.2.12 001 Unit 2 is at 100% RTP and 57SV-B21-006-2, Main Steam Line Pressure Instrument FT&C, is in progress.
2B21-N015A, Steam Line PS, was just removed from service and the Unit 2 SS has delayed entry into the associated Conditions and Required Actions as allowed by TS 3.3.6.1 SR Note 2.
Ten (10) minutes later, I&C personnel inform the Unit 2 SS that 2B21-N015A will not trip and repairs will take 3 hours3.472222e-5 days <br />8.333333e-4 hours <br />4.960317e-6 weeks <br />1.1415e-6 months <br />.
Based on the above conditions, which ONE of the choices below completes the following statements?
IAW Tech Spec Bases, the Main Steam Line Pressure - Low function automatically closes the MSIVs to maintain RPV pressure above a MINIMUM of __________.
Entry into Tech Spec 3.3.6.1, Primary Containment Isolation Instrumentation, Condition A, __________ IMMEDIATELY REQUIRED.
500 psig; is 500 psig; is NOT 685 psig; is 685 psig; is NOT A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 4
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 80. 223002A2.09 001 Unit 2 is operating at 100% RTP when the following events occur:
A leak develops in the RWCU Pump Room causing the Area Ventilation differential temperatures to RISE.
o At 12:00, Area Ventilation differential temperature is 65°F o At 12:05, Area Ventilation differential temperature is 145°F At 12:10, the following conditions exist:
o 2G31-F004, RWCU Outboard Isolation valve, is CLOSED o 2G31-F001, RWCU Inboard Isolation valve, is OPEN and will NOT close Subsequently, 2G31-F001 is declared INOPERABLE and the initial required actions of Tech Specs are performed.
Based on the above conditions, which ONE of the choices below completes the following statements?
The EARLIEST listed time RWCU will have RECEIVED an AUTOMATIC isolation signal is __________.
IAW Tech Spec 3.6.1.3, PCIVs, periodic verifications that the RWCU line is ISOLATED __________.
12:00; is required to be accomplished by actual hands on verification at the component 12:00; can be accomplished remotely by administrative means 12:05; is required to be accomplished by actual hands on verification at the component 12:05; can be accomplished remotely by administrative means A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 5
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 81. 226001A2.12 001 Plant Hatch experiences a seismic event that results in a LOCA/LOSP on Unit 2.
The following conditions are present:
o RHR pump 2A is the ONLY ECCS pump that will OPERATE o Alternate Injection System alignment is in progress Subsequently, the crew performs an Emergency Depressurization and now have the following conditions:
o Torus Water Level is in its NORMAL band o Torus Pressure is 9 psig o Torus Water Temperature is 220°F o RHR pump 2A flowrate 10,000 gpm o NO Alternate Injection Systems are aligned at this time o RWL is -182 inches and rising 0.5 inches/min Based on the above conditions AND IAW the EOP Flowcharts, which ONE of the choices below completes the following statements?
RHR loop 2A flowrate __________ REQUIRED to be LOWERED.
Exiting the EOPs and entering the SAGs is __________.
Reference Provided is; REQUIRED is; NOT REQUIRED is NOT; REQUIRED is NOT; NOT REQUIRED A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 6
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 82. 261000G2.2.37 001 Unit 2 is operating at 100% RTP with solvent-based painting in progress on the 130' elevation of the Unit 2 Reactor Building.
o A total of Four (4) gallons of solvent-based paint is being used IAW 34SO-T46-001-2, Standby Gas Treatment System, tags stating "SOLVENT BASED PAINTING IN PROGRESS" have been placed on the control switches for SBGT A & B Fans.
Based on the above conditions, which ONE of the choices below completes the following statement?
While the above tags are in place, Unit 2 SBGT A & B Fans are considered __________.
OPERABLE ONLY if an operator is stationed at the SBGT A & B Fan switches OPERABLE and an operator is NOT required to be stationed at the SBGT A & B Fan switches INOPERABLE but AVAILABLE ONLY if an operator is stationed at the SBGT A & B Fan switches INOPERABLE and NOT AVAILABLE A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 7
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 83. 288000G2.2.25 001 Both Units are operating at 100% RTP with the following conditions:
o There is a small fire in the Main Control Room (MCR) o The fire is extinguished by the MCR operating crew o Smoke has filled the MCR Which ONE of the choices below completes the following statements?
Whenever the Main Control Room Environmental (MCREC) System is operating in the Purge Mode, __________ of the MCREC subsystems MUST be declared INOPERABLE.
Based on the above conditions and to remove smoke from the MCR, MCREC __________
be operated in the Purge Mode.
NONE (0);
will NONE (0);
will NOT ONE (1);
will ONE (1);
will NOT A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 8
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
At 07:00, the following alarms are ILLUMINATED:
o REACTOR VESSEL WATER LEVEL HIGH/LOW, 603-141 o REACTOR VESSEL LEVEL 2 DIV I TRIP, 603-205 o REACTOR VESSEL LEVEL 2 DIV II TRIP, 603-206 o RECIRC PUMP A&B HIGH PRESS/LOW LEVEL TRIP, 602-111 At 07:02, the following alarm is as indicated:
o RECIRC PUMP A&B HIGH PRESS/LOW LEVEL TRIP, 602-111, is CLEAR At 07:05, o a LOSP occurs o NO EDGs are AVAILABLE Based on the above conditions and IAW the EOPs, which ONE of the choices below completes the following statements?
At 07:03, the ADS Auto Logic Inhibit Switches are REQUIRED to be in the __________ position.
At 07:06, RWL control is REQUIRED to be directed from __________.
NORMAL; 31EO-EOP-015-2, CP-1 Alternate Level Control NORMAL; 31EO-EOP-010-2, RPV Control (Non-ATWS), RC/L path INHIBIT; 31EO-EOP-015-2, CP-1 Alternate Level Control INHIBIT; 31EO-EOP-010-2, RPV Control (Non-ATWS), RC/L path A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 9
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 85. 295012AA2.02 001 Unit 1 is operating at 100% RTP when a loss of Drywell Cooling occurs.
34AB-T47-001-1, Complete Loss of Drywell Cooling, is in progress.
The Drywell temperatures on Attachment 1, Peak Drywell Temperature, are exceeded.
Drywell pressure is currently 1.2 psig, rising 0.1 psig/minute.
Based on the above conditions, which ONE of the choices below completes the following statements?
IAW 34AB-T47-001-1, the MAXIMUM amount of time that the Attachment 1 temperature is allowed to be exceeded before a fast reactor shutdown is required is __________.
With the current Drywell pressure trend continuing, five (5) muinutes later, if a DBA LOCA were to occur, the resultant peak DW pressure __________ EXCEED the Drywell design pressure.
30 minutes; will 30 minutes; will NOT 60 minutes; will 60 minutes; will NOT A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 10
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 86. 295013G2.2.25 001 Unit 2 is at 15% RTP following a refueling outage with HPCI running for surveillence 34SV-E41-002-2, HPCI PUMP OPERABILITY.
Based on the above conditions and IAW Tech Specs 3.6.2.1, which ONE of the following identifies the LCO for Suppression Pool Average Temperature when HPCI testing is in progress, including the bases for this value?
100°F This value was chosen to ensure that the unit has testing flexibility, and to provide margin below the limit at which a reactor shutdown is required.
100°F This value was chosen to ensure that the resultant peak accident temperature is maintained below the design temperature.
105°F; This value was chosen to ensure that the unit has testing flexibility, and to provide margin below the limit at which a reactor shutdown is required.
105°F This value was chosen to ensure that the resultant peak accident temperature is maintained below the design temperature.
A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 11
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 87. 295015G2.4.21 001 Unit 1 was operating at 50% RTP when a scram resulted in the following conditions:
o RWL
-20 inches, lowest since scram and slowly lowering o Reactor power 3% with multiple control rods at various positions o RPV pressure 1000 psig, highest since scram and stable Based on the above conditions, which ONE of the choices below completes the following statements?
The Alternate Rod Insertion (ARI) System ________ received an automatic initiation signal.
IAW 34AB-C71-001-1, Scram Procedure, entry into ________ is REQUIRED to insert control rods.
has; 31EO-EOP-103-1, EOP Control Rod Insertion Methods has; 34AB-C11-005-1, Control Rod Insertion Methods has NOT; 31EO-EOP-103-1, EOP Control Rod Insertion Methods has NOT; 34AB-C11-005-1, Control Rod Insertion Methods A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 12
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 88. 295021AA2.05 001 Unit 2 is recovering from a loss of shutdown cooling. RHR pumps are unavailable.
34SO-B31-001-2, Reactor Recirculation System, Recirc Pump Startup, is in progress.
At 10:00, the following conditions exist:
o RPV saturation temperature 330°F and steady o "A" Recirc suction temperature 305°F lowering 1°F/minute o "B" Recirc suction temperature 310°F lowering 1°F/minute o Vessel Bottom Head Drain temperature 245°F lowering 2°F/minute o An operator depresses the ASD "A" START pushbutton At 10:02, 2B31-F031A, Recirc Pump A Discharge Valve, red AND green indicating lights are BOTH illuminated.
Based on the above conditions, which ONE of the choices below completes the following statements?
IAW TS 3.4.9 RCS Pressure and Temperature (P/T) Limits, the LATEST listed time the crew could have started Recirc pump 2A and still meet TS 3.4.9 temperature requirements is NO LATER THAN __________.
At 10:03, Recirc Pump "2A" will be __________.
10:20; tripped 10:20; running at minimum speed 10:30; tripped 10:30; running at minimum speed A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 13
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 89. 295023G2.2.38 001 Unit 2 is in day 5 of a Refueling outage with fuel movement in progress.
A Refueling accident occurs resulting in the following radiation levels:
o All Refueling Floor Area Radiation Monitors (ARMs) indicate between 20 and 50 mr/hr o 2D11-K611A-D, Refueling Floor Vent Exhaust Radiation Monitors indicate 8 mr/hr Based on the above conditions, which ONE of the choices below completes the following statements?
The MCREC system __________ be operating in the Pressurization Mode.
IAW Tech Spec Bases, the MCREC System is designed to ensure that the Control Room operators will not exceed a __________ TEDE Whole Body dose for a 30 day period following a Design Basis Accident.
will NOT; 2 Rem will NOT; 5 Rem will; 2 Rem will; 5 Rem A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:14 AM 14
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 90. 295026EA2.03 001 Unit 2 experienced a loss of the Condensate system.
Current plant conditions are:
o RWL
-95 inches and slowly RISING o RPV Pressure 900 psig, being controlled by LLS o Torus Level 160 inches and slowly RISING o Torus Temperature 187°F and slowly RISING Based on the above conditions and IAW 31EO-EOP-012-2, Primary Containment Control, which ONE of the choices below completes the following statements?
The plant is in the __________ region of the Heat Capacity Temperature Limit (HCTL).
If the UNSAFE region is entered, it __________ ALLOWED to reduce and maintain RPV pressure between 500 psig to 550 psig to return to the SAFE region.
Reference provided SAFE; is SAFE; is NOT UNSAFE; is UNSAFE; is NOT A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 15
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 91. 295028EA2.02 001 Unit 1 was operating at 100% RTP when an event occurred causing Drywell temperature to begin RISING.
The following conditions exist:
At 10:00, Drywell temperature is 275°F and RISING at a rate of 2°F/min NOTE: The Drywell temperature trend remains constant Based on the above conditions and IAW 31EO-EOP-012-1, Primary Containment Control, which ONE of the choices below completes the following statements?
The EARLIEST listed time that RC[A] Point A is REQUIRED to be performed is __________.
At 10:37, RPV pressure will be controlled using __________.
10:02; CP-1 Point G 10:02; RC/P 10:32; CP-1 Point G 10:32; RC/P A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 16
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 92. 295038G2.1.25 001 Unit 1 was operating at 100% RTP when the following events occur:
10:00 RCIC Steam line break occurs in the Reactor Building with 1E51-F007 & F008, Isolation Valves, failing to close 10:01 Manual scram inserted, Reactor power 11% RTP 10:05 One (1) Reactor Building Area Temperature exceeds Max Safe Operating value 10:10 Drywell Wide Range Radiation Monitors (DWRRM) indicate 1000 R/hr 10:15 RWL is -150 inches and steady 10:20 Drywell pressure is 2.6 psig and slowly rising 10:25 Projected Dose at the Site Boundary is 1050 mRem TEDE and 3000 mRem CDE (thyroid)
Based on the above conditions, which ONE of the following is the EARLIEST listed time that sufficient plant conditions exist to provide enough information to declare a GENERAL Emergency, WITHOUT basing the declaration on ED judgment?
Reference Provided 10:10 10:15 10:20 10:25 A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 17
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 93. 700000G2.1.7 001 Unit 2 is operating at 100% RTP.
34SV-R43-001-2, Diesel Generator 2A Monthly Test, is in progress with EDG 2A fully loaded.
At 09:58, GCC notifies the the NPO that the Offsite system is one contingency (event) away from being unable to maintain normal minimum voltage on the 230KV bus.
34AB-S11-001-0, Operation With Degraded System Voltage, is entered.
At 10:00, EDG 2A automatically trips.
At 11:07, TS SR 3.8.1.1, (34SV-SUV-013-0, Weekly Breaker Alignment Checks), is INITIALLY completed for TS 3.8.1 AC Sources - Operating.
Based on the above conditions, which ONE of the choices below completes the following statements?
At 09:58, IAW 34AB-S11-001-0, there __________ a requirement for 34SV-R43-001-2 to be terminated AND restored to normal as soon as possible.
The 11:07 INITIAL completion time of 34SV-SUV-013-0, __________ meet the TS SR 3.8.1.1 completion time.
was; did was; did NOT was NOT; did was NOT; did NOT A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 18
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 94. G2.1.5 001 NMP-AD-016, Fatigue Management Program, contains the following NOTE:
NOTE The term Covered as used in this procedure is different than the term Covered as it applies to membership in a labor union.
Which ONE of the choices below completes the following statements IAW NMP-AD-016?
If someone is performing duties of a Fire Brigade Leader, this is considered __________.
If the On-shift Fire Brigade Leader contacted the Off-shift Fire Brigade Leader at home and discussed Fire Brigade concerns for 45 minutes, this 45 minutes __________ count toward the Off-shift Fire Brigade Leader's work hours.
Covered Work; will Covered Work; will NOT Incidental Duties; will Incidental Duties; will NOT A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 19
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 95. G2.1.35 001 Unit 2 is in REFUEL with core reload in progress.
Based on the above conditions and IAW 34FH-OPS-001-0, Fuel Movement Operation, which ONE of the choices below completes the following statements?
For core reload, the Unit 2 Reactor Mode switch is REQUIRED to be in the __________.
The fuel movement prerequisites must be completed prior to the initial fuel movement and __________.
Refuel position and LOCKED; at EACH shift change (12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> shift) during fuel movement Refuel position and LOCKED; PRIOR to restarting fuel movement after a one (1) hour delay Refuel position ONLY (NOT locked);
at EACH shift change (12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> shift) during fuel movement Refuel position ONLY (NOT locked);
PRIOR to restarting fuel movement after a one (1) hour delay A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 20
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 96. G2.2.5 001 A proposed plant modification must ALWAYS have prior approval from the NRC if it involves any __________.
system that requires a 50.59 screening change to any system included in Tech Specs design basis limit for Primary Containment being altered change to the Technical Requirements Manual (TRM) Bases A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 21
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 97. G2.2.13 001 Plant Hatch is in an emergency with the following conditions:
o A component needed to mitigate the emergency is being held by a clearance o The Work Document Holder for this clearance is NOT on site and can NOT be contacted Based on the above conditions, and IAW NMP-AD-003, Equipment Clearance and Tagging, which ONE of the choices below is the LOWEST level of authority that can AUTHORIZE the release of this clearance?
Operations Director Maintenance Director On-duty Shift Manager Tagging Official/Authorizer A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 22
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 98. G2.3.11 001 A LOCA has occurred on Unit 2.
The following conditions currently exist:
o RWL
-165 inches and stable o Drywell Pressure 54 psig and slowly RISING o Drywell Radiation 2,500 R/hr and slowly RISING o Torus Pressure 52 psig and slowly RISING o Torus Water Level
> 300 inches Based on the above conditions and IAW 31EO-EOP-012-2, Primary Containment Control, which ONE of the choices below completes the following statements?
31EO-EOP-101-2, Emergency Containment Venting, __________ the correct procedure to vent Primary Containment.
While venting the Primary Containment, exceeding the offsite radioactivity release rate limits __________ permitted.
is NOT; is NOT is NOT; is is; is NOT is; is A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 23
MASTER ILT-14 NRC Exam (SRO) (25 Qs)
- 99. G2.4.27 001 Unit 1 is operating at 100% RTP when the following occurs:
o At 10:00 Fire alarms are received in the Unit 1 130' Turbine Building SO dispatched to investigate o At 10:05 SO reports the Unit 1 Hydrogen Seal Oil System is on fire o At 10:17 SO reports Unit 1 Hydrogen Seal Oil System fire is EXTINGUISHED Based on the above conditions, which ONE of the choices below completes the following statements?
IAW 34AB-X43-001-1, Fire Procedure, at 10:05, entry into 34AB-C71-001-1, Scram Procedure, __________ REQUIRED.
IAW NMP-EP-141-002, Hatch Emergency Action Levels and Basis (NEI 99-01 Revision 6),
the fire duration clock BEGINS at __________.
Reference Provided is NOT; 10:00 is NOT; 10:05 is; 10:00 is; 10:05 A.
B.
C.
D.
Wednesday, December 22, 2021 7:42:15 AM 24
MASTER ILT-14 NRC Exam (SRO) (25 Qs) 100. G2.4.30 001 Given the following plant conditions:
At 08:00, A reactor scram occurred At 08:15, A Site Area Emergency is declared At 08:25, State and Local officials are notified At 08:45, An offsite release is confirmed to be in progress At 08:50, Declaration upgraded to a General Emergency Based on the above conditions and IAW NMP-EP-142, Emergency Notification, which ONE of the choices below identifies the LATEST listed time that the NEXT REQUIRED notification is to be made and the agency(ies) REQUIRED to be notified?
Time Agency(ies) 09:00 NRC 09:05 State and Local Agencies 09:15 NRC 09:25 State and Local Agencies A.
B.
C.
D.
You have completed the test!
Wednesday, December 22, 2021 7:42:15 AM 25